GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 06/13/2018 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5873126 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 01/30/2018 | final OK at coffee room and focus rooms pending other finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2). | DANE | DANE | | B= | P | 5751637 |
GREINER ELECTRIC, LLC. | BSP | P | 01/02/2018 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Revise coffee room lighting | SHELBY | SHELBY | | BSP | P | 5726849 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/30/2017 | light gauge framing at coffee area and wellness at 1st floor OK / discussed accessible elements | DANE | DANE | | BFR | P | 5670951 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/06/2017 | need to attach electrical mechanical and plumbing permits and have inspections / all light gauge framing at 2nd floor "command center" OK pending other rough inspections / still need to inspect work on 1st floor when ready | DANE | DANE | | BFR | P | 5647488 |
GREINER ELECTRIC, LLC. | E= | C | 01/09/2018 | | GARYL | GARYL | | E= | C | 5732851 |
GREINER ELECTRIC, LLC. | E= | R | 12/15/2017 | deleted several light fixtures, need to revise prints | GARYL | GARYL | | E= | R | 5714730 |
GREINER ELECTRIC, LLC. | ER | P | 12/04/2017 | coffee and wellness ceilings ok | RANDY | RANDY | | ER | P | 5701291 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 11/27/2017 | FIRE ALARM INSPECTION: see notes | RANDY | RANDY | | E= | C | 5693979 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 11/27/2017 | FIRE ALARM INSPECTION: building 1 south entry speed gate- coffee--wellness 1st floor----2nd floor WPM | RANDY | RANDY | | ER | C | 5693977 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 11/27/2017 | FIRE ALARM INSPECTION: building 1 south entry speed gate- coffee--wellness 1st floor----2nd floor WPM | RANDY | RANDY | | E= | C | 5693978 |
GREINER ELECTRIC, LLC. | ER | P | 11/22/2017 | 2nd floor ceilings in rooms 201-204 ok | RANDY | RANDY | | ER | P | 5693369 |
GREINER ELECTRIC, LLC. | ER | P | 10/25/2017 | walls coffee 150 wellness 151 | BRET | BRET | | ER | P | 5666963 |
GREINER ELECTRIC, LLC. | ER | P | 10/16/2017 | walls only for rooms 201, 202, 203, 204 | CRAIG | CRAIG | | ER | P | 5656017 |
MECHONE, INC. | H= | C | 12/19/2017 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. | NANCY | NANCY | | H= | C | 5716590 |
MECHONE, INC. | H= | P | 12/15/2017 | MECHANICAL FINAL OK PENDING RECEIPT OF TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 5713847 |
MECHONE, INC. | HD | P | 10/16/2017 | LEVEL TWO. 10 INCH ROUND HIGH PRESSURE DUCT TO VAV-2 OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 5656711 |
HARMON - BONDED PLUMBING & HEATING, INC. | P= | C | 12/18/2017 | | SHANEN | SHANEN | | P= | C | 5716046 |
HARMON - BONDED PLUMBING & HEATING, INC. | PTO | C | 10/25/2017 | Test OK, design per plan | SHANEN | SHANEN | | PTO | C | 5667296 |