COLORADO STRUCTURES INC | B= | C | 01/13/2021 | All items now corrected for final inspection | NATHAN | NATHAN | | B= | C | 6834908 |
COLORADO STRUCTURES INC | B= | T | 12/18/2020 | PAID (REC#1737850): Temp CO: TCO Extension for Phases 1-3 pending all required finals/ Trip fee assessed for TCO fee collection ( Expires: 1/17/2021 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 6813270 |
COLORADO STRUCTURES INC | B= | T | 11/19/2020 | PAID (REC#1731667): Temp CO: TCO Extension for Phases 1-3 pending all required finals/ Trip fee assessed for TCO fee collection ( Expires: 12/19/2020 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 6783303 |
COLORADO STRUCTURES INC | B= | P | 11/18/2020 | Phase 1 level 5 units 502, 513, 536, 537 mezzanine stair handrails installed okay ======= 1st floor lobby restroom remaining for correction of 60" clear floor space at side of toilet.======= -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6781586 |
COLORADO STRUCTURES INC | B= | P | 11/12/2020 | Phase 1 final walk items remaining spiral roof top deck stair handrails units 502, 513, 536, 537 and side wall clearance of 60" clear for 1st floor lobby bathroom . Remaining items have been corrected or installed. Roof anchor system at clubhouse roof for mechanical equipment service within 10' of edge installed per details.. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6774529 |
COLORADO STRUCTURES INC | B= | T | 10/20/2020 | PAID (REC#1722997): Temp CO: Temp CO: Phase 3 TCO pending all required finals/ Trip fee added for TCO fee collection ( Expires: 11/19/2020 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 6747237 |
COLORADO STRUCTURES INC | B= | P | 10/08/2020 | Phase 2 and phase 3 areas items corrected, Recall phase 1 items when ready, -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC (CES) Electrical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6734730 |
COLORADO STRUCTURES INC | B= | T | 09/25/2020 | PAID (REC#1716363): Temp CO: Phase 2 TCO pending all required finals / Trip fee added for TCO fee collection ( Expires: 10/25/2020 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 6720592 |
COLORADO STRUCTURES INC | B= | P | 09/25/2020 | Phase 2, 2nd floor club house restrooms need grab bars and divider walls installed, need kitchen completed for counter tops, sink and appliances completed. all remaining areas okay. | NATHAN | NATHAN | | B= | P | 6720072 |
COLORADO STRUCTURES INC | BSP | P | 09/23/2020 | Phase 1 handrails corrected at G1 level stairs and ramp Phase 2 missing guardrail at 218, 220 patio, need kitchen, restrooms, drinking fountain completed at clubhouse pool safety equipment and signage, unit 213 with completed required inspections okay. | NATHAN | NATHAN | | BSP | P | 6717073 |
COLORADO STRUCTURES INC | BSP | P | 09/16/2020 | Phase 2 2nd floor units and common area EXCEPT POOL, CLUB HOUSE and 213 okay balcony area on courtyard to pool enclosures not completed to 5' | NATHAN | NATHAN | | BSP | P | 6708026 |
COLORADO STRUCTURES INC | B= | P | 09/15/2020 | Phase 2 final Walk 2nd floor units only 201-235 okay with completed required inspections and balcony rails to pool area EXCEPT 213 -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC (CES) Electrical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6706482 |
COLORADO STRUCTURES INC | BSP | P | 09/03/2020 | Phase 1 fitness room drinking fountain and break room sink corrected, Phase 2 club house and stairs, discussed accessibility issues and pre walked for kitchen, thresholds and restrooms. | NATHAN | NATHAN | | BSP | P | 6696307 |
COLORADO STRUCTURES INC | B= | T | 08/27/2020 | PAID (REC#1708342): Temp CO: Phase 1 TCO ONLY ( pending all required finals) Trip fee added for TCO fee collection ( Expires: 9/26/2020 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 6688364 |
COLORADO STRUCTURES INC | B= | P | 08/27/2020 | Phase 1 level 1,3,4,5, roof and G1,-G3 level FINAL WALK, need to address egress landing at exterior NE G1 door to alley, stair 3 G1 level sign needs moved to alley exit door and new sign mounted at G1 level with correct wording, stair 2 level G1 SW sign needs moved to level G2 exit enclosure door and new sign added at G1 level, address level change at both G1 and G2 elevator 3 vestibule doors, 2nd side handrail at ramp and step G1 NE exit needed, need 60" clear floor space to sink at lobby bathroom and sign changed to for which one is accessible, yoga room door handle for accessibility, 27" knee clearance at fitness room drinking fountain, 34" max to break room sink, EDIT ADDED 8-27 5th floor mezzanine upper patio spiral stair handrails units 502, 523, 536, 537 need installed , elevator shafts corrected for penetrations and grouting . Barriers and signage installed at areas for phase 2 separation from phase 1 -- Schedule a new Building Final when above items are complete. | NATHAN | NATHAN | | B= | P | 6687981 |
COLORADO STRUCTURES INC | B= | P | 08/26/2020 | Phase 1 1st floor Yoga room need handle to meet accessibility requirements, drinking fountain in fitness room missing 27" knee clearance , break room sink over 34", 2nd side handrail at G1step to NE exterior door needed. landing at exterior NE door G1 level needed. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC (CES) Electrical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet, SCHINDLER ELEV. CORP. Mechanical Final Inspection is not Completed yet, TEXAS FIREPLACE EXPRESS, LLC DBA FIREPLA Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6686662 |
COLORADO STRUCTURES INC | BSP | P | 08/25/2020 | 5th floor final walk Phase 1 need spiral stair handrail to balcony installed,units 502, 513, 536, 537 , steps and remaining areas and units corrected.
4th floor Phase 1 unit 402 corrected all units and spaces okay,
elevator shaft 1 and 2 2nd floor up need grout and penetrations completed at inside shaft, elevator 3 CMU over 5th floor door. | NATHAN | NATHAN | | BSP | P | 6684754 |
COLORADO STRUCTURES INC | B= | P | 08/21/2020 | Phase 1 5th floor roof top patio, and all mezzanine units, units 502, 513, 537, 536 missing handrail at spiral stairs to upper patio , patio door swings over step down at exterior patio, remaining units okay -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC (CES) Electrical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet, SCHINDLER ELEV. CORP. Mechanical Final Inspection is not Completed yet, TEXAS FIREPLACE EXPRESS, LLC DBA FIREPLA Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6682158 |
COLORADO STRUCTURES INC | BSP | P | 08/20/2020 | level 1 garage entry fire protection, 5th floor ffnal walk PHASE 1 of corridor, electric, mechanical and janitor closets okay. 5TH FLOOR remaining Phase 1 areas roof top area, and all mezzaninies remaining. | NATHAN | NATHAN | | BSP | P | 6679683 |
COLORADO STRUCTURES INC | B= | P | 08/19/2020 | 4th FLOOR PHASE 1, final walk of 4th all areas okay EXCEPT UNIT 402 okay. discussed barriers for phase 1 and 2 separation. discussed handrails vs guardrails at 5th floor mezzanine stairs. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC (CES) Electrical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet, SCHINDLER ELEV. CORP. Mechanical Final Inspection is not Completed yet, TEXAS FIREPLACE EXPRESS, LLC DBA FIREPLA Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6678397 |
COLORADO STRUCTURES INC | B= | P | 08/18/2020 | 3RD FLOOR PHASE 1, common areas and units okay EXCEPT 313 not ready. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), BIBLE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, BRUCE MECHANICAL OF COLORADO, INC Mechanical Final Inspection is not Completed yet, COLORADO ELECTRICAL SYSTEMS, LLC (CES) Electrical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet, SCHINDLER ELEV. CORP. Mechanical Final Inspection is not Completed yet, TEXAS FIREPLACE EXPRESS, LLC DBA FIREPLA Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6676484 |
COLORADO STRUCTURES INC | BSP | P | 08/12/2020 | 5th floor final walk phase 1, common areas, type A unit and mezzanine units not inspected at this time remaining units okay. reviewed garage ramps level 1 and 2. | NATHAN | NATHAN | | BSP | P | 6670205 |
