SWINERTON BUILDERS | B= | C | 07/07/2017 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5556661 |
SWINERTON BUILDERS | B= | P | 06/15/2017 | items from phase 1 final corrected / final for both phases OK pending all other finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), GREINER ELECTRIC, LLC Electrical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5536831 |
SWINERTON BUILDERS | B= | P | 06/08/2017 | only looked at doors between phase 1 and phase 2 - still need complete inspection on phase 2 and remaining items from phase 1 / Met with Superintendent Dave of Swinerton Builders to discuss doors from fire department inspection log. These doors are all preexisting and have not been removed or added and are not included in the scope of work for the interior remodel permit -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), GREINER ELECTRIC, LLC Electrical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5529865 |
SWINERTON BUILDERS | BSP | P | 06/05/2017 | met on site with superintendent to discuss required exiting and exit signs / currently have pre-existing doors that are swinging the wrong way on the path of egress and one door that swings the wrong way that is new/upon further review with Dane and Bert W door #23 is ok per plans other doors are referenced in the fire dept inspection logs are prexisiting and not changed out. | DANE | DANE | | BSP | P | 5525451 |
GREINER ELECTRIC, LLC. | BSP | T | 05/25/2017 | PAID (REC#1430529) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Pipe for future cooling equipment | SHELBY | SHELBY | | BSP | T | 5517730 |
HEATING & PLUMBING ENGINEERS, INC | BSP | P | 05/23/2017 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical | JUSTINC | JUSTINC | | BSP | P | 5514253 |
HEATING & PLUMBING ENGINEERS, INC | BSP | P | 05/23/2017 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical | JUSTINC | JUSTINC | | BSP | P | 5514158 |
SWINERTON BUILDERS | BSP | P | 05/16/2017 | exit sign installed OK / engineering for structure for collapsible wall received / met with superintendent to discuss need for minimum class C smoke and flame spread of wood wall feature and researched product being used and it is OK as it has a flame spread of 70 and smoke index of 200 | DANE | DANE | | BSP | P | 5507775 |
SPECIAL SYSTEMS DESIGN,LLC | BSP | P | 05/08/2017 | PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised lighting, Revised furniture feeds, Revised panel schedules. | BERTHA | BERTHA | | BSP | P | 5499028 |
SWINERTON BUILDERS | B= | P | 05/05/2017 | phase 1 only / need to add an exit sign at the northwest corner of the open office room 137 / T-stat at room 143 collaboration is above 48" / both items an be checked at final for phase 2 / all other items for phase 1 OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), GREINER ELECTRIC, LLC Electrical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Mechanical Final Inspection is not Completed yet, HEATING & PLUMBING ENGINEERS, INC Plumbing Final Inspection is not Completed yet, SPECIAL SYSTEMS DESIGN,LLC Electrical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5497628 |
SWINERTON BUILDERS | BFR | P | 04/19/2017 | framing for movable wall in conference room OK pending splicing in the stamped design change for the mounting of the track to the structure above / this will complete the framing for phase 1 pending other roughs | DANE | DANE | | BFR | P | 5480353 |
SWINERTON BUILDERS | BFR | P | 04/04/2017 | Data room walls OK / grid X ceiling at break room and collaboration OK / still need to inspect framing at movable wall at room 130 | DANE | DANE | | BFR | P | 5464438 |
SWINERTON BUILDERS | BFR | P | 03/16/2017 | interior light gauge framing at grid line 14 to 20 (south end of scope) OK pending other rough inspections / still need to inspect room 150 data room and room 130 conference room framing for movable wall / discussed accessible elements with superintendent | DANE | DANE | | BFR | P | 5443120 |
SWINERTON BUILDERS | BFR | P | 03/09/2017 | interior light gauge framing at grid lines 9 to 14 OK except at room 150 data center office and at room 130 conference room at the structure for the moving wall in center of room / break room at north end of suite is existing and only changing fixtures / discussed accessible elements with superintendent | DANE | DANE | | BFR | P | 5436394 |
GREINER ELECTRIC, LLC. | E= | C | 06/15/2017 | | BRET | BRET | | E= | C | 5537073 |
GREINER ELECTRIC, LLC. | ER | P | 05/24/2017 | above ceiling in rooms 114, and 160 ok | CRAIG | CRAIG | | ER | P | 5515363 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 05/19/2017 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 5511467 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 05/19/2017 | FIRE ALARM INSPECTION: | BRET | BRET | | ER | C | 5511462 |
GREINER ELECTRIC, LLC. | ER | P | 05/18/2017 | 104,106,107,147 ,165 ceiling 103 ok except at 3 blast damper locations. f.a ok in same area. | BRET | BRET | | ER | P | 5510464 |
GREINER ELECTRIC, LLC. | E= | P | 05/05/2017 | Phase 1 area ok. Cubicals not in Rooms 124 and 142. | ROB | ROB | | E= | P | 5497942 |
