PREMIER HOMES, INC. | B= | C | 06/20/2018 | All other required Final inspections are complete. (This is a computer generated result) | RICHB | RICHB | | B= | C | 5879742 |
PREMIER HOMES, INC. | B= | P | 06/20/2018 | Slab-on-grade - no deck - AC installed. Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | RICHB | RICHB | | B= | P | 5879406 |
PREMIER HOMES, INC. | BIN | C | 05/21/2018 | Thermal in walls OK / verify attic at final / slab-on-grade | RICHB | RICHB | | BIN | C | 5850522 |
PREMIER HOMES, INC. | BFN | C | 05/18/2018 | BFT complete | SHAUN | SHAUN | | BFN | C | 5848911 |
PREMIER HOMES, INC. | BFT | C | 05/18/2018 | Received full open hole with stamp | SHAUN | SHAUN | | BFT | C | 5848904 |
PREMIER HOMES, INC. | BFR | C | 05/16/2018 | Framing OK / plans reviewed onsite | RICHB | RICHB | | BFR | C | 5846328 |
PREMIER HOMES, INC. | BFN | P | 05/16/2018 | No inspection required - still need to reconcile BFT, incomplete Open Hole submitted today | RICHB | RICHB | | BFN | P | 5846055 |
PREMIER HOMES, INC. | BFT | P | 05/16/2018 | Partial Open Hole received - correct job number indicated but missing rest of report including engineer stamp | RICHB | RICHB | | BFT | P | 5846052 |
PREMIER HOMES, INC. | BFI | C | 05/09/2018 | Foundation wall observation received - Job 180187, ufer noted // BFI observation received - Job 180187, 2" vertical // BFI observation received - incorrect address, not needed (correct address already submitted) // need to resolve BFT issue (job # discrepancy) | RICHB | RICHB | | BFI | C | 5839374 |
PREMIER HOMES, INC. | BFN | P | 05/09/2018 | Footing & pad observation received - references Job 180187, need to reconcile BFT issue (job # discrepancy) | RICHB | RICHB | | BFN | P | 5839359 |
PREMIER HOMES, INC. | BFT | P | 05/09/2018 | Foundation plan received - Entech Job 180187, already on file // Open Hole received - 2400 psf, drain (usable), floating framing, foundation indicated to be per Entech Job 180186 - need soils report and foundation deign job numbers to match. | RICHB | RICHB | | BFT | P | 5839356 |
PREMIER HOMES, INC. | BFN | P | 05/08/2018 | Changed from BFT to BFN // Foundation Design received - 2400 psf, Job # 180187 // still need Soils, Open Hole and observations for footing, foundation and foundation insulation | RICHB | RICHB | | BFN | P | 5838291 |
PREMIER HOMES, INC. | BSP | P | 04/19/2018 | Need to complete BFT, BFN and BFI prior to framing inspection / porch OK / plans reviewed electronically (none onsite) | RICHB | RICHB | | BSP | P | 5821244 |
PREMIER HOMES, INC. | BFI | P | 02/26/2018 | AUTHORIZED INSPECTION BY ENGINEER | GITA | GITA | GITA | BFI | P | 5773672 |
PREMIER HOMES, INC. | BFT | P | 02/26/2018 | AUTHORIZED INSPECTION BY ENGINEER | GITA | GITA | GITA | BFT | P | 5773671 |
PREMIER HOMES, INC. | BFN | P | 02/26/2018 | AUTHORIZED INSPECTION BY ENGINEER | GITA | GITA | GITA | BFN | P | 5773670 |
SEDLAK ELECTRIC CO. | E= | C | 06/15/2018 | a/c installed | GARYL | GARYL | | E= | C | 5875874 |
SEDLAK ELECTRIC CO. | ES | C | 05/15/2018 | Residential Underground: New 150 amp 3-wire service | GARYL | GARYL | | ES | C | 5844968 |
SEDLAK ELECTRIC CO. | ER | C | 05/15/2018 | No mcc., no vac, IR to ufer, | GARYL | GARYL | | ER | C | 5844964 |
THE FURNACE GUY HEATING & COOLING | H= | C | 06/15/2018 | | RANDYB | RANDYB | | H= | C | 5876556 |
THE FURNACE GUY HEATING & COOLING | H= | P | 06/14/2018 | Missing make up air to laundry. Note: Has a/c, 1 High to vented attic | MARK | MARK | | H= | P | 5874489 |
THE FURNACE GUY HEATING & COOLING | HC | C | 05/14/2018 | RELEASE METER | MARK | MARK | | HC | C | 5843268 |
THE FURNACE GUY HEATING & COOLING | HRR | C | 05/14/2018 | Change letter received. | MARK | MARK | | HRR | C | 5843267 |
THE FURNACE GUY HEATING & COOLING | HRR | P | 05/10/2018 | Corrections made, wall removed from mechanical area. Will close in the am, I need to print change letter. Not able to do so in the field. | MARK | MARK | | HRR | P | 5840904 |
THE FURNACE GUY HEATING & COOLING | HRR | P | 05/08/2018 | Furnace access blocked by wall. Missing 10x4 supply from trunk over dining area. Equipment schedule calls for 75k furnace, 66k installed. Missing 12" return to master bedroom per plans. NOTES: Outside air to furnace return through roof. 8" High combustion air to mechanical closet. A/C Rough line-set only. | RANDYB | RANDYB | | HRR | P | 5839149 |
J.J. BROOME PLUMBING AND HEATING LLC | HI | C | 05/04/2018 | 10 LB Test okay. 1" Main. 1 Furnace. 1 Water heater. | RANDYB | RANDYB | | HI | C | 5836888 |
J.J. BROOME PLUMBING AND HEATING LLC | P= | C | 06/18/2018 | corrections made | JOHNS | JOHNS | | P= | C | 5877867 |
J.J. BROOME PLUMBING AND HEATING LLC | P= | R | 06/15/2018 | leak at water meter, low flow on powder lav, rest ok | TED | TED | | P= | R | 5875581 |
J.J. BROOME PLUMBING AND HEATING LLC | PTO | C | 05/08/2018 | correction made | JOHNS | JOHNS | | PTO | C | 5838345 |
J.J. BROOME PLUMBING AND HEATING LLC | PTO | P | 05/07/2018 | low test, rest ok for corrections made | JOHNS | JOHNS | | PTO | P | 5837127 |
J.J. BROOME PLUMBING AND HEATING LLC | PTO | P | 05/04/2018 | re- grade drains for guest bathtub and master lav, rest ok, VTR. | TAYLOR | TAYLOR | | PTO | P | 5835875 |
J.J. BROOME PLUMBING AND HEATING LLC | PB | C | 04/02/2018 | | TAYLOR | TAYLOR | | PB | C | 5805563 |