GERALD H PHIPPS INC | B= | C | 05/11/2020 | | BOBF | BOBF | | B= | C | 6567702 |
GERALD H PHIPPS INC | B= | P | 03/21/2019 | Missing glass in all holding cell doors // Missing under sink protection at all sinks // Need to install restroom signage correctly at all restrooms // Missing accessible locker room bench per ANSI 803.4 // Still need to address landings in corridor outside command rooms // Vertical grab bar at transfer showers to installed 4" max INWARD from front edge of shower // Complete all other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), FRONTIER MECHANICAL INC Mechanical Final Inspection is not Completed yet, H20 PLUMBING & HEATING, INC. Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 6140341 |
GERALD H PHIPPS INC | BSP | P | 03/06/2019 | Penetrations for light fixtures at rated ceilings in detention corridors OK // Will need to address landings at doors in rooms 115 & 116 where the corridor is recessed. Landing on corridor side of doors only measures 28" in direction of travel | JEREMYA | JEREMYA | | BSP | P | 6125430 |
GERALD H PHIPPS INC | BFR | C | 02/08/2019 | Ceiling framing of support system for shaft ceiling OK in containment area | JEREMYA | JEREMYA | | BFR | C | 6102197 |
GERALD H PHIPPS INC | B16 | P | 01/30/2019 | Site meeting with Mechanical Inspection Mark and Contractor to discuss Detention Area (see Sheet A3.2, Area B) - Fire resistance rated ceiling assembly is being built per UL U415 as indicated on plans. Damper installation instructions and GH Phipps RFI 313 do not clearly state that the Ruskin dampers can be installed in a horizontal assembly constructed with shaft liner. Reviewed UL U415 with Contractor. | RICHB | RICHB | | B16 | P | 6091981 |
GERALD H PHIPPS INC | BSP | P | 01/21/2019 | Inspection for fire sprinkler bracing per seismic req. OK throughout all of Area A | JEREMYA | JEREMYA | | BSP | P | 6083721 |
GERALD H PHIPPS INC | BSP | P | 11/27/2018 | Area B seismic bracing - above ceiling in all hard lid areas OK, still need to inspect all other ceiling areas | RICHB | RICHB | | BSP | P | 6035800 |
GERALD H PHIPPS INC | BSP | P | 11/27/2018 | Area B firestopping - need listing for bar joist penetrations, firestopping for all other items OK per manufacturer listings | RICHB | RICHB | | BSP | P | 6035794 |
GERALD H PHIPPS INC | BSP | R | 11/20/2018 | Area A firestopping - not ready //// discussed transfer shower requirements | RICHB | RICHB | | BSP | R | 6031624 |
GERALD H PHIPPS INC | BSP | P | 11/14/2018 | Spoke with Contractor via phone - discussed threshold & slope for transfer showers / discussed firestopping inspection (required when all penetrations are completed) | RICHB | RICHB | | BSP | P | 6024806 |
GERALD H PHIPPS INC | BSP | P | 11/06/2018 | Reinforcing steel structural slab at generator OK // Maintenance building tie beam reinforcing OK | JEREMYA | JEREMYA | | BSP | P | 6016560 |
GERALD H PHIPPS INC | BIN | P | 10/26/2018 | Area A exterior wall insulation to deck with completed required inspections okay | NATHAN | NATHAN | | BIN | P | 6007079 |
GERALD H PHIPPS INC | BIN | R | 10/25/2018 | insulation inspection for exterior walls in area A cancelled onsite by superintendent Roger / no inspection performed | BRIANB | BRIANB | | BIN | R | 6005491 |
GERALD H PHIPPS INC | BFR | P | 10/22/2018 | Interior wall framing at north wing of building OK // Discussed accessible elements with asst. supt. Roger | JEREMYA | JEREMYA | | BFR | P | 6001072 |
GERALD H PHIPPS INC | B16 | P | 10/15/2018 | Spoke with Roger job super filling in for Jim Martin while Jim is on vacation about Staff toilet rooms 160 and 161 not shown as accessible on the approved plan set. per plan reviewer Michael A these should be accessible.Roger will get with architect on this situation. Also spoke with Jim Martin on cell phone about this. | BERTW | BERTW | | B16 | P | 5994255 |
GERALD H PHIPPS INC | BIN | P | 09/28/2018 | Exterior insulation at south half of building OK | JEREMYA | JEREMYA | | BIN | P | 5981750 |
GERALD H PHIPPS INC | BFN | P | 09/25/2018 | Building foundation inspection / Stoops at maintenance building and door 199 in Area B OK / training with Chuck. | RICHB | RICHB | | BFN | P | 5975835 |
GERALD H PHIPPS INC | BFR | P | 09/25/2018 | Building framing inspection / Area B interior metal framing OK per A1.2 and A10.2 detail shts. of the approved plans / Training with Chuck. | RICHB | RICHB | | BFR | P | 5975830 |
GERALD H PHIPPS INC | BFR | P | 09/06/2018 | Interior framing at electric room, mech room and fire riser room OK // Insulate as needed in those areas // OK to pre-rock tops of interior walls to install MEP components | JEREMYA | JEREMYA | | BFR | P | 5956214 |
GERALD H PHIPPS INC | BFR | P | 08/31/2018 | Exterior wall framing OK throughout entire building // OK to insulate all walls that MEP services have inspected // Will need to get all third party observations for soils, footing, foundation, masonry, bolting and welding | JEREMYA | JEREMYA | | BFR | P | 5953063 |
GERALD H PHIPPS INC | BSP | P | 08/22/2018 | Met Jim Martin on site and reviewed job progress and open permits for this job regarding attachments of other trades to those permits. | BERTW | BERTW | | BSP | P | 5942431 |
GERALD H PHIPPS INC | BFN | P | 06/11/2018 | Foundation at North wall OK, including vestibule | JEREMYA | JEREMYA | | BFN | P | 5869881 |
