THE WRIGHT GROUP, LLC | B= | C | 09/28/2018 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5979580 |
THE WRIGHT GROUP, LLC | B= | P | 09/26/2018 | final OK pending other finals / all items corrected. Additional Inspections Required (computer generated): BRUIN ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet, PARKEY'S REFRIGERATION CO., INC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5977381 |
THE WRIGHT GROUP, LLC | B= | P | 09/24/2018 | door to laundry chute termination room door still need minimum 3/4 hour rating / still need fire caulk sprinkler line in laundry termination room / still need to splice in south canopy design change / flashing installed OK at canopy -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), BRUIN ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet, PARKEY'S REFRIGERATION CO., INC Mechanical Final Inspection is not Completed yet, THYSSENKRUPP ELEVATOR CORP. Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5974555 |
THE WRIGHT GROUP, LLC | B= | P | 09/24/2018 | Temp CO: nned finals in building, mech ( Expires: 10/24/2018 12:00:00 AM) | JANE | JANE | | B= | P | 5974549 |
THE WRIGHT GROUP, LLC | B= | P | 09/20/2018 | laundry chute termination door needs to be a 90 minute rated door and currently has no tag / need to seal penetration at fire sprinkler line at inside of termination room / still need to splice into the plans the change of the listed assemblies at the canopy on the south end of the building as was stated before that DensGlass was used when the plans called for intumescent paint / still need to install the cap flashing on the top of the canopy / Occ load signs have been installed and items at employee lounge and employee lounge restroom have been corrected / discussed need to get TCO with contractor -- Schedule a new Building Final when above items are complete. | DANE | DANE | | B= | P | 5971203 |
THE WRIGHT GROUP, LLC | B= | P | 09/19/2018 | still need to splice into plans the change to the south canopy and the changes to the laundry chute at the 1st floor / sink at employee lounge needs to be no higher than 34" to the rim of the sink or counter top whichever is higher / still missing knee protection at bathroom at employee lounge / still need to install all occupancy load signs at exercise room, meeting room, breakfast room and great room (main lobby) / engineer observations received for intumescent paint and for welding and bolting / all other items from previous inspection dated 9/12 have been corrected -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External | DANE | DANE | | B= | P | 5970232 |
THE WRIGHT GROUP, LLC | B= | P | 09/12/2018 | BUILDING FINAL RE-INSPECT -- Still need to splice in design change for front canopy and laundry chute -- Reviewed stamped detail in field, frame and drywall OK pending splice into permit -- Still need engineer letter of observation for intumenscent paint on heavy steel --3RD FLOOR - Still need to add arrow indicator on exit signs -- 2ND FLOOR - ROOM 221 - Still missing door handle -- ROOM 201 - Still missing door handle -- 1ST FLOOR - ROOM 112 - Still need door handle installed -- ROOM 104 - Still need to install door handle -- EMPLOYEE BREAK ROOM - Still have side grab bars too close to rear wall at rest room -- Missing knee protection at sink in restroom -- COMMON AREA RESTROOMS - Still have side grab bar too close to rear wall in both restrooms -- Still need occupant load signs at exercise rooms, breakfast room, great room, and meeting room -- Other items from previous inspection corrected -- Schedule a new Building Final when above items are complete. Additional Inspections Req | DAKOTAB | DAKOTAB | | B= | P | 5962621 |
THE WRIGHT GROUP, LLC | B= | P | 09/12/2018 | BUILDING FINAL NOTES FROM 9/11 -- BUILDING FINAL RE-INSPECT -- Still need to splice in design change for front canopy and laundry chute -- Reviewed stamped detail in field, frame and drywall OK pending splice into permit -- Still need engineer letter of observation for intumenscent paint on heavy steel -- 4TH FLOOR - Still need to fix holes in electrical room behind elevators - Still need to add arrow indicator at exit signs -- 3RD FLOOR - Still need to fix holes in electrical room - Still need to add arrow indicators to exit signs -- 2ND FLOOR - ROOM 221 - Still missing toilet grab bars -- ROOM 201 - Still need to install door handle -- Still need to fix holes in electrical room - Still need to add arrow indicators to exit signs -- 1ST FLOOR -- ROOM 112 - Need to install door handle -- ROOM 105 - Missing smoke seal at door -- ROOM 104 - Still need to install door handle -- EMPLOYEE BREAK ROOM -- Side grab bars installed too close to wall at rest room -- Missing knee protection at sink | DAKOTAB | DAKOTAB | | B= | P | 5962144 |
THE WRIGHT GROUP, LLC | B= | P | 09/11/2018 | BUILDING FINAL RE-INSPECT CONTINUED -- COMMON AREA RESTROOMS -- Side grab bars installed too close to wall at both restooms -- Still need occupant load signs installed at exercise room, breakfast room, great room, and meeting rooms -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, BRUIN ENTERPRISES, INC. Mechanical Final Inspection is not Completed yet, BRUIN ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet, PARKEY'S REFRIGERATION CO., INC Mechanical Final Inspection is not Completed yet, THYSSENKRUPP ELEVATOR CORP. Mechanical Final Inspection i | DAKOTAB | DAKOTAB | | B= | P | 5961602 |
THE WRIGHT GROUP, LLC | B= | P | 09/10/2018 | Still need to splice in design change at front exterior canopy and design change at laundry chute on 1st floor -- Still need stamped observation for welding and bolting of heavy steel -- Still need stamped observation for intumenscent paint at interior steel post and beam -- BUILDING FINAL ON 2ND AND 1ST FLOOR -- 2ND FLOOR - ROOM 221 -- Missing toilet grab bars -- ROOM 201 -- Need to install door handle -- ELECTRICAL ROOM -- Need to seal penetrations and repair drywall at wall -- Need to add direction arrow to exit signs -- 1ST FLOOR - ROOM 112 - Need to install door handle -- ROOM 105 - Missing smoke seal at door -- ROOM 104 - Need to install door handle -- Need occupant load signs installed at exercise room, breakfast room, great room, and meeting room -- Missing grad bars at all common area restrooms -- Missing grab bars at employee break room restroom -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External A | DAKOTAB | DAKOTAB | | B= | P | 5959928 |
THE WRIGHT GROUP, LLC | B= | P | 09/07/2018 | Still need to splice in design change at front exterior canopy and design change at laundry chute on 1st floor -- Still need stamped observation for welding and bolting of heavy steel -- Still need stamped observation for intumenscent paint at interior steel post and beam -- BUILDING FINAL ON 3RD AND 4TH FLOOR ONLY -- 4TH FLOOR - ROOM 420 - Vanity still too high in bathroom -- Vertical grab bar at water closet still too high -- ELECTRIC ROOM - Still need to fix hole in electrical room - 3RD FLOOR - ROOM 321 - Missing all grab bars at water closet - Missing knee protection at sink -- ROOM 320 - Vertical grab bar too high at control wall of bath tub -- 3RD FLOOR ELECTRICAL ROOM - Need to fix hole at walls in electric room -- Need to add arrow indicator on exit lights on 3rd floor - -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), | DAKOTAB | DAKOTAB | | B= | P | 5958663 |
THE WRIGHT GROUP, LLC | BSP | P | 09/06/2018 | Reviewed accessible elements at 2nd floor accessible room -- Still need to splice in use of densglass at assembly at exterior canopy structure -- Need stamped copy of welding and bolting cert -- Need stamped copy of for intumescent paint at interior steel post and beams | DAKOTAB | DAKOTAB | | BSP | P | 5957141 |
THE WRIGHT GROUP, LLC | BSP | R | 08/30/2018 | exterior canopy steel structure fire protection not inspected as it is to be protected with intumescent paint per plans but has dens glass on it / need to splice into the plans the design change to use dens glass assemblies at verticals and horizontals / still need to splice into the plans the change that was made at the laundry chute on the first floor / still need stamped observations for intumescent paint at interior steel posts and beams / still need stamped observations for welding and bolting of heavy gauge steel / pool on seperate permit but still need engineer observations for foundation and open hole / discussed gate hardware with superintendent | DANE | DANE | | BSP | R | 5951266 |
THE WRIGHT GROUP, LLC | BSP | R | 08/17/2018 | inspection site canceled / rooms are not ready for final inspection / need to install all smoke alarms / discussed need for plumbing electrical and mechanical finals | DANE | DANE | | BSP | R | 5937795 |
