GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 09/22/2016 | All other required Final inspections are complete. (This is a computer generated result) | DAN | DAN | | B= | C | 5299706 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 08/19/2016 | Mechanical final to be completed when test and balance for duct work is received. Colorado State Plumbing inspection report for areas "B", "G", and "K" on file from Dustin Hood, 303-869-3440. Colorado State Electrical inspection report for areas "B", "G", and "K" on file from Terry Hale Nickels, 303-894-2986. Fire Final report on file from Bill McElligott. CSFD. Additional Inspections Required (computer generated): OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, US ENGINEERING COMPANY Mechanical Final Inspection is not Completed yet. | DAN | DAN | | B= | P | 5274132 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | C | 08/19/2016 | | DAN | DAN | | BFR | C | 5273113 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | C | 08/19/2016 | | DAN | DAN | | BLA | C | 5273109 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 08/18/2016 | walked K and G areas with Ben. Need confirmation from state for completion of electrical and plumbing in these areas. | DAN | DAN | | BSP | P | 5272340 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 08/15/2016 | Walked Area "B" with Kellen regarding bathrooms completion. OK except missing sinage. | DAN | DAN | | BSP | P | 5269660 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/12/2016 | Lath for north side OK | NICK | NICK | | BLA | P | 5268385 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/09/2016 | lath east wall area "B" grid B6 through B8 ; Kellen to call in for modular set tomorrow. | DAN | DAN | | BLA | P | 5264579 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/08/2016 | lath at east side of "B" library line B-6 through B-8. | DAN | DAN | | BLA | P | 5264104 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/06/2016 | lath east exterior of area "B" lines B-4 through B-6. | DAN | DAN | | BLA | P | 5263362 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 08/06/2016 | Walked area "B" with Kellen, Missing bathroom counter tops several area. complete bath room B233. Verify hardware on library egress doors. Complete work at north egress doors. Fire partial for area OK. OK to move n furniture and set up. | DAN | DAN | | BSP | P | 5263361 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/04/2016 | exterior wall lath B2 and B3 of B area ok. | DAN | DAN | | BFR | P | 5261515 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 08/03/2016 | Walked roof Area "B" OK pending parapet cap completed. | DAN | DAN | | BSP | P | 5261243 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BLA | P | 08/03/2016 | Lath east side of Area "B" line "B" to - "B1" and sheathing north side. | DAN | DAN | | BLA | P | 5261233 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/02/2016 | Area "B" east side exterior wall sheating OK over existing studs. | DAN | DAN | | BFR | P | 5259389 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 07/29/2016 | In progress inspection of exterior of library for mold migration. Looked at header and sill flashings. 5,8" rock and Tyvek Contractor will recall for lath. Insulation being replaced. | DAN | DAN | | BFR | P | 5257886 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | T | 07/26/2016 | PAID (REC#1344543): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise wall finishes | MICHAELA | MICHAELA | | BSP | T | 5253751 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 07/25/2016 | reviewed link rock and fire caulk. Talked with Kellen regarding labeling of fire wall above tile. | DAN | DAN | | BFR | P | 5253343 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 07/25/2016 | Area "B" floor ceiling protection at ducts OK. Area "B" exterior east side mold migration and insulation replacement in progress. | DAN | DAN | | BSP | P | 5253335 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 07/22/2016 | complete floor protection in area "B" for ducts. recall | DAN | DAN | | BSP | P | 5252339 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | R | 07/21/2016 | Cancelled; reschedule | DAN | DAN | | BSP | R | 5251419 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 07/20/2016 | walk with Kellen to review floor protections of duct work. Missing protection in storage room. Several areas where penetration through sheet rock need to be sealed. Talked regarding modular units needing engineer letter to approve the setting. | DAN | DAN | | BSP | P | 5250111 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 07/08/2016 | Girls shower wall framing and bench room G106 | DAN | DAN | | BFR | P | 5241136 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 07/06/2016 | hard lid framing room B223. PE type walls for jamb. Still need to see framing area G. | DAN | DAN | | BFR | P | 5238753 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/27/2016 | Lower level108, Area "B". Storage rooms B131 and B132 to be PB walls to deck. PE amd PF wall types on class rooms. PH type of wall to deck on with rock on both sides to seperate mechanical room. need floor penetration sealed for cooler pipes north end Room B132. | DAN | DAN | | BFR | P | 5232093 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/23/2016 | Area "G" CMU started girls shower room. Talked about accessibility to transfer showers. PN wall type shows CMU to roof deck, need new detail shows to existing roof joists. Area "K" ; rooms K105, K106 PO wall types framing OK. K102 PC wall type framing OK. Need wall framing detail for K115, K103B. | DAN | DAN | | BFR | P | 5229243 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/21/2016 | Area "B" level 121. Framing ; Line B-2 to B-1, grid B-D to B-B office wall framing Wall types PE, PB and PD OK. Framing Line B-6 through B-9 and grid B-A to B-D OK; Talked with Killen regarding floor penetration protection for drains and ducts. | DAN | DAN | | BFR | P | 5227027 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/17/2016 | Framing for area B level 121 / Need PB wall at east side to go all the way to deck / Need to complete partition walls on east side / Need all door frames installed / Need wall types for chase on east side / Still need to inspect PO walls for chase on west side / All other framing OK / Need all MEP's completed | NICK | NICK | | BFR | P | 5225667 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/09/2016 | Grid line B-E, Lines B-1 through B-8. Will require Architect to identify the wall type to be. The wall type is not part of the approved plans. | DAN | DAN | | BFR | P | 5218674 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 06/08/2016 | Walked with Rob. to be called in tomorrow for wall detail framing. | DAN | DAN | | BFR | P | 5218112 |
US ENGINEERING COMPANY | H= | C | 09/22/2016 | CORRECTIONS MADE.. | LUKE | LUKE | | H= | C | 5299705 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 09/22/2016 | CORRECTION MADE | LUKE | LUKE | | H= | C | 5299584 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 08/29/2016 | TEST AND BALANCE REPORT RECEIVED. STILL NEED TO SEE PLUMBING VENT MOVED AWAY FROM MAKE UP AIR HOOD. | LUKE | LUKE | | H= | P | 5279929 |
US ENGINEERING COMPANY | H= | P | 08/03/2016 | NEED TO MOVE VENTS ON ROOF 10' AWAY OR 3' ABOVE FRESH AIR INTAKE HOOD. NOTE: TEST AND BALANCE REPORT IS THE ONLY ITEM LEFT. | LUKE | LUKE | | H= | P | 5260725 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 08/03/2016 | NEED TO MOVE VENTS ON ROOF 10' OR 3' AWAY FROM FRESH AIR INTAKE HOOD. NOTE: TEST AND BALANCE REPORT IS THE ONLY ITEM LEFT.... | LUKE | LUKE | | H= | P | 5260719 |
US ENGINEERING COMPANY | HD | P | 07/27/2016 | ABOVE CEILING OK. FLEX AND DIFFUSERS ARE INSTALLED. | LUKE | LUKE | | HD | P | 5255530 |
US ENGINEERING COMPANY | HD | P | 07/21/2016 | (B) BUILDING FIRST AND SECOND FLOOR ABOVE CEILING OK.. FLEX AND DIFFUSERS ARE INSTALLED.. | LUKE | LUKE | | HD | P | 5250856 |
US ENGINEERING COMPANY | H16 | C | 07/21/2016 | KITCHEN AREA BUILDING (E) 2 TYPE ONE HOODS HAVE A BIG GAP WHERE HOOD CONNECT AND BEHIND THE HOODS I CAN SEE SHEET ROCK. NEED TO PROTECT WALL... | LUKE | LUKE | | H16 | C | 5250855 |
US ENGINEERING COMPANY | HRP | C | 07/14/2016 | 300 LB AIR TEST GOOD ON CRAC UNIT 8- 9- 10. OK TO WRAP. LINES ARE RAN FROM OUTDOOR UNIT TO INDOOR UNIT.. | LUKE | LUKE | | HRP | C | 5245199 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/11/2016 | 2ND FLOOR OK FOR INSULATION. UPPER MECHANICAL ROOM OK FOR HEATING PIPING AT 4 VAV'S TO BE INSULATED | JON | JON | | HWP | P | 5242421 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/08/2016 | 1ST FLOOR SUPPLY AND RETURN HOT WATER AND CHILLED WATER PIPING OK TO INSULATE | JON | JON | | HWP | P | 5240803 |
US ENGINEERING COMPANY | HD | P | 07/07/2016 | OK FOR WRAP IN BASEMENT ON OUTSIDE AIR SUPPLY AND RETURN DUCTS. | JON | JON | | HD | P | 5239911 |
US ENGINEERING COMPANY | HD | P | 07/06/2016 | RBD IS REVIEWING THE ARCHITECTURAL DETAIL FOR THE FIRE DAMPERS FOR THE FIREWALL BETWEEN A2 AND THE LINK. RBD WILL MAKE CONTACT WITH THE CONTRACTOR AFTER THE REVIEW | JON | JON | | HD | P | 5238006 |
US ENGINEERING COMPANY | HD | P | 06/30/2016 | THE FOLLOWING AREAS ABOVE CEILING OK - LINK LOWER LEVEL- LINK 2ND FLOOR VAV AND SA DUCT WORK - LINK AREA RESTROOM EXHAUST HARD LIDS - AREA B LOWER LEVEL - NEED KITCHEN RANGE HOOD EXHAUST SLEEVED AT LOWER LEVEL - AHU 9 MECHROOM - BUILDING K RESTROOM HARD LIDS - EX[POSE ALL FRAMING AT LINK FIRE DAMPERS AND SUPPLY ENGINEER DETAIL ON HOW DAMPERS WILL BE SUPPORTED | JERRYF | JERRYF | | HD | P | 5235091 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 06/28/2016 | THE FOLLOWING IS COMPLETE - ALL VAV PIPING IN AREA B PIPING AND PRESSURE TEST OK - AREA K118.6 PRESSURE TEST AND PIPING OK | JERRYF | JERRYF | | HWP | P | 5233068 |
US ENGINEERING COMPANY | HD | P | 06/28/2016 | BUILDING B 2ND FLOOR MECHROOM AHU'S 12 AND 13 DUCT MAINS OK ON PAGE 3M1.12. NEED TO SLEEVE DRYER DUCT IN RETURN AIR PLENUM. | JERRYF | JERRYF | | HD | P | 5233566 |
US ENGINEERING COMPANY | HD | P | 06/23/2016 | AREA B 2ND FLOOR FROM GRID LINE B-E TO MATCH LINE 1M.4 - STILL NEED DRYER VENT AND CRAC UNIT - AREA B 2ND FLOOR ABOVE CEILING OK | JERRYF | JERRYF | | HD | P | 5229537 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 06/23/2016 | UNDER GROUND CHILLED AND HOT WATER THERMOCORE TO KIVA - PRESSURE TEST AND PIPING OK | JERRYF | JERRYF | | HWP | P | 5229512 |
US ENGINEERING COMPANY | HD | P | 05/19/2016 | INSPECTED 5-19-16 WRONG PERMIT NUMBER WAS CALLED IN. OK TO WRAP ROOF TOP DUCT FOR 2 UNITS BUILDING H. | JON | JON | | HD | P | 5233558 |