COLORADO STRUCTURES INC | BSP | P | 08/11/2020 | Phase 1 final walk 3rd floor north units only except level 313. Unit 315 type A | NATHAN | NATHAN | | BSP | P | 6668448 |
COLORADO STRUCTURES INC | BSP | P | 08/10/2020 | Phase 1 5th floor south Final Walk of non mezzanine units only okay and units 401 501 corrected | NATHAN | NATHAN | | BSP | P | 6666733 |
COLORADO STRUCTURES INC | BIN | P | 08/10/2020 | Garage level 1 insulation at ceiling okay. | NATHAN | NATHAN | | BIN | P | 6666721 |
COLORADO STRUCTURES INC | BSP | P | 08/06/2020 | request is for building final of 5th floor units - all units are type B option A - units 503, 507, 511, 515, 521 and 529 okay / unit 501 missing threshhold to deck and guard is greater than 4 " from side wall / units 504, 505, 506, 508, 509, 510, 512, 517, 519, 531, 533 and 524 missing code compliant threshold to deck / unit 522 is a Type A unit and is okay Amended - Final inspection was for Phase 1 , 5th floor units only | BOBF | BOBF | | BSP | P | 6664373 |
COLORADO STRUCTURES INC | BSP | P | 08/06/2020 | 2nd layer drywall install above entry door unit 101 okay , 2nd layer drywall install at soffits above entries units 118, 120 and 122 okay | BOBF | BOBF | | BSP | P | 6664356 |
COLORADO STRUCTURES INC | BSP | P | 07/29/2020 | 4th floor Final Walk Phase 1 units only with completed required inspections, need threshold at sliding door beveled, 4th Floor Partial Finals South
Main Garage above Ceiling with approved required inspections
1st Layer drywall / frame units 122 - 116 at entry cove | NATHAN | NATHAN | | BSP | P | 6654200 |
COLORADO STRUCTURES INC | BSP | P | 07/28/2020 | 4th Final walk Phase 1 east units corridors, threshold at sliding doors remaining okay | NATHAN | NATHAN | | BSP | P | 6652761 |
COLORADO STRUCTURES INC | BSP | P | 07/27/2020 | 4TH Final walk Phase 1 units 401-412 need beveled transition to sliding door threshold, all units, 401 patio rail less than 4" to building. 405 missing trex decking pieces. | NATHAN | NATHAN | | BSP | P | 6651330 |
COLORADO STRUCTURES INC | BFR | P | 07/27/2020 | framing at trash enclosure room for damper okay | NATHAN | NATHAN | | BFR | P | 6651317 |
COLORADO STRUCTURES INC | BSP | P | 07/14/2020 | Insulation at G1 maintenance room walls | NATHAN | NATHAN | | BSP | P | 6636301 |
COLORADO STRUCTURES INC | BSP | P | 07/13/2020 | discussed soffit frame of fire barrier at entry 116-122 | NATHAN | NATHAN | | BSP | P | 6634922 |
COLORADO STRUCTURES INC | BIN | P | 07/09/2020 | Exterior thermal at clubhouse OK | JEREMYA | JEREMYA | | BIN | P | 6631823 |
COLORADO STRUCTURES INC | BSP | P | 07/08/2020 | Stair framing from upper level units, 502, 513, 536 & 537, to rooftop patios OK // Discussed threshold heights between Type A & B units | JEREMYA | JEREMYA | | BSP | P | 6629674 |
COLORADO STRUCTURES INC | BSP | P | 06/25/2020 | 5th Floor Mezzanine Units last of Fire caulk , Drops/ Soffits 513, 518, 537 with approved required inspections. | NATHAN | NATHAN | | BSP | P | 6617784 |
COLORADO STRUCTURES INC | BFT | C | 06/24/2020 | Summary observation letter on file | NATHAN | NATHAN | | BFT | C | 6615594 |
COLORADO STRUCTURES INC | BSP | P | 06/24/2020 | 525 last of framing for ceiling and duct framing firecaulking completed. | NATHAN | NATHAN | | BSP | P | 6615581 |
COLORADO STRUCTURES INC | BIN | P | 06/18/2020 | Stair 4 ceiling insulation to podium okay. | NATHAN | NATHAN | | BIN | P | 6609540 |
COLORADO STRUCTURES INC | BSP | P | 06/17/2020 | I503- Drywall 537 | NATHAN | NATHAN | | BSP | P | 6607608 |
COLORADO STRUCTURES INC | BSP | P | 06/16/2020 | I503 Drywall- 513 and 525 I503 Frame- 537 | NATHAN | NATHAN | | BSP | P | 6606542 |
COLORADO STRUCTURES INC | BSP | P | 06/15/2020 | Fire Stop at stair #2 I503 Frame- 525Fire Stop at stair #2 I503 Frame- 525Fire Stop at stair #2
I503 Frame- 525 | NATHAN | NATHAN | | BSP | P | 6604614 |
COLORADO STRUCTURES INC | BSP | P | 06/12/2020 | Stair #2 and #4 and units 102-112 Fire Caulking okay
I503 Drywall- 502, 536
I503 Frame- 513 | NATHAN | NATHAN | | BSP | P | 6603179 |
COLORADO STRUCTURES INC | BSP | P | 06/11/2020 | discussed damper framing 513 and inspected damper frame at 536 | NATHAN | NATHAN | | BSP | P | 6601403 |
COLORADO STRUCTURES INC | BSP | P | 06/10/2020 | 502- I503 Frame w/ Mechanical Inspector Fire Stop/ Frame Drops and Soffits 549, 520, 523 NOW COMPLETED
Stair #4 Frame need above ceiling at corridor firestopped
Unit 102-110 Frame fan coils and duct chases at kitchen
Stair #2 G2 2nd and 3rd layer with RC okay | NATHAN | NATHAN | | BSP | P | 6600165 |
COLORADO STRUCTURES INC | BSP | P | 06/08/2020 | discussed I503 assembly with Jon B, Aaron, John and Kyle with CSI for floor assembly at mezzanine | NATHAN | NATHAN | | BSP | P | 6596706 |
COLORADO STRUCTURES INC | BSP | P | 06/02/2020 | Unit 116 and pool boiler venting discussion with Jon Brazier and Aaron Lavy for EJ on file for boiler vents and rated assemblies on plans used at unit 116 entry. | NATHAN | NATHAN | | BSP | P | 6590518 |
COLORADO STRUCTURES INC | BSP | P | 05/29/2020 | Drops/ Soffits- Framing and Fire Caulking 527 all soffits and drops completed
5th Floor Trash Room above ceiling Fire Caulking and frame okay | NATHAN | NATHAN | | BSP | P | 6587546 |
COLORADO STRUCTURES INC | BSP | P | 05/27/2020 | Frame and Fire Stop Upstairs Bath; 502, 513 all framing and firestops at soffits and ceilings completed.
Clubhouse Framing and Columns with structural observation and truss repair letter okay with completed required inspections . D2B coulumn 2nd layer inside okay at Stair 4 | NATHAN | NATHAN | | BSP | P | 6584653 |
COLORADO STRUCTURES INC | BSP | P | 05/26/2020 | Drywall Screw Roof Top Vestibule Unit 518 Soffits and Drops Frame and Fire Stop G2 Vestibule at elevator 1 | NATHAN | NATHAN | | BSP | P | 6582688 |
COLORADO STRUCTURES INC | BSP | P | 05/21/2020 | 502 high ceiling framing
1st floor 110-122 fur out and stair wall framing / Stair 4 drywall at corridor and surrounding area okay
Garage levels vestibule framing, and discussed flue penetrations at garage and trash termination room. | NATHAN | NATHAN | | BSP | P | 6580149 |
COLORADO STRUCTURES INC | BSP | P | 05/15/2020 | fire barrier continuity at entry floor over door units 116-122 okay | NATHAN | NATHAN | | BSP | P | 6573232 |
COLORADO STRUCTURES INC | BSP | P | 05/13/2020 | Fire Stop High Soffits and Drop Ceilings 537, 549
Fire Stop above ceiling at, elevator lobby, trash room and telecom 5th, 4th, 3rd, 2nd | NATHAN | NATHAN | | BSP | P | 6570628 |
COLORADO STRUCTURES INC | BSP | P | 05/12/2020 | Mezzanine floor fireblocking over entry units 116-122 2nd layer inside okay,
Insulation corridor outside 110
| NATHAN | NATHAN | | BSP | P | 6568594 |
COLORADO STRUCTURES INC | BSP | P | 05/08/2020 | 1st Layer Ceilings at stair #4 and stair #2 OK 2nd Layer on wall in corridor at stair #4 OK
| JEREMYA | JEREMYA | | BSP | P | 6565425 |
COLORADO STRUCTURES INC | BSP | P | 05/06/2020 | Unit F/C 102,104,106,108 OK Corridors West OK Drywall Screw Mezzanine at stair 4 OK | JEREMYA | JEREMYA | | BSP | P | 6562771 |
COLORADO STRUCTURES INC | BSP | P | 05/04/2020 | Drywall Screw 110, 112, 114 Shear 114 Garage Framing and Fire Stop at north level 1 Soffit Framing 536 Elevator 3 lobby Fire Stop Level 5 | NATHAN | NATHAN | | BSP | P | 6560465 |
COLORADO STRUCTURES INC | BSP | P | 04/30/2020 | Shear;114. Drywall Layers / Screw 110 and 108 Corridor.
Kitchen Fur out walls ;513, 523, 518, 520, 527, 537, Misc Drop framing anf F/C at 502, 513, 523, 518, 520, 527, 537, 536, 549 | NATHAN | NATHAN | | BSP | P | 6557103 |
COLORADO STRUCTURES INC | BSP | P | 04/29/2020 | Drywall Screw 118, 116 Sheer 114 Above Ceiling @ Fan Coil 102, 104, 106, 108 | NATHAN | NATHAN | | BSP | P | 6555947 |
COLORADO STRUCTURES INC | BSP | P | 04/27/2020 | Drywall Screw 122,120 3rd layer drywall and F/C 112 under mezzanine, Insulation 110, 114 okay | NATHAN | NATHAN | | BSP | P | 6552465 |
COLORADO STRUCTURES INC | BSP | P | 04/24/2020 | 122, 120, 118, 116, 114 Fire Stop, 3rd layer drywall at 112 okay
Elevator 1 and 3 garage 2nd layer at jambs okay | NATHAN | NATHAN | | BSP | P | 6551212 |
COLORADO STRUCTURES INC | BSP | C | 04/23/2020 | 114, 116, 122 , 118, 120 3rd layer DW @ Mezzanine 112 2nd layer DW @ Mezzanine F/C remaining.