THE WRIGHT GROUP, LLC | B= | R | 08/16/2018 | 4th floor / need smoke alarms in all guest rooms / room 420 - flush handle is on wrong side of toilet - vanity is too high - vertical grab bar is too high - need knee protection - need 5' turning radius / room 408 - bath fan is not working / electric room by elevator is not ready / need to seal floor penetrations at north electric room / need to install exit sign outside of elevator lobby. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, BRUIN ENTERPRISES, INC. Mechanical Final Inspection is not Completed yet, BRUIN ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet, EMF ELECTRICAL CORPORATION Electrical Final | DANE | DANE | | B= | R | 5937068 |
THE WRIGHT GROUP, LLC | B= | P | 08/14/2018 | Field canceled via phone -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection HD= by HEALTHDEPT is not Completed yet, BRUIN ENTERPRISES, INC. Mechanical Final Inspection is not Completed yet, BRUIN ENTERPRISES, INC. Plumbing Final Inspection is not Completed yet, EMF ELECTRICAL CORPORATION Electrical Final Inspection is not Completed yet, PARKEY'S REFRIGERATION CO., INC Mechanical Final Inspection is not Completed yet, THYSSENKRUPP ELEVATOR CORP. Mechanical Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 5933029 |
THE WRIGHT GROUP, LLC | BSP | P | 07/26/2018 | line sets in elevator control room are now OK / soffits in exercise room OK / penetrations in both bathrooms ceilings in corridor outside of exercise room OK / penetrations in ceiling of mech room outside of exercise room OK | DANE | DANE | | BSP | P | 5915101 |
THE WRIGHT GROUP, LLC | BSP | P | 07/24/2018 | elevator control room 6" collar OK per EJ / need to remove the 2 AC line sets from the same enclosure as the 6" PVC as the EJ does not allow for them and listing for line sets is for one line set per penetration and both of these are through the same penetration | DANE | DANE | | BSP | P | 5912345 |
THE WRIGHT GROUP, LLC | BSP | R | 07/16/2018 | EJ for collar at 6" PVC roof drain and changing the assembly at the floor ceiling where it penetrates in the elevator control room is not how it is built / need new EJ that is explicitly how it has been built or it needs to be built per listed assemblies and penetration listings | DANE | DANE | | BSP | R | 5903712 |
THE WRIGHT GROUP, LLC | BSP | P | 07/12/2018 | RC at north electrical and mechanical room wall OK | DANE | DANE | | BSP | P | 5901128 |
THE WRIGHT GROUP, LLC | BSP | R | 07/11/2018 | STI collar on 6" PVC is not installed per listing and can not be cut into rated assemblies in the corner / still need to fire tape ceiling at electric room / all penetrations at lid of electric room OK | DANE | DANE | | BSP | R | 5898853 |
THE WRIGHT GROUP, LLC | BSP | P | 07/10/2018 | penetrations at low volt wires in elevator control room are now correct - still need collar at 6" PVC pipe at corner of room / exercise room drain pipe on north side of beam is 1/2 in and 1/2 out of 2nd layer of ceiling rock - will need design to protect this penetration / all other penetrations in exercise room ceiling are now OK | DANE | DANE | | BSP | P | 5897858 |
THE WRIGHT GROUP, LLC | BSP | R | 07/06/2018 | listings for penetrations are all for STI products and Hilti or 3M product has been used in the elevator control room at all of the low volt bundles of wires and at the ceilings of the exercise room around the wires and plumbing penetrations / need to remove the Hilti or 3 M product and install STI per the listed assemblies that have been provided | DANE | DANE | | BSP | R | 5895472 |
THE WRIGHT GROUP, LLC | BSP | P | 06/29/2018 | fire caulked ceiling penetrations at main lobby, mech room and office OK / 4th lyer of rock at ceilings of both stair towers OK / 2nd layer of rock at all of 1st floor corridor OK | DANE | DANE | | BSP | P | 5890148 |
THE WRIGHT GROUP, LLC | BSP | P | 06/28/2018 | 2nd layer of rock OK at main lobby / hat channel at top of both stair towers now OK / discussed accessible elements of accessible bathroom in accessible unit | DANE | DANE | | BSP | P | 5888389 |
THE WRIGHT GROUP, LLC | BSP | P | 06/26/2018 | need to fix the listed assembly for the low volt wire penetrations at the elevator control room / north and south stair towers at ceilings are OK to install hat channel as the 3 under layers are now OK | DANE | DANE | | BSP | P | 5886120 |
THE WRIGHT GROUP, LLC | BSP | P | 06/26/2018 | need to splice in change of where rated wall at door to laundry chute is / need EJ for hole cut into laundry chute wall above door for sprinkler / need to fix holes in 1st layer of rock at ceiling of west guest bathroom / 3" pipes are too close together and are missing the rock around them at the north side of the beam at the east end of the exercise room / still have can lights in the rated ceilings of all of the elevator lobbies and no rock has been installed at the 1st floor elevator lobby yet / north and south stair towers at ceilings are OK to install hat channel as the 3 under layers are now OK | DANE | DANE | | BSP | P | 5886111 |
THE WRIGHT GROUP, LLC | BSP | P | 06/20/2018 | 1st floor ceiling rock / first layer of rock at 1st floor corridor from elevator lobby north OK and at pantry and breakfast room and exercise room and electric room and mechanical room OK / south stair tower ceiling 1st and laps at 2nd layer OK / north stair tower need to replace rock at 1st layer that has hole cut in it | DANE | DANE | | BSP | P | 5879826 |
THE WRIGHT GROUP, LLC | BIN | P | 06/15/2018 | 1st floor RC and insulation still OK | DANE | DANE | | BIN | P | 5876392 |
THE WRIGHT GROUP, LLC | BFR | P | 06/15/2018 | unit 104 now OK / penetrations at elevator control room now OK / still need 3rd party letter for intumescent paint and for letters for all welding and bolting / still need listing for for to protect non-rated can lights in rated assemblies at all floors at elevator lobbies - listing provided today was rejected as it did not state that it could be used with the M502 floor/ceiling assembly that is being used / still need to inspect ceilings at tops of stair towers that were installed without inspections | DANE | DANE | | BFR | P | 5876387 |
THE WRIGHT GROUP, LLC | BIN | P | 06/14/2018 | RC and INSULATION 1st FLOOR / RC and insulation at remainder of first floor is OK pending other roughs and 3rd party letter for intumescent paint | DANE | DANE | | BIN | P | 5874768 |
THE WRIGHT GROUP, LLC | BFR | P | 06/14/2018 | 1st FLOOR FRAMING REINSPECTION AT GUEST ROOMS AND ALL OTHER PORTIONS OF 1ST FLOOR / unit 104 need to seal penetration around duct at dead space by shower at ceiling / all other guest rooms all items have been corrected / need to fix penetration at fire barrier at elevator lobby side of wall between joists over elevator control room door / all other items from previous inspection for first floor all rooms other than guest rooms have been corrected / discussed need for 3rd party letter for intumescent paint and for letters for all welding and bolting / still need listing for for to protect non-rated can lights in rated assemblies at all floors at elevator lobbies - listing provided today was rejected as it did not state that it could be used with the M502 floor/ceiling assembly that is being used / still need to inspect ceilings at tops of stair towers that were installed without inspections | DANE | DANE | | BFR | P | 5874759 |
THE WRIGHT GROUP, LLC | BSP | P | 06/11/2018 | RC at ceiling of telecom room by 1st floor elevators is OK / OK to prerock telecom ceiling | DANE | DANE | | BSP | P | 5870668 |
THE WRIGHT GROUP, LLC | BIN | R | 06/11/2018 | first floor frame items are not ready to be reinspected so 1st floor insulation was not inspected | DANE | DANE | | BIN | R | 5870665 |
THE WRIGHT GROUP, LLC | BFR | P | 06/07/2018 | FIRST FLOOR FRAMING ALL OTHER THAN GUEST ROOMS / need to strap top plates at north mech room wall / need to tie all bearing wall corners together / need fix for drilled top cord at joist over end of elevator lobby / need to seal all penetrations in fire barrier between joists at east side of elevator / need to fire caulk all top plate penetrations at at north electric room / plan calls all rock to be installed before drops in main lobby are installed but drops have already been installed / need listing for can lights in rated assembly at elevator lobby and exterior cover at main entry / need stamped letter of observation for intumescent paint at main lobby beams and posts and letter for welding and bolting | DANE | DANE | | BFR | P | 5867658 |
THE WRIGHT GROUP, LLC | BFR | R | 06/07/2018 | FIRST FLOOR GUEST ROOMS / above ceiling penetrations in bathrooms are not ready to be inspected | DANE | DANE | | BFR | R | 5867630 |
THE WRIGHT GROUP, LLC | BSP | R | 05/23/2018 | ceilings of both stair tower exit enclosures have been covered without inspections / need to remove drywall and have all inspections at all layers of assembly to check laps, screws and hat channel / no assembly in plans for the encasement of all of the steel beams and steel posts in the main lobby A2 portion of the main level- need assembly and stamped letter for how to seal all penetration at the floor joists and hangers to beam connections | DANE | DANE | | BSP | R | 5853561 |