GERALD H PHIPPS INC | BFN | P | 06/07/2018 | Structural slab at detention area: All reinforcing steel in place per approved details | JEREMYA | JEREMYA | | BFN | P | 5867031 |
GERALD H PHIPPS INC | BFT | P | 06/04/2018 | Form work & reinforcement / Area A / (1) interior pad M at area A okay / (2) pilasters at grid line A9 at Area A okay / (1) interior pad D at grid line A9 okay / pads and pilasters inspected are highlighted in green on sheet S1.1 of the approved design in the office | BRIANB | BRIANB | | BFT | P | 5862986 |
GERALD H PHIPPS INC | BFT | P | 05/24/2018 | Formwork & reinforcement - Area A interior pads OK except (1) pad at grid intersection AE and A9 / still need to inspect leave-out noted on May 7th / highlighted in orange on field plans | RICHB | RICHB | | BFT | P | 5855557 |
GERALD H PHIPPS INC | BFN | P | 05/07/2018 | Formwork & reinforcement - Area B, interior pads in Detention Area (B1 to B5 & BI to BL) OK // Area A, foundation walls OK in all areas except on Grid A2 (being left out for access) // highlighted in blue on field plans ////// UPDATED COMMENT (same day) - Area B, all interior pads OK | RICHB | RICHB | | BFN | P | 5837637 |
GERALD H PHIPPS INC | BSP | P | 04/30/2018 | Site visit. Met with Jim Martin, GH Phipps, to discuss scheduling. Also discussed pre-con meeting. | JEREMYA | JEREMYA | | BSP | P | 5831098 |
GERALD H PHIPPS INC | BFN | P | 04/24/2018 | Formwork & reinforcement, Area B - stem walls & grade beams OK (highlighted in purple on field copy Sheet S1.2) // Formwork & reinforcement, Area A - exterior pads OK (highlighted in yellow on field copy Sheet 1.1) | RICHB | RICHB | | BFN | P | 5826069 |
GERALD H PHIPPS INC | BFT | P | 04/12/2018 | Discussed third party inspections - need stamped copy of Open Hole / formwork & reinforcement for all continuous footings on Sheet @1.2 OK / still need to inspect all interior pads / highlighted field copy of plans with above items / plans reviewed onsite | RICHB | RICHB | | BFT | P | 5815350 |
FOSTER ELECTRIC CORPORATION | E= | C | 06/03/2019 | | CRAIG | CRAIG | | E= | C | 6217731 |
FOSTER ELECTRIC CORPORATION | ER | C | 06/03/2019 | | CRAIG | CRAIG | | ER | C | 6217723 |
FOUNDERS FIRE AND ELECTRIC LLC | E= | C | 04/15/2019 | FIRE ALARM INSPECTION: | CRAIG | CRAIG | | E= | C | 6165404 |
FOUNDERS FIRE AND ELECTRIC LLC | E= | C | 04/15/2019 | FIRE ALARM INSPECTION: | CRAIG | CRAIG | | E= | C | 6165392 |
FOUNDERS FIRE AND ELECTRIC LLC | ER | C | 04/15/2019 | FIRE ALARM INSPECTION: | CRAIG | CRAIG | | ER | C | 6165391 |
FOSTER ELECTRIC CORPORATION | E= | P | 03/13/2019 | reopened by Matt for splice---- air compressor and added recep; check plans | CRAIG | CRAIG | | E= | P | 6132686 |
FOUNDERS FIRE AND ELECTRIC LLC | E= | P | 03/13/2019 | FIRE ALARM INSPECTION: fire alarm complete -------------- changed to partial by Matt for 4 carbon monoxide detectors being added | CRAIG | CRAIG | | E= | P | 6132668 |
FOSTER ELECTRIC CORPORATION | E= | P | 03/12/2019 | rtu #4 needs 30 amp breaker / cu # 3 needs 20 amp breaker / rest rtu's ok-/ pole lights ok / PANELS --HPSA , LPSA, HBA, LPA, LPSC,LPSD, / NEED TO VERIFY THE BONDING IN THE GENERATOR | BRIAN | BRIAN | | E= | P | 6131843 |
FOSTER ELECTRIC CORPORATION | ES | C | 03/11/2019 | Commercial Service: Thanks for the paper work on GFPE | CRAIG | CRAIG | | ES | C | 6129704 |
FOSTER ELECTRIC CORPORATION | EP | P | 02/15/2019 | panels DPS 225 AMP 4/W / LPSD 100 AMP 4/W both ok | CRAIG | CRAIG | | EP | P | 6108625 |
FOSTER ELECTRIC CORPORATION | ER | P | 02/15/2019 | area B for above ceiling ok transfer switches ATSS / ATSE ok xfmrs TLPE / TLPA / TLPB / TLPSA / TLPSB all ok | CRAIG | CRAIG | | ER | P | 6108623 |
FOSTER ELECTRIC CORPORATION | EP | P | 02/12/2019 | HPSA 100 amp 4/w / HPA 100 amp 4/w ----- LPA 225 amp 4/w / LPSA 225 amp 4/w ok | CRAIG | CRAIG | | EP | P | 6104623 |
FOSTER ELECTRIC CORPORATION | ER | P | 02/12/2019 | above ceiling in area A ok | CRAIG | CRAIG | | ER | P | 6104612 |
FOUNDERS FIRE AND ELECTRIC LLC | ER | P | 02/08/2019 | FIRE ALARM INSPECTION: corridors for fire alarm ok | CRAIG | CRAIG | | ER | P | 6101441 |
FOSTER ELECTRIC CORPORATION | ES | P | 02/06/2019 | Commercial Service: 1200 amp 4 wire service--okay to set meter | CHIPO | CHIPO | | ES | P | 6099583 |
FOSTER ELECTRIC CORPORATION | ER | P | 01/24/2019 | Drop ceiling in following areas: Rooms 120, 121, 122, 123, 128, 129, 130, 131, 133, 134, & corridor 132 / Highlighted contractors set of plans | JOSEPH | JOSEPH | | ER | P | 6086804 |
FOUNDERS FIRE AND ELECTRIC LLC | ER | P | 01/15/2019 | FIRE ALARM INSPECTION: not ready are corridors and 204 room and need separate permit for vehicle maintenance area ------- ALL OTHER AREA OK 14/2 fplp for nac and 16/2 fplp for slc | CRAIG | CRAIG | | ER | P | 6078468 |
FOSTER ELECTRIC CORPORATION | ER | P | 01/09/2019 | hard lid ceiling on 166, 167, 168, 169, 170, 171, 172, 174, 175, 176, 177, 178, 179, 180, 181, 183, 185, 186, 187, 190, 191, and 192 note fire alarm not called in at same time | CRAIG | CRAIG | | ER | P | 6073034 |
FOSTER ELECTRIC CORPORATION | ER | P | 12/20/2018 | had consultation with contractor about electrical room | CRAIG | CRAIG | | ER | P | 6060241 |