5th Floor Drops & F/C @ Mezzanines except fan coil and duct work framing. | NATHAN | NATHAN | | BSP | C | 6549603 |
COLORADO STRUCTURES INC | BSP | P | 04/21/2020 | Drywall Screw; 102, 104, 106, 108
insulation; 120, 122 | NATHAN | NATHAN | | BSP | P | 6546688 |
COLORADO STRUCTURES INC | BSP | P | 04/20/2020 | Above ceiling; 122,120,118,116,114,112,110. and single layer under mezzanine 122-112 firecaulk at column joint 122 corrected.
Shear; 110, 106
F/C; Elevator 1 G2 | NATHAN | NATHAN | | BSP | P | 6545411 |
COLORADO STRUCTURES INC | BSP | P | 04/15/2020 | need fire barrier to go up through floor joist at cantilever floor units 116-122, 5th, 3rd, 2nd North/ South- Corridor FC
427, 436, 327, 320, 227 Drop Ceilings FC
116, 118, 120, 122 Fire stop/ fire caulk
Dryer boxes for 114, 110 | NATHAN | NATHAN | | BSP | P | 6541811 |
COLORADO STRUCTURES INC | BIN | P | 04/13/2020 | Insulation 106, 108. | NATHAN | NATHAN | | BIN | P | 6539075 |
COLORADO STRUCTURES INC | BSP | P | 04/13/2020 | F/C and F/S 110, 112, 114 1st layer corridor type C and RC at mezzanine 102-108 okay
F/C Elevator 3 jambs G1 and G2. | NATHAN | NATHAN | | BSP | P | 6539074 |
COLORADO STRUCTURES INC | BIN | P | 04/07/2020 | insulation units 102 okay | NATHAN | NATHAN | | BIN | P | 6533631 |
COLORADO STRUCTURES INC | BSP | P | 04/07/2020 | RC unit 108 to corridor per F2bs WP 1520 , 3rd layer drywall screw and stagger underside of mezzanine 102-108 per GA FC 4750, mineral wool insulation at corridor wall unit 102-106 only, | NATHAN | NATHAN | | BSP | P | 6533624 |
COLORADO STRUCTURES INC | BSP | P | 04/03/2020 | Drywall Screw 536 okay
Mezzanine First Layer 102, 104, 106 at bottom corridor and unit okay, -------Unit 102-108 corridor side WP 1520 need 1/2" type X per the listing, 1/2" light rock installed, address top and bottom of corridor ramps handrail extensions into door ways at unit 104, 108 | NATHAN | NATHAN | | BSP | P | 6530861 |
COLORADO STRUCTURES INC | BSP | P | 04/01/2020 | Mezzanine Floor Frame and Fire Stop 102, 104, 106, 108 and corridor 2nd layer except at sides of mezzanine 1st layer okay. | NATHAN | NATHAN | | BSP | P | 6528483 |
COLORADO STRUCTURES INC | BSP | P | 03/31/2020 | Drywall Screw- 502 5th Floor Roof Deck Vestibule Insulation and RC 536- Truss Repairs @ entry, repair design on file. | NATHAN | NATHAN | | BSP | P | 6526602 |
COLORADO STRUCTURES INC | BSP | P | 03/31/2020 | truss repair detail uploaded. | NATHAN | NATHAN | | BSP | P | 6526198 |
COLORADO STRUCTURES INC | BFR | R | 03/27/2020 | Level 1 Mezzanine Frame/ Fire Stop not ready 102, 104, 106, 108, correct back to back boxes and draft stops at double walls. | NATHAN | NATHAN | | BFR | R | 6524157 |
COLORADO STRUCTURES INC | BSP | P | 03/26/2020 | FC kitchen fur out and all drops 402, 425
Drywall Screw first layer west corridor up to head of ramp at stair 4 RC screw west corridor remaining mezzanine areas to stair #4 | NATHAN | NATHAN | | BSP | P | 6522592 |
COLORADO STRUCTURES INC | BSP | P | 03/24/2020 | Drywall Screw 436, 227
Fire Caulk/ Fire Stop- 102, 104, 106 and RC at corridors only no mezzanine same units Dryer Box 106
Isolation Clips 101/ fitness per U419 and U423 | NATHAN | NATHAN | | BSP | P | 6519695 |
COLORADO STRUCTURES INC | BSP | P | 03/23/2020 | Fire Stop Corridors at Stair #3- 5th, 4th, 3rd OK | NICK | NICK | | BSP | P | 6518359 |
COLORADO STRUCTURES INC | BSP | P | 03/20/2020 | Drywall screw 427, 327
5th Floor Trash Chute Liner 1st Layer Drywall Trash Chutes 2nd, 3rd, 4th
| NATHAN | NATHAN | | BSP | P | 6517291 |
COLORADO STRUCTURES INC | BSP | P | 03/19/2020 | Blow Batts RC 536
Bathroom Drops 402
Kitchen Fur Out Walls 402, 320
| NATHAN | NATHAN | | BSP | P | 6516238 |
COLORADO STRUCTURES INC | BSP | P | 03/17/2020 | Drywall Screw 537
Blow Batts RC 227 | NATHAN | NATHAN | | BSP | P | 6513131 |
COLORADO STRUCTURES INC | BSP | P | 03/16/2020 | Blow, Batts, RC 227, 536, not ready, 427, 327 okay
Lobby remaining exterior insulation northwest corner.
| NATHAN | NATHAN | | BSP | P | 6511578 |
COLORADO STRUCTURES INC | BSP | P | 03/13/2020 | Drywall Screw 523, 525
Bathroom Drops and Fur Out Walls 423, 418, 437, 449, 413, 420
Lobby Exterior Insulation at coffee bar, training and fitness rooms okay
Level 1 West Dryer Vent Boxes | NATHAN | NATHAN | | BSP | P | 6510406 |
COLORADO STRUCTURES INC | BSP | P | 03/11/2020 | Drywall Screw 522 Blow, Batts, RC 537 Frame corrections 536
1st floor Lobby Fire Caulk/ Fire Stop elevator 1st layer | NATHAN | NATHAN | | BSP | P | 6507691 |
COLORADO STRUCTURES INC | BSP | P | 03/09/2020 | Fire Caulk Fire Stop- 427, 327, 227
Drywall Screw- 513, 520, 402, 425
Framing Corrections at 537 | NATHAN | NATHAN | | BSP | P | 6504421 |
COLORADO STRUCTURES INC | BSP | P | 03/04/2020 | 5th Floor Drywall Screw- 549 Frame corrections 537, 513 completed
327, 427 column and beam inspection only full frame remaining | NATHAN | NATHAN | | BSP | P | 6499881 |
COLORADO STRUCTURES INC | BSP | P | 03/03/2020 | Blow Batts RC - 402, 425, 436 Unit 513
Lobby Exterior common wall to garage insulation | NATHAN | NATHAN | | BSP | P | 6498985 |
COLORADO STRUCTURES INC | BSP | P | 03/02/2020 | Shear- 523, 525, 425, 436 okay
RC batt and Blow walls and ceiling 522 okay | NATHAN | NATHAN | | BSP | P | 6497609 |
COLORADO STRUCTURES INC | BSP | P | 02/28/2020 | 2nd Floor Corridor Fire Caulk/ Fire Stop Except elevator lobby and stair extension areas
522 FC/FS
Discussed magnetic locks and latches and pool /club house west rated assemblies/ continuity. | NATHAN | NATHAN | | BSP | P | 6496216 |
COLORADO STRUCTURES INC | BSP | P | 02/26/2020 | 5th Floor Dead Spaces Drywall Screw STILL NEED FIRESTOP/FC 523, 520, 522, 549 SCREW OKAY
Fire Caulk Fire Stop 402, 436
Trash Chute Fire Caulk Bottom track 4th, 3rd , 2nd | NATHAN | NATHAN | | BSP | P | 6492940 |
COLORADO STRUCTURES INC | BSP | P | 02/25/2020 | Drywall Screw 518, 527
Trash Room 2nd Layer Fire Tape/ Fire Caulk 4th, 3rd, 2nd
1st Floor Lobby Perimeter Insulation 4' down from ceiling slab | NATHAN | NATHAN | | BSP | P | 6491740 |
COLORADO STRUCTURES INC | BSP | P | 02/24/2020 | 520, 523, 525 RC, Batts, Blown Insulation 518 dead space screw inspection | NATHAN | NATHAN | | BSP | P | 6490453 |
COLORADO STRUCTURES INC | BSP | P | 02/21/2020 | Upper wall Lobby Fire Caulk/ Fire Stop Partial Frame Exterior Walls and to Garage okay to insulate for prerock.
2-4th floor 1st layer drywall at trash chute,
2nd floor furout and FC at drop ceiling 239 okay | NATHAN | NATHAN | | BSP | P | 6489072 |
COLORADO STRUCTURES INC | BSP | P | 02/20/2020 | 320 Drywall Screw
2nd Floor South Fur outs and Drop Ceilings Fire Stop still need 227 and 239 remaining units on 2nd okay 220 | NATHAN | NATHAN | | BSP | P | 6487521 |
COLORADO STRUCTURES INC | BSP | R | 02/19/2020 | 5th Floor Frame and Fire Caulk 513, 537, missing 4 king studs at bedroom windows and straps at top plates, firecaulking missing at penetrations, 536 missing truss clips at bedroom low trusses, straps and firecaulking at penetrations.