THE WRIGHT GROUP, LLC | BSP | P | 05/11/2018 | 2nd layer of rock at 1st floor guest rooms OK / need to check all penetrations still with soffit framing | DANE | DANE | | BSP | P | 5842447 |
THE WRIGHT GROUP, LLC | BSP | P | 05/07/2018 | FIRST LAYER OF ROCK AT 1ST FLOOR GUEST ROOMS / screws and type of rock and joint offsets OK at 1st layer of rock at 1st floor guest room ceilings only | DANE | DANE | | BSP | P | 5837662 |
THE WRIGHT GROUP, LLC | BSP | P | 05/03/2018 | FIRST LAYER OF ROCK AT BATHROOM CEILINGS 1ST FLOOR - screws and type OK at all 1st floor guest room bathrooms only / joint staggers in rooms are not at 24" OC and need to be corrected / OK to install 2nd layer in guest room bathroom ceilings ONLY / need to have MEP inspection on all other parts of 1st floor before frame inspection can be done | DANE | DANE | | BSP | P | 5834933 |
THE WRIGHT GROUP, LLC | BSP | P | 05/03/2018 | still need to upload engineering for stair stringer fix / lags at ledgers for stair stringer fix OK at all stairs pending upload of engineering / engineering observed on site as electronic copy | DANE | DANE | | BSP | P | 5834923 |
THE WRIGHT GROUP, LLC | BSP | P | 05/02/2018 | still need to upload engineering for 1) the stair fix for the stringers not setting on the landings 2) for too much cut out of the 2x6 studs in the plumbing walls at 1st floor and 3) for the joist fix in unit 204 / still need to provide listing for can lights in rated assemblies at elevator lobbies / fire barriers at units 104 204 and 304 are not fire taped and fire caulked OK / fire caulking at common walls at plumbing in all 2nd 3rd and 4th floor units OK / all other framing items for 1st floor guest units have been corrected | DANE | DANE | | BSP | P | 5833613 |
THE WRIGHT GROUP, LLC | BIN | P | 04/30/2018 | FIRST FLOOR GUEST ROOMS ONLY FRAME REINSPECTION AND INSULATION AND RC / unit 104 - still need to fix penetrations in fire barrier below joists - still need to fire tape fire barrier joists above joists in main room / unit 107 - still need to install point load at right side of window / unit 109 - need to remove wood block at fire partition and fix penetration / discussed need to check all penetrations in all prerock before drops have drywall installed / still need to upload stamped letter and photo that letter references for studs with too much cut out | DANE | DANE | | BIN | P | 5830811 |
THE WRIGHT GROUP, LLC | BSP | P | 04/25/2018 | still need to fire tape fire barrier joists and corners and fire caulk penetrations at fire barriers at closets at units 304 and 204 / still need engineering for stair bearing on 2x6 extensions and for too much cut out of bearing studs and for joist repair at unit 320 next to fire barrier / still need to provide listing for can lights at elevator lobbies or need to remove can lights / top and bottom plates at units 420 320 and 220 now OK | DANE | DANE | | BSP | P | 5827019 |
THE WRIGHT GROUP, LLC | BSP | P | 04/24/2018 | FRAMING AT GUEST ROOMS ONLY at 1st floor / need to check fire caulking at all dead spaces by all tubs / there is still too much cut out of bearing studs at all bathroom common walls - still need engineer letter / unit 101 - need to fire caulk wire at top plate by bath door / 104 - fix penetration at south wall at room at low volt wires - fire tape prerock at fire barrier / 107 - missing point load over window / 113 - fix fire caulk at east bathroom wall at PVC pipe - fix fire caulking at south bathroom wall at PVC pipes / OK to insulate and RC guest rooms only pending other roughs / still need to inspect all other areas of first floor // Training with Lonny S | DANE | DANE | | BSP | P | 5826072 |
THE WRIGHT GROUP, LLC | BSP | P | 04/24/2018 | training with inspector Dane S, on type VA construction - R-1, A-2, A-3 occupancies / assisted with 1st floor framing and penetrations / reviewed shaft liner requirements and continuity / reviewed laundry shoot requirements and listed openings / reviewed roof requirements for guards and location of access / reviewed engineer corrections on framing issues | LONNYS | LONNYS | | BSP | P | 5826068 |
THE WRIGHT GROUP, LLC | BSP | P | 04/11/2018 | ELEVATOR SHAFT LID AND 1ST FLOOR GUEST ROOM BATHROOM CEILINGS / hat channel and 3rd layer of rock at top of elevator shaft OK - still need to see 4th layer of rock / 1st floor guest units bathroom ceilings ONLY OK - still need to inspect all dead space ceilings and prerock at all bathrooms in all 1st floor guest rooms | DANE | DANE | | BSP | P | 5814350 |
THE WRIGHT GROUP, LLC | BSP | P | 04/06/2018 | First layer of drywall at laundry chute on all floors OK | JEREMYA | JEREMYA | | BSP | P | 5810149 |
THE WRIGHT GROUP, LLC | BSP | P | 03/30/2018 | 2ND FLOOR SCREWS / screws at 2nd layer of ceilings and at all walls OK at all units and corridors except unit 204 ( first layer OK in 204) and elevator lobby where can lights still need listing / South exit enclosure 1st layer of screws and rock OK at all walls and landings and all laps at joints OK | DANE | DANE | | BSP | P | 5803782 |
THE WRIGHT GROUP, LLC | BSP | P | 03/20/2018 | 2nd FLOOR FIRST LAYER AT CEILINGS / still need listing for can light protection at elevator lobbies / unit 204 joist has been moved to allow for continuous rock at fore barrier but joist now has broken bottom cord over the bearing wall and now need engineer letter for joist fix / still need listing for bundles of wires at electrical rooms through floor ceiling assemblies / all other ceilings in corridor and units first layer of type C screws and laps for second layer are OK / 1st floor frame inspection stopped - too many items - need complete reinspection | DANE | DANE | | BSP | P | 5793883 |
THE WRIGHT GROUP, LLC | BSP | P | 03/15/2018 | RC AND INSULATION 2nd FLOOR / unit 204 still have joist in way to have continuous fire barrier at corner of stair tower and closet (this was errantly states to be room 226 in previous inspection) / still need protection for can lights in elevator lobby / all other units and corridors and rooms incidental to corridor insulation and RC OK pending other roughs | DANE | DANE | | BSP | P | 5789980 |
THE WRIGHT GROUP, LLC | BFR | P | 03/12/2018 | 2ND FLOOR FRAME REINSPECTION / unit 226 - still have joist in in the way to have continuous rock at the corner of the fire barrier by the closet / still need listing for protecting the can lights at all of the elevator lobbies / all other items corrected / listing for blank holes and alternate listing for tub drains / update: changed from BSP to BFR inspection 3/12/18 | DANE | DANE | | BFR | P | 5786112 |
THE WRIGHT GROUP, LLC | BSP | P | 03/09/2018 | screws at 2nd layer of rock at 3rd floor corridors OK / need listing for can lights at elevator lobbies in rated assemblies | DANE | DANE | | BSP | P | 5784854 |
THE WRIGHT GROUP, LLC | BFR | R | 03/07/2018 | 2nd FLOOR FRAME / missing roll blocks at lots of locations at bearing walls in all units / wrong screws were used in all tub drain penetrations in all units / 201 - need to install prerock and fix penetrations at dead space by shower / 204 - missing SDS screws at hangers in bathroom - need listing for blank hole in fire barrier in bathroom - fix the penetration at the wire at the bathroom fire barrier - joist is in the way for the corner of the fire barrier at the closet corner / 217 - fix penetration at low volt wire between joists in fire barrier / 220 - need engineer for cut top and bottom plates and EJ for fixing penetration at unit separation wall - need to strap top plates at north unit separation wall at line sets / 221 - need RC and prerock at 6" PVC pipe and need to fix penetration at 6' PCV through pre rock at bathroom / 226 - too much cut out of double bearing studs in bathroom at unit separation wall / 225 - missing SDS screw in hanger at fire barrier at bathroom | DANE | DANE | | BFR | R | 5782157 |
THE WRIGHT GROUP, LLC | BSP | P | 03/06/2018 | screws at 1st layer at 3rd floor corridors OK | DANE | DANE | | BSP | P | 5780892 |
THE WRIGHT GROUP, LLC | BSP | P | 02/28/2018 | still need to have rock be continuous at corner of fire barrier at room 304 / still need listing for wire penetrations at floor ceiling assemblies / still need to complete fixes at PVC pipes in walls at 420 320 and 220 / still need listing for ice maker drains / still need listing for 3 layers at tub drains / still need engineering for cut out top plates at 420 320 and 220 / listings received for 6" pipes, 4" pipes, 3" pipes and other various penetrations / EJ received for laps in rock at fire barriers at stair towers / screws at rated assemblies at rooms 404 and 417 are OK / screws at rated assemblies at all 3rd floor rooms OK except 320 and 304 / RC at ceilings at corridors and accessory rooms off of corridor OK | DANE | DANE | | BSP | P | 5776720 |
THE WRIGHT GROUP, LLC | BSP | P | 02/26/2018 | Splicing in P525 roof/ceiling assembly and M502 floor/ceiling assembly | LBENNETT | LBENNETT | | BSP | P | 5774321 |
