PALACE HOMES, INC. | B= | C | 07/18/2018 | All other required Final inspections are complete. (This is a computer generated result) | LONNYS | LONNYS | | B= | C | 5906953 |
PALACE HOMES, INC. | B= | P | 07/10/2018 | unfinished basement / walkout deck no stairs / upper level walkout deck no stairs. Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982). | LONNYS | LONNYS | | B= | P | 5897884 |
PALACE HOMES, INC. | BIN | C | 07/06/2018 | | LONNYS | LONNYS | | BIN | C | 5894747 |
PALACE HOMES, INC. | BFR | C | 07/06/2018 | | LONNYS | LONNYS | | BFR | C | 5894745 |
PALACE HOMES, INC. | BSP | P | 05/03/2018 | ES report for insulation on file | LONNYS | LONNYS | | BSP | P | 5834361 |
PALACE HOMES, INC. | BIN | P | 05/02/2018 | need to complete BFR / provide ES report for spray foam used / insulation OK | LONNYS | LONNYS | | BIN | P | 5833557 |
PALACE HOMES, INC. | BFR | P | 05/02/2018 | still need to isolate posts in basement / rear deck upper posts needs to be strapped to lower post - may upload picture upon completion | LONNYS | LONNYS | | BFR | P | 5833546 |
PALACE HOMES, INC. | BLA | C | 05/02/2018 | | LONNYS | LONNYS | | BLA | C | 5833538 |
PALACE HOMES, INC. | BSP | P | 05/02/2018 | engineer letter for rear deck posts , beam in garage , and C channel for post in crawlspace on file | LONNYS | LONNYS | | BSP | P | 5833240 |
PALACE HOMES, INC. | BFR | R | 04/25/2018 | need to complete HRR / missing HTS16 EE CX1 front study / tie in top plates left of front door to study room / beam in garage not paced throughout per detail / double notched LVL to steel beam in garage / wood shims in beam pockets / isolate 2x6 posts next to foundation in basement / missing post in crawler / fire block plumbing drains in basement / C-channel used in lieu of post in crawler / need to still inspect rear deck framing - steel post still missing | LONNYS | LONNYS | | BFR | R | 5826774 |
PALACE HOMES, INC. | BSP | R | 03/28/2018 | pop out right of front entrance already covered at time of inspection / rear deck post is not 6x6 steel per plans / rear deck cover lid OK / front entrance lid OK / still need to inspect deck | LONNYS | LONNYS | | BSP | R | 5801134 |
PALACE HOMES, INC. | BSP | P | 03/09/2018 | picture of pier depth and width on file / engineer letter for full height sono tube on file | LONNYS | LONNYS | | BSP | P | 5784421 |
PALACE HOMES, INC. | BSP | R | 03/06/2018 | Foundation design calls for one 21" diameter pier and one 27" diameter pier where two 24" diameter piers are present / Sono tubes are installed to full depth of pier | SHAUN | SHAUN | | BSP | R | 5780890 |
PALACE HOMES, INC. | BFT | C | 02/22/2018 | | LONNYS | LONNYS | | BFT | C | 5772003 |
PALACE HOMES, INC. | BFN | C | 02/22/2018 | | LONNYS | LONNYS | | BFN | C | 5772002 |
PALACE HOMES, INC. | BFD | C | 02/22/2018 | drain not ready / upon further review soils needs to address drain at perimeter of crawl space / upon further review drain is around the habitable portion of the basement to the rear west corner - damp proofing for all other areas / after further review with chief inspector status changed to complete / drain around habitable portion to west corner OK - damp proofing OK | LONNYS | LONNYS | | BFD | C | 5771850 |
PALACE HOMES, INC. | BFD | P | 02/22/2018 | open hole on file - 2400 PSF - usable / still need to perform drain inspection | LONNYS | LONNYS | | BFD | P | 5770931 |
PALACE HOMES, INC. | BFN | P | 02/13/2018 | Foundation reinforcement OK / Grounding rod OK / Interior piers OK / Still need to inspect exterior piers / Still need stamped open hole report | NICK | NICK | | BFN | P | 5764355 |
PALACE HOMES, INC. | BFT | P | 02/01/2018 | still need open hole / verified bearing capacity with field copy 2400 PSF / footing forms and reinforcing steel OK | LONNYS | LONNYS | | BFT | P | 5754156 |
PALACE HOMES, INC. | BFT | P | 01/30/2018 | need open hole / foundation design on file - 2400 PSF / geologic hazard addendum on file | LONNYS | LONNYS | | BFT | P | 5751066 |
