FRED FLETEMEYER COMPANY GENERAL CONTRACTORS, INC. | B= | C | 03/27/2018 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5799557 |
FRED FLETEMEYER COMPANY GENERAL CONTRACTORS, INC. | B= | P | 03/21/2018 | final OK pending other finals. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), HOGAN MECHANICAL, INC Plumbing Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5795534 |
FRED FLETEMEYER COMPANY GENERAL CONTRACTORS, INC. | BFR | P | 03/20/2018 | Architects letter for patches at electrical outlets at fire wall received / AM and M observed on site for air curtain ILO vestibule at entry / this completes the BFR inspections for this unit pending other rough inspections / prewalked unit for final with contractor / training with Dale J. | DANE | DANE | | BFR | P | 5794352 |
FRED FLETEMEYER COMPANY GENERAL CONTRACTORS, INC. | BFR | P | 02/14/2018 | still need listing or stamped letter for how to fix the penetrations that have been created in the firewall at the north side of the unit for electrical outlets (2' x 2' missing drywall around 4"x4" boxes) / letter provided was only listing what the existing wall is made of (letter was not taken from site) / still need to install vestibule walls or remove them from the plans | DANE | DANE | | BFR | P | 5765744 |
FRED FLETEMEYER COMPANY GENERAL CONTRACTORS, INC. | BFR | P | 01/30/2018 | need listing for all openings cut into firewall at north end of unit / still need to inspect walls at vestibule / all other hard lids and framing OK / discussed accessible elements with contractor including accessible service counter and break room sink and restrooms | DANE | DANE | | BFR | P | 5752274 |
SAWYER ELECTRIC, INC | E= | C | 03/19/2018 | | BRET | BRET | | E= | C | 5792542 |
SAWYER ELECTRIC, INC | ES | P | 02/14/2018 | Commercial Service: 2 200 amp services need meter set for 130 and 140. | BRET | BRET | | ES | P | 5766141 |
SAWYER ELECTRIC, INC | ER | P | 02/08/2018 | hard lids ok | BRET | BRET | | ER | P | 5761026 |
SAWYER ELECTRIC, INC | ER | R | 02/02/2018 | lighting stubs ok still need exhaust fans installed and wired prior to sheet rock installation | BRET | BRET | | ER | R | 5756189 |
SAWYER ELECTRIC, INC | ER | P | 02/02/2018 | ------------------------------hard lids ok, lights installed are self contained LED cut ins. Ray to leave several of these down at final for inspection. ----------------------------- | DEAN | DEAN | | ER | P | 5755354 |
SAWYER ELECTRIC, INC | ER | P | 01/30/2018 | new walls only, existing wall receptacles and lids not ready at this time. | BRET | BRET | | ER | P | 5751580 |
SAWYER ELECTRIC, INC | ESL | C | 01/16/2018 | | BRET | BRET | | ESL | C | 5738691 |
O.M.A.G.M., INC. | HC | C | 03/26/2018 | OK TO SET METER. 2lb. system | NANCY | NANCY | | HC | C | 5798520 |
O.M.A.G.M., INC. | H= | C | 03/21/2018 | GAS FINAL OK. | NANCY | NANCY | | H= | C | 5794616 |
EAGLE HEATING AND AIR CONDITIONING, INC. | H= | C | 03/21/2018 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT REPORT RECEIVED, SEE IMAGES. | NANCY | NANCY | | H= | C | 5794573 |
O.M.A.G.M., INC. | HSP | P | 03/20/2018 | GAS FINAL OK AFTER INSPECTION IS REQUESTED. ALSO NEED VENT LIMITING DEVICE FOR REGULATOR PROTECTED AT NEW RTU ON ROOF, PICTURE WILL BE OK | JON | JON | | HSP | P | 5793894 |
EAGLE HEATING AND AIR CONDITIONING, INC. | H= | P | 03/20/2018 | SPLICE COMPLETE. NEED BALANCE REPORT | JON | JON | | H= | P | 5793887 |
EAGLE HEATING AND AIR CONDITIONING, INC. | HD | P | 03/02/2018 | Duct installed per plan. Still need to see flex and diffusers in back area. Did not go on roof. | JEFFL | JEFFL | | HD | P | 5778609 |
O.M.A.G.M., INC. | HI | C | 02/23/2018 | 10 lb test ok. Gas line installed per plan. | JEFFL | JEFFL | | HI | C | 5772473 |
EAGLE HEATING AND AIR CONDITIONING, INC. | HD | P | 02/09/2018 | NEED GAS CONTRACTOR ATTACHED TO PERMIT. NEED REVISED/APPROVED PRINTS WITH NEW EQUIPMENT SCHEDULE ( 7.5 TON NOT BEING INSTALLED), NEW DUCT LAYOUT AND BATH EXHAUST TERMINATING ON BACK SIDE OF BUILDING INSTEAD OF ON ROOF. PROVIDE STRUCTURAL LETTER PER NOTE THREE OF ROOFTOP UNIT SCHEDULE. BATH EXHAUST ABOVE CEILING OK, OK TO COVER. | NANCY | NANCY | | HD | P | 5762260 |
HOGAN MECHANICAL, INC. | P= | C | 03/27/2018 | corrections made, see images | JOHNS | JOHNS | | P= | C | 5799556 |
HOGAN MECHANICAL, INC. | P= | P | 03/19/2018 | Need revisions or engineers letters for second water heater and tank type water closets, add second water heater to scope of work, rest OK | SHANEN | SHANEN | | P= | P | 5792648 |
HOGAN MECHANICAL, INC. | PTO | P | 01/30/2018 | Plans call for type "L" copper water distribution (PEX installed) and flush valve water closets (roughed in and sized for tank style) need plans revised or engineers letter, rest OK, need to see vent roof penetrations at final | SHANEN | SHANEN | | PTO | P | 5751770 |
HOGAN MECHANICAL, INC. | PB | C | 01/08/2018 | Corrections made | SHANEN | SHANEN | | PB | C | 5731443 |
HOGAN MECHANICAL, INC. | PB | P | 01/05/2018 | Rest rooms and break room areas DWV OK, grease waste and sanitary in sales area back-graded and bellied throughout, plans reflect 1/4" per foot grade | SHANEN | SHANEN | | PB | P | 5730535 |
EAGLE HEATING AND AIR CONDITIONING, INC. | XMS | T | 03/01/2018 | PAID (REC#1484870) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised layout, gas, schedules | JUSTINC | JUSTINC | | XMS | T | 5777677 |