4th Floor Drywall Screw 413, 437
Discussed shaft construction for K2B wall type Fire Barrier continuity through floor ceiling and roof ceiling assemblies at trash shaft
| NATHAN | NATHAN | | BSP | R | 6486240 |
COLORADO STRUCTURES INC | BSP | P | 02/18/2020 | 5th Floor Center Corridor Fire Caulk/ Fire Stop, Janitor Closets Chase, UR1 light box shrouds unit 502, 518, 520, 525, 537,
Drywall Screw inspection 535, 420
523 Frame added windows need engineer letter windows on architectural pages,
2nd floor Fan Coil drop frame and Firestop units, 209, 223, 218, 225, 229, 231, 233, 224, 235, 237 | NATHAN | NATHAN | | BSP | P | 6485139 |
COLORADO STRUCTURES INC | BSP | P | 02/12/2020 | 5th Floor North & South Janitor closets EX Fan Shaft 513 UR1 Boxes recessed light protection 504 Kitchen Fur Out 512 Fur out and Combo Unit Drop Ceiling
449- Drywall Screw 425- F/C F/S okay Above ceiling F/S to Telecom okay 4th and 3rd
Batt, Blow, R/C and sheer 320 okay
2nd floor above ceiling bathroom frame and F/S 201-221 EXCEPT for 209, 218, 220 NOT READY
| NATHAN | NATHAN | | BSP | P | 6480741 |
COLORADO STRUCTURES INC | BSP | P | 02/11/2020 | Sheer / Blow/ Batts/ RC ceiling and walls 549, 437, 420, 413
| NATHAN | NATHAN | | BSP | P | 6479077 |
COLORADO STRUCTURES INC | BSP | P | 02/10/2020 | 2nd floor Kitchen fur out walls Frame and Firestop | NATHAN | NATHAN | | BSP | P | 6477717 |
COLORADO STRUCTURES INC | BSP | P | 02/07/2020 | Frame/ Fire Caulk/ Fire Stop 420, 320
Drywall Screw 423, 418
Batt, Blow, RC and Sheer 449 | NATHAN | NATHAN | | BSP | P | 6476708 |
COLORADO STRUCTURES INC | BSP | P | 02/06/2020 | Shear 423, 4 South RTU, 4 North RTU
Drywall Screw 527 not ready
Fire Caulk Bathroom Drops 309, 329, 333, 349 | NATHAN | NATHAN | | BSP | P | 6475854 |
COLORADO STRUCTURES INC | BSP | P | 02/04/2020 | 3rd Floor Bathroom drops 311-349 EXCEPT 327, 329, 333, 349
Drywall Screw 412
5th RTU Shaft Double layer | NATHAN | NATHAN | | BSP | P | 6473514 |
COLORADO STRUCTURES INC | BSP | P | 02/03/2020 | 4th Floor Blow, Batts, RC 423,
F/C-F/S sheer walls only unit 420, 427, 436, 320, 327, 227 | NATHAN | NATHAN | | BSP | P | 6472437 |
COLORADO STRUCTURES INC | BSP | P | 01/31/2020 | 4th-5th north and south shaft wall okay with completed required inspections remaining of 5th to roof deck remaining
4th Floor Frame and Fire Stop 413, 437, need tub trap completed 449 okay
3rd Floor Above Ceiling F/S and Frame301, 302, 303, 304, 305, 306, 307, 308, 310, 309, 312 | NATHAN | NATHAN | | BSP | P | 6471006 |
COLORADO STRUCTURES INC | BFR | P | 01/29/2020 | 525 Frame/firecaulk/ Firestop. secure closest wall main level, repair drywall at stair wall, | NATHAN | NATHAN | | BFR | P | 6467588 |
COLORADO STRUCTURES INC | BSP | P | 01/27/2020 | 5th 502 sheer and dead space firestop, RC Batts Blow and sheer 518, 527, Frame 520 need drywall at both sides of dead air space over other unit for continuity.
4th RC Batts Blow and sheer at 412
3rd Floor Fire Caulk main Corridor no connecting or turn out portions | NATHAN | NATHAN | | BSP | P | 6464690 |
COLORADO STRUCTURES INC | BSP | P | 01/22/2020 | 512 Drywall Screw and above ceiling at bathrooms 5th Floor Truss Repairs 527, 525, 523
520 2nd layer by elevator #3 | NATHAN | NATHAN | | BSP | P | 6460181 |
COLORADO STRUCTURES INC | BSP | P | 01/22/2020 | upload truss fix details unit 527, 525, 523 inspection to follow. | NATHAN | NATHAN | | BSP | P | 6459816 |
COLORADO STRUCTURES INC | BSP | P | 01/21/2020 | 5th floor #502 deadspace-drywall screw ok-remove wood blocks at sprinlker penetrations,need Firecaulking inspection. #504 firecaulking above hardlid at bathroom ok/504,520 drywall screw ok rated walls/4th floor 412-418-423 fireblock and firecaulking top plates and collars on PVC ok/CMU garage area window infills @ 2hour insulation ok/ Dryer Box Exhaust firecaulking ok #102,104,106,108,110 | BERTW | BERTW | | BSP | P | 6458271 |
COLORADO STRUCTURES INC | BSP | P | 01/17/2020 | Level 1 Framing Infills at CMU walls and 2 layers office side need joint detail both sides
Drywall screw entire and above ceiling and FC at bath 515
5th Floor Blow, Batts, RC Reframe items 502, 512
Frame/ Fire Caulk/ Fire Stop 549 straps and corner connections H6 headers | NATHAN | NATHAN | | BSP | P | 6456887 |
COLORADO STRUCTURES INC | BSP | P | 01/15/2020 | 5th Frame Fire Caulk 527
need gusset at 3 ply girder and 2ply C2 post at each end. note 8 on S-106BM 5th Blow, Batts, RC and Sheer 504
| NATHAN | NATHAN | | BSP | P | 6453737 |
COLORADO STRUCTURES INC | BSP | P | 01/14/2020 | 5th
Shear 515, 535
Frame and Fire Caulk 518 need straps at bedroom top plate, firestop top of wall at elevator fur wall, add stud for south wall sheer
5th corridor ceiling except 12' high sections and areas outside stairs 1&2 ,
4th-5th RTU ccore board shaft frame okay with completed required | NATHAN | NATHAN | | BSP | P | 6452264 |
COLORADO STRUCTURES INC | BFR | P | 01/10/2020 | 5th Floor Frame 502 2 straps at bedroom, 512 , 523 R305 truss gusset over stairs, header at bedroom and 2 straps at bedroom top plate
5th Floor Mezzanine F/C F/S 502, 512, 523 | NATHAN | NATHAN | | BFR | P | 6449407 |
COLORADO STRUCTURES INC | BSP | P | 01/09/2020 | 5th Floor Mezzanine Dead Space, insulation and under stair floor gypcrete 502, 523, 518, 525, 520, 527, 536, 549
3rd Floor Kitchen Fur Out Wall F/C F/S 336
2nd Floor Drywall Screw 235, 236 | NATHAN | NATHAN | | BSP | P | 6448031 |
COLORADO STRUCTURES INC | BFR | P | 01/07/2020 | 3rd floor furred out wall and Firecaulk, 347, 349, 334, 332, 343, 330, 328 5th unit 512 truss repair not correct need 3 rows 2" on center. 2nd floor screw inspection janitors closet,
| NATHAN | NATHAN | | BFR | P | 6445407 |
COLORADO STRUCTURES INC | BFR | P | 01/07/2020 | truss repair for R142A uploaded inspection to follow | NATHAN | NATHAN | | BFR | P | 6444886 |
COLORADO STRUCTURES INC | BSP | P | 01/06/2020 | 2nd Floor Drywall Screw
, 249
Batt, Blow and RC at 236
RTU Shaft Liner
3rd and 4th, 2nd layer drywall at 3rd floor, coreboard and shaft construction up to 4th | NATHAN | NATHAN | | BSP | P | 6444109 |
COLORADO STRUCTURES INC | BSP | P | 01/03/2020 | Mezzanine unit Frame
at stairs, landing and sheer at that area. 502, 518, 520, 536 Mezzanine frame over elevator lobby area okay for 520 okay
3rd Floor Kitchen Fur Outs 329, 333, 337, 339, 326 | NATHAN | NATHAN | | BSP | P | 6442757 |
COLORADO STRUCTURES INC | BSP | P | 01/02/2020 | 2nd Floor Drywall Screw