FOSTER ELECTRIC CORPORATION | EUG | P | 12/19/2018 | 4 - 3" pvc for secondary side of city xfmr -------- 1 1/2" pvc to metering | CRAIG | CRAIG | | EUG | P | 6058683 |
FOSTER ELECTRIC CORPORATION | EUG | P | 12/12/2018 | 9 ballards lights / 3 lights in ground facing up in front of main entry of building | CRAIG | CRAIG | | EUG | P | 6050274 |
FOSTER ELECTRIC CORPORATION | ER | P | 11/29/2018 | 3 plugs ok | CRAIG | CRAIG | | ER | P | 6037501 |
FOSTER ELECTRIC CORPORATION | ER | P | 11/16/2018 | bathrooms---160-161--118--119--107---hard lids---ok | BRIAN | BRIAN | | ER | P | 6028481 |
FOSTER ELECTRIC CORPORATION | ER | P | 11/02/2018 | Above hardlids as marked this date | SHELBY | SHELBY | | ER | P | 6014880 |
FOSTER ELECTRIC CORPORATION | EUG | P | 10/30/2018 | pvc from building to generator pad ok | CRAIG | CRAIG | | EUG | P | 6010387 |
MORTON ELECTRIC INC | EUG | R | 10/24/2018 | need separate permit for car wash / gas station | CRAIG | CRAIG | | EUG | R | 6004201 |
FOUNDERS FIRE AND ELECTRIC LLC | ER | P | 10/22/2018 | FIRE ALARM INSPECTION: area A, B for wall inspection for FPLP for 14/2 notification and 16/2 for SLC only ok | CRAIG | CRAIG | | ER | P | 6001396 |
FOSTER ELECTRIC CORPORATION | EUG | P | 10/22/2018 | hand hole south east gate ok | CRAIG | CRAIG | | EUG | P | 6001389 |
FOSTER ELECTRIC CORPORATION | ER | P | 10/19/2018 | area A --walls see plans | BRIAN | BRIAN | | ER | P | 6000565 |
FOSTER ELECTRIC CORPORATION | EUG | P | 10/05/2018 | 5 -2" / 1 - 1" / 1 - 1 1/2" all pvc west side of building 80' to 90' out | CRAIG | CRAIG | | EUG | P | 5986921 |
FOSTER ELECTRIC CORPORATION | ER | P | 09/27/2018 | MDF room for walls only ok | CRAIG | CRAIG | | ER | P | 5978311 |
FOSTER ELECTRIC CORPORATION | EUG | P | 09/25/2018 | SEE PLANS--- | BRIAN | BRIAN | | EUG | P | 5976086 |
FOSTER ELECTRIC CORPORATION | ER | P | 09/21/2018 | area B for walls only ok | CRAIG | CRAIG | | ER | P | 5972265 |
FOSTER ELECTRIC CORPORATION | EUG | P | 09/14/2018 | 4 - 2" pvc for data ------- 2 - 1" pvc for power from pull box to road way only ok | CRAIG | CRAIG | | EUG | P | 5965193 |
FOSTER ELECTRIC CORPORATION | EUG | P | 09/11/2018 | 4 - 2" pvc for data ----- 2 - 1" pvc for power ----- 1 1/4" pvc for camera' s from building to pull box then out of pull box on | CRAIG | CRAIG | | EUG | P | 5960782 |
FOSTER ELECTRIC CORPORATION | ER | P | 09/11/2018 | riser room walls only ok | CRAIG | CRAIG | | ER | P | 5960775 |
FOSTER ELECTRIC CORPORATION | ER | P | 09/05/2018 | walls in electric room , mech room south wall | TOMC | TOMC | | ER | P | 5955075 |
FOSTER ELECTRIC CORPORATION | EUG | P | 08/28/2018 | EUG TO POLE LIGHTS OK// | GREGM | GREGM | | EUG | P | 5948866 |
FOSTER ELECTRIC CORPORATION | EUG | P | 08/17/2018 | pole lights on south and southwest sides | TOMC | TOMC | | EUG | P | 5937352 |
FOSTER ELECTRIC CORPORATION | EUG | P | 08/15/2018 | 14 POLE LIGHTS EUG OK/ | GREGM | GREGM | | EUG | P | 5935311 |
FOSTER ELECTRIC CORPORATION | EUG | P | 08/03/2018 | pvc conduit west side gate and street lights , southeast side street lights | TOMC | TOMC | | EUG | P | 5923021 |
FOSTER ELECTRIC CORPORATION | EUG | P | 07/26/2018 | southeast side pvc to street lights | TOMC | TOMC | | EUG | P | 5914602 |
FOSTER ELECTRIC CORPORATION | EUG | P | 07/02/2018 | EUG FROM MAIN BUILDING TO CAR WASH 1 1/4" &1" STUBS OK------ | GREGM | GREGM | | EUG | P | 5890938 |
FOSTER ELECTRIC CORPORATION | ESL | P | 06/20/2018 | | TOMC | TOMC | | ESL | P | 5879419 |
FOSTER ELECTRIC CORPORATION | ESL | P | 06/19/2018 | floor boxes in rooms: 147, 151, 152 --------------- second time contractor has called for inspection in the afternoon that required a same day inspection; I talked to contractor about inspection scheduling | MATTHEW | MATTHEW | | ESL | P | 5879468 |
FOSTER ELECTRIC CORPORATION | EUG | P | 06/18/2018 | 7 -floor boxes along north side | TOMC | TOMC | | EUG | P | 5877922 |
FOSTER ELECTRIC CORPORATION | EUG | P | 06/01/2018 | underground hi lighted on page E01.1 | TOMC | TOMC | | EUG | P | 5861714 |
FOSTER ELECTRIC CORPORATION | ESL | P | 05/25/2018 | AREA B AND ELECT ROOM--- | BRIAN | BRIAN | | ESL | P | 5856880 |
FOSTER ELECTRIC CORPORATION | EUG | P | 05/22/2018 | pvc conduit stubs under foundation walls on south and west sides , 2 - 4" pvc data pipes on northeast side , Discussed accessibility requirements with contractor / | TOMC | TOMC | | EUG | P | 5851832 |
FOSTER ELECTRIC CORPORATION | ER | P | 05/11/2018 | 2-4" conduits for data, crossing road | GARYL | GARYL | | ER | P | 5842255 |
FOSTER ELECTRIC CORPORATION | EUG | P | 05/11/2018 | crossing road with 2-4' data conduits, okay to cover | GARYL | GARYL | | EUG | P | 5842252 |
FOSTER ELECTRIC CORPORATION | ER | P | 05/09/2018 | ufer ---- ok | TOMC | TOMC | | ER | P | 5839561 |
FOSTER ELECTRIC CORPORATION | EUG | P | 04/30/2018 | REBAR FOR UFER--OK -----NEED TO SEE THE WIRE CONNECTION TO THE J BOLTS ----- | BRIAN | BRIAN | | EUG | P | 5831638 |
H2O PLUMBING & HEATING, INC. | H= | C | 01/09/2020 | 3 PSI GAS PRESSURE APPROVAL FROM CSU ON FILE | MARKB | MARKB | | H= | C | 6447389 |
FRONTIER MECHANICAL INC. | H= | C | 12/31/2019 | REVISED TEST AND BALANCE REPORT RECEIVED | MARKB | MARKB | | H= | C | 6440183 |
FRONTIER MECHANICAL INC. | HSP | P | 04/18/2019 | FINISHED REVIEWING TEST AND BALANCE REPORT: 4/18/19 - Need to address EF-2, 3, & 8 not within 10% of plans. Other Balance items fro previous notes need to be addressed. | MARKB | MARKB | | HSP | P | 6169671 |
