REDROCK CUSTOM HOMES LLP | B= | C | 01/26/2018 | received ES report for spray foam insulation / all items corrected | LONNYS | LONNYS | | B= | C | 5749254 |
REDROCK CUSTOM HOMES LLP | B= | P | 01/24/2018 | complete gutters and downspouts / pack drywall mud around spigot in garage / / hand rails need finger gooves both sides and must return to wall top and bottom / provide 3 landing/ level ground at bottom of all exterior stairs / provide es report for spray foam insulation / fire protect spray foam in mech room -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | BOBF | BOBF | | B= | P | 5746860 |
REDROCK CUSTOM HOMES LLP | BSP | P | 01/09/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: FLOOR PLAN REVISIONS | JUSTINC | JUSTINC | | BSP | P | 5732500 |
REDROCK CUSTOM HOMES LLP | BSP | T | 01/08/2018 | PAID (REC#1477005) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: REVISED FLOOR PLAN AND EXTERIOR | SHELLEY | SHELLEY | | BSP | T | 5731030 |
REDROCK CUSTOM HOMES LLP | BFN | C | 01/04/2018 | ufer observation letter on file | BRIANB | BRIANB | | BFN | C | 5728410 |
REDROCK CUSTOM HOMES LLP | BIN | P | 11/07/2017 | pending completed frame inspection and foundation inspection / by final need to provide letter for foam insulation installed at walls and lid / batt insulation okay / fire blocking okay / note - met with Mitch from Red Rock custom homes - also will need to revise plan to reflect exposed shipping container exterior in lieu of siding and provide flashing details | BRIANB | BRIANB | | BIN | P | 5678951 |
REDROCK CUSTOM HOMES LLP | BFR | P | 10/23/2017 | pending observation letter for eufer rod to complete foundation inspection / check firestopping at insulation inspection / plan splice for floor layout changes to be completed by final / stamped details for structural modifications at north exterior wall in master bedroom received / trusses and non load bearing wall framing okay / observation letter for structural components, welding, and bolting received onsite / walked inspection with RedRock rep Mitch | BRIANB | BRIANB | | BFR | P | 5663998 |
REDROCK CUSTOM HOMES LLP | BFR | P | 10/23/2017 | pending observation letter for eufer to complete foundation inspection / check firestopping at insulation inspection / plan splice for floor layout changes to be completed by final / stamped details for structural modifications at north exterior wall in master bedroom received / trusses and non load bearing wall framing okay / observation letter for structural components, welding, and bolting received onsite / walked inspection with RedRock rep Mitch | BRIANB | BRIANB | | BFR | P | 5664041 |
REDROCK CUSTOM HOMES LLP | BFD | C | 10/23/2017 | Engineers observation letter received onsite | BRIANB | BRIANB | | BFD | C | 5663993 |
REDROCK CUSTOM HOMES LLP | BFN | P | 10/23/2017 | pending observation letter for eufer / Engineers observation letter received onsite / Foundation design on file / Soils report on file / 3500 psf / habitable drain / drain daylight to south west | BRIANB | BRIANB | | BFN | P | 5663992 |
REDROCK CUSTOM HOMES LLP | BFT | C | 10/23/2017 | Engineers observation letter received onsite | BRIANB | BRIANB | | BFT | C | 5663985 |
REDROCK CUSTOM HOMES LLP | BFT | P | 05/26/2017 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFT | P | 5517972 |
REDROCK CUSTOM HOMES LLP | BFD | P | 05/26/2017 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFD | P | 5517973 |
REDROCK CUSTOM HOMES LLP | BFN | P | 05/26/2017 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFN | P | 5517971 |
REDROCK CUSTOM HOMES LLP | BE | L | 05/26/2017 | Renewed at 5/26/2017 8:31:44 AM | JANE | JANE | | BE | L | 5517969 |