North Elec, South Elec and janitors , units 226, 232, 234, 247 | NATHAN | NATHAN | | BSP | P | 6441773 |
COLORADO STRUCTURES INC | BSP | P | 12/31/2019 | 5th Drywall Screw 534
2nd Drywall screw 241, 228, 230, 243, 245
3rd Floor Kitchen Fur Out Walls 301, 302, 303, 304, 306, 308, 310, 312, 311, 313, 317, 321 | NATHAN | NATHAN | | BSP | P | 6440624 |
COLORADO STRUCTURES INC | BSP | P | 12/30/2019 | 1st floor walk up unit drywall at 4' below podium ceiling screw inspection okay,
2nd floor drywall screw janitor closet north ceiling only and south walls and ceiling, walls and ceiling units 231, 233, 224, 239 | NATHAN | NATHAN | | BSP | P | 6439439 |
COLORADO STRUCTURES INC | BSP | P | 12/26/2019 | 2nd floor screw inspection walls and ceiling 209, 212, 213, 215, 216, 220. 229
2nd floor Blow, Batt, RC and Sheer 226, 228, 230, 243, 232, 245, 234, 247, 249, | NATHAN | NATHAN | | BSP | P | 6436937 |
COLORADO STRUCTURES INC | BSP | P | 12/23/2019 | 5th floor south corridor F/C at line sets
2nd floor Drywall screw inspection walls and ceiling 207, 219, 221, 223, 218, 225
2nd floor Batt, Blow, RC and sheer 224, 235, 237, 239, 241
1st floor Insulation top 4' of west walk up units okay 102 -112 | NATHAN | NATHAN | | BSP | P | 6435373 |
COLORADO STRUCTURES INC | BSP | P | 12/20/2019 | 2nd floor drywall screw 208, 210, 211, 217
2nd floor batt, blow and RC 212, 233 north janitor,electric and pool corridor, south electric, janitors and pool corridor
2nd floor shear 215, 225, 220, 229, 231, 233 | NATHAN | NATHAN | | BSP | P | 6433845 |
COLORADO STRUCTURES INC | BSP | P | 12/19/2019 | 5th floor R142A missing gusset at bottom plate over bath wall 4th Frame 412, 413, 423, 418, 425, 402 need hanger on F143 to 3 ply LVL also nails in HGUS5.5 to triple LVL , 420 need H4 header at combo bedroom exterior wall, post in floors below for 4 plyLVL, | NATHAN | NATHAN | | BSP | P | 6432739 |
COLORADO STRUCTURES INC | BSP | P | 12/18/2019 | 1st floor frame FC/FS bottom of podium down okay for prerock with completed required inspections / address back to back dryer boxes and dryer boxes in rated walls,102,104,106,108, 110, 112, 114 also 2 sleeves in wall to parking garage will be 2 short and end inside unit wall unit 102 upper mezzanine floor | NATHAN | NATHAN | | BSP | P | 6431265 |
COLORADO STRUCTURES INC | BSP | P | 12/17/2019 | 2nd floor drywall screw walls and ceiling 201, 202, 203, 204, 205, 206 north and south mechanical shaft wall 2nd and 3rd Batt ,blow and RC 225, 220, 231
| NATHAN | NATHAN | | BSP | P | 6429781 |
COLORADO STRUCTURES INC | BSP | P | 12/16/2019 | 5th floor fur out walls and FC at kitchens units 517, 539, 526, 528, 530, 543, 547
2nd floor blow batt and RC units 217, 223, 218, 229 | NATHAN | NATHAN | | BSP | P | 6428781 |
COLORADO STRUCTURES INC | BSP | P | 12/13/2019 | 2nd floor blow, batt, RC and sheer 208,210, 209, 211, 213, 219, 221, 216 217 not ready 215 sheer not ready RC,batt and Blow okay | NATHAN | NATHAN | | BSP | P | 6427062 |
COLORADO STRUCTURES INC | BSP | P | 12/12/2019 | 2nd FC/FS, tub drains and Frame Reinspection units 239, 226, 241, 228, 230, 243, 232, 245, 234, 247, 236, 249 with completed required inspections okay | NATHAN | NATHAN | | BSP | P | 6425625 |
COLORADO STRUCTURES INC | BSP | P | 12/11/2019 | 4th floor corridor F/C and FS Provide listing for cable bundle firestop system at Telecom to corridor
2nd floor Sheer, RC and insulation 201, 202, 203, 204, 205, 206, 207, 2nd floor Frame F/C, F/S 225, 220, 229, 231, 233, 224, 235, 237, 2nd floor pool corridors FC/FS | NATHAN | NATHAN | | BSP | P | 6424074 |
COLORADO STRUCTURES INC | BSP | P | 12/10/2019 | 5th floor above ceiling FC/FS and drop frame 501, 503, 505, 509, 516, 529, 539, 541, 543
3rd floor drywall screw walls and ceiling 337
2nd floor north janitor closet FC at wall plates, okay to install RC at north electric room 2nd 215 frame corrected | NATHAN | NATHAN | | BSP | P | 6422841 |
COLORADO STRUCTURES INC | BSP | P | 12/09/2019 | open excavation, compaction, footer and foundation needed,
5th floor 501 drywall screw okay, discussed 502 dryer vent through interior non bearing wall top plate.
4th floor above ceiling 441 and North wing corrected
2nd floor FC/FS and tub chase NOT READY 215, 225, 220, 227. 229 and remaining east and south units FC/FS and tub chase including frame items okay at 213, 217, 219, 216, 221, 223, 218 | NATHAN | NATHAN | | BSP | P | 6420721 |
COLORADO STRUCTURES INC | BFR | P | 12/06/2019 | 2nd floor frame south end okay with completed required inspections | NATHAN | NATHAN | | BFR | P | 6419340 |
COLORADO STRUCTURES INC | BSP | P | 12/06/2019 | 5th floor above ceiling frame and firecaulking in bathrooms need repairs or not ready 501,503, 512, 513, 515, 516, 523, 518, 525, 520, 527, 529, 535, 537, 539, 534, 536, 549. 509 and 541 fan coil and frame only need light and frame over 2nd bathroom
| NATHAN | NATHAN | | BSP | P | 6419325 |
COLORADO STRUCTURES INC | BSP | P | 12/05/2019 | 5th floor 501, 1st layer drywall at roof/ceiling
4th above ceiling and FC at bathrooms match line south east and south wings EXCEPT 420,427, 437, 441, 446, 449, drywall attachment at janitor north and south walls and ceiling
3rd floor drywall attachment walls and ceiling, 313,315, janitor and electric rooms north and south,Telecom okay
| NATHAN | NATHAN | | BSP | P | 6418014 |
COLORADO STRUCTURES INC | BFR | P | 12/05/2019 | 2nd floor east frame units 213 need strap at HD and 2nd layer H6 header, 219 need strap, 221 add stud bearing wall, 216,218,220,227 need bottom plates pinned, 231 need strap at top plate over sliding door,
2nd floor frame north side frame items corrected | NATHAN | NATHAN | | BFR | P | 6417979 |
COLORADO STRUCTURES INC | BSP | P | 12/04/2019 | 4th above ceiling north end bathroom frame and FC EXCEPT 412, 402, 413, 423, 418, 425
3rd floor blow,batt and RC 337, north and south electric rooms
3rd drywall attachment walls and ceiling 347, 336. | NATHAN | NATHAN | | BSP | P | 6416095 |
COLORADO STRUCTURES INC | BFR | P | 12/04/2019 | 2nd floor north wing frame shot pins and strap 201, pins at 204, 206, 208, 210, 212, 213 not inspected 2nd floor north FC/FS north except 208, 211, 213 | NATHAN | NATHAN | | BFR | P | 6416083 |
COLORADO STRUCTURES INC | BSP | P | 12/03/2019 | discussed type B kitchen flooring at sink cabinet not being required under sink cabinet and 2nd floor frame inspection being required.