THE CORE ELECTRIC GROUP, LLC | E= | C | 07/03/2018 | | JOHNN | JOHNN | | E= | C | 5892701 |
THE CORE ELECTRIC GROUP, LLC | E= | R | 06/29/2018 | contractor needs to check house before recall; stopped inspection; I inspected exterior, garage and main level only: need back exterior outlet accessible from grade, cap unused wires in a/c disconnects, gfci garage outlet at work bench (afci outlet installed), gfci outlet in room in garage, lamp light at garage service door, outlet under sink on breaker marked small appliance circuit, need to add outlet in back splash on island, need to add outlet on dining room countertop (3' of counter from plugmold), afci smokes, open lamps master closet, spa outlet needs to face access opening --------- still need to check all afci breakers with upper and basement level on re-inspect--------- | MATTHEW | MATTHEW | | E= | R | 5890284 |
THE CORE ELECTRIC GROUP, LLC | ER | C | 04/18/2018 | | JOHNN | JOHNN | | ER | C | 5820104 |
THE CORE ELECTRIC GROUP, LLC | ES | C | 04/16/2018 | Residential Underground: 200 amp UG RES NEW Ok to energize / | ROB | ROB | | ES | C | 5817886 |
THE CORE ELECTRIC GROUP, LLC | ER | R | 04/16/2018 | Basement area needs to be complete for rough-- #6 AL to oven/range / Irreversible UFER connection / No Cent Vac / Unfinished Basement / | ROB | ROB | | ER | R | 5817884 |
AIR CONCEPTS HEATING & COOLING | H= | C | 06/28/2018 | UNFINISHED BASEMENT , DIRECT VENT EQUIP, A/C X2 | DAVIDH | DAVIDH | | H= | C | 5888887 |
AIR CONCEPTS HEATING & COOLING | HC | C | 04/25/2018 | RELEASE METER | BILLS | BILLS | | HC | C | 5827100 |
AIR CONCEPTS HEATING & COOLING | HRR | C | 04/25/2018 | | BILLS | BILLS | | HRR | C | 5827099 |
AIR CONCEPTS HEATING & COOLING | HRR | P | 04/24/2018 | HORIZONTAL DRYER VENT NEEDS TO BE SUPPORTED, FIREPLACE INSULATION SHIELD NEEDS TO BE LOWERED DOWN TO PLYWOOD, LINESET NEEDS NAIL PROTECTION AT UPPER AND MAIN FLOOR TOP PLATES, MISSING SUPPLY AIR AT STUDY CLOSET, ATTIC FURNACE DRAIN LINE ENDS IN WALL?? NEED TO SEE TERMINATION OUTSIDE OF WALL CAVITY. BY FINAL: NEED DUCT LEAKAGE REPORT, CONFIRM 2 SUPPLY AIRS AND 1 RETURN AIR IN CRAWLSPACE, CONFIRM 1 SUPPLY AND 1 RETURN AIR IN BASEMENT. NOTE: CONDITIONED CRAWLSPACE, UNFINISHED BASEMENT, 2 DIRECT VENT FURNACES, 2 A/C ROUGH INS COILS AND LINESETS, DIRECT VENT WATER HEATER, NO OUTSIDE AIR | BILLS | BILLS | | HRR | P | 5825440 |
AIR CONCEPTS HEATING & COOLING | HRR | L | 04/23/2018 | FIELD CANCELLED BY CONTRACTOR,, NOT READY | BILLS | BILLS | | HRR | L | 5824025 |
SPRINGS GAS, INC. | HI | C | 04/17/2018 | 10LB TEST OK, 1 1/4" MAIN, 2 FURNACES, 1 WATER HEATER, 1 COOKTOP, 1 FIREPLACE, 1 BBQ | BILLS | BILLS | | HI | C | 5819119 |
JOLLY PLUMBING & HEATING INC. | P= | C | 07/09/2018 | Correction made | SHANEN | SHANEN | | P= | C | 5897040 |
JOLLY PLUMBING & HEATING INC. | P= | P | 07/06/2018 | Stand pipe under upper level jack and jill bath lav too short, rest OK, PVB installed | SHANEN | SHANEN | | P= | P | 5895674 |
JOLLY PLUMBING & HEATING INC. | P= | L | 07/05/2018 | Field canceled | SHANEN | SHANEN | | P= | L | 5894203 |
JOLLY PLUMBING & HEATING INC. | PTO | C | 04/18/2018 | see images. | TAYLOR | TAYLOR | | PTO | C | 5819695 |
JOLLY PLUMBING & HEATING INC. | PTO | P | 04/16/2018 | waive trip fee, still missing nail protection at shower for upstairs 3/4 bathroom. | TAYLOR | TAYLOR | | PTO | P | 5817756 |
JOLLY PLUMBING & HEATING INC. | PTO | P | 04/13/2018 | missing nail protection at upstairs 3/4 bathroom, re- grade and support laundry sink drain, can not tie water lines for master bathroom into irrigation line, rest ok, unfinished basement, aav's at both master lavs, upstairs jack and jill lavs, in closet for sink in garage, laundry sink. | TAYLOR | TAYLOR | | PTO | P | 5816335 |
JOLLY PLUMBING & HEATING INC. | PB | C | 03/05/2018 | | TAYLOR | TAYLOR | | PB | C | 5779627 |