CRYSTAL ROSE CONSTRUCTION, LLC | B= | C | 08/30/2017 | insignia # 32023 | SCOTTS | SCOTTS | | B= | C | 5611545 |
CRYSTAL ROSE CONSTRUCTION, LLC | B= | P | 08/28/2017 | post address-- provide landing at bottom of stairs on side door steps -- provide egress ladder in basement bedroom -- serial #16-M33221 -- Schedule a new Building Final when above items are complete. | SCOTTS | SCOTTS | | B= | P | 5608673 |
CRYSTAL ROSE CONSTRUCTION, LLC | B= | R | 08/14/2017 | attach State licensed setter to permit and recall final | SCOTTS | SCOTTS | | B= | R | 5594636 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFR | C | 04/04/2017 | | SCOTTS | SCOTTS | | BFR | C | 5464296 |
CRYSTAL ROSE CONSTRUCTION, LLC | BIN | C | 04/04/2017 | | SCOTTS | SCOTTS | | BIN | C | 5464280 |
CRYSTAL ROSE CONSTRUCTION, LLC | BIN | R | 03/31/2017 | complete BFR | SCOTTS | SCOTTS | | BIN | R | 5461263 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFR | R | 03/31/2017 | stair ledger/stairs incomplete -- missing anchor bolts in garage within 12" of plate break at man door | SCOTTS | SCOTTS | | BFR | R | 5461256 |
CRYSTAL ROSE CONSTRUCTION, LLC | BIN | P | 03/28/2017 | complete BFR -- basement insulation ok | SCOTTS | SCOTTS | | BIN | P | 5457698 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFR | P | 03/28/2017 | partial frame inspection for basement -- still need to see stairs installed and garage framing -- rest ok | SCOTTS | SCOTTS | | BFR | P | 5457692 |
CRYSTAL ROSE CONSTRUCTION, LLC | BLA | C | 03/23/2017 | | SCOTTS | SCOTTS | | BLA | C | 5453810 |
CRYSTAL ROSE CONSTRUCTION, LLC | BSP | T | 03/20/2017 | PAID (REC#1411497) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised floor plan and hvac equipment cert. | JUSTINC | JUSTINC | | BSP | T | 5445826 |
CRYSTAL ROSE CONSTRUCTION, LLC | BSP | T | 03/17/2017 | PAID (REC#1410802): PLAN SPLICE FEE: $50 by: DANM for Construction: Revisions to basement floor plan | DANM | DANM | | BSP | T | 5444589 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFN | C | 03/16/2017 | engineering on file -- eufer noted | SCOTTS | SCOTTS | | BFN | C | 5442846 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFT | C | 03/16/2017 | engineering on file | SCOTTS | SCOTTS | | BFT | C | 5442845 |
CRYSTAL ROSE CONSTRUCTION, LLC | BTD | C | 03/16/2017 | | SCOTTS | SCOTTS | | BTD | C | 5442836 |
CRYSTAL ROSE CONSTRUCTION, LLC | BTD | P | 02/17/2017 | complete BFT/BFN -- foundation plan already on file -- pin steel column on north end -- marriage line ok | SCOTTS | SCOTTS | | BTD | P | 5418214 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFD | P | 02/15/2017 | complete BFT/BFN | SCOTTS | SCOTTS | | BFD | P | 5415520 |
CRYSTAL ROSE CONSTRUCTION, LLC | BFD | R | 02/14/2017 | complete BFT/BFN -- provide foundation design/soils report/open hole/engineering observations on footing/foundation -- no damp proofing in place | SCOTTS | SCOTTS | | BFD | R | 5414518 |
BOULTON ELECTRICAL SERVICES | E= | C | 08/11/2017 | | MATTHEW | MATTHEW | | E= | C | 5593180 |
BOULTON ELECTRICAL SERVICES | E= | R | 08/10/2017 | Three way to basement still not working properly. -------- Still need to adjust Dead - Front at upstairs panel. ---------- Trip fee if not 100 % on next trip. | JOSEPH | JOSEPH | | E= | R | 5591890 |
BOULTON ELECTRICAL SERVICES | ES | C | 07/26/2017 | Residential Overhead: 200 amp 3w new res meter is in need reseal | JOSEPH | JOSEPH | | ES | C | 5576226 |
BOULTON ELECTRICAL SERVICES | E= | R | 07/26/2017 | Backfill trench containing feeders from utility pole. ----------- Bathroom receptacles have no power. ----------- Upstairs bathroom in new home is missing bathroom receptacle (may be behind mirror). -----Blocking in Mech room and Garage. ----- Adjust dead front at home. -------- Need Dedicated circuit for sump pump. ----------------- Install lamp in stairwell for 3 way inspection. | JOSEPH | JOSEPH | | E= | R | 5576217 |
