COLARELLI CONSTRUCTION, INC. | B= | C | 02/18/2016 | All other required Final inspections are complete. (This is a computer generated result) | JEREMYA | JEREMYA | | B= | C | 5137648 |
COLARELLI CONSTRUCTION, INC. | B= | P | 02/18/2016 | Corrections at counter tops made. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 5136919 |
COLARELLI CONSTRUCTION, INC. | B= | P | 02/12/2016 | Need to lower coffee bar to 34" per plans for accessibility / Need accessible space at checkout counter / Complete all other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, FRONT RANGE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, PIKES PEAK REFRIGERATION, INC. Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 5133372 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 02/08/2016 | Remove kitchen from scope of work | SHELBY | SHELBY | | BSP | P | 5129798 |
COLARELLI CONSTRUCTION, INC. | BSP | T | 02/08/2016 | PAID (REC#1311997) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Remove kitchen from scope of work | MICHAELA | MICHAELA | | BSP | T | 5129779 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 02/03/2016 | Framing complete / Need to complete all mech inspections / Open hole on file | JEREMYA | JEREMYA | | BFR | P | 5127437 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 01/14/2016 | Interior wall framing at carving room and restroom screen wall OK / Open hole did not come through with inspection request, so I still need a stamped copy / Complete all other roughs / Need to see entry canopy framing once complete | JEREMYA | JEREMYA | | BFR | P | 5116392 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 01/07/2016 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: added kitchen to scope of work | JUSTINC | JUSTINC | | BSP | P | 5112183 |
COLARELLI CONSTRUCTION, INC. | BSP | T | 01/07/2016 | PAID (REC#1308242): ADDITIONAL PLAN REVIEW TIME: $20 From: MICHAELA splice to create commercial kitchen | MICHAELA | MICHAELA | | BSP | T | 5111610 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 01/07/2016 | PLAN SPLICE: (No Fee) by: MICHAELA for Construction: Create commercial kitchen | MICHAELA | MICHAELA | | BSP | P | 5111607 |
OLSON PLUMBING & HEATING COMPANY | BSP | P | 01/07/2016 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing | TCRIPPEN | TCRIPPEN | | BSP | P | 5111595 |
COLARELLI CONSTRUCTION, INC. | BFR | P | 01/06/2016 | Steel structure for hanging meat OK / Need to get copy of stamped open hole | JEREMYA | JEREMYA | | BFR | P | 5111058 |
COLARELLI CONSTRUCTION, INC. | BSP | P | 01/05/2016 | PLAN SPLICE: (No Fee) by: DANM for Construction: Structural roof framing clarification | DANM | DANM | | BSP | P | 5110417 |
COLARELLI CONSTRUCTION, INC. | BFT | P | 12/21/2015 | forms and rebar okay for (2) interior pads / need stamped open hole letter / pour at own risk | BRIANB | BRIANB | | BFT | P | 5102433 |
COLARELLI CONSTRUCTION, INC. | BFT | R | 12/18/2015 | not ready for inspection / rebar and forms incomplete / cancelled by Scott on site | BRIANB | BRIANB | | BFT | R | 5101535 |
FRONT RANGE ELECTRIC, INC. | E= | C | 02/17/2016 | | CRAIGS | CRAIGS | | E= | C | 5135519 |
FRONT RANGE ELECTRIC, INC. | E= | P | 02/16/2016 | A1 need working clearance on disconnect -- need same fuses h5-- send pictures a1 15 fused at the unit --b2 15 fused ---f&g 20 fused---l-8 15 fused ---j-6 20 fused---k7 20 fused --e3 20 fused ---m9 15 fused ---h5---35 fused | CRAIGS | CRAIGS | | E= | P | 5135453 |
FRONT RANGE ELECTRIC, INC. | E= | R | 02/12/2016 | coolers / freezers need labeled , condenser and panel schedule to match ----gfci protect 4 plex at the end of the end of the counter with the sink ---- gfci protect drinking fountain receptacle ---- this is a partial list complete inspection required --- please meet me here to do the final inspection --- I will need roof access | CRAIGS | CRAIGS | | E= | R | 5134129 |
FRONT RANGE ELECTRIC, INC. | ER | P | 02/09/2016 | above ceiling from just behind the counter to front of store ---- need to look at name plates on the coolers in main store area next inspection | CRAIGS | CRAIGS | | ER | P | 5130843 |
FRONT RANGE ELECTRIC, INC. | ER | P | 01/15/2016 | new walls for carving station and coffee bar ok. stamped set of electrical missing 1 page please have on site for next inspection. | BRET | BRET | | ER | P | 5116892 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 02/17/2016 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5135545 |
PIKES PEAK REFRIGERATION, INC. | H= | C | 02/16/2016 | PRESSURE TEST OK ON 2 REMAINING COOLER CONDENSERS - ALL OTHER CORRECTIONS MADE | JERRYF | JERRYF | | H= | C | 5134349 |
PIKES PEAK REFRIGERATION, INC. | HRP | P | 02/12/2016 | FIVE 375 LB TESTS OK ON PRODUCE CASE, DRY STORAGE, 4 DOOR FREEZER AND 3 DOOR COOLER. NEED 1 INCH AIR GAP ON PRODUCE CASE CONDENSATE DRAIN. | NANCY | NANCY | | HRP | P | 5133297 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 02/10/2016 | PARTIAL PENDING TAB REPORT - REST OK | JERRYF | JERRYF | | H= | P | 5131352 |
OLSON PLUMBING & HEATING COMPANY | HD | C | 02/10/2016 | ABOVE CEILING OK ALL SA/RA AND EXHAUST GRILLES INSTALLED | JERRYF | JERRYF | | HD | C | 5131350 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 02/11/2016 | remodel | TED | TED | | P= | C | 5132503 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 12/30/2015 | to plan | TED | TED | | PTO | C | 5107503 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 12/16/2015 | to plan | TED | TED | | PB | C | 5100296 |