THE WRIGHT GROUP, LLC | BSP | R | 02/26/2018 | 3RD FLOOR RC AT CORRIDORS / need to splice in the new UL assemblies for the roof ceiling and floor ceiling assemblies / still need all listings that coincide with the new floor ceiling and roof ceiling assemblies once they are splices in - all need to be STI listings / still missing RC at prerock at bathroom ceiling at 6" PVC at room 321 / still need engineering for all cut out plates for (4) 3" PVC plumbing vents in unit separation walls at units 420 320 and 220 and also need listing for (4) 3" PVC vents tight in one stud bay in these walls / need listings for ice maker drains, tub and shower drains with 3 layers of rock, for 4" sheet metal exhaust vents, all plumbing pipes including drains and supply's and for all wires both line volt and low volt and for 6" PVC roof drain pipes and sprinkler pipes / still need EJ for cut out rock at sprinkler lines in stair towers that causes the inability to have 2' horizontal joint separation on the fire barriers | DANE | DANE | | BSP | R | 5773913 |
THE WRIGHT GROUP, LLC | BSP | P | 02/22/2018 | 4TH FLOOR FIRE BARRIER REINSPECTIONS AND RC AT 3RD FLOOR BATHROOMS / room 421 - still need listing for 6" PVC penetration at bathroom dead space through P545 roof ceiling assembly and M502 floor ceiling assembly / all other items at units 425, 4177 and 401 corrected OK / need to splice into plans the new floor ceiling assembly M502 and roof ceiling assembly P545 / RC at all 3rd floor bathrooms OK except in unit 321 that is not ready / still need RC at corridor and all accessory rooms | DANE | DANE | | BSP | P | 5771535 |
THE WRIGHT GROUP, LLC | BSP | P | 02/20/2018 | RC at mechanical room at northeast corner of 1st floor south wall OK | DANE | DANE | | BSP | P | 5769094 |
THE WRIGHT GROUP, LLC | BSP | P | 02/20/2018 | RC AT 3RD FLOOR LIVING AREAS INSIDE UNITS ONLY / ceiling RC at living areas at units only OK per the UL M502 assembly in all rooms except room 304 where the joist at the corner of the fire barrier still needs to be moved / still need listings for all penetrations through a P500 and M500 series assemblies / still need to install at corridors and all accessory rooms and bathrooms / 3rd layer of rock at 4th floor corridor OK | DANE | DANE | | BSP | P | 5769089 |
THE WRIGHT GROUP, LLC | BSP | P | 02/16/2018 | site visit with contractor to discuss need for a floor ceiling assembly that calls for engineered joists and a need for all listings for the corrected floor ceiling assembly / all penetrations at the fore barrier at unit 325 are now corrected - still need to fix penetrations at units 304 and 317 at fire barriers / top of east and west walls at top of elevator shaft pre rock is now OK | DANE | DANE | | BSP | P | 5767812 |
THE WRIGHT GROUP, LLC | BSP | R | 02/15/2018 | REINSPECTION OF PENETRATIONS AT 3RD AND 4TH FLOORS / need listing for P500 series roof ceilings for all penetrations / all listing provided for floor ceilings are for an L500 series floor ceiling assembly but the floor ceiling assembly on plans (GA 2601) does nto match what is built as 2601 is for 2x10 joists and BCI joists have been used / still need to fix all penetrations in all fire barriers at units by elevator and stair enclosures / unit 420 - still need engineering for removed top plates and bottom plates / need to install pre rock at east and west ends of inside of elevator shaft ( must be continuous to roof deck ) / 323 missing electrical box at north wall / 321 - still need listing for 6" collar and need correct floor ceiling assembly / 304 - need to fix corner of pre rock at fire barrier at closet to room wall by stair enclosure / need EJ for adding layers of rock to the listing for the tub drains throughout / need to complete prerock at corridor by elevator | DANE | DANE | | BSP | R | 5766859 |
THE WRIGHT GROUP, LLC | BSP | P | 02/12/2018 | 4TH FLOOR SCREWS AT RATED ASSEMBLIES / 404 417 and 425 - still need 2' lap at fire barriers layers / 420 need engineer fix for cut out top plates an bottom plates at north wall / still need to fix penetrations in bath dead spaces in units 401 and 421 / still need listing for 6" penetration of PVC pipes / need to have all penetrations ready at fire barriers when next inspection is called for units 404 417 and 425 / units 409 411 413 415 422 424 426 and 428 - screws OK at rated assemblies | DANE | DANE | | BSP | P | 5763271 |
THE WRIGHT GROUP, LLC | BSP | P | 02/08/2018 | 4TH FLOOR SCREWS AT RATED ASSEMBLIES AND FRAME REINSPECTION / 401 - Sill need listing for 4" metal duct penetrations at tub dead space (fire taping complete) / 404 - need 2' stagger between horizontal joints at double layer drywall at fire barrier / 421 - still need listing for 6" PVC pipe in dead space at bathroom (fire taping complete) / 425 - still need 2' stagger at double layer drywall system at fire barrier / still need spec seal listing for 3" PVC penetrations, 6" PVC penetrations, and 4" metallic penetrations / screws OK at rooms 410 403 405 406 407 408 410 412 414 416 and 418 / all others not ready | DANE | DANE | | BSP | P | 5760978 |
THE WRIGHT GROUP, LLC | BFR | R | 02/08/2018 | 3RD FLOOR FRAME REINSPECTION / still need to fix all previous items from previous inspection / can not verify putty pads are correct in unit separation walls with insulation in walls / still need listing for floor drains for ice makers / still need listing for 3" PVC penetrations in floor ceilings / still need to prerock in dead spaces by tubs / tub drain listing received but listing is for WF300 fire caulk but LCI fire caulk was used / need all corrections made before any more inspections made | DANE | DANE | | BFR | R | 5760957 |
THE WRIGHT GROUP, LLC | BFR | P | 02/05/2018 | FIRST FLOOR ELECTRICAL ROOM AND DEAD SPACES IN DWELLING UNITS BY TUBS / need stamped letter for 3 stacked top plates throughout 1st floor walls / framing at electrical room at northeast corner OK pending other roughs and letter for stacked plates - OK to prerock ceiling at electrical room pending other roughs / OK to prerock all dead spaces at unit bathrooms pending other roughs | DANE | DANE | | BFR | P | 5757017 |
THE WRIGHT GROUP, LLC | BIN | P | 02/05/2018 | 4TH FLOOR RC AND INSULATION / RC and insulation at 4th floor units and corridor OK pending other rough inspections except unit 417 and elevator lobby where drywall joint must be fire taped above the ceiling line at the fire barrier for the elevator / 401 and 421 still need tire tape at dead spaces by showers / electric room east of elevators still need listing for 6" PVC pipe penetration and listing for 4" PVC conduit from electrical panels and one sprinkler head has been buried in fore caulk at laundry chute / still need hard copy or upload of truss fixes for A2 and B1 | DANE | DANE | | BIN | P | 5756997 |
THE WRIGHT GROUP, LLC | BSP | P | 02/02/2018 | FRAME INSPECTION FOR NEW STRUCTURE AT SOUTHWEST CORNER OF ROOF / missing H3 truss clips at all rafters at added roof structure / all other framing for added roof structure OK / OK to insulate remainder of units at 4th floor (units 422 424 426 and 428) | DANE | DANE | | BSP | P | 5755519 |
THE WRIGHT GROUP, LLC | BFR | P | 02/01/2018 | 3RD FLOOR FRAME INSPECTION / still need listing for all tub drains that are able to use spec seal products / need listing for floor drains at ice makers in corridors / need putty pads through out / 301 - need to prerock dead space at tub / 304 - fix penetrations at corridor wall top plate - fix penetrations at fire farier over tub / 317 - fix penetrations at fire barrier in bath and living area | DANE | DANE | | BFR | P | 5754678 |
THE WRIGHT GROUP, LLC | BIN | R | 02/01/2018 | RC AND INSULATION 4TH FLOOR / RC and insulation at 4th floor not ready / still need to complete items from previous frame inspection / still need listing for 6" PVC pipes that penetrate rated assemblies in several places | DANE | DANE | | BIN | R | 5754657 |
THE WRIGHT GROUP, LLC | BSP | P | 01/24/2018 | Repairs for trusses A2 and B1 field verified, hard copies to follow // No other truss corrections // 4th floor framing: 421 - Need mud and tape behind bathtub // Missing putty packs at units 403 & 404 // EXCLUDES ELEVATOR LOBBY // Will need to get verification that 4" diameter boxes in walls that are labeled as "CEILING" boxes can be in walls | JEREMYA | JEREMYA | | BSP | P | 5746875 |
THE WRIGHT GROUP, LLC | BSP | P | 01/18/2018 | RC at dead space in bathrooms at rooms 401 and 421 OK / roof framing at elevator shaft and north and south stair towers OK (OK to insulate roofs only at north and south stair towers and at elevator shaft) / still need all listing from previous inspection / need to splice into the plans the added storage room on the roof at the southwest corner | DANE | DANE | | BSP | P | 5741398 |
