THE COPESTONE COMPANY | B= | C | 12/22/2015 | All other required Final inspections are complete. (This is a computer generated result) | BRIANB | BRIANB | | B= | C | 5104222 |
THE COPESTONE COMPANY | B= | P | 12/22/2015 | Units 2318 and 2340 - 5/8" type x gypsum repairs okay / pending other final inspections. Additional Inspections Required (computer generated): CO. DELTA MECHANICAL, INC Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 5104017 |
THE COPESTONE COMPANY | B= | P | 12/17/2015 | PARTIAL ONLY / inspected units - 2320 / 2322 / 2332 / 2334 / 2336 / 2338 / 2342 / 2312 / 2314 / 2316 / 5/8" type X gypsum repairs okay / Units 2318 and 2340 locked and still need inspection / pending other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): CO. DELTA MECHANICAL, INC Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 5101148 |
THE COPESTONE COMPANY | BFR | P | 12/14/2015 | Unit 2320 okay / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 5098350 |
THE COPESTONE COMPANY | BFR | P | 12/10/2015 | Units 2318, 2338, 2336, 2316, 2334, 2314, 2312, 2332, 2340, 2322 and 2342 OK / 2320 locked, inspect at next visit | JEREMYA | JEREMYA | | BFR | P | 5096030 |
THE COPESTONE COMPANY | B= | P | 12/09/2015 | PARTIAL ONLY / inspected units - 2306 / 2308 / 2310 / 2326 / 2328 / 2330 / 5/8" type X gypsum repairs okay / see plumbing inspectors comments for unit 2304 and unit 2306 PTO inspection still partial only / pending other final inspections / need to complete inspection of remaining units still -- Schedule a new Building Final when above items are complete. | BRIANB | BRIANB | | B= | P | 5095490 |
THE COPESTONE COMPANY | BFR | P | 11/24/2015 | PARTIAL ONLY / inspected 6 units - 2306 / 2308 / 2310 / 2326 / 2328 / 2330 - no damaged found at exposed existing framing / still need to inspect remaining units / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 5086673 |
COLORADO DELTA MECHANICAL, INC | P= | C | 12/22/2015 | 2334, 2312 completes building | JOEL | JOEL | | P= | C | 5104221 |
COLORADO DELTA MECHANICAL, INC | P= | P | 12/10/2015 | units 2314/2316/2318/2320/2322/2324/2332/2336/2338/2340/2342 | JOEL | JOEL | | P= | P | 5096659 |
COLORADO DELTA MECHANICAL, INC | P= | P | 12/03/2015 | insulated k-sink lines | JOEL | JOEL | | P= | P | 5090632 |
COLORADO DELTA MECHANICAL, INC | P= | P | 11/24/2015 | will final when all units are inspected, see pto notes for units that are o.k | JOEL | JOEL | | P= | P | 5086847 |
COLORADO DELTA MECHANICAL, INC | PTO | P | 11/24/2015 | units 2310/2330/2308/2328/2326 o.k check freeze protection 2306 and 2304 | JOEL | JOEL | | PTO | P | 5086649 |