BOULTON ELECTRICAL SERVICES | ES | C | 04/05/2017 | Residential Overhead: 200 amp 3w service. ------ Contractor will co-ordinate with utility to re-locate meter from existing location to different utility pole. -------- Notes; UFER is not ir. ------- Existing main panel at utility pole is to be removed. | JOSEPH | JOSEPH | | ES | C | 5465420 |
BOULTON ELECTRICAL SERVICES | ES | R | 03/21/2017 | At sub inside home -------- use connectors for romex going to basement.--------- Feeders from exterior panel to interior panel do not appear to be rated for 200 amps. --------- Did not see ufer connection at home. ----------Remember all grounding electrode conductors need to be run to the first sub panel on the exterior of the home. | JOSEPH | JOSEPH | | ES | R | 5446640 |
BOULTON ELECTRICAL SERVICES | ER | C | 03/21/2017 | | JOSEPH | JOSEPH | | ER | C | 5446629 |
BOULTON ELECTRICAL SERVICES | EUG | C | 03/20/2017 | 4 wire | JOSEPH | JOSEPH | | EUG | C | 5445432 |
BOULTON ELECTRICAL SERVICES | ER | R | 03/20/2017 | Can't drill or nail into plastic boxes. ------------- Cables in foam wall need to be secured at least 1 - 1/4 inch back from edge of foam. (Could use two nail set at an angle). --------- May need one additional receptacle by sink (I marked stud). ---------- Garage ok | JOSEPH | JOSEPH | | ER | R | 5445421 |
DESIGNED FOR COMFORT INC | H= | C | 08/10/2017 | corrections made. note: finished basement, direct vent furnace, 6" outside air to return, direct vent tank less water heater, no a/c. | PAULO | PAULO | | H= | C | 5591345 |
DESIGNED FOR COMFORT INC | H= | P | 07/26/2017 | need proper R.A. path to both basement bedrooms. rest ok. note: finished basement, direct vent furnace, 6" outside air to return, direct vent tank less water heater, no a/c. | PAULO | PAULO | | H= | P | 5576257 |
DESIGNED FOR COMFORT INC | HI | C | 03/23/2017 | CORRECTION MADE.note: 1" main at 60' to furnace, tank less water heater and range. | LIDO | LIDO | | HI | C | 5454540 |
DESIGNED FOR COMFORT INC | HI | P | 03/22/2017 | JON B REMOVED TRIP FEE...3-22-17 not ready. can not reduce gas line before T. note: 1" main at 60' to furnace, tank less water heater and range. | PAULO | PAULO | | HI | P | 5452311 |
DESIGNED FOR COMFORT INC | HI+ | R | 03/20/2017 | added btu load from range and distance will not carry on 3/4" main. added 1/2" blk at 60' to new range. note: 3/4" main at 60' to tank less water heater (199,00k), furnace (80k) and range. | PAULO | PAULO | | HI+ | R | 5445358 |
DESIGNED FOR COMFORT INC | HC | C | 03/16/2017 | RELEASE METER | PAULO | PAULO | | HC | C | 5442731 |
DESIGNED FOR COMFORT INC | HRR | C | 03/16/2017 | finished basement, direct vent furnace, 6" outside air to return, direct vent tank less water heater, no a/c. | PAULO | PAULO | | HRR | C | 5442723 |
WESTMAN HEATING AND REPAIR LLC. | HO | C | 03/15/2017 | 60# test ok. note: 1/2" poly at 100' to home, tracer wire installed. L.P. | PAULO | PAULO | | HO | C | 5441292 |
DESIGNED FOR COMFORT INC | HI | P | 03/08/2017 | 10# test ok. note: 3/4" main at 20' to furnace and water heater. L.P. | PAULO | PAULO | | HI | P | 5434424 |
WOLVERINE CONSTRUCTION LLC | P= | C | 08/10/2017 | correction made, certificate of potable water to scanning | TED | TED | | P= | C | 5592614 |
WOLVERINE CONSTRUCTION LLC | P= | P | 07/26/2017 | complete basement bathroom ( next to stairs) lav install, cap open bar sink rough drain, need certificate of potable water, note: finished basement | TED | TED | | P= | P | 5576810 |
WOLVERINE CONSTRUCTION LLC | PTO | C | 03/16/2017 | .Note:basement bar aav,water heater room floor drain aav in same room,certification for potable water at final,tank less combustible sealed water heater rest ok. | CRADE | CRADE | | PTO | C | 5442611 |
WOLVERINE CONSTRUCTION LLC | PB | C | 02/15/2017 | DWV IN BASEMENT , ON TEST BASEMENT TO PUMP ONLY | GABE | GABE | | PB | C | 5415878 |