THE WRIGHT GROUP, LLC | BSP | P | 01/08/2018 | courtesy walk with superintendent and fire stop contractor / splice for use of specseal in lieu of 3M on file / need listings for tub drains / need listing for 26 gage vents through floor/ceilings and roof/ceilings / need listing for 2" and 3" PVC through walls and through floor/ceilings and roof/ceilings / need listing for 6" PVC penetrations through wall assemblies and floor/ceilings assemblies and roof/ceiling assemblies / need to install RC in dead spaces and have inspected so dead spaces can be prerocked / will need EJ's for PVC penetrations in fire barriers that have more annular space than allowed per the listings / still need to have all MEP inspections at upper floors to start frame inspections | DANE | DANE | | BSP | P | 5731531 |
PARKEY'S REFRIGERATION CO., INC | BSP | T | 12/29/2017 | PAID (REC#1473807) PLAN SPLICE FEE: $100 by: JUSTINC for Mechanical | JUSTINC | JUSTINC | | BSP | T | 5725808 |
BRUIN ENTERPRISES, INC. | BSP | T | 12/19/2017 | PAID (REC#1472158) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 12-19-2017 | TCRIPPEN | TCRIPPEN | | BSP | T | 5717623 |
THE WRIGHT GROUP, LLC | BSP | P | 12/18/2017 | OK to prerock at all tubs and set tubs / met on site with owner of project and discussed need for MEP inspections before frame inspection / discussed need for splice to be completed and need for listings for all penetrations that have been done with Spec Seal as all listings on plans are for 3M preducts | DANE | DANE | | BSP | P | 5715645 |
THE WRIGHT GROUP, LLC | B16 | P | 12/15/2017 | Talked on phone with site superintendent about the need for frame and insulation inspections before drywall could be hung. | DANE | DANE | | B16 | P | 5714533 |
THE WRIGHT GROUP, LLC | BSP | T | 12/13/2017 | PAID (REC#1471417) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Minor floor plan revisions | MICHAELA | MICHAELA | | BSP | T | 5711164 |
THE WRIGHT GROUP, LLC | BSP | R | 12/04/2017 | met with superintendent to discuss penetrations in rated assemblies / contractor is currently using a spec seal product and all listings on plans are for 3M products / will need all listings for Spec Seal products to be spliced into plans / discussed where and when putty pads are to be used with contractor / discussed need for listings to be able to inspect any of the penetrations that have spec seal fire caulk on them | DANE | DANE | | BSP | R | 5701484 |
THE WRIGHT GROUP, LLC | BSP | P | 11/20/2017 | first layer of rock at all electrical room walls OK at 4th 3rd and 2nd floors / discussed need for listings for blank holes in plates and over drilled holes in membranes around pipes | DANE | DANE | | BSP | P | 5690390 |
THE WRIGHT GROUP, LLC | BSP | T | 11/07/2017 | PAID (REC#1465575) PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: Revised title page AO | BPHILLIPS | BPHILLIPS | | BSP | T | 5679299 |
THE WRIGHT GROUP, LLC | BFT | P | 11/07/2017 | all footing pads and vertical uprights for all piers for west and south canopies are OK / still need all engineer observations for building footings and foundation and Eufer / open hole on file | DANE | DANE | | BFT | P | 5678983 |
THE WRIGHT GROUP, LLC | BSP | P | 10/05/2017 | fire barriers at south stair tower penthouse and elevator parapit walls and north stair tower parapit walls / stagger and and nailing OK at roof line up on outside of walls / discussed rated assemblies with contractor and framer / will need clarification of rated assembly for all floor ceiling assemblies | DANE | DANE | | BSP | P | 5646195 |
THE WRIGHT GROUP, LLC | BSP | T | 09/27/2017 | PAID (REC#1457142) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Trusses | MICHAELA | MICHAELA | | BSP | T | 5638543 |
THE WRIGHT GROUP, LLC | BSP | T | 09/25/2017 | PAID (REC#1457142) PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: Revised floor plan, changed some showers to tubs. | BPHILLIPS | BPHILLIPS | | BSP | T | 5636504 |
THE WRIGHT GROUP, LLC | BSP | P | 09/13/2017 | shear wall at southwest stair tower OK / joints at drywall for GA 4230 are to be offset 24" and are not currently at pre rock areas for landings and joists / need EJ of penetrations of micro lam beams into fire barriers for landings at stair towers / discussed inspection process with framer and superintendent / need engineer letter for header change at breakfast room for pocket door | DANE | DANE | | BSP | P | 5624785 |
THE WRIGHT GROUP, LLC | BFN | C | 08/15/2017 | Engineers observation Letters received / Eufer noted | DANE | DANE | | BFN | C | 5595536 |
THE WRIGHT GROUP, LLC | BFT | C | 08/15/2017 | Engineers observation Letter received / Soils report received | DANE | DANE | | BFT | C | 5595534 |
THE WRIGHT GROUP, LLC | BSP | P | 08/09/2017 | 2' horizontal R10 under slab insulation around perimeter of interior of foundation OK / discussed need for open hole and footing and foundation observations by frame inspection | DANE | DANE | | BSP | P | 5590288 |
THE WRIGHT GROUP, LLC | BFI | C | 07/06/2017 | R10 foundation insulation OK | DANE | DANE | | BFI | C | 5556280 |
THE WRIGHT GROUP, LLC | BSP | P | 07/05/2017 | PLAN SPLICE: (No Fee) by: DANM for Construction: Revise slab insulation on IECC from R 1.0 to R 10 | DANM | DANM | | BSP | P | 5555388 |
THE WRIGHT GROUP, LLC | BFN | P | 06/15/2017 | AUTHORIZED THIRD PARTY INSPECTIONS - Stamped letters to follow | JEREMYA | JEREMYA | | BFN | P | 5536286 |
THE WRIGHT GROUP, LLC | BFT | P | 06/15/2017 | AUTHORIZED THIRD PARTY INSPECTIONS - Stamped letters to follow | JEREMYA | JEREMYA | | BFT | P | 5536285 |
EMF ELECTRICAL CORPORATION | E= | C | 09/07/2018 | | RANDY | RANDY | | E= | C | 5958092 |
EMF ELECTRICAL CORPORATION | E= | P | 09/06/2018 | lobby, commons and office area, gfci at office and laundry sink, gfci receptacle cannot be behind kitchen refrigerator, freezer and laundry refrigerator, install support wires bath fans and smoke device, will need a ep inspection on all panels. | BRET | BRET | | E= | P | 5956698 |
EMF ELECTRICAL CORPORATION | E= | P | 09/04/2018 | 1st floor rooms also looked at drop ceilings | RANDY | RANDY | | E= | P | 5953667 |
EMF ELECTRICAL CORPORATION | ESL | P | 08/29/2018 | correction made | RANDY | RANDY | | ESL | P | 5949639 |
EMF ELECTRICAL CORPORATION | ESL | R | 08/28/2018 | need #8 to all wet niche fixtures----need capsulation inspection before pool is filled | RANDY | RANDY | | ESL | R | 5947768 |
EMF ELECTRICAL CORPORATION | E= | P | 08/21/2018 | check 2nd fl ice maker outlets on next inspection-----3rd fl corridor ok | RANDY | RANDY | | E= | P | 5940746 |
EMF ELECTRICAL CORPORATION | E= | P | 08/15/2018 | 201.301.401 and 4th floor corridor | BRET | BRET | | E= | P | 5934583 |
EMF ELECTRICAL CORPORATION | E= | R | 08/14/2018 | not ready no power to half corridor receptacles, reverse polarity , make door bell transformer, plug hole in same box, gfci receptacles still behind built in appliance space , if tv receptacle within 6' of sink gfci protect it | BRET | BRET | | E= | R | 5933028 |
EMF ELECTRICAL CORPORATION | EUG | R | 08/08/2018 | notes on pool permit | BRET | BRET | | EUG | R | 5927495 |
EMF ELECTRICAL CORPORATION | ER | C | 08/08/2018 | FIRE ALARM INSPECTION: red card not on site | BRET | BRET | | ER | C | 5927213 |
EMF ELECTRICAL CORPORATION | E= | C | 08/08/2018 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 5927214 |
EMF ELECTRICAL CORPORATION | E= | P | 07/25/2018 | 2nd floor east units except 201 gfci issue | BRET | BRET | | E= | P | 5913326 |
EMF ELECTRICAL CORPORATION | EUG | P | 07/25/2018 | eug to pool equipment room ok to backfill | BRET | BRET | | EUG | P | 5913320 |
EMF ELECTRICAL CORPORATION | EUG | P | 07/20/2018 | conduits and uf at ground box location at entry driveway | BRET | BRET | | EUG | P | 5908999 |
EMF ELECTRICAL CORPORATION | ER | P | 07/18/2018 | rough complete will need bore log attached to permit for conduit depth across road for sign | BRET | BRET | | ER | P | 5906265 |
EMF ELECTRICAL CORPORATION | E= | P | 07/05/2018 | 2nd level westside rooms only / | ROB | ROB | | E= | P | 5894086 |
EMF ELECTRICAL CORPORATION | ER | P | 06/29/2018 | elevator lobby on all floors adding 3 new lights only ok | CRAIG | CRAIG | | ER | P | 5889711 |
EMF ELECTRICAL CORPORATION | ER | P | 06/28/2018 | west and east exit light box installed | BRET | BRET | | ER | P | 5888221 |
EMF ELECTRICAL CORPORATION | E= | P | 06/27/2018 | 320 ok, east units 3rd floor except bath not ready in 321 and 301 sink area gfci issue. | BRET | BRET | | E= | P | 5886758 |
EMF ELECTRICAL CORPORATION | E= | P | 06/26/2018 | 3rd floor west units ok except 320 no power bath receptacle. | BRET | BRET | | E= | P | 5885442 |
EMF ELECTRICAL CORPORATION | ER | P | 06/22/2018 | attachment is for flower pot lighting, need ul listing on unit bath mirror, stating that it is a listed assembly. | BRET | BRET | | ER | P | 5882594 |
EMF ELECTRICAL CORPORATION | EUG | R | 06/22/2018 | pool eug notes on pool permit | BRET | BRET | | EUG | R | 5882580 |
EMF ELECTRICAL CORPORATION | E= | P | 06/20/2018 | 4th floor east units ok except 401, 421. west unit 420 ok, | BRET | BRET | | E= | P | 5879536 |
