CMG CORP | B= | C | 03/17/2018 | All other required Final inspections are complete. (This is a computer generated result) | NATHAN | NATHAN | | B= | C | 5791884 |
CMG CORP | BSP | P | 02/23/2018 | Training with Nathan on final for interior remodel | JUSTINL | JUSTINL | | BSP | P | 5773351 |
CMG CORP | B= | P | 02/23/2018 | Training with Justin. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 5773296 |
EL PASO ELECTRIC, LLC. | E= | C | 03/15/2018 | | TIMA | TIMA | | E= | C | 5789528 |
EL PASO ELECTRIC, LLC. | E= | R | 02/23/2018 | can't have gfci recept behind washer | TIMA | TIMA | | E= | R | 5772516 |
EL PASO ELECTRIC, LLC. | ER | C | 01/11/2018 | wall and ceiling ok---WILL NEED PLAN REVISED SHOWING NO NEW CIRCUIT FOR WATER HEATER RECEPT FOR FINAL--- | TIMA | TIMA | | ER | C | 5735323 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 02/22/2018 | | MARKB | MARKB | | H= | C | 5771063 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | C | 02/22/2018 | | MARKB | MARKB | | HD | C | 5771062 |
RIAL HEATING AND AIR CONDITIONING, INC. | HV | C | 02/22/2018 | | MARKB | MARKB | | HV | C | 5771056 |
LANDMARK PLUMBING AND HEATING, INC. | H= | C | 02/21/2018 | RELOCATE WATER HEATER. NOTE: ROOM MEETS 50:1 PER PLAN | MARKB | MARKB | | H= | C | 5770084 |
LANDMARK PLUMBING AND HEATING, INC. | HI | C | 02/21/2018 | 10 PSI PRESSURE TEST OK - PIPING PER PLAN | MARKB | MARKB | | HI | C | 5770082 |
LANDMARK PLUMBING AND HEATING, INC. | HI | R | 02/20/2018 | Need new gas piping put under an air test and provide access to roof. | MARKB | MARKB | | HI | R | 5768759 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | L | 02/16/2018 | Need gas contractor attached to permit and gas inspections. Change permit scope to 1 duct and 1 vent. Complete : "HV" & "HD" inspections. | MARKB | MARKB | | H= | L | 5767465 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 02/16/2018 | Need access to roof. Dryer duct needs to be supported every 4' per code. NOTE ADDED 2/21/18: ROOF TERMINATION WILL REQUIRE A BACK-DRAFT DAMPER. | MARKB | MARKB | | HD | P | 5767460 |
RIAL HEATING AND AIR CONDITIONING, INC. | HV | P | 02/16/2018 | New water heater vent - Need access to roof. | MARKB | MARKB | | HV | P | 5767453 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 02/21/2018 | corrections made | DANR | DANR | | P= | C | 5770554 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 02/20/2018 | Route t&p to floor sink per detail 2 on P-1, floor sink grate causing indirect drain to splash out on floor need half grate or cut grate, rest ok. | DANR | DANR | | P= | P | 5768996 |
LANDMARK PLUMBING AND HEATING, INC. | P= | L | 02/16/2018 | Door locked, no call ahead number. | DANR | DANR | | P= | L | 5767890 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 01/31/2018 | Corrections made. | DANR | DANR | | PTO | C | 5753173 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 01/30/2018 | Strap pex in wall by water heater stubs, 1/2" domestic water cap in wall leaking by washer box, need nail protection on water line at mop sink, 1-1/2" abandoned waste line needs capped by mop sink, cap domestic waters at removed water heater. | DANR | DANR | | PTO | P | 5751779 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 01/25/2018 | Test and design ok. | DANR | DANR | | PB | C | 5747462 |