FRONTIER MECHANICAL INC. | HSP | P | 04/15/2019 | STILL GOING OVER TEST AND BALANCE REPORT: 4/15/19 - TAB FOR RTU-4 SUPPLY/EF, CRAC-1 & EF-1 ARE WITHIN 10 % OF PLAN | MARKB | MARKB | | HSP | P | 6165336 |
FRONTIER MECHANICAL INC. | HSP | P | 04/12/2019 | STILL GOING OVER TEST AND BALANCE REPORT: 4/12/19 - TEST AND BALANCE REPORT FOR RTU-3 MATCHES PLAN SPLICE | MARKB | MARKB | | HSP | P | 6163426 |
FRONTIER MECHANICAL INC. | HSP | P | 04/10/2019 | STILL GOING OVER TEST AND BALANCE REPORT: 4/10/19 - FINISHED REVIEW FOR RTU'S 1 & 2. Still need to review RTU'S 3 & 4 | MARKB | MARKB | | HSP | P | 6161197 |
FRONTIER MECHANICAL INC. | HSP | P | 04/08/2019 | STILL GOING OVER TEST AND BALANCE REPORT - ITEMS FOUND SO FAR TO BE ADDRESSED: 4/8/19 - VAVR-203 diffuser #5 for room 188 is not within 10% of plans. Plans call for 200 CFM. | MARKB | MARKB | | HSP | P | 6158255 |
FRONTIER MECHANICAL INC. | HSP | P | 04/05/2019 | STILL GOING OVER TEST AND BALANCE REPORT - ITEMS FOUND SO FAR TO BE ADDRESSED: 4/5/19 - RTU-1 is shown on equipment schedule requiring 15,000 CFM but diffusers total18,545 CFM. VAVR-115 is listed for 750 CFM but diffusers total 1100 CFM (see note on page 16). VAVR-109 has an extra diffuser for 120 CFM | MARKB | MARKB | | HSP | P | 6156095 |
FRONTIER MECHANICAL INC. | HSP | P | 04/04/2019 | STILL GOING OVER TEST AND BALANCE REPORT - ITEMS FOUND SO FAR TO BE ADDRESSED: 4/4/19 - RTU make and models do not match equipment schedule, need to address note 1 on page 1, FPB-116 & VAVR-115 do not match schedule, RTU-1 & 2 supply CFM does not match schedule, no reading for FC-1, EF-4 do not match schedule, EF-8 is above 10% of schedule | MARKB | MARKB | | HSP | P | 6154627 |
H2O PLUMBING & HEATING, INC. | HSP | P | 03/26/2019 | Called Mike (G.H. Phipps) with Jon B. (senior mechanical inspector) to go over splices required - Need equipment schedule on M5.1 revised to show boilers installed that differ in manufacture and model from original. Will need engineer to address gas supply pressure or CSU to provide a gas approval of 3 PSI (As noted in precon)- Engineer has a design pressure of 3 PSI but CSU has provided documentation that they are providing 2 PSI. IF engineer is to change to a 2 PSI design, M1.2 note #10 will need to be changed and pressure will need to be changed on gas isometric for M2.2 sheet.
| MARKB | MARKB | | HSP | P | 6144275 |
H2O PLUMBING & HEATING, INC. | H= | P | 03/19/2019 | Final Pending - Splice of new boiler equipment schedule. | MARKB | MARKB | | H= | P | 6136585 |
H2O PLUMBING & HEATING, INC. | H= | P | 03/18/2019 | FINAL PENDING - Finish medium pressure labels, boiler common vent condensate line lacks a trap and splice a new equipment schedule into the plans with correct boiler make and models. | MARKB | MARKB | | H= | P | 6135535 |
H2O PLUMBING & HEATING, INC. | HSP | L | 03/13/2019 | CALL AHEAD FOR CONTRACTOR GOES TO VOICE MAIL, SUER GOES TO VOICE MAIL. MECHANICAL CLOSET LOCKED. CONTRACTOR TO RESCHEDULE INSPECTION. | MARKB | MARKB | | HSP | L | 6132813 |
FRONTIER MECHANICAL INC. | H= | P | 03/12/2019 | FINAL PENDING - TEST AND BALANCE REPORT, OTHER ITEMS ADDRESSED. | MARKB | MARKB | | H= | P | 6132070 |
H2O PLUMBING & HEATING, INC. | HWP | L | 03/11/2019 | NO CALL AHEAD PROVIDED, CONTRACTOR NOT ON SITE AT 3:56. COULD NOT FIND BOILER INSTRUCTIONS FOR COMBUSTION AIR PIPING. | MARKB | MARKB | | HWP | L | 6130820 |
H2O PLUMBING & HEATING, INC. | HWP | C | 02/26/2019 | FOR FINAL PARTIAL - Need to complete combustion air and condensate piping to boilers. BY FINAL - Install medium pressure labels on gas piping. HYDRONIC PIPING COMPLETED, INSULATED AND UNDER SYSTEM OPERATING PRESSURE. | MARKB | MARKB | | HWP | C | 6117651 |
FRONTIER MECHANICAL INC. | H= | P | 02/19/2019 | FOR FINAL - Install RH-5 hood in sally port, install grills on dampers in detention corridors, address return air for room 158, complete condensate drains on roof and provide Test And Balance report. | MARKB | MARKB | | H= | P | 6110768 |
FRONTIER MECHANICAL INC. | HD | C | 02/19/2019 | DAMPERS/GRID LABELS COMPLETE, DETENTION CORRIDOR DAMPER ANGLES COMPLETE AND ROOF LADDER COMPLETE. | MARKB | MARKB | | HD | C | 6110762 |
FRONTIER MECHANICAL INC. | HSP | P | 02/19/2019 | Engineer letter on file for detention area corridor dampers. | MARKB | MARKB | | HSP | P | 6110059 |
H2O PLUMBING & HEATING, INC. | HI | C | 02/14/2019 | 10 PSI PRESSURE TEST AND PIPING PER PLAN OK FOR GAS PIPING FROM METER WITH UNDERGROUND TIED IN TO MECH ROOM. Still need medium pressure stickers and regulators installed. | MARKB | MARKB | | HI | C | 6107347 |
FRONTIER MECHANICAL INC. | HD | P | 02/12/2019 | DETENTION CORRIDOR DAMPERS - ALL DAMPERS INCLUDING BOOKING AREAS ARE FRAMED AND INSTALLED PER MANUFACTURER INSTRUCTIONS AND OK TO FINISH DUCT INSULATION. Still need to see all angles installed on bottom side of ceiling. AREA (B) ABOVE CEILING DUCT - FLEX AND DIFFUSERS COMPLETE FOR RM'S # 100, 101, 102, 103, 108, 116, 193, 202. Still need to complete all grid labels for F/S dampers. AREA (A) ABOVE CEILING DUCT - FLEX AND DIFFUSERS COMPLETE FOR RM'S # 146, 155, 156, 157, 158, 159, 160, 161, 163. Still need to complete all grid labels for F/S dampers. Need engineer to address return air path to room 158. ROOF - Need roof ladder, all condensate drains completed and makeup air hood to Sally Port completed per plan splice. | MARKB | MARKB | | HD | P | 6104727 |
