B & N CONSTRUCTION, INC. | B= | C | 05/17/2018 | All other required Final inspections are complete. (This is a computer generated result) | SCOTTS | SCOTTS | | B= | C | 5847796 |
B & N CONSTRUCTION, INC. | B= | P | 05/08/2018 | corrections complete. Additional Inspections Required (computer generated): External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | SCOTTS | SCOTTS | | B= | P | 5838425 |
B & N CONSTRUCTION, INC. | B= | P | 05/04/2018 | missing attic insulation -- post address facing road served -- extend step at garage man door to house -- finished basement/balcony/no decks -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection HD= by HEALTHDEPT is not Completed yet. | SCOTTS | SCOTTS | | B= | P | 5836059 |
B & N CONSTRUCTION, INC. | BLA | C | 03/21/2018 | weep screed to be a minimum of 4" above grade by final / Rear porch slab not poured at time of inspection | SHAUN | SHAUN | | BLA | C | 5795387 |
B & N CONSTRUCTION, INC. | BIN | C | 03/09/2018 | R19 batt insulation at ceiling okay with blown to follow / Insulation okay | SHAUN | SHAUN | | BIN | C | 5785058 |
B & N CONSTRUCTION, INC. | BFR | C | 03/09/2018 | Frame items completed | SHAUN | SHAUN | | BFR | C | 5785055 |
B & N CONSTRUCTION, INC. | BFN | C | 03/09/2018 | | SHAUN | SHAUN | | BFN | C | 5784450 |
B & N CONSTRUCTION, INC. | BFT | C | 03/09/2018 | | SHAUN | SHAUN | | BFT | C | 5784449 |
B & N CONSTRUCTION, INC. | BFN | C | 03/07/2018 | Open hole report received | SHAUN | SHAUN | | BFN | C | 5781774 |
B & N CONSTRUCTION, INC. | BFT | C | 03/07/2018 | Open hole report received | SHAUN | SHAUN | | BFT | C | 5781773 |
B & N CONSTRUCTION, INC. | BFR | P | 03/06/2018 | Foam and firestop // Garage entry side door added not on plans (has 1T and 1K EE with (2) 2X8 for header) // Missing (2) ST18 at CG north end // Need HTS20s at triple LVL by upstairs slider // Window above stairs needs 1 king west side // Strap balloon framed wall by stairs // Complete BFN and BFT | NOAH | NOAH | | BFR | P | 5780996 |
B & N CONSTRUCTION, INC. | BSP | P | 02/07/2018 | Letter on file for porch connections and extended trusses over rear porch // Front and rear porches okay | SHAUN | SHAUN | | BSP | P | 5759138 |
B & N CONSTRUCTION, INC. | BSP | R | 02/05/2018 | Post caps and bases different from plans // Deck joist and ledger connections okay Update: Trusses at covered porch don't match plans | SHAUN | SHAUN | | BSP | R | 5757200 |
B & N CONSTRUCTION, INC. | BSP | P | 01/18/2018 | Portal wall okay | SHAUN | SHAUN | | BSP | P | 5741184 |
B & N CONSTRUCTION, INC. | BSP | P | 01/04/2018 | piers ok | SCOTTS | SCOTTS | | BSP | P | 5728945 |
B & N CONSTRUCTION, INC. | BFD | C | 12/29/2017 | Soils report requires drain around entire, Field inspection shows drain around habitable and not around garage or across front of walk out // Received Soils report, 1,300 psf // Drain around entire // Isolate and float // 10% grade // Drain design // foundation design 1,000 psf // Footing and foundation observation // Still need open hole report -UPDATE- Received open holes report // Update - Drain does not need to be across front of walkout basement per open hole letter | SHAUN | SHAUN | | BFD | C | 5724863 |
B & N CONSTRUCTION, INC. | BFN | P | 12/29/2017 | Received Soils report, 1,300 psf // Drain around entire // Isolate and float // 10% grade // Drain design // foundation design 1,000 psf // Footing and foundation observation // Still need open hole report | SHAUN | SHAUN | | BFN | P | 5724861 |
B & N CONSTRUCTION, INC. | BFT | P | 12/29/2017 | Received Soils report, 1,300 psf // Drain around entire // Isolate and float // 10% grade // Drain design // foundation design 1,000 psf // Footing and foundation observation // Still need open hole report | SHAUN | SHAUN | | BFT | P | 5724859 |
B & N CONSTRUCTION, INC. | BFD | R | 12/28/2017 | Complete BFT and BFN // Provide soils, Open hole, Footing and foundation observations // Drain around habitable space and gravity out fall both sides to the west // Damp proofing okay | SHAUN | SHAUN | | BFD | R | 5724465 |
