STOUT BUILDING CONTRACTORS,LLC | B= | C | 09/19/2018 | All other required Final inspections are complete. (This is a computer generated result) | RICHB | RICHB | | B= | C | 5969907 |
STOUT BUILDING CONTRACTORS,LLC | B= | P | 03/23/2018 | Remodel complete pending other Finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet, NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5797540 |
STOUT BUILDING CONTRACTORS,LLC | BFR | C | 03/13/2018 | Framing complete pending other Roughs (demo of several walls and new walls for Elec Room 116) / discussed B= requirements with Andrew (Superintendent) | RICHB | RICHB | | BFR | C | 5787207 |
STOUT BUILDING CONTRACTORS,LLC | BSP | P | 02/16/2018 | Called for drywall inspection - not required for this scope (cladding existing non-rated wall) / discussed overall project scope with interim Superintendent (Gene) | RICHB | RICHB | | BSP | P | 5767576 |
STOUT BUILDING CONTRACTORS,LLC | BFT | P | 01/17/2018 | Formwork & rebar for paint booth pit walls (see S1.2) OK / plans reviewed onsite | RICHB | RICHB | | BFT | P | 5739959 |
STOUT BUILDING CONTRACTORS,LLC | BSP | T | 12/27/2017 | PAID (REC#1476518) PLAN SPLICE FEE: $75 by: TCRIPPEN for Plumbing: plumbing splice 12-27-17 | TCRIPPEN | TCRIPPEN | | BSP | T | 5723385 |
NIELSEN MECHANICAL CONTRACTORS, INC. | BSP | T | 12/27/2017 | PAID (REC#1487484) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: revised entire design | DALEH | DALEH | | BSP | T | 5722806 |
STOUT BUILDING CONTRACTORS,LLC | BSP | T | 12/21/2017 | PAID (REC#1476518) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised entire floor plan | SHELLEY | SHELLEY | | BSP | T | 5719544 |
E K ELECTRIC, LLC | E= | C | 03/20/2018 | | DEAN | DEAN | | E= | C | 5794434 |
E K ELECTRIC, LLC | E= | R | 03/20/2018 | mc cable at jbox above lift needs a strapped to beam--upload pic with inspection request-- | MIGUEL | MIGUEL | | E= | R | 5794174 |
E K ELECTRIC, LLC | E= | P | 03/19/2018 | CAN NOT USE SO CORD FOR LIFT -----LABEL PANELS WITH AIC AND THE RATING OF REPLACEMENT BREAKERS-----INSTALL 30 AMP BREAKER FOR MUA-----SOUTH PAINT BOOTH DOESN'T SHUT DOWN THE AIR WHEN DOOR OPENS------ | BRIAN | BRIAN | | E= | P | 5792930 |
E K ELECTRIC, LLC | ER | P | 02/20/2018 | main floor bathroom lids x2 ok/ | MIGUEL | MIGUEL | | ER | P | 5769247 |
E K ELECTRIC, LLC | ER | P | 02/15/2018 | ceilings in front lobby, offices, and bull pen ok/ | MIGUEL | MIGUEL | | ER | P | 5767189 |
E K ELECTRIC, LLC | ER | P | 01/17/2018 | wall with two gang switch box next to the door headed for the offices ----OK | CRAIGS | CRAIGS | | ER | P | 5739982 |
E K ELECTRIC, LLC | EUG | C | 01/17/2018 | 2 --- pvc from reception desk to in the wall -OK | CRAIGS | CRAIGS | | EUG | C | 5739978 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 09/19/2018 | REST OF TAB REPORT RECEIVED. | MARKB | MARKB | | H= | C | 5969906 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 09/14/2018 | FINAL PENDING - Completion of TAB report. CONFIRMED OVERHEAD DOORS HAVE STOPS BUILT IN TO COMPLY WITH IMC SECTION 304.6 | MARKB | MARKB | | H= | P | 5965902 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 09/14/2018 | Engineer letter addressing unit heater removal, exhaust fan removal for the electrical room and Test And Balance readings for MAU and exhaust in shop area. Still need site visit and Test And Balance readings for RTU-1 with outside air readings. | MARKB | MARKB | | H= | P | 5965169 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 09/13/2018 | STILL NEED - TAB for building and need to check door height in relation to "Big Ass Fans" Engineer letter for MAU unit and TAB for paint booth on file. | MARKB | MARKB | | H= | P | 5963574 |
LANDMARK PLUMBING AND HEATING, INC. | H= | C | 03/23/2018 | CORRECTIONS MADE | MARKB | MARKB | | H= | C | 5797530 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 03/22/2018 | Regulator vents on roof need to be piped or turned down. Rest OK. | MARKB | MARKB | | H= | P | 5796345 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 03/20/2018 | FINAL PENDING - 1. Stamped Structural engineering letter for MUA unit weight on roof. 2. Plan splice for changes to TF-1, unit heater and cut sheets for paint booths. 3. "Big Ass" fans need to comply to 2009 IMC section 304.6 4. Provide Test And Balance report and factory start up for paint booths showing ventilation and exhaust rates. | MARKB | MARKB | | H= | P | 5794011 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | R | 03/16/2018 | Need structural engineer letter addressing new MAU - weight on roof and penetrations through roof. Need mechanical contractor attached to permit for paint booths. Need plan splice removing TF-1 and Unit heater. Further research required on BIG ASS fans - mounting height and contractor attachment. Provide Test And Balance Report. | MARKB | MARKB | | H= | R | 5791010 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | C | 03/16/2018 | EF-1 AND MUA DUCT COMPLETE | MARKB | MARKB | | HD | C | 5790990 |
LANDMARK PLUMBING AND HEATING, INC. | HC | C | 03/12/2018 | RELEASE METER - new piping for interior remodel | MARKB | MARKB | | HC | C | 5785888 |
LANDMARK PLUMBING AND HEATING, INC. | HI | C | 03/12/2018 | 10 PSI PRESSURE TEST OK. PIPING PER PLAN. Note: 2 psi At Final - 2 psi approval letter from CSU, medium pressure stickers and regulators | MARKB | MARKB | | HI | C | 5785884 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 05/17/2018 | Corrections made. | DANR | DANR | | P= | C | 5848058 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 03/22/2018 | need bfp @ coffee maker, flush handle @ accessible stalls need to be on open side, (x2) trap guards @ both baths and wash bay, (x4) need 60" side clearance @ womens accessible stall, check valve installed @ wrong location, need access panel for hub drain in wall @ utility sink, cap off un used water line @ wash bay, rest ok | JOHNS | JOHNS | | P= | P | 5796077 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 01/25/2018 | delete 1 urinal from scope (total 1 urinal), delete 1nfwh (total 4 nfwh), add 1 water connected appliance, rest ok for test and design per plan. note: vtr (existing), concealable hammer aerestor @ mens bath above ceiling @ urinal, check water connected appliance, water htr , and final water connections @ water entry by final | JOHNS | JOHNS | | PTO | C | 5747411 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 01/19/2018 | ok for test and design per plan @ detail area oil waste, this completes base. note: oil interceptor outside the structure, water existing @ water entry | JOHNS | JOHNS | | PB | C | 5742574 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 01/18/2018 | ok for both bath groups only, test and design per plan | JOHNS | JOHNS | | PB | P | 5740947 |