GUARINO CONSTRUCTION, LLC | B= | C | 09/14/2018 | items corrected / finished basement - no stairs | LONNYS | LONNYS | | B= | C | 5965311 |
GUARINO CONSTRUCTION, LLC | B= | R | 08/30/2018 | install address # on house / need handrail at garage / handrail tight to wood floor to basement | DALE | DALE | | B= | R | 5951737 |
GUARINO CONSTRUCTION, LLC | BIN | C | 03/26/2018 | | DALE | DALE | | BIN | C | 5799239 |
GUARINO CONSTRUCTION, LLC | BFR | C | 03/26/2018 | eng. for headers and T studs received | DALE | DALE | | BFR | C | 5799236 |
GUARINO CONSTRUCTION, LLC | BFD | C | 03/26/2018 | soils received | DALE | DALE | | BFD | C | 5799235 |
GUARINO CONSTRUCTION, LLC | BFN | C | 03/26/2018 | soils received | DALE | DALE | | BFN | C | 5799230 |
GUARINO CONSTRUCTION, LLC | BFR | P | 03/20/2018 | need sois report to complete bfn bfd / 3T at lvl basement to patio / plans call for lintels at basement bedroom, east side / foam and firestop / looked at sip panels and post and beam construction / ok to insulate | DALE | DALE | | BFR | P | 5794112 |
GUARINO CONSTRUCTION, LLC | BIN | P | 03/19/2018 | Qualified third party energy inspection documentation must be presented at time of final building (B=) inspection | INTERNET | INTERNET | | BIN | P | 5792899 |
GUARINO CONSTRUCTION, LLC | BSP | P | 11/30/2017 | Under slab insulation inspection- Observed 2" R10 rigid insulation board to basement floor | SHAUN | SHAUN | | BSP | P | 5698670 |
GUARINO CONSTRUCTION, LLC | BLA | C | 11/17/2017 | | BRIANB | BRIANB | | BLA | C | 5688534 |
GUARINO CONSTRUCTION, LLC | BLA | R | 11/15/2017 | incorrect inspection request / BSP added for portal wall inspection | LONNYS | LONNYS | | BLA | R | 5686005 |
GUARINO CONSTRUCTION, LLC | BSP | P | 11/15/2017 | portal wall at 3rd northeast garage door OK | LONNYS | LONNYS | | BSP | P | 5686002 |
GUARINO CONSTRUCTION, LLC | BFD | R | 11/15/2017 | based on dated referenced in observation letter for foundation footings home was started prior to permit / please contact chief building inspector John Welton / Engineers observation Letter for drain on file | BRIANB | BRIANB | | BFD | R | 5685652 |
GUARINO CONSTRUCTION, LLC | BFN | P | 11/15/2017 | need copy of soils letter / Engineers observation Letter on file / Eufer OK / Foundation design on file / open hole letter on file / 5000 psf / habitable drain / exterior pier observation letter on file | BRIANB | BRIANB | | BFN | P | 5685650 |
GUARINO CONSTRUCTION, LLC | BFT | C | 11/15/2017 | Engineers observation Letter on file | BRIANB | BRIANB | | BFT | C | 5685646 |
GUARINO CONSTRUCTION, LLC | BLA | R | 11/13/2017 | lath installed prior to garage portal inspection - see portal wall details on sheet S4 of approved design / need to expose garage portal wall framing for inspection prior to lath / note - need all paper work to complete foundation inspections | BRIANB | BRIANB | | BLA | R | 5682480 |
GUARINO CONSTRUCTION, LLC | BE | L | 09/11/2017 | Renewed at 9/11/2017 1:09:50 PM | NELIDA | NELIDA | | BE | L | 5621862 |
GUARINO CONSTRUCTION, LLC | BFI | P | 03/13/2017 | AUTHORIZED INSPECTION BY ENGINEER | NELIDA | NELIDA | NELIDA | BFI | P | 5438520 |
GUARINO CONSTRUCTION, LLC | BFD | P | 03/13/2017 | AUTHORIZED INSPECTION BY ENGINEER | NELIDA | NELIDA | NELIDA | BFD | P | 5438519 |
GUARINO CONSTRUCTION, LLC | BFT | P | 03/13/2017 | AUTHORIZED INSPECTION BY ENGINEER | NELIDA | NELIDA | NELIDA | BFT | P | 5438518 |
GUARINO CONSTRUCTION, LLC | BFN | P | 03/13/2017 | AUTHORIZED INSPECTION BY ENGINEER | NELIDA | NELIDA | NELIDA | BFN | P | 5438517 |
MESA ELECTRIC, LLC. | E= | C | 08/10/2018 | both ac' s ok 20 amp / 25 amp | CRAIG | CRAIG | | E= | C | 5930754 |
MESA ELECTRIC, LLC. | EP | C | 08/09/2018 | 100 amp 4/w to sub panel ok | CRAIG | CRAIG | | EP | C | 5929782 |
