SHARP GENERAL CONTRACTORS, INC | B= | C | 09/01/2016 | all other finals now completed | MINDY | MINDY | | B= | C | 5283544 |
SHARP GENERAL CONTRACTORS, INC | B= | R | 08/22/2016 | Need land mark plumbing to void out permit. need electrical, plumbing and heating completed. Have partials now. Need fire final completed have partial to train only. Building OK to train only. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet, ELECTRIC TECH INC. Electrical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet. | DAN | DAN | | B= | R | 5275188 |
SHARP GENERAL CONTRACTORS, INC | BFR | C | 08/22/2016 | | DAN | DAN | | BFR | C | 5275185 |
SHARP GENERAL CONTRACTORS, INC | BFR | P | 07/12/2016 | Frame OK / Reviewed accessible elements / Need mechanical and electrical rough complete | NICK | NICK | | BFR | P | 5242650 |
LANDMARK PLUMBING AND HEATING, INC. | BSP | T | 07/11/2016 | PAID (REC#1340903) PLAN SPLICE FEE: $50 by: DALEH for Plumbing: relocated drop in sink to the upper level | DALEH | DALEH | | BSP | T | 5241802 |
SHARP GENERAL CONTRACTORS, INC | BFR | R | 06/07/2016 | Need to install backing for grab bars in rest rooms / Need all MEP's complete / Need one sink to be 34" by final | NICK | NICK | | BFR | R | 5216834 |
ELECTRIC TECH INC. | E= | C | 08/24/2016 | | MIKEC | MIKEC | | E= | C | 5277279 |
ELECTRIC TECH INC. | E= | P | 08/22/2016 | NEED 80 AMP FEED FOR WATER HEATER---GFCI PROTECTION ON BACK SINK-----PANEL SCH----- | BRIAN | BRIAN | | E= | P | 5274409 |
ELECTRIC TECH INC. | ER | C | 07/15/2016 | | MIKEC | MIKEC | | ER | C | 5245969 |
ELECTRIC TECH INC. | ER | P | 07/13/2016 | CEILINGS | MIKEC | MIKEC | | ER | P | 5244379 |
ELECTRIC TECH INC. | ER | P | 07/12/2016 | WALLS | MIKEC | MIKEC | | ER | P | 5243171 |
ELECTRIC TECH INC. | ER | P | 06/30/2016 | RECEPTION AREA AND HALL --SEE PLANS---- | BRIAN | BRIAN | | ER | P | 5234855 |
ELECTRIC TECH INC. | ESL | C | 05/26/2016 | | BRIAN | BRIAN | | ESL | C | 5209642 |
AIRTECH MECHANICAL, INC. | H= | C | 09/01/2016 | TAB REPORT RECEIVED - ALL COMPLETE | JERRYF | JERRYF | | H= | C | 5282928 |
AIRTECH MECHANICAL, INC. | H= | P | 08/29/2016 | PARTIAL PENDING TAB REPORT - REST OK | JERRYF | JERRYF | | H= | P | 5279791 |
AIRTECH MECHANICAL, INC. | H= | P | 08/22/2016 | PARTIAL PENDING TAB REPORT AND SCREEN AT 6" ROOF EXHAUST CAP - REST OK - SMOKE AND REMOTE COMPLETE | JERRYF | JERRYF | | H= | P | 5275020 |
AIRTECH MECHANICAL, INC. | HD | P | 06/22/2016 | SEAL EF 2 EXHAUST DUCT IN WALLS - NEED TO CLAIM EF 1 AND 2 ON PERMIT - SOMEONE NEEDS TO CLAIM ALL ELECTRIC BASEBOARD HEATERS - REST OK WILL NEED ROOF INSPECTION AT FUTURE INSPECTION - CONFIRM ALL TRANSFER AIR AT FUTURE INSPECTION | JERRYF | JERRYF | | HD | P | 5228430 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 08/25/2016 | corrections made. | TAYLOR | TAYLOR | | P= | C | 5278291 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 08/19/2016 | crossed water lines at lav in restroom 112, handle for toilet needs to be on the open side at restroom 103, need mixing valve at sink in sterile room 111, rest ok. | TAYLOR | TAYLOR | | P= | P | 5273859 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 06/27/2016 | check water heater/ H2O tie in at water entry room by final, revise plans to show mop sink that will move to second floor. | TAYLOR | TAYLOR | | PTO | C | 5232016 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 05/25/2016 | corrections made. | TAYLOR | TAYLOR | | PB | C | 5208294 |
LANDMARK PLUMBING AND HEATING, INC. | PB | R | 05/24/2016 | need to bed in all piping, toilet next to sewer tie in needs its own vent. | TAYLOR | TAYLOR | | PB | R | 5207174 |