FRONTIER MECHANICAL INC. | HSP | P | 02/11/2019 | BOILER MANUFACTURER LETTER ON FILE APPROVING BOILER VENTING - SEE IMAGES. STILL NEED - Equipment schedule changed with current boiler make, model and size. | MARKB | MARKB | | HSP | P | 6102919 |
FRONTIER MECHANICAL INC. | HD | P | 02/07/2019 | DAMPER FRAMING: DETENTION CORRIDORS - CEILING DAMPER FRAMING PER INSTALL SUPPLEMENT, still need damper framing in booking rooms. | MARKB | MARKB | | HD | P | 6100771 |
FRONTIER MECHANICAL INC. | HSP | P | 02/01/2019 | CONVERSATION WITH BUILDING SENIOR INSPECTOR AND MECHANICAL CONTRACTOR FOR CORRIDOR FIRE SMOKE DAMPERS. NEED STAMPED APPROVED LETTER FROM MECHANICAL ENGINEER APPROVING RUSKIN TUNNEL CORRIDOR SUPPLEMENT INSTRUCTION FOR THIS INSTALLATION. PER THE CONSTRUCTION DETAILS OF THE U415 UL ASSEMBLY DOES NOT INDICATE THAT ANY DAMPER HAS BEEN TESTED PENETRATING THIS ASSEMBLY IN A HORIZONTAL APPLICATION. DAMPERS MUST BE FRAMED TO THOSE INSTRUCTIONS ONCE APPROVED BY ENGINEER. | JON | JON | | HSP | P | 6095480 |
FRONTIER MECHANICAL INC. | HSP | P | 01/30/2019 | Training with Paul O. ON SITE CONSULT FOR CEILING AND DAMPER INSTALL IN DETENTION CORRIDOR AREA CEILING - MET WITH ROGER (G.H. PHIPPS), RICH B. (PPRBD), FRAMER (G.H. PHIPPS) MECHANICAL INSTALLER (FRONTIER). What is currently installed is a UL listed shaft wall assembly being used for a ceiling. Mechanical contractor can not provide at this time damper installation instructions for damper being installed in a shaft liner ceiling. Will need correct ceiling assembly listed on approved plans and then damper install instructions for that particular ceiling listing or an engineer stamped detail for damper support and an engineer stamped letter stating damper will provide the correct protection for the listing and his detail meets the intent of manufacturer instructions for support with provided listings and damper make and model. | MARKB | MARKB | | HSP | P | 6092090 |
H2O PLUMBING & HEATING, INC. | HI | P | 01/23/2019 | ----PLAN SPLICE REQUIRED FOR CHANGED BOILER BRAND, MODEL, SIZE AND VENTING---- 10 PSI PRESSURE TEST ON GAS PIPING IN MECHANICAL ROOM INSTALLED PER PLAN OK. Still need: Meter connections, regulators and medium pressure labels installed. | MARKB | MARKB | | HI | P | 6085653 |
H2O PLUMBING & HEATING, INC. | HWP | L | 12/28/2018 | Cancelled on site - wrong inspection called in. | MARKB | MARKB | | HWP | L | 6065068 |
FRONTIER MECHANICAL INC. | HD | P | 12/17/2018 | ----STILL NEED SPLICE FOR DUCT CHANGES FOR ROOMS # 103, 163 AND DETENTION AREA--- ABOVE CEILING DUCT - FLEX AND DIFFUSERS COMPLETED FOR AREA (A) ROOMS 121-148 AND AREA (B) ROOMS 109, 111, 112, 113, 114, 115, 117, 196, 198, 200, 201. STILL NEED - All damper access doors and grid labeled. | MARKB | MARKB | | HD | P | 6055055 |
FRONTIER MECHANICAL INC. | HSP | P | 12/17/2018 | SPOKE WITH DAN ON SITE: DETENTION CORRIDOR DAMPERS - THE CORRIDOR CEILING IS NOT BEING BUILT TO MATCH RUSKIN FSD-60C DAMPER INSTALL INSTRUCTIONS OR LISTING CALLED OUT ON PLANS. WILL NEED TO KNOW WHAT LISTING THE CEILING WILL BE BUILT TO IN ORDER TO DETERMINE IF CURRENT DAMPERS ARE CORRECT AND IF SO WILL NEED BETTER CLARIFICATION FROM RUSKIN ON DAMPER FRAMING IF USING C3 INSTRUCTIONS. | MARKB | MARKB | | HSP | P | 6055045 |
FRONTIER MECHANICAL INC. | HSP | P | 12/13/2018 | ON SITE CONSULT WITH MECHANICAL CONTRACTOR TO DISCUSS FIRE/SMOKE DAMPERS BEING INSTALLED IN DETENTION CORRIDORS AND BOILER VENTING:
Further research required detention corridor ceiling rating, damper being used and damper installation.
Either need boilers in cascade system vented per manufacturers instructions or venting detail supplied by boiler manufacturer to meet current installation. | MARKB | MARKB | | HSP | P | 6052079 |
H2O PLUMBING & HEATING, INC. | HSP | P | 12/13/2018 | -----Need equipment schedule and gas plan revised for boilers installed (boilers installed are different brand, model and size) and spliced through RBD plan review---- | MARKB | MARKB | | HSP | P | 6052062 |
FRONTIER MECHANICAL INC. | HSP | C | 11/27/2018 | CONDENSATE PIPING INSPECTED 11/21/18 UNDER HOT WATER PIPING CONTRACTOR. | MARKB | MARKB | | HSP | C | 6035020 |
H2O PLUMBING & HEATING, INC. | HWP | P | 11/21/2018 | 60 PSI PRESSURE TEST ON SUPPLY/RETURN HEAT PIPING FOR UNITS # 101, 102, 103, 104, 105, 112, 113, 114, 115, 116, CUH-154 & 127, UH-1 & 2 AND RTU-3. CONDENSATE PIPING FOR CRAC-1, DF UNIT AND MINI-SPLIT UNIT COMPLETE. | MARKB | MARKB | | HWP | P | 6032366 |
FRONTIER MECHANICAL INC. | HSP | P | 11/15/2018 | ROOF ACCESS INSPECTION - SPOKE WITH ROGER (GH PHIPPS), ROOF ACCESS LADDER NEEDS TO COMPLY WITH 2009 IMC SECTION 306.5 FOR TOE SPACING - REST OF LADDER COMPLIES. | MARKB | MARKB | | HSP | P | 6026445 |
FRONTIER MECHANICAL INC. | HD | P | 11/14/2018 | FIRE/SMOKE DAMPER INSTALL WITH ANGLES AND ACCESS DOOR COMPLETE FOR VAVR-210 | MARKB | MARKB | | HD | P | 6025046 |
FRONTIER MECHANICAL INC. | HRP | P | 11/14/2018 | Still need to complete condensate disposal. NO PRESSURE TEST REQUIRED - NO CONCEALED JOINTS. LINESETS FOR CRAC-1, 2 & FC-2 COMPLETE. Training with Paul O. | MARKB | MARKB | | HRP | P | 6025040 |