PORCH ELECTRIC, INC. | E= | C | 05/04/2018 | Photo accepted | JOSEPH | JOSEPH | | E= | C | 5835701 |
PORCH ELECTRIC, INC. | E= | R | 05/03/2018 | At the AC disconnect on the load side "A" phase. Half the strands are cut clean thru. I need you to restrip & reterminate that conductor. Will accept a photo send to joseph@pprbd.org ------- Notes: Rest is good ------- 30 amp ac | JOSEPH | JOSEPH | | E= | R | 5834930 |
PORCH ELECTRIC, INC. | E= | R | 05/02/2018 | Conductors scored at AC disconnect. Restrip & reterminate. ----- AC breaker too large (Min 25 Max 30) --------- Adjust dead front so it fit correctly. ------ Blocking in Mech room should go on top of cables not in front of cables. (exactly as you did next to the sub panel) ------ Notes: Hot tub pre wire ------- AC unit in | JOSEPH | JOSEPH | | E= | R | 5833803 |
PORCH ELECTRIC, INC. | ES | C | 02/28/2018 | Residential Underground: 200 amp 3w new res meter in need reseal | JOSEPH | JOSEPH | | ES | C | 5776592 |
PORCH ELECTRIC, INC. | ER | C | 02/28/2018 | Finished basement ------------- UFER is not ir ---------- 2 - 6/3 cu ---- SER 2224 to floated 100 amp sub -------- No vac | JOSEPH | JOSEPH | | ER | C | 5776590 |
PORCH ELECTRIC, INC. | EUG | C | 12/28/2017 | 250 al service lat ped to home | MATTHEW | MATTHEW | | EUG | C | 5724400 |
THE FURNACE GUY HEATING & COOLING | H= | C | 05/02/2018 | NOTE: No outside air to either furnace, 1- A/C installed, finished basement, HI-LOW grilles to mechanical room. | DUSTINS | DUSTINS | | H= | C | 5833356 |
THE FURNACE GUY HEATING & COOLING | HC | C | 03/05/2018 | RELEASE METER | PAULO | PAULO | | HC | C | 5779803 |
THE FURNACE GUY HEATING & COOLING | HRR | C | 03/05/2018 | note: finished basement, no outside air to either furnace return, 2- indirect vent furnaces, a/c rough and line set to furnace on left, no a/c to furnace on right. | PAULO | PAULO | | HRR | C | 5779802 |
NASRALLAH PLUMBING & HEATING, INC. | HO | C | 03/01/2018 | 10# test ok. note: 1/2" poly at 40' to home, tracer wire installed. L.P. | PAULO | PAULO | | HO | C | 5777589 |
THE FURNACE GUY HEATING & COOLING | HRR | P | 03/01/2018 | need the following-- insulation shield to b-vent, nail protection to dryer duct. note: finished basement, no outside air to either furnace return, 2- indirect vent furnaces, a/c rough and line set to furnace on left, no a/c to furnace on right. | PAULO | PAULO | | HRR | P | 5777588 |
ADEPT PLUMBING & HEATING LLC | HI | C | 02/28/2018 | 1 1/4'' 2- furnaces, 2- water heaters, range, dryer, bbq, 2- garage outlets below ceiling | TED | TED | | HI | C | 5776160 |
ADEPT PLUMBING & HEATING LLC | P= | C | 05/03/2018 | correction made backflow installed | TED | TED | | P= | C | 5835491 |
ADEPT PLUMBING & HEATING LLC | P= | P | 05/02/2018 | certificate of potable water to scanning | TED | TED | | P= | P | 5833082 |
ADEPT PLUMBING & HEATING LLC | P= | P | 05/01/2018 | need backflow on line to barn and hydrant, need certificate of potable water, rest ok, finished basement | TED | TED | | P= | P | 5832972 |
ADEPT PLUMBING & HEATING LLC | PTO | C | 02/28/2018 | at final will need tempering valve for master tub (will need to have access for it also, tub and fill valve not installed at this time), note: finished basement, aav on bar sink, will check water heater and pressure tank connections at final | TED | TED | | PTO | C | 5776173 |
ADEPT PLUMBING & HEATING LLC | PWO | C | 02/06/2018 | pipie sleeve ok, will check rest at final | TED | TED | | PWO | C | 5758899 |
ADEPT PLUMBING & HEATING LLC | PWO | R | 02/05/2018 | sleeve water line run through wall into basement, will need backflow protection on line run to barn and yard hydrant, will need certificate of potable water by final | TED | TED | | PWO | R | 5757610 |
ADEPT PLUMBING & HEATING LLC | PB | C | 01/03/2018 | base drain ok, no water under footer or through wall at this time | TED | TED | | PB | C | 5728197 |