GREINER ELECTRIC, LLC. | EP | P | 05/05/2017 | Existing feeders remained--Added neutrals to to correct circuiting for handle tys. | ROB | ROB | | EP | P | 5497934 |
GREINER ELECTRIC, LLC. | ER | P | 04/19/2017 | ceilings,rms:115-119,121-123,125,140-142,150,159 | JOHNN | JOHNN | | ER | P | 5479967 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 04/19/2017 | FIRE ALARM INSPECTION: ceilings,rms:115-119,121-123,125,140-142,150,159 | JOHNN | JOHNN | | ER | P | 5479952 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 04/11/2017 | FIRE ALARM INSPECTION: 124,130 and 138. | BRET | BRET | | ER | P | 5471088 |
GREINER ELECTRIC, LLC. | ER | P | 04/11/2017 | break room 138 24x30 min access at 2 locations. | BRET | BRET | | ER | P | 5471087 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 04/10/2017 | FIRE ALARM INSPECTION: same areas as electric rough. | BRET | BRET | | ER | P | 5470012 |
GREINER ELECTRIC, LLC. | ER | P | 04/10/2017 | walls complete, suspended ceiling open office area and town hall . hard lid 143 collaboration . | BRET | BRET | | ER | P | 5469998 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 03/23/2017 | FIRE ALARM INSPECTION: walls ok except room 160 | BRET | BRET | | ER | P | 5454167 |
GREINER ELECTRIC, LLC. | ER | P | 03/23/2017 | new walls ok except data office room 160 | BRET | BRET | | ER | P | 5454145 |
GREINER ELECTRIC, LLC. | ER | P | 03/16/2017 | walls marked on plans .(blue) | BRET | BRET | | ER | P | 5443057 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 03/16/2017 | FIRE ALARM INSPECTION: same areas as electrical | BRET | BRET | | ER | P | 5443056 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 03/09/2017 | FIRE ALARM INSPECTION: wall stubs only grid line 9-13 | BRET | BRET | | ER | P | 5436113 |
GREINER ELECTRIC, LLC. | ER | P | 03/09/2017 | walls see electricians plans for locations n.e area | BRET | BRET | | ER | P | 5436101 |
GREINER ELECTRIC, LLC. | ESL | P | 03/07/2017 | 18 floor box locations ok to cover. | BRET | BRET | | ESL | P | 5433247 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 07/07/2017 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5556660 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 06/09/2017 | CHILLED WATER PIPING FOR FUTURE COOLING TOWER OK - STILL NEED TAB REPORT - ADDING CHILLED LINES TO PERMIT | JERRYF | JERRYF | | H= | P | 5530628 |
HEATING & PLUMBING ENGINEERS, INC | HWP | C | 06/09/2017 | PRESSURE TESTS OK ON 2 FUTURE CHILLED WATER LINES FOR FUTURE COOLING TOWER PER PLAN SPLICE DATED 5/23/17 - PIPING PER PLAN | JERRYF | JERRYF | | HWP | C | 5530617 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 05/30/2017 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5520091 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 05/19/2017 | PHASE 1 ABOVE CEILING OK TO WRAP - ALL SA / RA GRILLES AND FINAL CONNECTIONS OK | JERRYF | JERRYF | | HD | P | 5511606 |
HEATING & PLUMBING ENGINEERS, INC | HRP | C | 05/03/2017 | TEN 200 LB TESTS OK ON CRACS 10 THROUGH 14. FOR FINAL PERMANENTLY LABEL EQUIPMENT ON ROOF. WILL NEED TO SEE CONDENSATE DRAINS AND WHERE THEY TERMINATE. | NANCY | NANCY | | HRP | C | 5494674 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 04/26/2017 | PHASE 2. DIRTY MECHANICAL: ROUGH EXHAUST AND SUPPLY AIR TRUNK LINES AND LATERALS OK. OK TO WRAP. DATA CENTER: ROUGH SUPPLIES OK, OK TO WRAP. CLEAN MECHANICAL: ABOVE CEILING ALL OK AND COMPLETE. | NANCY | NANCY | | HD | P | 5487493 |
HEATING & PLUMBING ENGINEERS, INC | HRP | P | 04/20/2017 | AIR TEST GOOD FOR 16 CONDENSERS AND CRAC UNITS 1 THROUGH 8 IN DATA CENTER. | LUKE | LUKE | | HRP | P | 5481209 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 04/20/2017 | PHASE ONE ABOVE CEILING GOOD ALL FLEX AND DIFFUSERS ARE INSTALLED.. NOTE: WILL NEED TEST AND BALANCE REPORT. | LUKE | LUKE | | HD | P | 5481207 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 03/20/2017 | PHASE ONE DOWN TO SOUTH END OF BUILDING AND WEST FROM LAB ENTRANCE: ROUGH ABOVE CEILING OK, OK TO WRAP. WILL HIGH LIGHT PRINTS AT NEXT INSPECTION. | NANCY | NANCY | | HD | P | 5446255 |
HEATING & PLUMBING ENGINEERS, INC | HD | P | 03/10/2017 | NEED REVISED/APPROVED PRINTS DELETING FLUID COOLER, PUMP, EXPANSION TANK AND GLYCOL FEED SYSTEM. M-201: PHASE ONE ROUGH SUPPLIES ABOVE CEILING OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 5437631 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 05/22/2017 | NOTE : ALL TO PLAN , BACK FLOW INSTALLED , | GABE | GABE | | P= | C | 5513324 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 04/12/2017 | VENT , WATER TO TIE IN , RECIRC LINE IN SK2 AND SK3, ON TEST , WIL RED LINE PLANS TO SHOW PIPING LAYOUT | GABE | GABE | | PTO | P | 5473447 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/27/2017 | sk-3 ok to cover in wall dwv and water | TED | TED | | PTO | P | 5456577 |
HEATING & PLUMBING ENGINEERS, INC | PTO | L | 03/24/2017 | contractor canceled | GABE | GABE | | PTO | L | 5454649 |
HEATING & PLUMBING ENGINEERS, INC | PTO | P | 03/20/2017 | dwv and water in walls ok to cover | TED | TED | | PTO | P | 5445936 |
HEATING & PLUMBING ENGINEERS, INC | PB | C | 03/10/2017 | test and design to plan | TED | TED | | PB | C | 5437976 |