GUARINO CONSTRUCTION, LLC | B= | C | 09/13/2018 | All other required Final inspections are complete. (This is a computer generated result) | RICHB | RICHB | | B= | C | 5964795 |
GUARINO CONSTRUCTION, LLC | B= | P | 04/18/2018 | Remodel complete pending Mechanical. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), PREMIER MECHANICAL Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5820398 |
GUARINO CONSTRUCTION, LLC | BIN | C | 11/21/2017 | Ceiling insulation OK | RICHB | RICHB | | BIN | C | 5691767 |
GUARINO CONSTRUCTION, LLC | BFR | P | 09/20/2017 | Interior non bearing not rated framing okay, pending other roughs. Discussed accessible elements. Will need to inspect roof ceiling insulation once above ceiling work is complete. Permit set review on site, Training with Noah. | RICHB | RICHB | | BFR | P | 5631702 |
GUARINO CONSTRUCTION, LLC | BSP | T | 08/18/2017 | PAID (REC#1447445) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: splice to go from mini splits to rtu's | DALEH | DALEH | | BSP | T | 5600805 |
GUARINO CONSTRUCTION, LLC | BSP | P | 08/18/2017 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Added RTU-1 and RTU-2. | BERTHA | BERTHA | | BSP | P | 5600728 |
SPRINGS ELECTRIC | E= | C | 12/27/2017 | Corrections complete / | ROB | ROB | | E= | C | 5723089 |
SPRINGS ELECTRIC | E= | R | 12/18/2017 | Need service disconnects and panel labeling service 1 of 2 and 2 of 2---Need GF access at water cooler---2-60 amp RTU,s ok / | ROB | ROB | | E= | R | 5716239 |
SPRINGS ELECTRIC | ER | P | 11/02/2017 | Rough in ok for lay in ceiling / | ROB | ROB | | ER | P | 5674811 |
SPRINGS ELECTRIC | ER | P | 09/15/2017 | 2- Bathrooms, and mech room / | ROB | ROB | | ER | P | 5627272 |
PREMIER MECHANICAL | H= | C | 09/06/2018 | | MARKB | MARKB | | H= | C | 5957536 |
PREMIER MECHANICAL | H= | R | 07/09/2018 | No call ahead number provided, lock box number provided did not work and no access to roof provided. | MARKB | MARKB | | H= | R | 5896498 |
PREMIER MECHANICAL | HSP | C | 04/16/2018 | TAB RECEIVED | MARKB | MARKB | | HSP | C | 5817353 |
PREMIER MECHANICAL | H= | R | 03/07/2018 | PLANS CALL FOR 2- 150K RTUS CURRENTLY HAS 2- 100K RTUS INSTALLED. LACKS SERVICE OUTLETS WITHIN 25' OF RTUS AS PER PLAN. WILL NEED ELECTRICAL INSPECTION ON SERVICE OUTLET. PERMANENTLY LABEL RTUS FOR ADDRESS AND AREAS SERVED. EXTEND CONDENSATE DRAINS BEYOND CURB TO ROOF. NEED LOCKBOXES ON THERMOSTATS LOCATED ABOVE 48". SUPPORT BATH EXHAUST TERMINATION FOR MEN'S AND WOMEN'S BATHROOMS. UNDERCUT BATHROOM DOORS 1" PER PLAN. PROVIDE TEST AND BALANCE REPORT. | MARKB | MARKB | | H= | R | 5782982 |
PREMIER MECHANICAL | HD | C | 11/16/2017 | ABOVE CEILING DUCT INSTALLED PER PLAN. TOP SIDE OF DUCT IS INSULATED BOTTOM OF DUCT IS IN CONDITIONED SPACE. Still need RTU's inspected and TAB report. | MARKB | MARKB | | HD | C | 5688255 |
PREMIER MECHANICAL | HD | P | 09/19/2017 | Bath exhaust duct OK. Further research required on why Approved plans on site do not match approved plans in system. Note Added: Need to correct scope of work. Spoke with inspector Rich about RTU's placement and roof insulation - he will look on site and get back with me. | MARKB | MARKB | | HD | P | 5630730 |
CASCADE PLUMBING & HEATING | P= | C | 04/16/2018 | corrections made | JOHNS | JOHNS | | P= | C | 5817733 |
CASCADE PLUMBING & HEATING | P= | P | 03/07/2018 | trip fee waived, still need to caulk drinking fountains and base of water closets as previously noted, can complete w/ uploaded images to inspection request, rest ok for corrections | JOHNS | JOHNS | | P= | P | 5782591 |
CASCADE PLUMBING & HEATING | P= | P | 12/15/2017 | caulk d.f and base of both water closets, women's lav needs to be only 34" above floor, need women's flush handle on open side, water htr must be in pan and pan piped to utility sink as plans indicate, need roof access for vent termination inspection, rest ok. | JOHNS | JOHNS | | P= | P | 5714755 |
CASCADE PLUMBING & HEATING | PTO | C | 09/19/2017 | test and design ok per plan. note:vtr (1), NEED TO CHECK WATER HEATER @ FINAL | JOHNS | JOHNS | | PTO | C | 5630186 |
CASCADE PLUMBING & HEATING | PB | C | 08/22/2017 | still need elec and mech permits attached, rest ok, corrections made | JOHNS | JOHNS | | PB | C | 5603213 |
CASCADE PLUMBING & HEATING | PB | P | 08/21/2017 | gc needs to attach all permits, need to run floor drain as required per plans, rest ok | JOHNS | JOHNS | | PB | P | 5601628 |