5th kitchen wall fur out address 4" pipes at unit 511, 539 , remaining units 503, 506, 508, 510, 521, 516, 529, 533, 524, with completed inspoection frame and FC okay | NATHAN | NATHAN | | BSP | P | 6414314 |
COLORADO STRUCTURES INC | BSP | P | 12/02/2019 | 3rd RC and insulation 313, 315, 336, 347 and janitor closet south
3rd drywall attachment 328, 332, 334, 349
4th kitchen fur out wall and FC 426, 428, 430, 443, 432, 434, 447. RC at north and south janitor closet | NATHAN | NATHAN | | BSP | P | 6412912 |
COLORADO STRUCTURES INC | BSP | P | 11/27/2019 | 3rd floor firecaulk/firestop telecom, and janitors closets, drywall attachment wall and ceiling 328, 243, 345, 3rd floor sheer units 347,336,
5th floor corridor separation wall FC/FS for unit stair wall 502, 518, 520, 536 | NATHAN | NATHAN | | BSP | P | 6411181 |
COLORADO STRUCTURES INC | BSP | P | 11/25/2019 | 3rd drywall attachment ceiling and walls units 302, 329, 333, 339, 341, 330 ,
5th unit 502 R42 B2 truss reinforcement | NATHAN | NATHAN | | BSP | P | 6409700 |
COLORADO STRUCTURES INC | BSP | P | 11/22/2019 | 3rd floor screw inspection walls and ceilings, units 301,325,331,324,335,326
3rd floor Firecaulk and Firestop units 337,347 | NATHAN | NATHAN | | BSP | P | 6408609 |
COLORADO STRUCTURES INC | BSP | P | 11/20/2019 | 3rd drywall screw walls and ceiling 317,319,316,323,318
3rd blow,batt,RC 341,328,330,343,332,345,334,329,349,
3rd second sided sheer 302,315,325,329,333,339,341,343,334 all above okay with completed required inspections | NATHAN | NATHAN | | BSP | P | 6406264 |
COLORADO STRUCTURES INC | BSP | P | 11/19/2019 | 3rd floor firestop and hold down at 336 3rd blow, batts and RC okay | NATHAN | NATHAN | | BSP | P | 6403641 |
COLORADO STRUCTURES INC | BSP | P | 11/18/2019 | 3rd Drywall Screw 317 OK //
RC, Blow, Batts 501, 331, 333, 324, South Elec. 335, 339, 326 OK // 1st Floor Drywall Screw 101, 116, 118, 120, 122 OK | JEREMYA | JEREMYA | | BSP | P | 6402702 |
COLORADO STRUCTURES INC | BIN | P | 11/15/2019 | walls 318,325 insulation at exterior walls and garage only above ceiling units 116,118,120,122 and all exterior wall at 101 | NATHAN | NATHAN | | BIN | P | 6400786 |
COLORADO STRUCTURES INC | BSP | P | 11/15/2019 | 3rd floor drywall screw at walls and ceiling 303,304,305,306,307,308,310,309,312,311,314 blow, batt insulation and RC at 318,325 | NATHAN | NATHAN | | BSP | P | 6400775 |
COLORADO STRUCTURES INC | BSP | P | 11/14/2019 | 3rd Floor Fire Stop 341, 328, 330, 343, 332, 345, 334, 347,349 OK //
2nd Floor Tub Shear 220, 239, 243, 247 OK //
3rd & 4th Floor Corridor Fire Stop OK | JEREMYA | JEREMYA | | BSP | P | 6398606 |
COLORADO STRUCTURES INC | BSP | P | 11/13/2019 | 3rd Floor 2nd Side Shear
317, 319, 321 OK //
1st Floor Units Fire Caulk OK // Ok to Insulate
122, 120, 118, 116 OK to insulate | JEREMYA | JEREMYA | | BSP | P | 6397041 |
COLORADO STRUCTURES INC | BSP | P | 11/12/2019 | 3rd Floor Fire Caulk/ Fire Stop
301, 302, 313, 335, 326 OK //
3rd Floor Blow/ Batt/ RC
312, 311, 314, 317, 319, 321, 316 OK | JEREMYA | JEREMYA | | BSP | P | 6395502 |
COLORADO STRUCTURES INC | BSP | P | 11/08/2019 | 3rd floor south frame units okay except 336 missing courtyard side HD2 strap 3rd floor FC,FS units 329,331,333,324,335,339 okay 3rd floor 2nd side sheer 305,307,309,311 | NATHAN | NATHAN | | BSP | P | 6393152 |
COLORADO STRUCTURES INC | BSP | P | 11/06/2019 | 5th floor screw wall and ceilings okay, 3rd floor insulation/ and ceiling R/C units 308,310,309 and FS/FC at 315 okay | NATHAN | NATHAN | | BSP | P | 6390107 |
COLORADO STRUCTURES INC | BSP | P | 11/05/2019 | 5th Floor Unit Screw 533, 528, 530, 543, 545, 547 3rd Floor RC, Batts, Blow 303, 304, 305, 306 2nd Floor Corridor Drywall Screw 2nd Layer OK | JEREMYA | JEREMYA | | BSP | P | 6389402 |
COLORADO STRUCTURES INC | BSP | P | 11/01/2019 | 2nd floor corridor 1st layer drywall 3rd floor F/C and F/S at units 317,319,323,318 okay, units 321 collar at 4", 316 low volt hole, 325 collars at 4"x2 and low volt | NATHAN | NATHAN | | BSP | P | 6385693 |
COLORADO STRUCTURES INC | BSP | P | 10/31/2019 | 2-5 janitor closet FC,FS okay, 3rd telecom room FC,FS okay | NATHAN | NATHAN | | BSP | P | 6384903 |
COLORADO STRUCTURES INC | BSP | P | 10/30/2019 | 3rd floor north except 313, F/C, FS frame okay,
4th kitchen fur out wall frame and F/C units 402,404,406,408,410,411,417,421,429,431,424,439 okay with completed inspections | NATHAN | NATHAN | | BSP | P | 6384076 |
COLORADO STRUCTURES INC | BSP | P | 10/29/2019 | trash shaft walls sides and back okay 1-5, 5th drywall screw at ceiling and walls 531,524,539,526 | NATHAN | NATHAN | | BSP | P | 6382880 |
COLORADO STRUCTURES INC | BSP | P | 10/23/2019 | 2nd floor prerock at tub chase walls units 217,219,216,221,223,218, 225,227,229,2231,233,237,239,226,241 units 224 and 235 not ready. | NATHAN | NATHAN | | BSP | P | 6377850 |
COLORADO STRUCTURES INC | BSP | P | 10/22/2019 | 5th floor ceiling and wall drywall inspection units unit 517 not ready, 503,505,506,507,508,510,509,511,519,521,519,521,516,529,531 okay | NATHAN | NATHAN | | BSP | P | 6376216 |
COLORADO STRUCTURES INC | BSP | P | 10/18/2019 | 5th floor second side sheer nailing units 503,531,533,541,543,545,547, okay RTU 1 and 2 shaft inside openings okay with completed mechanical inspections 2nd floor north 4" pipe at tub wall review | NATHAN | NATHAN | | BSP | P | 6373324 |
COLORADO STRUCTURES INC | BSP | P | 10/16/2019 | 5th floor blow,batts and RC 515,517,533,535,539,528,530,543,532,545,534,547 okay. | NATHAN | NATHAN | | BSP | P | 6370199 |
COLORADO STRUCTURES INC | BSP | P | 10/15/2019 | 5th Floor Blow, Batts, RC 506, 508, 510, 519, 521, 516, 529, 531, 524, 526, 541
2nd Floor North Tub Chases | JEREMYA | JEREMYA | | BSP | P | 6368163 |
COLORADO STRUCTURES INC | BSP | P | 10/11/2019 | trash chute joint detail 2-5 and 2nd layer drywall okay unit 503 exterior wall for sheer not ready insulation okay | NATHAN | NATHAN | | BSP | P | 6365816 |
COLORADO STRUCTURES INC | BSP | P | 10/09/2019 | 5th floor insulation ceiling RC okay 5th floor F/C 545,547 completed 5th floor draftstop at unit wall 534 okay | NATHAN | NATHAN | | BSP | P | 6363242 |
COLORADO STRUCTURES INC | BSP | P | 10/08/2019 | 5th floor 2nd side sheer nailing units 505,507,509,511,517 okay | NATHAN | NATHAN | | BSP | P | 6361235 |
COLORADO STRUCTURES INC | BSP | P | 10/07/2019 | Trash chute at East side of building OK at 2nd floor | JEREMYA | JEREMYA | | BSP | P | 6360686 |
COLORADO STRUCTURES INC | BSP | P | 10/04/2019 | 5th floor fire collars corrected units 515,521,529,535
5th floor F/C draftstop and back to back boxes all okay units 538,526,541,528,530,532 | NATHAN | NATHAN | | BSP | P | 6358235 |
COLORADO STRUCTURES INC | BSP | P | 10/02/2019 | 2nd floor(3rd) corridor floor frame and firecaulk okay | NATHAN | NATHAN | | BSP | P | 6355184 |
COLORADO STRUCTURES INC | BSP | P | 09/30/2019 | 5th floor units 502,512,514,513 units not ready remaining north wing okay,
5th floor F/C and Draftstops east wing except mezzanine units and collars in 515, 521x2, 529x2, 535x3
4th floor screw walls and ceiling 429,431,433,424,435,434 | NATHAN | NATHAN | | BSP | P | 6351977 |
COLORADO STRUCTURES INC | BSP | P | 09/26/2019 | 4th floor drywall attachment at walls and ceiling 419,421,416,445,447 / 4th floor batt, blow and RC channel electric rooms and 434 okay / 5th floor units 501,503,504, FC and draftstops okay, 505, 510 draftstop and pipes not FC, 506,507,508,509,511 need draftstops at wall plates, FC okay | NATHAN | NATHAN | | BSP | P | 6348651 |
COLORADO STRUCTURES INC | BSP | P | 09/25/2019 | 2nd side sheer inspection units 434,447,445, and tub trap FC and drywall unit 512 okay | NATHAN | NATHAN | | BSP | P | 6347240 |
COLORADO STRUCTURES INC | BSP | P | 09/25/2019 | 423 Fire Tape/ Mud behind dryer vent/ washer box OK //
4th Floor Fire Caulking at fancoil brackets 403, 404, 405, 406, 407, 408, 410, 409, 411, 415 & 417 OK | JEREMYA | JEREMYA | | BSP | P | 6346658 |
