SUN CONSTRUCTION & FACILITY SERVICES, INC. | B= | C | 04/04/2018 | all other finals now signed off | MINDY | MINDY | | B= | C | 5806964 |
SUN CONSTRUCTION & FACILITY SERVICES, INC. | BE | L | 04/04/2018 | Renewed at 4/4/2018 7:51:08 AM | MINDY | MINDY | | BE | L | 5806962 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | BSP | T | 09/05/2017 | PAID (REC#1450919) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised for as-built conditions | JUSTINC | JUSTINC | | BSP | T | 5616488 |
SUN CONSTRUCTION & FACILITY SERVICES, INC. | B= | R | 08/30/2017 | No call-ahead number provided, no one on site / called Sun's office, transferred to PM Matt Sigward - left VM / need to complete BFR. /////ADDED COMMENT - met with Cliff (Sun) - verified framing per BFR notes - Building Final OK pending other Finals Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), M TECH MECHANICAL TECHNOLOGIES GROUP, IN Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | R | 5611403 |
SUN CONSTRUCTION & FACILITY SERVICES, INC. | BFR | P | 07/18/2017 | All interior framing at Micro-Focus complete to include walls and all hardlids. Verified all backing to be fire retardant treated lumber // Phase 2 of corridor framing complete at all EXCEPT south end of corridor. Will need to see completion of wall and door framing once finished. | JEREMYA | JEREMYA | | BFR | P | 5568208 |
DYNALECTRIC COMPANY | E= | C | 08/29/2017 | | JOHNN | JOHNN | | E= | C | 5609579 |
DYNALECTRIC COMPANY | E= | P | 08/28/2017 | need cb lock on insta hot,ok to upload pic to permit | JOHNN | JOHNN | | E= | P | 5608579 |
DYNALECTRIC COMPANY | E= | C | 08/28/2017 | FIRE ALARM INSPECTION: | JOHNN | JOHNN | | E= | C | 5608561 |
DYNALECTRIC COMPANY | ER | P | 08/10/2017 | all hard lids | JOHNN | JOHNN | | ER | P | 5591789 |
DYNALECTRIC COMPANY | ER | P | 07/24/2017 | all walls,ok | JOHNN | JOHNN | | ER | P | 5573432 |
DYNALECTRIC COMPANY | ER | L | 07/21/2017 | need POC on site,need correct call ahead # | JOHNN | JOHNN | | ER | L | 5571734 |
DYNALECTRIC COMPANY | ER | P | 07/18/2017 | walls, except:4 a/v boxes, and west perimeter wall, | JOHNN | JOHNN | | ER | P | 5567442 |
DYNALECTRIC COMPANY | ER | P | 07/18/2017 | FIRE ALARM INSPECTION: wall stubs only, | JOHNN | JOHNN | | ER | P | 5567436 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | C | 11/20/2017 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5689742 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 08/25/2017 | CFM READING FOR FCU 2 WELL OUTSIDE +/- 10% - WILL NEED LETTER FROM ENGINEER APPROVING READINGS OR REVISED TAB REPORT - ATTACH TO NEXT INSPECTION REQUEST - REST OK | JERRYF | JERRYF | | H= | P | 5607448 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | H= | P | 08/21/2017 | NEED ALL MEDIUM PRESSURE FINAL CONNECTIONS AT BOXES - COMPLETE FCU IN ELECTRIC ROOM - TAB REPORT - PLAN SPLICE FOR RELOCATED TRANSFER DUCT - ALL OTHER SA / RA GRILLES AND FINAL CONNECTIONS ARE COMPLETE | JERRYF | JERRYF | | H= | P | 5602274 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HWP | C | 08/21/2017 | AT FINAL VERIFY CONDENSATE DRAIN AT FCU IN ELECTRIC ROOM - ALL OTHER OK - PIPING PER PLAN - OK TO INSULATE | JERRYF | JERRYF | | HWP | C | 5602268 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HD | P | 08/11/2017 | ABOVE CEILING LOW / MEDIUM PRESSURE SA MAINS AND RUN OUTS OK TO WRAP - STILL NEED ALL BOXES / MEDIUM / LOW PRESSURE DUCT TIE INS - BY FINAL REVISE PLAN SHOWING RELOCATED TRANSFER FROM STORAGE TO HALLWAY AND TRANSFER AIR FROM THE FOLLOWING OFFICES F54 - F53 - F52 | JERRYF | JERRYF | | HD | P | 5593302 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HWP | P | 07/20/2017 | PRESSURE TEST OK TO 4 ZONES FOR HWP / CHILLED WATER LINES OK TO WRAP - STILL NEED ALL FINAL CONNECTIONS AT BOXS - BY FINAL REVISE PLAN TO SHOW ACTUAL INSTALLED ROUTING | JERRYF | JERRYF | | HWP | P | 5571047 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | P= | C | 08/28/2017 | | TAYLOR | TAYLOR | | P= | C | 5608473 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | PTO | C | 07/18/2017 | VTR, check water heater by final. | TAYLOR | TAYLOR | | PTO | C | 5567881 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | PB | C | 07/18/2017 | | TAYLOR | TAYLOR | | PB | C | 5567872 |