EMF ELECTRICAL CORPORATION | E= | P | 06/19/2018 | 4th floor west units except 420, protect nm cable at all ptac | BRET | BRET | | E= | P | 5878209 |
EMF ELECTRICAL CORPORATION | ER | P | 06/06/2018 | FIRE ALARM INSPECTION: first floor walls and hard lids | BRET | BRET | | ER | P | 5865860 |
EMF ELECTRICAL CORPORATION | ER | P | 06/06/2018 | first floor hard lid and walls ok except great room soffit lighting and all exit light locations, south exterior soffit ok whips for column lights | BRET | BRET | | ER | P | 5865859 |
EMF ELECTRICAL CORPORATION | ER | P | 06/04/2018 | FIRE ALARM INSPECTION: first floor rough ok | BRET | BRET | | ER | P | 5862980 |
EMF ELECTRICAL CORPORATION | ER | P | 06/04/2018 | staple nm per code reception area and lobby, make up box under sink ko, install clamp on cable for range. need soffit and columns built in lobby for receptacles and lights. boxes installed for exit lights. hard lids and pre-rock ceilings ok except north door soffit | BRET | BRET | | ER | P | 5862974 |
EMF ELECTRICAL CORPORATION | ER | P | 05/24/2018 | FIRE ALARM INSPECTION: bath lids, corridor 113 north | BRET | BRET | | ER | P | 5854450 |
EMF ELECTRICAL CORPORATION | ER | P | 05/24/2018 | first floor unit bath hard lids, first floor corridor ceiling fro 113 north except soffit at north door, electric room ceiling. pantry walls, (ground box and fill un-used opening. | BRET | BRET | | ER | P | 5854448 |
EMF ELECTRICAL CORPORATION | ER | P | 05/11/2018 | Walls rough ok for rooms 103,104,105,106,107,108--install cable stackers where required--cannot cover common walls on the Market and Registration sides / | ROB | ROB | | ER | P | 5842775 |
EMF ELECTRICAL CORPORATION | ER | R | 04/24/2018 | attach to pool permit. ground clamp installed are for 1/2 -3/4 rods not 3/8 rebar listed | BRET | BRET | | ER | R | 5825131 |
EMF ELECTRICAL CORPORATION | ES | C | 04/02/2018 | Commercial Service: 2000 amp 6 sets of 600 mcm al ok to set meter inspected up to main breaker only need to verify bonding to building steel on next inspection need to splice one line to show what' s being installed | CRAIG | CRAIG | | ES | C | 5804738 |
EMF ELECTRICAL CORPORATION | ER | P | 03/23/2018 | 2nd floor corridor. | BRET | BRET | | ER | P | 5797518 |
EMF ELECTRICAL CORPORATION | ER | R | 03/22/2018 | correction not made remove sheet rock and insulation | BRET | BRET | | ER | R | 5796061 |
EMF ELECTRICAL CORPORATION | ER | P | 03/05/2018 | FIRE ALARM INSPECTION: 2nd floor ok | BRET | BRET | | ER | P | 5779516 |
EMF ELECTRICAL CORPORATION | ER | P | 03/05/2018 | pre-rock bath rooms first floor guest units | BRET | BRET | | ER | P | 5779511 |
EMF ELECTRICAL CORPORATION | ER | R | 03/02/2018 | cables bundled north corridor, connector not made to bath fan 223 and 226. other units ok | BRET | BRET | | ER | R | 5778490 |
EMF ELECTRICAL CORPORATION | ER | P | 03/02/2018 | FIRE ALARM INSPECTION: 2nd floor f.a ok | BRET | BRET | | ER | P | 5778482 |
EMF ELECTRICAL CORPORATION | EUG | P | 01/16/2018 | 4 of 5 pole bases informed contractor of bore log for sign circuit. | BRET | BRET | | EUG | P | 5738165 |
EMF ELECTRICAL CORPORATION | EUG | P | 01/10/2018 | EUG ok foe 2-4" communication pipes from back of building to the south end of building and out to stub ups that are in line with front of building, 1-1" PVC for light pole along south side of building to communication stub up area / | ROB | ROB | | EUG | P | 5734987 |
EMF ELECTRICAL CORPORATION | EUG | P | 01/10/2018 | conduit between three light poles east lot | BRET | BRET | | EUG | P | 5734096 |
EMF ELECTRICAL CORPORATION | EUG | P | 01/05/2018 | secondary from transformer leave open for csu inspection. | BRET | BRET | | EUG | P | 5729866 |
EMF ELECTRICAL CORPORATION | ER | P | 01/05/2018 | FIRE ALARM INSPECTION: 3rd floor units and corridors only | BRET | BRET | | ER | P | 5729865 |
EMF ELECTRICAL CORPORATION | ER | P | 01/05/2018 | 3rd floor units and corridors only. | BRET | BRET | | ER | P | 5729860 |
EMF ELECTRICAL CORPORATION | ER | P | 12/14/2017 | 4 th floor ok except s.e hall cables bundled not secured. stairwell walls ok | BRET | BRET | | ER | P | 5712660 |
EMF ELECTRICAL CORPORATION | ER | P | 12/14/2017 | FIRE ALARM INSPECTION: 4th floor ok | BRET | BRET | | ER | P | 5712657 |
EMF ELECTRICAL CORPORATION | ER | R | 12/13/2017 | 4 th floor only need f.a attach to permit f.a ok on 4 th floor install nail plates at all hvac units where hole is within 1 1/4 from edge of stud. secure all nm cables thru corridor cannot drape thru trusses be sure not to bundle them. only units and corridor inspected at this time. | BRET | BRET | | ER | R | 5711151 |
EMF ELECTRICAL CORPORATION | ER | R | 12/05/2017 | units 420-428 ok cannot give electrical rough without f.a installed | BRET | BRET | | ER | R | 5702711 |
EMF ELECTRICAL CORPORATION | ER | R | 11/17/2017 | fourth floor units and corridor ok except box for hvac, cannot run screws thru box for lighting all units, need f.a rough | BRET | BRET | | ER | R | 5688939 |
EMF ELECTRICAL CORPORATION | EST | P | 09/18/2017 | Temporary Service: 200 amp service ok to energize | BRET | BRET | | EST | P | 5628935 |
EMF ELECTRICAL CORPORATION | ES | T | 09/18/2017 | PAID (REC#1466206) need to pull separate permit for temp service cannot attach to building permit | BRET | BRET | | ES | T | 5671752 |
EMF ELECTRICAL CORPORATION | ESL | R | 08/24/2017 | need to talk to Bret | CRAIG | CRAIG | | ESL | R | 5605364 |
EMF ELECTRICAL CORPORATION | EST | R | 08/10/2017 | need new permit for temp | CRAIG | CRAIG | | EST | R | 5591549 |
EMF ELECTRICAL CORPORATION | ESL | P | 08/02/2017 | slab ok except electric room | BRET | BRET | | ESL | P | 5583551 |
EMF ELECTRICAL CORPORATION | ESL | P | 08/01/2017 | 3 -4" 5 -3" pvc from center to north, 2 3/4 from east to west. ufer not inspected prior to pour. | BRET | BRET | | ESL | P | 5582264 |
PARKEY'S REFRIGERATION CO., INC | H= | C | 09/28/2018 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 5979585 |
PARKEY'S REFRIGERATION CO., INC | H= | C | 09/28/2018 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 5979579 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/26/2018 | LETTER FROM ENGINEER APPROVING INSTALLATION OF BATH FANS BELOW RATED LID RECEIVED AND SENT TO SCANNING. MECHANICAL FINAL OK PENDING TEST AND BALANCE REPORT. | DUSTINS | DUSTINS | | H= | P | 5977505 |
PARKEY'S REFRIGERATION CO., INC | H= | L | 09/25/2018 | CONTRACTOR CANCELLED AT CALL AHEAD. | DUSTINS | DUSTINS | | H= | L | 5976146 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | C | 09/25/2018 | ELEVATOR COMPLETE | ERIC | ERIC | | HE= | C | 5975300 |
BRUIN ENTERPRISES, INC. | H= | C | 09/24/2018 | 2 LB APPROVAL FROM CSU RECEIVED. GAS FINAL OK. | DUSTINS | DUSTINS | | H= | C | 5974262 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/24/2018 | NEED CONTRACTOR THAT INSTALLED POOL BOILERS ATTACHED TO PERMIT AND CALL FOR INSPECTION. PROVIDE LETTER FROM ENGINEER APPROVING INSTALLATION OF EXHAUST FANS IN FIRST FLOOR GUEST ROOMS. FANS ARE BEING INSTALLED IN FRAMING BELOW RATED LID WITH NO DAMPERS. NEED PLAN SPLICE DELETING FIRE DAMPERS IN LAUNDRY IF THE WALL IS NOT RATED AND DAMPERS NOT REQUIRED. HAVE ENGINEER ADDRESS COMBUSTION AIR FOR POOL BOILERS. PLAN SHOWS DIRECT VENT BOILERS AND NON DIRECT VENT INSTALLED. NEED TO REVISE EQUIPMENT SCHEDULE FOR POOL BOILERS AS WELL. ENGINEER TO DRAW DETAIL FOR CLEARANCE REDUCTION FOR COMMERCIAL DRYER VENT. BRING 4" DRYER VENTS BELOW CEILING AND CAP VENT FOR FUTURE USE. | DUSTINS | DUSTINS | | H= | P | 5974255 |
PARKEY'S REFRIGERATION CO., INC | H= | L | 09/21/2018 | CONTRACTOR CANCELLED AT CALL AHEAD. | DUSTINS | DUSTINS | | H= | L | 5972945 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/17/2018 | NEED CONTRACTOR THAT INSTALLED POOL BOILERS ATTACHED TO PERMIT AND CALL FOR INSPECTION. PROVIDE LETTER FROM ENGINEER APPROVING INSTALLATION OF EXHAUST FANS IN FIRST FLOOR GUEST ROOMS. FANS ARE BEING INSTALLED IN FRAMING BELOW RATED LID WITH NO DAMPERS. NEED PLAN SPLICE DELETING FIRE DAMPERS IN LAUNDRY IF THE WALL IS NOT RATED AND DAMPERS NOT REQUIRED. HAVE ENGINEER ADDRESS COMBUSTION AIR FOR POOL BOILERS. PLAN SHOWS DIRECT VENT BOILERS AND NON DIRECT VENT INSTALLED. NEED TO REVISE EQUIPMENT SCHEDULE FOR POOL BOILERS AS WELL. ENGINEER TO DRAW DETAIL FOR CLEARANCE REDUCTION FOR COMMERCIAL DRYER VENT. NEED DRYER INSTALLATION INSTRUCTIONS FOR GUEST DRYERS TO VERIFY VENT LENGTHS. NEED TO SEE THERMOSTATS INSTALLED IN ALL ROOMS. ROOF OK, JUST NEED TO LABEL ALL EQUIPMENT FOR AREA SERVED, INCLUDING EQUIPMENT ON GROUND. REPAIR ARMAFLEX ON SUCTION LINE IN PANTRY, ALSO NEED TO SEE EXHAUST FAN IN PANTRY ONCE DRY WALL INSTALLED. | DUSTINS | DUSTINS | | H= | P | 5966974 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 09/13/2018 | NEED "DO NOT USE ELEVATOR IN CASE OF EMERGENCY" SIGNS POSTED ON ALL FLOORS NEAR HALL CALL STATIONS, REST OK. | ROBERTV | ROBERTV | | HE= | P | 5964684 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/13/2018 | NEED CONTRACTOR THAT INSTALLED POOL BOILERS ATTACHED TO PERMIT AND CALL FOR INSPECTION. PROVIDE LETTER FROM ENGINEER APPROVING INSTALLATION OF EXHAUST FANS IN FIRST FLOOR GUEST ROOMS. FANS ARE BEING INSTALLED IN FRAMING BELOW RATED LID WITH NO DAMPERS. NEED ENGINEER LETTER WILL BE ACCEPTABLE FOR THE OUTSIDE AIR DELETION FOR F-1, THE LETTER WILL ALSO NEED TO ADDRESS THE VENTILATION SCHEDULE ON THE PLAN. NEED PLAN SPLICE DELETING FIRE DAMPERS IN LAUNDRY IF THE WALL IS NOT RATED AND DAMPERS NOT REQUIRED. HAVE ENGINEER ADDRESS COMBUSTION AIR FOR POOL BOILERS. PLAN SHOWS DIRECT VENT BOILERS AND NON DIRECT VENT INSTALLED. NEED TO REVISE EQUIPMENT SCHEDULE FOR POOL BOILERS AS WELL. ENGINEER TO DRAW DETAIL FOR CLEARANCE REDUCTION FOR COMMERCIAL DRYER VENT. NEED DRYER INSTALLATION INSTRUCTIONS FOR GUEST DRYERS TO VERIFY VENT LENGTHS. FIRST FLOOR COMMON AREA MECHANICAL FINAL OK. NEED TO SEE ALL HOTEL ROOMS AND ROOF STILL. FURNACE VENT TERMINATIONS ON EAST SIDE NEED CORRECTED. | DUSTINS | DUSTINS | | H= | P | 5964691 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/11/2018 | HAVE ENGINEER ADDRESS COMBUSTION AIR FOR POOL BOILERS. PLAN SHOWS DIRECT VENT BOILERS AND NON DIRECT VENT INSTALLED. NEED TO REVISE EQUIPMENT SCHEDULE FOR POOL BOILERS AS WELL. ENGINEER TO DRAW DETAIL FOR CLEARANCE REDUCTION FOR COMMERCIAL DRYER VENT. NEED DRYER INSTALLATION INSTRUCTIONS FOR GUEST DRYERS TO VERIFY VENT LENGTHS. | DUSTINS | DUSTINS | | H= | P | 5961344 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/07/2018 | NEED PLAN SPLICE DELETING FIRE DAMPERS IN LAUNDRY IF THE WALL IS NOT RATED AND DAMPERS NOT REQUIRED. MISSING SUPPLY AIR FLEX AND DIFFUSERS IN BATHROOMS OK. CLEAR VINYL TUBING IN SOFFIT FOR CONDENSATE CORRECTED AND IS NOW OK. | DUSTINS | DUSTINS | | H= | P | 5958751 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 09/05/2018 | (ELEVATORS #1 AND #2 ) - NEED "IN CASE OF EMERGENCY DO NOT USE ELEVATOR" SIGNS AT EACH ELEVATOR LOBBY HALL CALL FIXTURE. NEED OPERABLE EMERGENCY PHONES IN ELEVATORS. NUMBER ELEVATOR CROSSHEAD AND CONTROLLER WITH APPROPRIATE DESIGNATION. ADJUST DOOR CLUTCH AND ROLLERS SO HOISTWAY DOORS DO NOT SEPARATE FROM CAB DOORS. DOOR RESTRICTORS NEED ADJUSTED TO ALLOW CAB DOOR TO BE OPENED BETWEEN A ZERO AND SEVEN INCH THRESHOLD WITH LOSS OF POWER. TOP OF HOISTWAY DAMPER ROMEX WIRING NEEDS TO COMPLY WITH NEC 2014 620.21 WIRING METHODS. NEED HEAT DETECTOR IN ELEVATOR PIT TO COVER MACHINE SPACE/S, AND MUST INITIATE AN ALTERNATE FLOOR RECALL WITH FLASHING HAT. SEAL HOISTWAY PENETRATIONS FOR SUMP PIPING | ROBERTV | ROBERTV | | HE= | P | 5954987 |
PARKEY'S REFRIGERATION CO., INC | HSP | P | 09/05/2018 | CONTRACTOR MENTIONED THE OUTSIDE AIR TO THE PTAC UNITS IS NOT GOING TO BE USED AND THE SHIPPING SCREW IS STILL IN THE VENT DOOR FOR ALL PTAC UNITS AND THERE WOULD NOT BE AN ISSUE FOR FURNACE VENT TERMINATIONS ON F1 AND F2 TO THE PTAC UNITS, HOWEVER, THE PLAN CALLS FOR 33 CFM OF TOTAL OUTSIDE AIR FOR EACH OF THE PTAC UNITS SO THE VENT DOORS WOULD NOT BE ABLE TO BE LEFT CLOSED AND UN OPERABLE. | DUSTINS | DUSTINS | | HSP | P | 5954790 |
PARKEY'S REFRIGERATION CO., INC | H= | P | 09/04/2018 | F1-MISSING SUPPLY AIR TO BOTH BATHROOMS NEAR WORKOUT AREA. F2, F3 AND F4 SUPPLY AND RETURN DUCTS AND OUTSIDE AIR COMPLETE, FLEX DIFFUSERS OK, F3- CAN NOT HAVE CLEAR VINYL TUBING IN SOFFIT SPACE FOR CONDENSATE AND F4 CONDENSATE IS OK . PLAN SHOWS FIRE DAMPER TRANSFER GRILLES FROM GUEST LAUNDRY TO COMMERCIAL LAUNDRY AND FIRE DAMPER FOR SUPPLY TO GUEST LAUNDRY AND IS NOT INSTALLED . NEED TO RESEARCH F1 AND F2 VENT TERMANTION CLEARANCES. | DUSTINS | DUSTINS | | H= | P | 5954421 |
BRUIN ENTERPRISES, INC. | H= | P | 08/29/2018 | REGULATORS AND MEDIUM PRESSURE STICKERS IN PLACE. FINAL PENDING 2 LB APPROVAL LETTER FROM CSU. | DUSTINS | DUSTINS | | H= | P | 5949926 |
BRUIN ENTERPRISES, INC. | HV | C | 08/29/2018 | WATER HEATER VENTS OK. | DUSTINS | DUSTINS | | HV | C | 5949921 |
PARKEY'S REFRIGERATION CO., INC | HV | P | 08/23/2018 | F-1, F-2, F-3 AND F-4 ALL COMBUSTION AIR PIPES AND EXHAUST VENTS NEED CORRECTED, CAN NOT HAVE THE 2" TO 3" REDUCER IN THE HORIZONTAL. | DUSTINS | DUSTINS | | HV | P | 5944067 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 08/23/2018 | UPDATED 8-24-18 DS: ENGINEER LETTER WILL BE ACCEPTABLE FOR THE OUTSIDE AIR DELETION FOR F-1, THE LETTER WILL ALSO NEED TO ADDRESS THE VENTILATION SCHEDULE ON THE PLAN. NEED TO CONSULT WITH SENIOR INSPECTOR ABOUT OUTSIDE AIR REMOVAL, CONTRACTOR ASKED IF ENGINEER LETTER WILL BE ACCEPTABLE FOR F-1. WILL UPDATE. SUPPLY AND RETURN DUCTS OK FOR F-3 AND F-4. STILL NEED TO COMPLETE F-1 AND F-2 STILL NEED TO SEE ALL FLEX AND DIFFUSERS. COMPLETE OUTSIDE AIR DUCT FOR F-4. F-1 AND F-2 CONDENSATE LINES OK. | DUSTINS | DUSTINS | | HD | P | 5944062 |
PARKEY'S REFRIGERATION CO., INC | HSP | P | 07/30/2018 | RANGE EXHAUST NOT REQUIRED PER RBC 304.4.6 | DUSTINS | DUSTINS | | HSP | P | 5918164 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 07/30/2018 | DUCTS IN SOFFIT SPACE OK. F-1: COMPLETE OUTSIDE AIR AND RETURN AIR DUCTS. F2: COMPLETE OUTSIDE AIR, RETURN AIR AND SUPPLY AIR DUCTS. F3: COMPLETE OUTSIDE AIR, RETURN AIR AND SUPPLY AIR DUCTS. F4: COMPLETE OUTSIDE AIR, RETURN AIR, AND THE 2 SUPPLY AIR DUCTS IN BREAKFAST AREA. WHEN VENTS FOR FURNACES ARE INSTALLED PLEASE CALL FOR INSPECTION. | DUSTINS | DUSTINS | | HD | P | 5918156 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 07/16/2018 | NEED CONTRACTOR INSTALLING POOL BOILER AND SPA BOILER TO ATTACH TO PERMIT. NEED TO CHECK ON IF THE OVEN NEEDS A RANGE EXHAUST. M2.1 (BDA 290) F-4 SUPPLY DUCT IN SOFFIT OK. | DUSTINS | DUSTINS | | HD | P | 5903556 |
BRUIN ENTERPRISES, INC. | HO | P | 06/29/2018 | NEED TO SEE REGULATOR AND MEDIUM PRESSURE STICKERS FOR FINAL. 10 LB TEST OK ON GAS LINE TO FIRE PIT. PIPING INSTALLED PER PRINT. OK TO COVER. | DUSTINS | DUSTINS | | HO | P | 5889609 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 05/30/2018 | PROVIDE LETTER FROM ENGINEER APPROVING INSTALLATION OF EXHAUST FANS IN FIRST FLOOR GUEST ROOMS. FANS ARE BEING INSTALLED IN FRAMING BELOW RATED LID WITH NO DAMPERS. FIRST FLOOR GUEST ROOM EXHAUST FANS ABOVE CEILING ALL OK. | NANCY | NANCY | | HD | P | 5859520 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 05/24/2018 | CANCELED AT CALL AHEAD. | NANCY | NANCY | | HD | P | 5855601 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 05/21/2018 | MAIN FLOOR GUEST ROOM BATH EXHAUST FANS ARE NOW BEING INSTALLED IN METAL FRAMED CEILING BELOW THE RATED LID. PRINTS SHOW FANS TO BE INSTALLED IN GYP BOARD CEILING WITH FIRE DAMPER. NEED REVISED/APPROVED PRINT OR LETTER FROM ENGINEER APPROVING THIS NEW INSTALLATION ON FIRST FLOOR. IF INSTALLING FAN BELOW RATING NO DAMPER REQUIRED BUT NEED ENGINEER TO ADDRESS PROTECTION OF EXHAUST DUCT AT RATED LID. | NANCY | NANCY | | HD | P | 5851227 |
BRUIN ENTERPRISES, INC. | HC | C | 05/16/2018 | OK TO SET 2 LB METER. | NANCY | NANCY | | HC | C | 5846650 |
BRUIN ENTERPRISES, INC. | HI | P | 05/16/2018 | BY FINAL NEED LETTER FROM CSU APPROVING MEDIUM PRESSURE GAS FOR THIS ADDRESS. 10 LB TEST OK ON ALL INSIDE GAS LINES EXCEPT STILL NEED GAS LINES TO WATER HEATERS INSTALLED AND TESTED. INSTALLED AS PER PLAN. SEE PREVIOUS NOTES REGARDING GAS LINE TO FIRE PIT. | NANCY | NANCY | | HI | P | 5846645 |
BRUIN ENTERPRISES, INC. | HI | P | 05/15/2018 | INSTALL 1 INCH GAS LINE TO POOL BOILER EQUIPMENT ROOM AS PER PLAN. RETEST GAS LINE. REST OF INSIDE GAS LINE INSTALLED AS PER PLAN EXCEPT STILL NEED TO SEE GAS TO WATER HEATERS, GAS IS ONLY STUBBED INTO ROOM. 10 LB TEST OK TODAY. STILL NEED TO SEE UNDERGROUND GAS LINE TO FIREPIT (SLEEVE GAS LINE). BY FINAL INSTALL REGULATORS AND LABELS. | NANCY | NANCY | | HI | P | 5845869 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 05/14/2018 | EF-2 ON LEVELS 2, 3 AND 4 OK. OK TO COVER. | NANCY | NANCY | | HD | P | 5844037 |
PARKEY'S REFRIGERATION CO., INC | HV | P | 03/19/2018 | F-3 AND F-4 VENTS IN WALL OUT THROUGH ROOF OK. FOLLOW MANUFACTURERS INSTRUCTIONS FOR CORRECT TERMINATION OF VENTS ON ROOF. | NANCY | NANCY | | HV | P | 5792595 |
PARKEY'S REFRIGERATION CO., INC | HV | P | 03/15/2018 | AUTO CALL COMPLETE AT 2:01 - ARRIVED 2:40 - NO ON SITE PERSONNEL - CALLED CALLED AHEAD NUMBER TWICE / NO ANSWER - STOPPED INSPECTION - NEED FURNACE MANUAL TO VERIFY VENTING PER PREVIOUS NOTES | JERRYF | JERRYF | | HV | P | 5790261 |
