BRENNAN DOWNEY, INC. | B= | C | 11/02/2017 | all items corrected | NATHAN | NATHAN | | B= | C | 5674623 |
BRENNAN DOWNEY, INC. | B= | R | 10/17/2017 | need vertical grab bars at both restrooms, lever action knobs on interior doors, lip at bottom of ramp to high, need signage over all exterior doors, missing handrails throughout all stairs and ramp at exterior. need fire final | NATHAN | NATHAN | | B= | R | 5657763 |
BRENNAN DOWNEY, INC. | BE | L | 10/09/2017 | Renewed online for 1/2 Fee at 10/9/2017 6:44:06 PM (RECEIPT #: 1458146) | WEBSITE | WEBSITE | | BE | L | 5649676 |
BRENNAN DOWNEY, INC. | BFR | P | 04/10/2017 | with completed required inspections frame okay | NATHAN | NATHAN | | BFR | P | 5470167 |
PARAMOUNT HEATING AND COOLING, INC. | BSP | T | 04/04/2017 | PAID (REC#1414490): PLAN SPLICE FEE: $50 by: DALEH for Mechanical | DALEH | DALEH | | BSP | T | 5464542 |
PARAMOUNT HEATING AND COOLING, INC. | BSP | T | 03/23/2017 | PAID (REC#1411964): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical | JUSTINC | JUSTINC | | BSP | T | 5453674 |
BRENNAN DOWNEY, INC. | BFT | P | 11/17/2016 | Eng letter on file stating no re bar required for piers / 2 piers for ramp OK, plans call for 6 at ramp | NICK | NICK | | BFT | P | 5347501 |
BRENNAN DOWNEY, INC. | BFR | P | 11/17/2016 | Eng letter on file to change deck joist to 2x8 / Deck frame OK / Still need to inspect ramp and interior remodel frame | NICK | NICK | | BFR | P | 5347500 |
BRENNAN DOWNEY, INC. | BFT | P | 11/10/2016 | exterior deck piers depth and dia OK; plans require steel reinforcement but no detail. Need letter to delete steel or detail on required steel. | DAN | DAN | | BFT | P | 5341433 |
BOULTON ELECTRICAL SERVICES | E= | C | 08/28/2017 | note ---50 amp ac--ok | BRIAN | BRIAN | | E= | C | 5608436 |
BOULTON ELECTRICAL SERVICES | ER | C | 02/28/2017 | | BRIAN | BRIAN | | ER | C | 5427075 |
BOULTON ELECTRICAL SERVICES | ER | P | 02/27/2017 | MAIN FLOOR AND 2ND FLOOR --OK -------BASEMENT NEED STAND OFF STRAPS AND NAIL PLATES---MOVE 1 OUTLET OUT INTO NEW WALL--- | BRIAN | BRIAN | | ER | P | 5425498 |
PARAMOUNT HEATING AND COOLING, INC. | H= | C | 10/02/2017 | TEST AND BALANCE REPORT RECEIVED . | LIDO | LIDO | | H= | C | 5641663 |
PARAMOUNT HEATING AND COOLING, INC. | H= | P | 09/26/2017 | BALANCE REPORT ON JOB SITE WAS INCORRECT FOR OUTSIDE AIR. MORE THAN 200 CFM SHORT. REST OK | JON | JON | | H= | P | 5637528 |
PARAMOUNT HEATING AND COOLING, INC. | H= | P | 08/08/2017 | NEED THE FOLLOWING - TAB REPORT - MISSING SUPPLY GRILLES IN ROOM 211 - 302 - 308 - UNDER CUT ALL DOORS FOR RA PATH PER PLAN - SECURE FURNACE FLUE TO FURNACE - REST OK | JERRYF | JERRYF | | H= | P | 5589173 |
PARAMOUNT HEATING AND COOLING, INC. | HD | P | 04/05/2017 | ABOVE CEILING OK ON ALL FLOORS - STILL NEED ALL MECHROOM COMPLETED AT FUTURE INSPECTION VERIFY ALL ZONE AND OSA AIR DAMPERS PER PLAN / CO2 SENSOR - CONTRACTOR TO SUPPLY PICTURE OF RETURN AIR PATCH IN DUCT WORK | JERRYF | JERRYF | | HD | P | 5465327 |
PARAMOUNT HEATING AND COOLING, INC. | HD | T | 04/03/2017 | PAID (REC#1414501): PLAN DOES NOT MATCH INSTALLED SYSTEM - PLAN CALLS FOR 2 FURNACES WITH COMMON RETURN HAS 1 INSTALLED - DUCT SIZING DOES NOT MATCH IN MECHROOM - NEED ALL RETURNS ON MAIN FLOOR CUT INTO DUCT AND HOLE PATCHED NEXT TO RA DUCT - NEED OSA DAMPERS INSTALLED - STOPPED INSPECTION - MAY BE MORE - CONTRACTOR TO CALL INSPECTION WHEN ALL CORRECTIONS ARE MADE | JERRYF | JERRYF | | HD | T | 5463285 |
PARAMOUNT HEATING AND COOLING, INC. | HD | P | 03/31/2017 | NEED THE FOLLOWING IS BASEMENT - COMPLETE TIES IN AT FURNACE - TIE IN VENTILATION AIR - 14 x 14 RETURN IN ROOM 311 - SUPPLY IN 307 - PAN OFF RETURNS IN BASEMENT CEILING TO ISOLATE FROM LIGHTS AND WIRING - NOTES: 1ST AND 2ND FLOOR OK | JERRYF | JERRYF | | HD | P | 5461757 |
PARAMOUNT HEATING AND COOLING, INC. | HD | R | 02/24/2017 | STOPPED INSPECTION - PLANS DO NOT MATCH INSTALLED SYSTEM - RE INSPECT ALL | JERRYF | JERRYF | | HD | R | 5424612 |
R AND D PLUMBING | P= | C | 10/16/2017 | corrections made. | TAYLOR | TAYLOR | | P= | C | 5656841 |
R AND D PLUMBING | P= | P | 09/19/2017 | install S2, need 16 - 18 inches from side wall to center of toilet at restroom 210, break room exceeds 34 inches in height, need 60 inches from wall to edge of sink at restroom 210, rest ok. | TAYLOR | TAYLOR | | P= | P | 5630305 |
R AND D PLUMBING | PE | C | 08/23/2017 | | CHERYL | CHERYL | | PE | C | 5604015 |
R AND D PLUMBING | PTO | C | 02/28/2017 | correction made. | TAYLOR | TAYLOR | | PTO | C | 5427629 |
R AND D PLUMBING | PTO | P | 02/27/2017 | mop sink drains need to connect to 3 drain, rest ok, aav's at both break room sinks on main floor by final. | TAYLOR | TAYLOR | | PTO | P | 5425553 |