FRONTIER MECHANICAL INC. | HD | P | 11/08/2018 | ----ENGINEER LETTER RECEIVED FOR DAMPER SUPPORT ABOVE DOUBLE DOORS---- AREA (B): ABOVE CEILING DUCT - MEDIUM PRESSURE DUCT (STILL NEED PLAN SPLICE AND DAMPER ACCESS DOOR) AND SLOT DIFFUSER BOXES FOR FPB-209 AND TF-7 (CHECK MAKEUP AIR AT FINAL) OK TO WRAP. PROCEED AT OWN RISK ON MEDIUM PRESSURE DUCT. UH-3, 4 IN SALLY PORT INSTALLED PER PLAN. AREA (A): ABOVE CEILING DUCT - LOW PRESSURE DUCT FOR FPB-102, 103, 114 & VAVR-113 INSTALLED PER PLAN OK TO WRAP. No flex or diffusers. MEDIUM PRESSURE DUCT TO FPB-102 & 103 INSTALLED PER PLAN OK TO WRAP. Training with Paul O. | MARKB | MARKB | | HD | P | 6019963 |
H2O PLUMBING & HEATING, INC. | HWP | P | 11/08/2018 | 60 PSI PRESSURE TEST ON SUPPLY/RETURN PIPING FOR 2 UNIT HEATERS IN SALLY PORT BACK TO MAIN OK AND PIPING PER PLAN. STILL NEED - Insulation on piping | MARKB | MARKB | | HWP | P | 6019907 |
FRONTIER MECHANICAL INC. | HD | P | 11/01/2018 | ----ENGINEER TO ADDRESS: Damper support above double doors and return air through corridor wall to AREA (A) east side where walls have been run to deck---- ABOVE HARD LID DUCT - DUCT FOR STAFF TOILETS 118/119/160/161, SOUND ROOMS 156/157, ARMORY 159, INTERVIEW 151/152 & DETENTION CELLS OK TO CONCEAL - Still need return air path provided to 156, 157, 151. AREA (A): ABOVE CEILING DUCT - LOW PRESSURE DUCT FOR FPB-106/108/101/116/105, VAVR-115/104 & CRAC-1 INSTALLED PER PLAN OK TO INSULATE. MEDIUM PRESSURE DUCT FOR FPB-105 OK TO INSULATE. Training with Paul O. | MARKB | MARKB | | HD | P | 6012749 |
H2O PLUMBING & HEATING, INC. | HC | C | 10/31/2018 | OK TO RELEASE CONSTRUCTION METER FOR TEMP. HEAT. | MARKB | MARKB | | HC | C | 6011877 |
H2O PLUMBING & HEATING, INC. | HO | P | 10/31/2018 | 10 PSI PRESSURE TEST ON 2' OF BLACK PIPE OFF OF TEMP GAS METER OK. NO INSPECTION DONE ON TEMP HEAT SYSTEM. | MARKB | MARKB | | HO | P | 6011874 |
H2O PLUMBING & HEATING, INC. | HSP | P | 10/30/2018 | TEMP. HEAT INSPECTION TO RELEASE METER - Need at least 2' of gas pipe on meter with pressure test to release meter. DISCUSSED WITH ROGER AND BENNY. | MARKB | MARKB | | HSP | P | 6010572 |
FRONTIER MECHANICAL INC. | HSP | P | 10/17/2018 | MET WITH MICHAEL FROM PHIPPS TO DISCUSS TEMPORARY HEAT REQUIREMENTS. WE ALSO DISCUSSED NEED FOR THE ENGINEER TO ADDRESS THE FIRE SMOKE DAMPER INSTALLATIONS ABOVE DOUBLE DOOR OPENINGS. THESE OPENINGS WILL NOT COMPLY WITH THE DAMPER MANUFACTURER INSTALLATION INSTRUCTIONS FOR PROPER SUPPORT OF THE DAMPER. WILL NEED A DETAIL FOR ANY ADDED SUPPORT FRAMING AND A LETTER FROM THE ENGINEER THAT SPECIFIES THIS FRAMING WILL MEET THE INTENT FOR DAMPER SUPPORT AS TESTED BY THE MANUFACTURE LISTING. | JON | JON | | HSP | P | 5997897 |
FRONTIER MECHANICAL INC. | HD | P | 10/17/2018 | AREA (B): ABOVE CEILING DUCT - ABOVE HARD LIDS OK EXCEPT FOR HOLDING AREA. AREA (A) ABOVE CEILING DUCT - LOW PRESSURE DUCT FOR VAV-11O OK TO WRAP. LOOKED AT FPB-110 BUT STILL NEED SPLICE, WRAP AT OWN RISK. DAMPER INSPECTION - F/S DAMPER FOR FPB-110 FRAMING, ANGLES AND ANNULAR SPACE PER MANUFACTURERS INSTRUCTIONS - STILL NEED SPLICE FOR CHANGED LOCATION. MEDIUM PRESSURE DUCT FOR FPB'S-103, 104, 105, 106, 109, 110, 113, 114, 115 OK TO WRAP. FYI - 300 CFM EXHAUST FAN/DUCT FOR STAFF TOILET 161 APPEARS IT MAY BE IN AN ABOVE CEILING PLENUM WHEN INSTALLED. | MARKB | MARKB | | HD | P | 5997763 |
FRONTIER MECHANICAL INC. | HD | P | 10/08/2018 | AREA (A): UNIT HEATERS # 1 & 2 - HEIGHT OK IN FRONT OF OVERHEAD DOORS. DAMPER FRAMING AND INSTALL WITH ANGLES AND ANNULAR SPACE OK FOR EF-1 & VAVR-113 TO GARAGE AREA. AREA (B): ABOVE CEILING DUCT - SUPPLY/RETURN MAINS/BRANCHES TO CELLS FOR CORRIDOR (D) OK TO WRAP. ----SPLICE REQUIRED FOR CHANGE IN DUCT-----No corridor dampers, flex or diffusers this inspection. | MARKB | MARKB | | HD | P | 5988871 |
FRONTIER MECHANICAL INC. | HSP | P | 10/08/2018 | HAD ON SITE CONSULT WITH ROGER (G.H. PHIPPS) AND CHARLIE G./Dan M. (FRONTIER MECHANICAL) ABOUT WHAT IS BEING REQUIRED FOR ENGINEER FRAMING DETAIL ABOVE DOORS AND SHOWED THEM AN EXAMPLE | MARKB | MARKB | | HSP | P | 5988850 |
H2O PLUMBING & HEATING, INC. | HWP | P | 10/04/2018 | 65 PSI PRESSURE TEST OK ON SUPPLY/RETURN MAINS/BRANCHES FROM BOILER ROOM TO VAV-104 INCLUDING VAV-112 & CUH-154 | MARKB | MARKB | | HWP | P | 5985763 |
H2O PLUMBING & HEATING, INC. | HWP | P | 10/03/2018 | HOT WATER PIPING - SUPPLY/RETURN MAINS FROM BOILER ROOM UP TO VAV--104 INSTALLED PER PLAN EXCEPT NEED TEE'S CUT IN FOR VAV-112 & CUH-154. NO PRESSURE TEST AT THIS TIME - COVER AT OWN RISK. NO CONNECTIONS TO UNITS OR INSULATION | MARKB | MARKB | | HWP | P | 5984275 |
FRONTIER MECHANICAL INC. | HSP | P | 10/03/2018 | SPOKE WITH ROGER (G.H. PHIPPS) AND CHARLIE G. (FRONTIER MECHANICAL) ABOUT WHAT IS BEING REQUIRED FOR ENGINEER FRAMING DETAIL ABOVE DOORS AND REQUIRED INSPECTIONS. | MARKB | MARKB | | HSP | P | 5984262 |
FRONTIER MECHANICAL INC. | HD | P | 10/01/2018 | AREA (B) DAMPER FRAMING - FRAMING FOR DAMPER TO VAV-209 OK PER INSTALL INSTRUCTION. AREA (A) DAMPER FRAMING - ALL 4 DAMPER OPENING IN ROOM 163 OK FOR FRAMING AND DAMPERS INSTALLED PER INSTALL INSTRUCTIONS WITH ANGLES EXCEPT FOR DAMPER FOR FPB-110 NOT YET INSTALLED. | MARKB | MARKB | | HD | P | 5982138 |