COLORADO STRUCTURES INC | BSP | P | 09/24/2019 | 4th Floor Unit Screw 439, 426, 441, 428, 430, 443, 432 OK //
3rd Floor North & South Elec Fire Caulking OK | JEREMYA | JEREMYA | | BSP | P | 6345128 |
COLORADO STRUCTURES INC | BSP | P | 09/23/2019 | 4th Floor Drywall Screw/ Kitchen Fur Out Wall OK // 403F, 404F, 411, 415, 417
3rd Floor Insulation on Exterior Walls OK //
Misc. Fire Caulking OK | JEREMYA | JEREMYA | | BSP | P | 6343628 |
COLORADO STRUCTURES INC | BSP | P | 09/19/2019 | 4th floor blow in lids, batt in exterior walls and RC for lids OK for units 439, 441, 430, 443, 432 and 447 | NICK | NICK | | BSP | P | 6340815 |
COLORADO STRUCTURES INC | BSP | P | 09/19/2019 | 4th Floor Blow, Batt, RC OK | JEREMYA | JEREMYA | | BSP | P | 6340342 |
COLORADO STRUCTURES INC | BSP | P | 09/17/2019 | 3rd Floor 2nd Layer Screw OK // Corridor
4th Floor Unit Screw OK //
4th Floor Batts, Blow, RC OK | JEREMYA | JEREMYA | | BSP | P | 6338542 |
COLORADO STRUCTURES INC | BSP | P | 09/17/2019 | Level 4 unit blown and batt insulation OK // level 4 unit RC OK // level 3 corridor drywall (2nd layer) OK | JEREMYA | JEREMYA | | BSP | P | 6338540 |
COLORADO STRUCTURES INC | BSP | P | 09/16/2019 | 4th Blow/ Batt, & RC OK // 409, 411, 415, 417, 419, 421, 416
4th Floor Batts on Shear walls
OK // 3rd Floor Corridor 1st layer east
3rd tub chase insulation OK | JEREMYA | JEREMYA | | BSP | P | 6335565 |
COLORADO STRUCTURES INC | BSP | P | 09/16/2019 | 4th Floor Blow/ Batt insulation, RC OK // 409, 411, 415, 417, 419, 421, 416
4th Floor Party wall Insulation OK //
3rd Floor Tub chase insulation OK | JEREMYA | JEREMYA | | BSP | P | 6335564 |
COLORADO STRUCTURES INC | BSP | P | 09/12/2019 | RC/ Insulation 410, 409, 411
Frame OK // Fire Caulk 401, 426, 434, 445, 443, 441, 426 OK | JEREMYA | JEREMYA | | BSP | P | 6332575 |
COLORADO STRUCTURES INC | BSP | P | 09/11/2019 | 4th Floor: Contractor to fix a few line set penetrations, has list of units // Fire caulk OK throughout the remaining units // Tub traps OK throughout // Insulation and RC at North wing, center units OK at ceilings | JEREMYA | JEREMYA | | BSP | P | 6330726 |
COLORADO STRUCTURES INC | BSP | P | 09/06/2019 | 3rd floor corridor fire caulking OK // 4th floor telcom drywall screw OK // 4th floor south electrical room fire caulking OK | JEREMYA | JEREMYA | | BSP | P | 6326044 |
COLORADO STRUCTURES INC | BSP | P | 09/05/2019 | 3rd floor dead air chases fire caulked at floor and cleared out for gypcrete poured floor topping, discussed RC spacing and overlap at 4th floor ceiling for L574 . | NATHAN | NATHAN | | BSP | P | 6324953 |
COLORADO STRUCTURES INC | BSP | P | 08/30/2019 | 4th floor frame, firecaulking and firestops units 425,429,431,433,435,421,419,417,415,416,410 / tub drain fire stop for units 515,517,519,521,529,531,533,535,510,504,503,508,509 . | NATHAN | NATHAN | | BSP | P | 6320568 |
COLORADO STRUCTURES INC | BIN | P | 08/29/2019 | 4th floor east units not ready,need collars and firestops completed, unit 418 backing installed for swing down grab bar, units 501,505,506 tub drain firestop completed. | NATHAN | NATHAN | | BIN | P | 6318724 |
COLORADO STRUCTURES INC | BSP | P | 08/28/2019 | inspection was meant to be called for the 29th inspector has edited the request date | NATHAN | NATHAN | | BSP | P | 6317100 |
COLORADO STRUCTURES INC | BFR | P | 08/26/2019 | UNITS 301-337, Headers, kings, trimmers, point loads and floor trusses OK. Will still need to do pre-rock, fire penetrations and frame in all units once ready. | JEREMYA | JEREMYA | | BFR | P | 6314399 |
COLORADO STRUCTURES INC | BFR | P | 08/23/2019 | frame inspections on units 415, 416,417,419,421 OK to insulate | JEREMYA | JEREMYA | | BFR | P | 6312215 |
COLORADO STRUCTURES INC | BFR | P | 08/20/2019 | 5th floor corridor drywall screw OK // frame units 403,405,407,409,411, re-inspect 402 OK to insulate | JEREMYA | JEREMYA | | BFR | P | 6307987 |
COLORADO STRUCTURES INC | BFR | P | 08/19/2019 | frame inspect units 401,404,406,408,410 OK // Need to seal pipes in 402 // Insulation at 5th floor corridor, east wing OK at exterior exposed walls | JEREMYA | JEREMYA | | BFR | P | 6305821 |
COLORADO STRUCTURES INC | BSP | P | 08/19/2019 | Pre-rock at tub chases OK on 4th floor, north wing | JEREMYA | JEREMYA | | BSP | P | 6304990 |
COLORADO STRUCTURES INC | BSP | P | 08/13/2019 | still need backing swing up grab bar 418, 4th floor prerock at tub chases screw spacing per U341 units 404.405,406,408,410 / items corrected units 403,417,429,433,447. | NATHAN | NATHAN | | BSP | P | 6298374 |
COLORADO STRUCTURES INC | BFR | P | 08/12/2019 | 4th floor sheer, holddowns straps, backing and frame at tub/shower walls unit 403 missing strap at plate break, 417 nail off sheer correctly at tub chase, 418 backing at wall for swing down grab bar, 429,433 nail off sheer at tub chase, 447 need holddown strap nailed. | NATHAN | NATHAN | | BFR | P | 6296797 |
COLORADO STRUCTURES INC | BFR | P | 08/07/2019 | truss repairs at 02 and 36 stack per uploaded details okay | NATHAN | NATHAN | | BFR | P | 6292301 |
COLORADO STRUCTURES INC | BSP | P | 08/07/2019 | unit 525 per U305 drywall at stairs only to ceiling okay, insulation at tub wall unit 518 per U341, drywall screw inspection at 2nd and 3rd stair core 3rd layer per P533 okay | NATHAN | NATHAN | | BSP | P | 6292297 |
COLORADO STRUCTURES INC | BFR | P | 08/07/2019 | truss repair details for 02 and 36 stack attached. | NATHAN | NATHAN | | BFR | P | 6291339 |
COLORADO STRUCTURES INC | BSP | P | 08/05/2019 | 3rd and 2nd stair shaft high ceiling double layer drywall and RC okay. | NATHAN | NATHAN | | BSP | P | 6288519 |
COLORADO STRUCTURES INC | BSP | P | 08/02/2019 | 5th floor prerock at stair landing ledgers per U305 and 341 depending on wall, RC attachment and drywall attachment okay units 520,523.525,527,549. / discussed accessibility requirements for mezzanine units and Type B also stand pipes and corrections to be made. | NATHAN | NATHAN | | BSP | P | 6286532 |
COLORADO STRUCTURES INC | BIN | P | 08/02/2019 | 5th floor stair 2 and 3 high roof insulation okay with completed required inspections, | NATHAN | NATHAN | | BIN | P | 6286519 |
COLORADO STRUCTURES INC | BSP | P | 07/31/2019 | 4th floor corridor alcove RC attachment at walls per U305, 2nd - 4th floor unit wall separation to trash chute okay . | NATHAN | NATHAN | | BSP | P | 6283120 |
COLORADO STRUCTURES INC | BSP | P | 07/26/2019 | 2nd and 3rd floor trash room ceiling RC and 4th floor trash, telecom ceiling RC and 5th floor stair 2 lower roof ceiling drywall okay with completed required inspections. need minimum 44" clear at landing in exit enclosure landings to protruding objects or stand pipes. | NATHAN | NATHAN | | BSP | P | 6278459 |
COLORADO STRUCTURES INC | BSP | P | 07/24/2019 | drywall at 2nd stair core low roof and elevator 3rd layer with joint detail firecaulking okay / 4th floor telecom and trash room frame and firecaulking, 3rd and 2nd floor trash room frame and firecaulking with completed required inspections okay. | NATHAN | NATHAN | | BSP | P | 6275605 |
COLORADO STRUCTURES INC | BSP | P | 07/22/2019 | 2nd layer drywall and RC at top of elevator 2 / frame at low roof stair 2 roof, 4th floor corridor drywall screw per U305 okay EXCEPT ENTRY ALCOVES. | NATHAN | NATHAN | | BSP | P | 6272132 |
COLORADO STRUCTURES INC | BIN | P | 07/22/2019 | low roof stair tower 2 R-38 okay | NATHAN | NATHAN | | BIN | P | 6272102 |
COLORADO STRUCTURES INC | BSP | P | 07/19/2019 | 5th floor south RC at corridors okay 1st layer drywall at elevator 2 ceiling okay. | NATHAN | NATHAN | | BSP | P | 6269657 |
COLORADO STRUCTURES INC | BSP | P | 07/16/2019 | 5th floor trash room screw and fire tape, ceiling not on plans removed, elevator 3, 3 rd layer drywall installed. | NATHAN | NATHAN | | BSP | P | 6264894 |
COLORADO STRUCTURES INC | BSP | P | 07/15/2019 | 5th floor corridor high ceiling attachment per P533 okay and ceiling RC and drywall at 3 elevator core | NATHAN | NATHAN | | BSP | P | 6263656 |
