SKYLINE PROPERTY MAINTENANCE, INC | B= | C | 08/13/2018 | other final inspections completed | BRIANB | BRIANB | | B= | C | 5931422 |
YK ENTERPRISES INC. | B= | P | 05/24/2018 | items corrected. Additional Inspections Required (computer generated): PREMIER MECHANICAL Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 5855367 |
YK ENTERPRISES INC. | B= | P | 05/23/2018 | missing restroom signage / need to complete other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), PREMIER MECHANICAL Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 5854131 |
YK ENTERPRISES INC. | BFR | P | 03/20/2018 | New partial-height wall at Service area OK pending other Roughs / new restroom framing OK pending other Roughs / discussed accessible elements with Owner (Contractor not available) / plans reviewed onsite | RICHB | RICHB | | BFR | P | 5793833 |
S&B ELECTRICAL | E= | C | 05/21/2018 | 15A exhaust fan and mua on roof ok / | MIGUEL | MIGUEL | | E= | C | 5851421 |
S&B ELECTRICAL | ER | C | 05/21/2018 | | MIGUEL | MIGUEL | | ER | C | 5851419 |
S&B ELECTRICAL | ER | P | 03/14/2018 | above ceiling and bathroom walls OK | CRAIGS | CRAIGS | | ER | P | 5788210 |
S&B ELECTRICAL | ER | P | 03/07/2018 | knee wall by the counter OK | CRAIGS | CRAIGS | | ER | P | 5781972 |
PREMIER MECHANICAL | H= | C | 07/03/2018 | CONTRACTORS SCOPE COMPLETE | MARKB | MARKB | | H= | C | 5892780 |
PREMIER MECHANICAL | H= | P | 06/15/2018 | TAB REPORT RECEIVED, STILL NEED OTHER ITEMS ADDRESSED | MARKB | MARKB | | H= | P | 5875528 |
PREMIER MECHANICAL | HD | C | 05/21/2018 | GREASE DUCT WRAP - SECOND LAYER AND BANDS OK. HOOD INTERLOCK WITH MAKEUP AIR CONFIRMED. | MARKB | MARKB | | HD | C | 5851019 |
PREMIER MECHANICAL | H= | P | 05/21/2018 | FOR FINAL - Need bath exhaust fans addressed, either installed and inspected or removed from plans to show existing. Install extensions on grease fan and provide Test And Balance Report. | MARKB | MARKB | | H= | P | 5851018 |
PREMIER MECHANICAL | HD | P | 05/16/2018 | MAKEUP AIR UNIT AND DUCT INSTALLED PER PLAN. HIGH TEMP GASKET INSTALLED ON GREASE FAN. | MARKB | MARKB | | HD | P | 5846568 |
PREMIER MECHANICAL | HC | C | 05/16/2018 | TOTAL METER WITH NEW LOAD IS 674K PER PLAN | MARKB | MARKB | | HC | C | 5846567 |
PREMIER MECHANICAL | HI | C | 05/16/2018 | 10 PSI PRESSURE TEST OK. PIPING PER PLAN. Note: Less than 2 psi | MARKB | MARKB | | HI | C | 5846566 |
PREMIER MECHANICAL | HD | P | 05/11/2018 | GREASE DUCT LIGHT TEST - COMPLETE GREASE DUCT WRAP - FIRST LAYER OK | MARKB | MARKB | | HD | P | 5842756 |
PREMIER MECHANICAL | HD | P | 05/10/2018 | Had discussion with mechanical contractor on site about extending Type 1 fan discharge Level or above wall within 8'. Will need a mechanical contractor attached to permit for Bath exhaust fans shown on plans as being replaced with larger CFM. GREASE DUCT LIGHT TEST - LIGHT TEST COMPLETE FROM CURB DOWN TO HOOD COLLAR - Has one hole in weld at hood collar. OK to wrap grease duct as long as light test can still be done on hood collar. | MARKB | MARKB | | HD | P | 5841057 |
PREMIER MECHANICAL | HD | P | 04/10/2018 | HOOD WALL INSPECTION - HOOD IS GOING ON AN EXISTING WALL, I LOOKED DOWN ALL STUD SPACES FROM TOP AND DID NOT SEE ANY COMBUSTIBLES (ALL STEEL STUDS). STAINLESS WILL NEED TO BE EXTENDED ON LEFT SIDE BY FINAL TO COVER 18" OUTSIDE OF HOOD PRINT. HOOD WILL REQUIRE 3" CLEARANCE TO LIMITED COMBUSTIBLES ON RIGHT SIDE ONCE HUNG. | MARKB | MARKB | | HD | P | 5813157 |
CASCADE PLUMBING & HEATING | P= | C | 05/22/2018 | Correction made. | DANR | DANR | | P= | C | 5852401 |
CASCADE PLUMBING & HEATING | P= | P | 05/21/2018 | Need tempering valve at lav rest ok. | DANR | DANR | | P= | P | 5850888 |
CASCADE PLUMBING & HEATING | P= | P | 05/08/2018 | toilet tank handle on wrong side, need hot water to test lav tempering valve | TED | TED | | P= | P | 5838434 |
CASCADE PLUMBING & HEATING | PTO | C | 04/12/2018 | water run | TED | TED | | PTO | C | 5814836 |
CASCADE PLUMBING & HEATING | PTO | P | 04/05/2018 | adding bathroom, new toilet riser ok, need water piping run to toilet, existing wall hung sink | TED | TED | | PTO | P | 5808427 |