FRONTIER MECHANICAL INC. | HD | P | 09/27/2018 | ----ENGINEER TO ADDRESS: AREA (B) DAMPER SUPPORT ABOVE DOUBLE DOOR ASSEMBLIES TO VAV-207, 210 & 211---- ----STILL NEED PLAN SPLICE FOR: AREA (B) VAV- 210 & 209 (DRYWALL TAPED ACROSS TOP PLATES OK) AND CHANGED DUCT IN HOLDING CELL AREA---- CONTRACTOR TO CORRECT SCOPE OF WORK TO DELETE UNIT HEATERS AND ADD VAV'S, FPB'S, DUCT AND EXHAUST. DAMPER INSPECTION - DAMPER FRAMING, INSTALLATION AND ONE-SIDED ANGLES FOR FITNESS TRANSFER OPENING PER INSTALL INSTRUCTIONS. Still need break away connections. ABOVE CEILING DUCT AREA (B): EXHAUST DUCT FOR TOILET/SHOWER AREA INSTALLED PER PLAN OK TO WRAP. SUPPLY/RETURN MAINS AND BRANCHES FOR HOLDING AREA (CORRIDOR B/CELLS) OK TO WRAP. Still need to see volume dampers above hard lids and no flex or diffusers. DUCT COMPLETE TO RM # 188 PER PLAN OK TO WRAP. | MARKB | MARKB | | HD | P | 5978758 |
FRONTIER MECHANICAL INC. | HD | P | 09/21/2018 | ABOVE CEILING DUCT FOR AREA (B): MEDIUM PRESSURE DUCT TO FPB-201 OK TO WRAP. Box not installed at this time. LOW PRESSURE DUCT FOR FPB-209 OK TO WRAP. No box, flex or diffusers installed.
ABOVE CEILING DUCT FOR AREA (A): MEDIUM PRESSURE DUCT FOR RTU-1 COMPLETE DOWN CORRIDOR AND TO VAV'S # 107, 109, 111, 112 & 115 INSTALLED PER PLAN OK TO WRAP. LOW PRESSURE DUCT FOR VAV'S # 107, 109, 112 INSTALLED PER PLAN OK TO WRAP. No flex or diffusers. EXHAUST DUCT FOR EF-5 INSTALLED PER PLAN UP THROUGH ROOF. No flex or grills.
| MARKB | MARKB | | HD | P | 5972834 |
FRONTIER MECHANICAL INC. | HD | P | 09/12/2018 | ABOVE CEILING DUCT AREA (B): LOW PRESSURE DUCT FOR: FPB-201, VAV-211, VAV-210, VAV-202, VAV-203 INSTALLED PER PLAN OK TO WRAP. MEDIUM PRESSURE DUCT FOR: VAV-211, VAV-203 & VAV-208 INSTALLED PER PLAN OK TO INSULATE. FIRE/SMOKE DAMPER FOR MEDIUM SIDE OF VAV-211: FRAMING AND DAMPER INSTALL PER MANUFACTURER INSTRUCTIONS. ROUGH DUCT FOR EF-06 INSTALLED PER PLAN. | MARKB | MARKB | | HD | P | 5962837 |
FRONTIER MECHANICAL INC. | HD | P | 09/07/2018 | -----PLAN SPLICE REQUIRED FOR AREA (A) FPB- 110 ROOM 163---- AREA (A) DAMPER FRAMING: 4 DAMPER OPENINGS IN ROOM 163 - Transfer opening needs top plate and knock outs in metal studs need to be covered with metal. AREA (B) ABOVE CEILING DUCT: 2 SUPPLY BRANCHES IN ROOM #199 INSTALLED PER PLAN. MEDIUM PRESSURE DUCT FOR RTU-2 COMPLETE TO VAV'S # 204, 205 & 206 INSTALLED PER PLAN OK TO WRAP. LOW PRESSURE MAINS/BRANCHES DUCT FOR VAV'S 204, 205 & 206 INSTALLED PER PLAN OK TO WRAP. | MARKB | MARKB | | HD | P | 5958666 |
FRONTIER MECHANICAL INC. | HD | P | 09/05/2018 | ----PLAN SPLICE REQUIRED FOR AREA (B) MEDIUM PRESSURE DUCT TO VAV-210 & FPB-209 WITH DAMPERS---- ABOVE CEILING DUCT AREA (B): (RTU-4) SUPPLY/RETURN MAINS/BRANCHES INSTALLED PER PLAN OK TO WRAP EXCEPT FOR 2 missing supplies in room # 199 and exhaust in room # 197. (RTU-2) FPB-207 MEDIUM/LOW PRESSURE SUPPLY MAINS/BRANCHES INSTALLED PER PLAN OK TO WRAP EXCEPT FOR rest of RTU-2. NO INSPECTIONS ON FPB'S OR DAMPERS. | MARKB | MARKB | | HD | P | 5955391 |
H2O PLUMBING & HEATING, INC. | P= | C | 03/21/2019 | correction made | TED | TED | | P= | C | 6139239 |
H2O PLUMBING & HEATING, INC. | P= | P | 03/18/2019 | need shower seats installed on locker room ADA showers, install vacuum breaker on hose thread spout on service sink, leak on break room sink, note: rest ok | TED | TED | | P= | P | 6135091 |
H2O PLUMBING & HEATING, INC. | PTO | P | 02/06/2019 | wrong permit called | TED | TED | | PTO | P | 6098970 |
H2O PLUMBING & HEATING, INC. | PTO | P | 01/07/2019 | hot and cold water piping in mechanical room ok | TED | TED | | PTO | P | 6069828 |
H2O PLUMBING & HEATING, INC. | PTO | P | 01/03/2019 | lost test water piping in mechanical room | TED | TED | | PTO | P | 6067110 |
H2O PLUMBING & HEATING, INC. | PTO | P | 01/02/2019 | conciliation on drain for combination toilet/lav in cell, need trap on lav, need to know material in wall that can be used, can not find requirement on plan | TED | TED | | PTO | P | 6066362 |
H2O PLUMBING & HEATING, INC. | PTO | P | 11/30/2018 | This inspection for grade fixed on added sink armory and isolation valves cut in off bathroom, need engineer approval for piping and plan splice on added sink, cover at own risk. | DANR | DANR | | PTO | P | 6039036 |
H2O PLUMBING & HEATING, INC. | PTO | P | 11/28/2018 | Inspection for DWV and domestic water to added sink armory room (ASI # 20), need plan splice on add and engineer approval for piping water off bathroom group without isolation valves, drain back graded, Added ice maker room 163 (ASI # 9 R1), need engineer approval for no isolation valve and piping tie in location, need plan splice. | DANR | DANR | | PTO | P | 6037072 |
H2O PLUMBING & HEATING, INC. | PTO | P | 11/09/2018 | Vtr and domestic water to holding cells ok. | DANR | DANR | | PTO | P | 6022097 |
H2O PLUMBING & HEATING, INC. | PTO | P | 11/08/2018 | overhead water main for car wash building from meter room to under ground riser | TED | TED | | PTO | P | 6019641 |
H2O PLUMBING & HEATING, INC. | PTO | P | 10/16/2018 | water and venting area A ceiling and through roof | TED | TED | | PTO | P | 5995511 |
H2O PLUMBING & HEATING, INC. | PTO | P | 10/12/2018 | discussed with plan reviewer Michael A staff bathrooms in area A will need to be accessible, will need plans changed to reflect changes, rest of area A walls ok still need to see over head | JOSEPHD | JOSEPHD | | PTO | P | 5992990 |
