THE COPESTONE COMPANY | B= | C | 03/28/2016 | | JEREMYA | JEREMYA | | B= | C | 5164050 |
THE COPESTONE COMPANY | B= | P | 02/25/2016 | Building final complete pending other final inspections. Additional Inspections Required (computer generated): FOSTER ELECTRIC CORP Electrical Final Inspection is not Completed yet, NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 5141999 |
FOSTER ELECTRIC CORPORATION | BSP | T | 01/28/2016 | PAID (REC#1310759) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: add ac units | SHELBY | SHELBY | | BSP | T | 5125702 |
NIELSEN MECHANICAL CONTRACTORS, INC. | BSP | P | 01/28/2016 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: added mini-split to VDC room | JUSTINC | JUSTINC | | BSP | P | 5125664 |
THE COPESTONE COMPANY | BFR | P | 12/21/2015 | interior non-load bearing wall framing okay / penetrations above grid line in existing 1hr fire rated assembly (wall type A) at break room, conference room, mail room, and room 201 - 203 on approved plans / reviewed accessible elements with site rep BIll on sheet A7 for break room and 34" height for accessible sink / need to complete other rough inspections | BRIANB | BRIANB | | BFR | P | 5102969 |
THE COPESTONE COMPANY | BSP | T | 12/07/2015 | PAID (REC#1302771) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: add new electrical sheets | SHELBY | SHELBY | | BSP | T | 5092837 |
FOSTER ELECTRIC CORPORATION | E= | C | 02/25/2016 | | BRET | BRET | | E= | C | 5142470 |
FOSTER ELECTRIC CORPORATION | E= | P | 02/17/2016 | wrong call ahead number, 719-761-9142, ceiling and reeceptacle for tv ok, furniture being installed not energized at this time. | BRET | BRET | | E= | P | 5135841 |
FOSTER ELECTRIC CORPORATION | E= | P | 01/27/2016 | EXCEPT FURNITURE | MIKEC | MIKEC | | E= | P | 5124722 |
FOSTER ELECTRIC CORPORATION | E= | R | 01/26/2016 | missing receptacle for conference room tv. boxes still open in ceiling conference room west. furniture not installed at this time. | BRET | BRET | | E= | R | 5123331 |
FOSTER ELECTRIC CORPORATION | E= | P | 01/25/2016 | 208 thru 212 offices only other area not ready. | BRET | BRET | | E= | P | 5122138 |
FOSTER ELECTRIC CORPORATION | ER | C | 01/19/2016 | | BRET | BRET | | ER | C | 5118752 |
FOSTER ELECTRIC CORPORATION | ER | P | 12/21/2015 | | MIKEC | MIKEC | | ER | P | 5102646 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 03/03/2016 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT AND LETTER FROM ENGINEER APPROVING TEST AND BALANCE REPORT RECEIVED AND SCANNED. | NANCY | NANCY | | H= | C | 5146732 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 02/18/2016 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5137102 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 01/14/2016 | ROOM 203: WALLS GO TO DECK, WHERE DOES FAN EXHAUST TO? PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5116183 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 01/08/2016 | rough duct ok, all flex and defusers are installed. note: room # 203 not ready, still need to see sound boots in stalled, test and balance by final. | LUKE | LUKE | | HD | P | 5112640 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 02/05/2016 | correction made. | TAYLOR | TAYLOR | | P= | C | 5128837 |
FRONTIER MECHANICAL SYSTEMS INC | P= | P | 02/03/2016 | need expansion device at water heater, rest ok. | TAYLOR | TAYLOR | | P= | P | 5127223 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 01/11/2016 | NOTE : TIE IN OK , ALL CAST . IN BREAK ROOM UNIT 104 | GABE | GABE | | PTO | C | 5113958 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 01/05/2016 | walls and above ceiling ok, still need to verify drain connection below floor, by final need vacuum breaker above water heater. | TAYLOR | TAYLOR | | PTO | P | 5109806 |