CMG CORP | B= | C | 04/04/2018 | All other required Final inspections are complete. (This is a computer generated result) | RICHB | RICHB | | B= | C | 5807348 |
CMG CORP | B= | P | 04/02/2018 | Previous items OK - remodel complete pending other Finals. Additional Inspections Required (computer generated): RIAL HEATING & AIR COND, INC Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5805035 |
CMG CORP | B= | P | 03/27/2018 | men's toilet needs to be 16" to 18" from side wall / need knee protection under both bathroom sinks / need to complete all other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, MARTINSON MECHANICAL, LLC Plumbing Final Inspection is not Completed yet, RIAL HEATING & AIR COND, INC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5799929 |
CMG CORP | BFR | P | 02/26/2018 | Framing OK pending other Roughs / reviewed accessible elements / plans reviewed onsite | RICHB | RICHB | | BFR | P | 5774389 |
EL PASO ELECTRIC, LLC. | E= | C | 03/27/2018 | | CRAIGS | CRAIGS | | E= | C | 5800386 |
EL PASO ELECTRIC, LLC. | E= | R | 03/26/2018 | see rough notes | CRAIGS | CRAIGS | | E= | R | 5799130 |
EL PASO ELECTRIC, LLC. | ER | R | 03/26/2018 | track lights have to be supported back to structure | CRAIGS | CRAIGS | | ER | R | 5799129 |
EL PASO ELECTRIC, LLC. | ER | T | 02/27/2018 | PAID (REC#1489477): door locked, no one on site, | JOHNN | JOHNN | | ER | T | 5775127 |
EL PASO ELECTRIC, LLC. | ER | L | 02/26/2018 | no one around @ 2:04 | CRAIGS | CRAIGS | | ER | L | 5774302 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 04/04/2018 | MECHANICAL FINAL OK. | NANCY | NANCY | | H= | C | 5807347 |
RIAL HEATING AND AIR CONDITIONING, INC. | HSP | P | 04/04/2018 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. | NANCY | NANCY | | HSP | P | 5807148 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 04/03/2018 | NEED EXTENSION LADDER FOR ROOF ACCESS. | NANCY | NANCY | | H= | P | 5806622 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 04/02/2018 | FOR FINAL - Need access to roof to inspect RTU and exhaust fan, need to confirm duct smoke detector and remote indicator. Provide Test And Balance report. | MARKB | MARKB | | H= | P | 5805654 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | C | 04/02/2018 | FLEX AND DIFFUSERS INSTALLED. | MARKB | MARKB | | HD | C | 5805633 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 03/21/2018 | ABOVE CEILING DUCT - SUPPLY MAINS/BRANCH'S AND EXHAUST DUCT INSTALLED PER PLAN OK TO WRAP. All supply branches and ef-1,2 duct will require proper support. No flex, diffusers or roof inspection. | MARKB | MARKB | | HD | P | 5795823 |
MARTINSON MECHANICAL, INC | P= | C | 03/30/2018 | corrections made, see images | JOHNS | JOHNS | | P= | C | 5803370 |
MARTINSON MECHANICAL, INC | P= | P | 03/29/2018 | still need to caulk mop sink, pic to complete, rest ok for corrections made | JOHNS | JOHNS | | P= | P | 5802405 |
MARTINSON MECHANICAL, INC | P= | P | 03/26/2018 | need to caulk all fixtures, mens bath does not meet minimum side clearance from wall to center of water closet, need dome strainer @ 3 comp sink floor sink, need to install t&p drain line, rest ok | JOHNS | JOHNS | | P= | P | 5799179 |
MARTINSON MECHANICAL, INC | PTO | C | 02/20/2018 | GC TO ATTACH MECH AND ELEC PERMITS, rest ok for test and design per plan. note: vtr (existing), water htr checked @ pto MINUS T&P LINE | JOHNS | JOHNS | | PTO | C | 5769114 |
MARTINSON MECHANICAL, INC | PB | C | 02/16/2018 | test and design per plan | JOHNS | JOHNS | | PB | C | 5767863 |