H2O PLUMBING & HEATING, INC. | PTO | P | 10/11/2018 | area A in walls water pipe & vent ok plans marked | JOSEPHD | JOSEPHD | | PTO | P | 5991782 |
H2O PLUMBING & HEATING, INC. | PWO | P | 10/02/2018 | water line from main building to maintenance building | TED | TED | | PWO | P | 5982552 |
H2O PLUMBING & HEATING, INC. | PTO | P | 10/01/2018 | staff restrooms walls and ceiling ok, plan marked | TED | TED | | PTO | P | 5981151 |
H2O PLUMBING & HEATING, INC. | PTO | P | 09/27/2018 | public rest room area, break room area, walls and ceilings ok, water lines in ceilings of hall ok, plan marked | TED | TED | | PTO | P | 5978304 |
H2O PLUMBING & HEATING, INC. | PRD | C | 09/27/2018 | primary and secondary roof drains | TED | TED | | PRD | C | 5978293 |
H2O PLUMBING & HEATING, INC. | PTO | P | 09/25/2018 | field cancel, not ready | TED | TED | | PTO | P | 5975184 |
H2O PLUMBING & HEATING, INC. | PTO | P | 09/18/2018 | dwv and water in walls and ceiling for locker rooms and bathrooms | TED | TED | | PTO | P | 5967963 |
H2O PLUMBING & HEATING, INC. | PTO | P | 09/14/2018 | consultation discussed accessible elements for mens and womens locker room bathrooms, accessible shower valves to high in both showers, need to test dwv, and water pipe | JOSEPHD | JOSEPHD | | PTO | P | 5965200 |
H2O PLUMBING & HEATING, INC. | PTO | P | 09/05/2018 | dwv vents in wall and ceiling of mechanical room ok | TED | TED | | PTO | P | 5955006 |
H2O PLUMBING & HEATING, INC. | PB | P | 07/13/2018 | water main pictures in images | TED | TED | | PB | P | 5901530 |
H2O PLUMBING & HEATING, INC. | PB | P | 07/06/2018 | field cancel, 3'' copper water main not ready, still digging trench | TED | TED | | PB | P | 5894698 |
H2O PLUMBING & HEATING, INC. | PB | P | 07/03/2018 | car wash sand/oil base ok (inspection transferred to correct permit) | TED | TED | | PB | P | 5892234 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/28/2018 | city utilities looks at piping outside of building for trench drains building A | JOSEPHD | JOSEPHD | | PB | P | 5888130 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/20/2018 | added 90s on water main inside car wash (inspection transferred to correct permit) | TED | TED | | PB | P | 5879412 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/18/2018 | under ground water line from sally port to car wash | TED | TED | | PB | P | 5876947 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/13/2018 | area ''a'' trench drains | TED | TED | | PB | P | 5872840 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/08/2018 | ok for 2" water line stubbed under footer @ sally port car wash area, plan P0.1, plans marked | JOHNS | JOHNS | | PB | P | 5868635 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/07/2018 | staff rest room B1, area A | TED | TED | | PB | P | 5867265 |
H2O PLUMBING & HEATING, INC. | PB | P | 06/06/2018 | field cancel | TED | TED | | PB | P | 5865819 |
H2O PLUMBING & HEATING, INC. | PB | P | 05/30/2018 | holding cells area | TED | TED | | PB | P | 5858511 |
H2O PLUMBING & HEATING, INC. | PB | P | 05/24/2018 | staff bathroom area | TED | TED | | PB | P | 5854394 |
H2O PLUMBING & HEATING, INC. | PB | P | 05/22/2018 | woman's shower area, break room area plan marked | TED | TED | | PB | P | 5851869 |
H2O PLUMBING & HEATING, INC. | PB | P | 05/18/2018 | men's locked room plan marked | TED | TED | | PB | P | 5849016 |
H2O PLUMBING & HEATING, INC. | PB | P | 05/17/2018 | showers and lavs, and fire riser floor drain plans marked ok | JOSEPHD | JOSEPHD | | PB | P | 5847567 |
H2O PLUMBING & HEATING, INC. | PB | P | 05/11/2018 | sand and oil drain for SALLY PORT trench drain area B | TED | TED | | PB | P | 5842783 |
H2O PLUMBING & HEATING, INC. | PRD | P | 05/11/2018 | under ground roof drain | TED | TED | | PRD | P | 5842109 |
FOSTER ELECTRIC CORPORATION | XES | T | 05/07/2019 | PAID (REC#1596577) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Added air compressor | BERTHA | BERTHA | | XES | T | 6191503 |
FOSTER ELECTRIC CORPORATION | XES | P | 04/11/2019 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised plans - as-built conditions. | BERTHA | BERTHA | | XES | P | 6162879 |
GERALD H PHIPPS INC | XBS | P | 04/04/2019 | PLAN SPLICE: (No Fee) by: DANM for Construction: Revise second accessible holding cel to non-accessible (Only one required - one provided)l | DANM | DANM | | XBS | P | 6155430 |
FRONTIER MECHANICAL INC. | XMS | T | 04/04/2019 | PAID (REC#1587862) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: Mechanical splice 4/4/19: Delta 28 revisions- relocate IH-2, reroute gas line overhead, install new underground gas line and meter, adjusted boiler schedule using different brand, showing new gas line | TCRIPPEN | TCRIPPEN | | XMS | T | 6155354 |
FOSTER ELECTRIC CORPORATION | XES | P | 02/07/2019 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised one-line. Revised Transformer T112. | BERTHA | BERTHA | | XES | P | 6101199 |
FRONTIER MECHANICAL INC. | XMS | T | 02/07/2019 | PAID (REC#1574950) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: SEE RFI-0218, RFI219, RFI221, RFI256 | DALEH | DALEH | | XMS | T | 6101163 |
GERALD H PHIPPS INC | XBS | T | 02/07/2019 | PAID (REC#1574824) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Booking area ceiling detail | SHELLEY | SHELLEY | | XBS | T | 6100552 |