CUCUZZA CONSTRUCTION, INC. | B= | C | 07/24/2018 | All other required Final inspections are complete. (This is a computer generated result) | SHAUN | SHAUN | | B= | C | 5912926 |
CUCUZZA CONSTRUCTION, INC. | B= | P | 07/20/2018 | . Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | SHAUN | SHAUN | | B= | P | 5910050 |
CUCUZZA CONSTRUCTION, INC. | BFR | C | 07/20/2018 | | SHAUN | SHAUN | | BFR | C | 5910033 |
CUCUZZA CONSTRUCTION, INC. | BLA | C | 05/18/2018 | note - inspection added onsite per request from GC | BRIANB | BRIANB | | BLA | C | 5850008 |
CUCUZZA CONSTRUCTION, INC. | BIN | C | 05/18/2018 | corrections okay | BRIANB | BRIANB | | BIN | C | 5850004 |
CUCUZZA CONSTRUCTION, INC. | BFN | C | 05/18/2018 | foundation design on file | BRIANB | BRIANB | | BFN | C | 5848737 |
CUCUZZA CONSTRUCTION, INC. | BIN | R | 05/17/2018 | need to complete foundation inspection prior to further inspections / insulation incomplete around all main floor rim above basement | BRIANB | BRIANB | | BIN | R | 5848595 |
CUCUZZA CONSTRUCTION, INC. | BFR | P | 05/17/2018 | pending completed foundation inspection / framing corrections are okay / received letter for framing modifications onsite | BRIANB | BRIANB | | BFR | P | 5848594 |
CUCUZZA CONSTRUCTION, INC. | BFN | P | 05/17/2018 | pending copy of foundation design / Engineers observation Letter on file / Eufer OK / soils letter received / 2600 psf / usable drain | BRIANB | BRIANB | | BFN | P | 5848592 |
CUCUZZA CONSTRUCTION, INC. | BFT | C | 05/17/2018 | Engineers observation Letter on file | BRIANB | BRIANB | | BFT | C | 5848586 |
CUCUZZA CONSTRUCTION, INC. | BFR | P | 05/15/2018 | need to complete foundation inspections prior to further inspections / missing bearing block at 2ply T02G truss over front of garage at porch wall / (2) H2.5 at single ply trusses over rear garage are not installed on opposite sides of top plate per note on design / missing HTS20 at rear porch beam to post in mbr / altered H2.5 installed at H01G truss over rear sliding glass door header / combustibles in b-vent chase / could not verify dbl 2x6 post under each end of dropped dbl 2x8 header over front porch - covered at time of inspection / H10 truss over stairs missing bracing in (1) location / stair landing framing completed is not per approved design / missing DBL 2x10 at basement stair landing / fireblocking incomplete top of concealed areas and tub drains / finished basement / no deck installed / okay to insulate as long as corrections are exposed for re-inspection | BRIANB | BRIANB | | BFR | P | 5845818 |
CUCUZZA CONSTRUCTION, INC. | BFD | P | 02/26/2018 | Complete BFT and BFN / Drain around habitable space / Damp proofing okay | SHAUN | SHAUN | | BFD | P | 5774529 |
1 CALL ELECTRIC, LLC | E= | C | 07/19/2018 | | DEAN | DEAN | | E= | C | 5908678 |
1 CALL ELECTRIC, LLC | E= | R | 07/19/2018 | the afci protection has to be in the panel , | CRAIGS | CRAIGS | | E= | R | 5907989 |
1 CALL ELECTRIC, LLC | E= | R | 07/17/2018 | washer requires afci protection --- need a way to test the garage door opener for gfci protection | CRAIGS | CRAIGS | | E= | R | 5905067 |