MESA ELECTRIC, LLC. | E= | R | 08/09/2018 | label all ac' s inside and out ---------- afci / gfi all disposal plugs --------- install exterior gfi plug back of garage deck ---------- hot tub pre wire ------------- note: pendant lights above master bath tub not installed at this time | CRAIG | CRAIG | | E= | R | 5929781 |
MESA ELECTRIC, LLC. | ES | C | 03/13/2018 | Residential Underground: 200 - amp 3 Wire new service, ok to seal meter / | CRAIG | CRAIG | | ES | C | 5787826 |
MESA ELECTRIC, LLC. | ER | C | 03/13/2018 | no mcc 4 - 10/3 4 - 6/3 cu 4/w #2 al to sub panel 4/w 4/0 al to sub panel No Cent Vac / Non Irreversible UFER connection in bedroom closet in basement / Finished Basement / | CRAIG | CRAIG | | ER | C | 5787822 |
MESA ELECTRIC, LLC. | EUG | C | 09/29/2017 | 3/w 4/0 al last 20 ' to house is new wire | CRAIG | CRAIG | | EUG | C | 5641157 |
PREMIER MECHANICAL | H= | C | 08/29/2018 | COIL CHANGE LETTER ATTACHED TO IMAGES | BENH | BENH | | H= | C | 5949055 |
PREMIER MECHANICAL | H= | P | 08/07/2018 | WRONG COIL STILL IN PLACE,CONTRACTOR STATES THAT COIL MANUFACTURER CHANGED DESIGNATION FOR COIL. WILL NEED LETTER FROM THEM TO CONFIRM THIS. NOTE: FINISHED BASEMENT, DIRECT VENT BOILER, 2 FULL A/C'S (AHU-1 &2) | BILLS | BILLS | | H= | P | 5926904 |
PREMIER MECHANICAL | HC | C | 03/15/2018 | RELEASE METER | BENH | BENH | | HC | C | 5790464 |
PREMIER MECHANICAL | HRR | C | 03/15/2018 | COIL # 2 MODEL NUMBER DOESN'T MATCH WHAT IS ON DUCT DESIGN, WILL NEED REVISED APPROVED DUCT DESIGN OR THE CORRECT COIL INSTALLED NOTES: FINISHED BASEMENT, DIRECT VENT BOILER, AHU1 AND AHU 2, A/C ROUGH COIL AND LINE SET | BENH | BENH | | HRR | C | 5790463 |
PREMIER MECHANICAL | HRR | L | 02/06/2018 | Took inspection from inspector that went home sick. Unable to pull up plans. Please re schedule | JEFFL | JEFFL | | HRR | L | 5758718 |
PREMIER MECHANICAL | HI | C | 02/05/2018 | 10# test ok. note: 1 1/4" main at 90' to 1- boiler, 1- range and 1- 1" future stub out at upper level on south side of home. | PAULO | PAULO | | HI | C | 5757556 |
PREMIER MECHANICAL | HRR | R | 02/05/2018 | not ready. too many to list. need revised pints (spliced) for removal of outside air to both returns, addition of basement laundry,duct designs to match installation of all ducting and equipment list to match coil, air handlers and boiler to plans. re inspect all. | PAULO | PAULO | | HRR | R | 5757551 |
PREMIER MECHANICAL | HWP | C | 11/30/2017 | 2- 100 LB TEST OK, OK TO POUR FLOOR IN BASEMENT | BENH | BENH | | HWP | C | 5699122 |
CASCADE PLUMBING & HEATING | P= | C | 08/16/2018 | potable water certification sent to scanning, by-pass removed see images | JOSEPHD | JOSEPHD | | P= | C | 5935844 |
CASCADE PLUMBING & HEATING | P= | P | 08/07/2018 | need potable water certification, cant have by pass at boiler that by passes back flow can submit photo of fix, rest ok note: finished basement, pvb installed | JOSEPHD | JOSEPHD | | P= | P | 5926180 |
CASCADE PLUMBING & HEATING | PTO | C | 03/15/2018 | note: tempering valve at hwh, at final check connection to boiler for backflow and the quick fill is run before backflow needs to be after, need certification of potable water by final | JOSEPHD | JOSEPHD | | PTO | C | 5790100 |
CASCADE PLUMBING & HEATING | PTO | P | 02/06/2018 | need to see finished water piping, and master bathroom dwv completed, need strapping to 2" kitchen sink line, rest of dwv on test and ok, note: finished basement, aav @ both master lavs & both basement lavs in back LH corner, vtr(3) | JOSEPHD | JOSEPHD | | PTO | P | 5758030 |
CASCADE PLUMBING & HEATING | PB | C | 11/06/2017 | water under footer, cert of potable water by final | JOSEPHD | JOSEPHD | | PB | C | 5678001 |