REDROCK CUSTOM HOMES LLP | BFT | R | 11/02/2016 | footing forms measure 22" and 23" in width where approved design requires 24" and footing forms measure 24" in width where approved design requires 26" / reinforcing at buttress wall footings are installed 12"o.c - approved design requires 8" o.c / footings for pilaster, interior 18" footing and front low garage wall not ready / okay to use engineer to do inspection if needed - will need to provide stamped observation letter from engineer / field copy of open hole onsite / 3500psf | BRIANB | BRIANB | | BFT | R | 5334674 |
CASPER ELECTRIC, INC. | E= | C | 01/16/2018 | | MATTHEW | MATTHEW | | E= | C | 5738539 |
CASPER ELECTRIC, INC. | E= | R | 01/12/2018 | install closet doors or need to correct outlets spacing in bedrooms | CRAIG | CRAIG | | E= | R | 5737520 |
CASPER ELECTRIC, INC. | E= | P | 01/10/2018 | gfci outlets in unfinished area of basement, need to hardwire oven and breaker lock, need to correct outlet spacing in bedrooms or install closet----------- no a/c | MATTHEW | MATTHEW | | E= | P | 5734167 |
CASPER ELECTRIC, INC. | ES | C | 01/10/2018 | Residential Overhead: 200 amp 3/w: new res--------------- meter set and sealed by MTVE | MATTHEW | MATTHEW | | ES | C | 5734161 |
CASPER ELECTRIC, INC. | EUG | C | 10/09/2017 | 3/w 4/0 al | CRAIG | CRAIG | | EUG | C | 5649636 |
CASPER ELECTRIC, INC. | ER | C | 10/09/2017 | no mcc 2 - 6/3 cu No Cent Vac / Non Irreversible UFER connection / Finished Basement / | CRAIG | CRAIG | | ER | C | 5649635 |
CASPER ELECTRIC, INC. | ES | P | 10/09/2017 | Residential Underground: Pre release ok / | ROB | ROB | | ES | P | 5648644 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | H= | C | 01/22/2018 | | RICKR | RICKR | | H= | C | 5744052 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | HO | C | 10/18/2017 | 10# test OK, NEEDED BY FINAL-- 2# LETTER AND STICKERS WHERE APPLICABLE. note: 1.25 main coupled to existing 1.25 main, tracer wire installed on new poly line. (2# system). | PAULO | PAULO | | HO | C | 5659344 |
HOMEOWNER | HC | C | 10/17/2017 | RELEASE METER | PAULO | PAULO | | HC | C | 5658793 |
HOMEOWNER | HRR | C | 10/17/2017 | direct vent boiler with storage tank for hot potable water , no a/c. | PAULO | PAULO | | HRR | C | 5658687 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | HWP | P | 10/03/2017 | 60# test ok to upper level home runs to mechanical room. | PAULO | PAULO | | HWP | P | 5643493 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | HI | C | 10/03/2017 | 10# test ok. note: 1" main at 30' to boiler, range, dryer and BBQ. | PAULO | PAULO | | HI | C | 5643487 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | HWP | P | 06/22/2017 | 60# test ok to all zone manifolds, insulation board in garage installed. NEEDED BY FINAL-- TEST ON HOME RUN RADIANT TUBING FROM UPPER LEVEL. | PAULO | PAULO | | HWP | P | 5543709 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | P= | C | 01/22/2018 | note: potable water certification in images | JOSEPHD | JOSEPHD | | P= | C | 5743983 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | P= | P | 01/19/2018 | potable water certification in images | JOSEPHD | JOSEPHD | | P= | P | 5742196 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | PTO | C | 10/04/2017 | aav powder bath lav, kitchen sink, washer box/laundry sink and mech. room floor drain | TED | TED | | PTO | C | 5644880 |
HOMEOWNER | PWO | C | 09/26/2017 | need certificate of potable ware by final, yard hydrant backflow protected | TED | TED | | PWO | C | 5637555 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | PB | C | 06/01/2017 | ok.No water in at this point. | CRADE | CRADE | | PB | C | 5522968 |