1 CALL ELECTRIC, LLC | ES | C | 05/10/2018 | Residential Underground: 200 amp 3/w new res note to inspectors no multi wire branch circuits | CRAIGS | CRAIGS | | ES | C | 5841079 |
1 CALL ELECTRIC, LLC | ER | C | 05/09/2018 | finished basement --- accessible ufer | CRAIGS | CRAIGS | | ER | C | 5839686 |
MILLER HEATING & AIR CONDITIONING, INC. | H= | C | 07/20/2018 | RECEIVED IMAGES OF CORRECTIONS, SEE IMAGES. | MATTM | MATTM | | H= | C | 5908890 |
MILLER HEATING & AIR CONDITIONING, INC. | H= | P | 07/19/2018 | MISSING COIL CHANGE LETTER, DRYER VENT TERMINATION CANNOT HAVE A SCREEN, OK TO ATTACH PICTURE TO NEXT INSPECTION REQUEST (NOTE ADDED 7/19/18 BY MATT MORGAN----CALLED CONTRACTOR AND LEFT A MESSAGE--MISSING BACKDRAFT DAMPER IN OUTSIDE AIR) NOTES: FINISHED BASEMENT, OUTSIDE AIR TO FURNACE RETURN, DIRECT VENT FURNACE, A/C INSTALLED | MATTM | MATTM | | H= | P | 5908739 |
MILLER HEATING & AIR CONDITIONING, INC. | H= | T | 07/18/2018 | PAID (REC#1518466): not ready. no access (locked, no lock box code) to home. | PAULO | PAULO | | H= | T | 5907245 |
MILLER HEATING & AIR CONDITIONING, INC. | H= | L | 07/17/2018 | No call ahead or lock box number provided | MARKB | MARKB | | H= | L | 5905717 |
MILLER HEATING & AIR CONDITIONING, INC. | HC | C | 05/14/2018 | RELEASE METER | MARKB | MARKB | | HC | C | 5843969 |
MILLER HEATING & AIR CONDITIONING, INC. | HRR | C | 05/14/2018 | Tar paper removed around Bvent. | MARKB | MARKB | | HRR | C | 5843966 |
MILLER HEATING & AIR CONDITIONING, INC. | HRR | P | 05/11/2018 | CUT TAR PAPER AWAY FROM BVENT AT ROOF. BY FINAL - CONTRACTOR TO PROVIDE EQUIPMENT CHANGE LETTER FOR FURNACE, INSTALL BACK DRAFT DAMPER IN OUTSIDE AIR. NOTE: 6" OSA TO RETURN, FINISHED BASEMENT AND A/C ROUGH (COIL AND LINESET)
| MARKB | MARKB | | HRR | P | 5842938 |
MILLER HEATING & AIR CONDITIONING, INC. | HRR | L | 05/10/2018 | No call ahead provided, house boarded up | MARKB | MARKB | | HRR | L | 5841367 |
PRECISION PLUMBING | HI | C | 05/07/2018 | 10# test ok. note: 1" main at 70' to 1- furnace, 1- water heater, 1- range and 1- fire place. | PAULO | PAULO | | HI | C | 5837907 |
PRECISION PLUMBING | P= | C | 07/13/2018 | finished basement, 3/4'' pvb installed | TED | TED | | P= | C | 5901764 |
PRECISION PLUMBING | PTO | C | 04/27/2018 | finished basement, aav bar sink, tempering valve in master closet, sprinkler stub | TED | TED | | PTO | C | 5829425 |
PRECISION PLUMBING | PB | C | 03/20/2018 | ok, water under footer | TED | TED | | PB | C | 5793636 |
PRECISION PLUMBING | PB | R | 03/19/2018 | not ready, still working (waive trip fee this time) | TED | TED | | PB | R | 5792144 |
CUCUZZA CONSTRUCTION, INC. | XBS | T | 04/02/2018 | PAID (REC#1500112) PLAN SPLICE FEE: $50 by: LBENNETT for Construction: floor plan changes; header changes | LBENNETT | LBENNETT | | XBS | T | 5805516 |
CUCUZZA CONSTRUCTION, INC. | XBS | T | 02/21/2018 | PAID (REC#1483274) PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised or added window and door locations, added basement wet bar | LBENNETT | LBENNETT | | XBS | T | 5770658 |