DAYSTAR BUILDING COMPANY | B= | C | 02/19/2016 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5138637 |
DAYSTAR BUILDING COMPANY | B= | P | 02/19/2016 | OK pending other finals. Additional Inspections Required (computer generated): FRONTIER MECHANICAL SYSTEMS INC Plumbing Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5138605 |
DAYSTAR BUILDING COMPANY | BFR | P | 12/18/2015 | need to pull plumbing permit and have inspections / framing Ok pending other roughs / discussed accessibility with contractor | DANE | DANE | | BFR | P | 5102007 |
DOWNTOWN ELECTRIC AND LIGHTING INC | E= | C | 02/18/2016 | | RANDY | RANDY | | E= | C | 5137036 |
DOWNTOWN ELECTRIC AND LIGHTING INC | ER | C | 01/29/2016 | | GARYL | GARYL | | ER | C | 5126383 |
DOWNTOWN ELECTRIC AND LIGHTING INC | EP | P | 01/27/2016 | panels and transformers ok replace #10 and 12 black red blue conductors with brown orange yellow to vav. cannot re-phase that size conductor. | BRET | BRET | | EP | P | 5124471 |
DOWNTOWN ELECTRIC AND LIGHTING INC | ER | P | 01/27/2016 | ceiling ok except in treatment rooms, replace mc to fixtures with hospital grade, (fixtures did not come with factory whips) contractor made whips over 6' in length. | BRET | BRET | | ER | P | 5124456 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 01/19/2016 | FIRE ALARM INSPECTION: | GARYL | GARYL | | E= | C | 5118688 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 01/19/2016 | FIRE ALARM INSPECTION: | GARYL | GARYL | | ER | C | 5118656 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 12/23/2015 | FIRE ALARM INSPECTION: walls, stub ups only | GARYL | GARYL | | ER | P | 5105200 |
DOWNTOWN ELECTRIC AND LIGHTING INC | ER | P | 12/23/2015 | hard lids through out | GARYL | GARYL | | ER | P | 5105195 |
DOWNTOWN ELECTRIC AND LIGHTING INC | ER | P | 12/18/2015 | NOTE! it's not suite 100 but 125, 2nd door on right as you enter, WALLS only, | GARYL | GARYL | | ER | P | 5102044 |
HVAC SOLUTIONS, INC. | H= | C | 02/11/2016 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT RECEIVED. | NANCY | NANCY | | H= | C | 5132256 |
HVAC SOLUTIONS, INC. | H= | P | 02/09/2016 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5130875 |
HVAC SOLUTIONS, INC. | H= | P | 02/04/2016 | NO ONE ON SITE AT 1:15 PM. DRYER VENT MUST BE HARD PIPE FROM DRYER TO TERMINATION. SLEEVE/ISOLATE DRYER VENT FROM RETURN PLENUM. NO ACCESS TO ROOF TODAY. PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5128747 |
HVAC SOLUTIONS, INC. | H= | L | 02/03/2016 | NO KEY FOR ROOF ACCESS TODAY. ALREADY RESCHEDULED FOR TOMORROW. | NANCY | NANCY | | H= | L | 5127734 |
HVAC SOLUTIONS, INC. | H= | P | 01/28/2016 | NEED CONSULT WITH SENIOR INSPECTOR ON DRYER DUCT - ALL SA/RA AND EXHAUST GRILLES COMPLETE- PARTIAL PENDING TAB REPORT / ROOF INSPECTION FOR EXHAUST FAN | JERRYF | JERRYF | | H= | P | 5125852 |
HVAC SOLUTIONS, INC. | HD | P | 12/29/2015 | BEFORE FINAL CHANGE SUITE NUMBER TO 125 ON APPROVED PRINTS. ROUGH SUPPLY TRUNK LINES AND LATERALS OK, OK TO WRAP. ROUGH EXHAUST DUCT OK. NO DRYER VENT YET. DRYER VENT WILL NEED TO BE ISOLATED FROM RETURN PLENUM WHEN INSTALLED. NO VAV'S, FLEX OR DIFFUSERS YET. STILL NEED TO SEE ROOF. INSTALL EIGHT SQUARE FEET OF RETURN AIR PATH AS PER PRINTS BY FINAL. | NANCY | NANCY | | HD | P | 5107062 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 02/19/2016 | NOTE : HAMMER ARRESTERS AT ALL QUICK CLOSE VALVES , EXP TANK AT WATER HEATER , TEMPERING AT BATH LAV | GABE | GABE | | P= | C | 5138636 |
FRONTIER MECHANICAL SYSTEMS INC | PB | C | 02/17/2016 | DWV IN GARAGE OK , | GABE | GABE | | PB | C | 5136378 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 12/21/2015 | ALL TO PLAN , WILL NEED HAMMER ARRESTER AT ICE MAKER SUPPLY BY FINAL , NOTE : CONSULT WITH BUILDING ON ADA BREAK SINK | GABE | GABE | | PTO | C | 5103168 |