PARKEY'S REFRIGERATION CO., INC | HV | R | 03/05/2018 | STOPPED INSPECTION NOT READY - NEED FURNACE INSTALL MANUAL TO VERIFY VENTING MATERIALS AND DISTANCE REQUIREMENTS / HAS 3 DIFFERENT TYPES OF PVC MATERIALS USED ON VENTING / USING F891 CELL CORE / ASTM 2665 / ASTM 1785 - NEED NAIL PROTECTION ON BOTH SIDES OF WALLS AT ALL FLOORS AND CEILINGS - NEED VERTICAL SUPPORT IN WALLS - NEED PLAN REVISION FOR RELOCATED FURNACE VENTS IN WALLS - HOW ARE VENTS TO BE CONCEALED IN WALLS VENTS ARE NOT IN WALLS COMPLETELY | JERRYF | JERRYF | | HV | R | 5780414 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 02/07/2018 | ITEMS FROM INSPECTION DATE 05/FEB/2018 CORRECTED | LIDO | LIDO | | HD | P | 5760194 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 02/05/2018 | SECOND FLOOR. 207: SEAL JOINT AT UPPER FLOOR. CHECK BACK DRAFT DAMPER, DOES NOT WANT TO CLOSE. 213: SEAL JOINT IN WALL. REST OF SECOND FLOOR GUEST ROOMS EXHAUST OK. | NANCY | NANCY | | HD | P | 5757324 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 02/01/2018 | SECOND FLOOR. 221: STRAP EXHAUST DUCT. 222: STRAP EXHAUST DUCT AND INSTALL DAMPER IN FAN. 223: SEAL MISSED JOINT AT FLOOR. 224: OK. 225: PROPERLY SECURE WOOD BLOCK TO STRUCTURE. 226: SCREWS DO NOT ALLOW BACK DRAFT DAMPER TO CLOSE. 228: OK. | NANCY | NANCY | | HD | P | 5754668 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/31/2018 | THIRD FLOOR GUEST ROOMS ABOVE CEILING ALL OK. | NANCY | NANCY | | HD | P | 5753574 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/30/2018 | ROOF CEILING ASSEMBLY NOW BEING INSTALLED IS THE UL-P545, WILL NEED LETTER FROM ENGINEER APPROVING INSTALLATION OF BATH EXHAUST FANS AND DAMPERS IN THIS ASSEMBLY. THIRD FLOOR. 317: REPAIR TWO BROKEN JOINTS ON BATH EXHAUST. 324: PROPERLY INSTALL FAN FROM STRUCTURE. REST OF THIRD FLOOR GUEST ROOMS OK. | NANCY | NANCY | | HD | P | 5751891 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/29/2018 | THIRD FLOOR. STOPPED INSPECTION. REINSPECT ALL ROOMS EXCEPT ONES PREVIOUSLY NOTED AS OK. | NANCY | NANCY | | HD | P | 5750650 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/26/2018 | THIRD FLOOR NORTH END GUEST ROOMS. 301, 304 AND 314: NOT READY. 305, 306, 307, 308, 309, 310, 311, 312, 313: EXHAUST ABOVE CEILING OK. | NANCY | NANCY | | HD | P | 5749271 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/24/2018 | FOURTH FLOOR. BATH EXHAUST IN ALL ROOMS OK. | NANCY | NANCY | | HD | P | 5746958 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/23/2018 | FOURTH FLOOR. ROOMS 401, 403 AND 404 NOT READY. REST OF ROOMS ON FOURTH FLOOR OK. NO EF-2 OR PTAC'S YET. | NANCY | NANCY | | HD | P | 5745252 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/18/2018 | FOURTH FLOOR EXHAUST DROPS OK TO WRAP EXCEPT FOR ROOM # 424 MISSING END CAP . Need to square up exhaust fan in room # 410 Rooms 401,403,404,405 not ready . | LIDO | LIDO | | HD | P | 5742033 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/11/2018 | P-522 ASSEMBLY DOES NOT LIST THE BROAN RDM-1 AS AN APPROVED DAMPER, SEE PAGE FR-2. FOURTH FLOOR EXHAUST: PROPERLY INSTALL START COLLARS AT EXHAUST DROPS. BEND AND SEAL CORNERS ON EXHAUST DROPS. PROPERLY INSTALL EXHAUST FANS TO STRUCTURE PER MANUFACTURERS INSTRUCTIONS. OK TO WRAP ROUND EXHAUST DUCTS. | NANCY | NANCY | | HD | P | 5735572 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 01/05/2018 | GAS/WATER HEATER VENT CONTRACTOR MUST ATTACH TO PERMIT AND CALL FOR INSPECTION WHEN READY. WILL NEED REVISED/APPROVED PRINTS FOR CHANGES BEING MADE IN FIELD (VENT TERMINATION LOCATIONS, METER LOCATION, BATH EXHAUST ON ROOF ETC.). BATH EXHAUST IN ATTIC WILL REQUIRE INSULATION. | NANCY | NANCY | | HD | P | 5729779 |
PARKEY'S REFRIGERATION CO., INC | HD | P | 12/05/2017 | NEED REVISED/APPROVED PRINTS. CONTRACTOR IS WORKING OFF A SET OF PRINTS THAT HAS NOT BEEN APPROVED BY RBD. SET ON SITE HAS MULTIPLE CHANGES FROM THE STAMPED SET. REVISED PRINTS MUST SHOW ALL CHANGES SUCH AS THE ADDED KITCHEN, POOL BOILER ROOM AND POOL EQUIPMENT, NEW GAS INSTALLATION AND METER LOCATION, SIZING FOR GAS TO FIREPIT, CHANGES TO BATH EXHAUST FANS IN CEILINGS ETC. CONTRACTOR INSTALLING GAS LINES MUST ATTACH TO PERMIT. CONTRACTOR INSTALLING WATER HEATER VENTS MUST ATTACH TO PERMIT OR ADD VENTS TO SCOPE OF WORK AND CALL FOR INSPECTION WHEN READY. CONTRACTOR TO VERIFY ALL DAMPERS BEING INSTALLED IN RATED ASSEMBLIES ARE APPROVED FOR THAT ASSEMBLY TYPE. RELAYED INFORMATION TO BRANDON TO CALL FREQUENT INSPECTIONS FOR THIS PROJECT. | NANCY | NANCY | | HD | P | 5702783 |
BRUIN ENTERPRISES, INC. | P= | C | 09/27/2018 | note: engineers letter sent to scanning. | TAYLOR | TAYLOR | | P= | C | 5979521 |
BRUIN ENTERPRISES, INC. | P= | P | 09/26/2018 | need 16-18 inches from side wall to center of toilet at mens restroom, missing trap guard at pool equipment room, need to inspect piping in elevator shaft, still need to revise plans for elimination of isolation valves. | TAYLOR | TAYLOR | | P= | P | 5976694 |
BRUIN ENTERPRISES, INC. | P= | P | 09/14/2018 | womens restroom, break room sink, employee sink and restroom ok. | TAYLOR | TAYLOR | | P= | P | 5965318 |
BRUIN ENTERPRISES, INC. | P= | P | 09/13/2018 | 2nd, 3rd, and 4th floors complete. | TAYLOR | TAYLOR | | P= | P | 5964534 |
BRUIN ENTERPRISES, INC. | P= | P | 09/05/2018 | rooms 101 - 113 ok. | TAYLOR | TAYLOR | | P= | P | 5955036 |
BRUIN ENTERPRISES, INC. | P= | P | 09/04/2018 | 3rd floor ok minus rooms 320 and 321, 2nd floor ok minus rooms 220 and 221. | TAYLOR | TAYLOR | | P= | P | 5953709 |
BRUIN ENTERPRISES, INC. | P= | P | 08/31/2018 | Room 420 not ready, 405 waters crossed at shower valve, rest of fourth floor OK, rooms 301 - 310 OK, caulk tub spouts throughout | SHANEN | SHANEN | | P= | P | 5953325 |
BRUIN ENTERPRISES, INC. | PRD | C | 08/22/2018 | canopy roof and overflow drains ok, need to revise plans to show piping. | TAYLOR | TAYLOR | | PRD | C | 5941908 |
BRUIN ENTERPRISES, INC. | PTO | C | 08/22/2018 | flanges ok on 1st floor, check oil alarm at sump in elevator shaft and revise plans by final. | TAYLOR | TAYLOR | | PTO | C | 5941903 |
BRUIN ENTERPRISES, INC. | PRD | C | 01/08/2018 | Test and design OK | SHANEN | SHANEN | | PRD | C | 5732125 |
BRUIN ENTERPRISES, INC. | PTO | P | 01/08/2018 | Need plans revised or letter from engineer eliminating isolation valves for individual units, set and secure main level closet flanges, rest OK, AAV - floor drain for south side 2nd floor ice machine, pantry sink, sink behind front desk, and employee sink, trench drain, floor sink in commercial laundry | SHANEN | SHANEN | | PTO | P | 5732068 |
BRUIN ENTERPRISES, INC. | PTO | P | 01/05/2018 | DWV test OK all rooms all floors, need to check plans and design on next inspection, stem walls in accessible units encroach into 5' turn radius, | SHANEN | SHANEN | | PTO | P | 5730703 |
BRUIN ENTERPRISES, INC. | PRD | P | 07/25/2017 | 6 inch on test to plan | GABE | GABE | | PRD | P | 5575616 |
BRUIN ENTERPRISES, INC. | PB | C | 07/25/2017 | corrections made , dwv on test , base complete . | GABE | GABE | | PB | C | 5575594 |
BRUIN ENTERPRISES, INC. | PB | P | 07/21/2017 | need 3'' f.d for laundry room, still need to install all shower p-traps | JOEL | JOEL | | PB | P | 5571857 |
BRUIN ENTERPRISES, INC. | XPS | T | 09/26/2018 | PAID (REC#1541752): PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 9-26-18 | TCRIPPEN | TCRIPPEN | | XPS | T | 5977998 |
THE WRIGHT GROUP, LLC | XBS | T | 09/24/2018 | PAID (REC#1540526) PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised column and beam assemblies for porte-cochere | LBENNETT | LBENNETT | | XBS | T | 5974449 |
BRUIN ENTERPRISES, INC. | XPS | P | 09/24/2018 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing: plumbing splice 9-24-18 | TCRIPPEN | TCRIPPEN | | XPS | P | 5974382 |
PARKEY'S REFRIGERATION CO., INC | XMS | T | 09/24/2018 | PAID (REC#1540528) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: delta 9 | DALEH | DALEH | | XMS | T | 5974339 |
EMF ELECTRICAL CORPORATION | XES | T | 09/12/2018 | PAID (REC#1536408) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised rating and fault current for Panel P. | BERTHA | BERTHA | | XES | T | 5962480 |
EMF ELECTRICAL CORPORATION | XES | T | 08/31/2018 | PAID (REC#1533033) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: As Built conditions | BERTHA | BERTHA | | XES | T | 5953264 |
THE WRIGHT GROUP, LLC | XBS | T | 08/21/2018 | PAID (REC#1529206) PLAN SPLICE FEE: $50 by: DANM for Construction: Notes pertaining to connecting roof drain to storm drain system | DANM | DANM | | XBS | T | 5940600 |
BRUIN ENTERPRISES, INC. | XPS | T | 07/17/2018 | PAID (REC#1529100) PLAN SPLICE FEE: $50 by: DALEH for Plumbing: domestic cold water tie in to pool equipment | DALEH | DALEH | | XPS | T | 5905442 |
THE WRIGHT GROUP, LLC | XBS | P | 06/12/2018 | PLAN SPLICE: (No Fee) by: DANM for Construction: Sheet FR-4 - several details revised | DANM | DANM | | XBS | P | 5871378 |
THE WRIGHT GROUP, LLC | XBS | T | 06/05/2018 | PAID (REC#1505132) PLAN SPLICE FEE: $50 by: DANM for Construction: Sheet FR-4 (not a part of original permitted drawings) shows various details and fire rating clarification | DANM | DANM | | XBS | T | 5864673 |
PARKEY'S REFRIGERATION CO., INC | XMS | T | 04/12/2018 | PAID (REC#1496480): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: mechanical splice 4-12-18 | TCRIPPEN | TCRIPPEN | | XMS | T | 5814924 |
THE WRIGHT GROUP, LLC | XBS | T | 01/29/2018 | PAID (REC#1478916) PLAN SPLICE FEE: $50 by: DANM for Construction: minor architectural revisions and structural details | DANM | DANM | | XBS | T | 5750655 |