COLORADO STRUCTURES INC | BSP | P | 07/12/2019 | Drywall screw at 4th floor corridor OK | JEREMYA | JEREMYA | | BSP | P | 6262184 |
COLORADO STRUCTURES INC | BIN | P | 07/12/2019 | Insulation at 5th floor Telecom room OK | JEREMYA | JEREMYA | | BIN | P | 6262183 |
COLORADO STRUCTURES INC | BSP | P | 07/12/2019 | 4th floor corridor drywall OK // second layer screw inspection. 5th floor OK // F/C drywall screw OK | JEREMYA | JEREMYA | | BSP | P | 6261076 |
COLORADO STRUCTURES INC | BSP | P | 07/10/2019 | Discussed rated assemblies at 5th floor mezz units. What is built does not meet the approved plans. Drawings will need to be revised or walls will need to be re-built | JEREMYA | JEREMYA | | BSP | P | 6258822 |
COLORADO STRUCTURES INC | BSP | P | 07/10/2019 | 4th floor corridor drywall screw first layer OK // Pre Rock / fire tape 5th floor OK | JEREMYA | JEREMYA | | BSP | P | 6258086 |
COLORADO STRUCTURES INC | BSP | P | 07/10/2019 | All remaining fan coil OK // RC except mezzanine units 5th OK // Stair 1 F/C at ceiling OK // Exterior sheer screw at unit 101 OK // Ceiling drywall at trash room 5th OK | JEREMYA | JEREMYA | | BSP | P | 6258085 |
COLORADO STRUCTURES INC | BSP | P | 07/03/2019 | discussed draftstops at unit walls per plans full NFPA 13 sprinkler is being installed, drywall attachment floor/ceiling assembly P545 at 5th floor unit bathrooms 515,517,519,516,521,529,531 MEZZ UNITS not included. | NATHAN | NATHAN | | BSP | P | 6252862 |
COLORADO STRUCTURES INC | BSP | P | 07/02/2019 | drywall attachment at Telcom room 589 and ceiling RC and firecaulk at electric room 582 corridor wall / drywall attachment per listing P545 at bathroom ceiling and unit separation wall per U341 at 504,506,508,510,512 / NW elevator and stair core ceiling drywall attachment okay per P545, RC attachment and spacing in bathrooms ceiling 533,524,535,531,526,528,530,532,534 okay with completed required inspections / 4th floor corridor in ceiling penetrations at east and south wings okay with completed required inspections, room 470 electric penetrations at corridor wall firecualked. | NATHAN | NATHAN | | BSP | P | 6251581 |
COLORADO STRUCTURES INC | BSP | P | 07/01/2019 | discussed Draftstops per section 717.3 for floor concealed spaces, RC at top of stair/elevator core per UL P533 | NATHAN | NATHAN | | BSP | P | 6249856 |
COLORADO STRUCTURES INC | BSP | T | 06/28/2019 | PAID (REC#1610571): 5th floor firecaulking in walls of communication and trash room okay, rim at room side drywall prerock at ledger okay, 4th floor corridor ceiling/wall penetrations okay | NATHAN | NATHAN | | BSP | T | 6248398 |
COLORADO STRUCTURES INC | BFR | P | 06/27/2019 | stair/elevator 2 roof frame and connections / 5th floor trash room side walls and com room ceiling and walls fire partition need rim or rated ceiling east side / discussed 4th floor truss repairs. | NATHAN | NATHAN | | BFR | P | 6246609 |
COLORADO STRUCTURES INC | BSP | P | 06/27/2019 | Floor trusses at 5th floor, south wing OK // Fan coil RC OK at north and northeat wings OK at all units on 5th floor | JEREMYA | JEREMYA | | BSP | P | 6245952 |
COLORADO STRUCTURES INC | BSP | P | 06/26/2019 | RC at corridor lids, 5th floor, north corridor and northeast corridor OK // RC at rooms 504, 506, 508, 512, 516, 519, 521 and 529 OK at air handler units | JEREMYA | JEREMYA | | BSP | P | 6244069 |
COLORADO STRUCTURES INC | BFR | P | 06/24/2019 | Framing corrections from previous inspection corrected (LVL's, Headers, etc.) // Insulation at stair 1 OK // Framing at stair lid 2 OK | JEREMYA | JEREMYA | | BFR | P | 6240843 |
COLORADO STRUCTURES INC | BFR | P | 06/14/2019 | 4th floor headers, kings and trimmers, west exterior wall headers need 2nd ply added, east headers at concentric vents 2-9 1/2" LVL needed, clarify non bearing header call out inside units, Bolt LVL 4 play at unit 420 | NATHAN | NATHAN | | BFR | P | 6231896 |
COLORADO STRUCTURES INC | BFR | P | 06/12/2019 | NW roof deck 4 ply LVL missing bolting per detail, == remaining soffit and roof cantilever okay at north side and east sides only, roof and ceiling UL needed for stair/elevator tower 2 and 3 ceiling or fire barrier continuous to bottom of roof deck, previous comment per header detail on top of walls per pages S-501,502,S-600,601 roof framing/trusses and attachment at stair/elevator enclosure 1 and 2 okay. | NATHAN | NATHAN | | BFR | P | 6229013 |
COLORADO STRUCTURES INC | BIN | P | 06/11/2019 | Insulation at tub chases on 5th floor, center wing OK | JEREMYA | JEREMYA | | BIN | P | 6226713 |
COLORADO STRUCTURES INC | BFR | P | 06/10/2019 | Truss repairs on file | JEREMYA | JEREMYA | | BFR | P | 6225060 |
COLORADO STRUCTURES INC | BSP | P | 06/05/2019 | Level 5, center wing, tub pre-rock OK at all units | JEREMYA | JEREMYA | | BSP | P | 6221272 |
COLORADO STRUCTURES INC | BFR | P | 05/24/2019 | Floor trusses at 4th floor, center wing: WIll need all truss repairs uploaded // Need to install FHA straps where plumbing pipe holes have removed too much of the top plate // Will need the design change for the units with the deck framing above // Prior to cover, ensure ALL DAMPER FRAMING HAS BEEN OBSERVED BY A MECHANICAL INSPECTOR | JEREMYA | JEREMYA | | BFR | P | 6209387 |
COLORADO STRUCTURES INC | BFR | P | 05/22/2019 | 4th floor posts, headers, trimmers and king studs at north wing units 401-413, EXCEPT UNIT 402. UNIT 413 ADD CLARIFICATION OF SPECIAL HEADER H6 TO CORRECT FLOOR | NATHAN | NATHAN | | BFR | P | 6207520 |
COLORADO STRUCTURES INC | BFR | P | 05/21/2019 | Roof trusses at east and south wings, low roof units OK // Headers, kings and trimmers OK in 5th floor, low roof units on east and south wings | JEREMYA | JEREMYA | | BFR | P | 6205485 |
COLORADO STRUCTURES INC | BFR | P | 05/16/2019 | Roof trusses at 5th floor, north wing, low ceilings and corridor OK | JEREMYA | JEREMYA | | BFR | P | 6200724 |
COLORADO STRUCTURES INC | BFR | P | 05/14/2019 | interior shear north 3rd & 5th floor OK at all areas // 5th floor corridor hardware & joists OK // 5th floor north headers, king studs and trimmers OK // drywall trans. room OK for first layer | JEREMYA | JEREMYA | | BFR | P | 6199258 |
COLORADO STRUCTURES INC | BIN | P | 05/02/2019 | north wall insulation okay at transformer room. | NATHAN | NATHAN | | BIN | P | 6185360 |
COLORADO STRUCTURES INC | BSP | P | 05/02/2019 | lower pump/riser room 2nd layer interior attachment of drywall and 1st layer exterior per V489 okay will need joint detail completed top and wall, stuff and spray head of wall detail at transformer and electric room has been completed in electric and transfer room northwest corner. please provide head of wall and joint details for rated assemblies. | NATHAN | NATHAN | | BSP | P | 6185356 |
COLORADO STRUCTURES INC | BSP | P | 04/30/2019 | 4th FLOOR: Corridor lid framing OK // Interior shear OK // Interior strapping OK | JEREMYA | JEREMYA | | BSP | P | 6182129 |
COLORADO STRUCTURES INC | BFR | P | 04/24/2019 | Corridor lid framing and hardware OK at 2nd floor corridor // Interior shear and hold down straps OK at 3rd floor, south and west wings. | JEREMYA | JEREMYA | | BFR | P | 6177344 |
COLORADO STRUCTURES INC | BSP | P | 04/22/2019 | Insulation at water entry room OK // Fire tape at electrical rooms OK | JEREMYA | JEREMYA | | BSP | P | 6173000 |
COLORADO STRUCTURES INC | BSP | P | 04/19/2019 | Water entry room framing OK pending splice changing from CMU to steel stud // First layer of drywall at interior of water entry room OK // Interior shear, 3d floor, north wing OK // Hold down strapping 3rd floor, north wing OK // 5th floor, west wing, exterior shear at Mezz OK | JEREMYA | JEREMYA | | BSP | P | 6171115 |
COLORADO STRUCTURES INC | BSP | P | 04/16/2019 | Exterior shear at North wall, 5th floor OK // Exterior shear at west wing, courtyard from 2-5 OK | JEREMYA | JEREMYA | | BSP | P | 6167346 |
COLORADO STRUCTURES INC | BSP | P | 04/15/2019 | OK to one side interior electric rooms | JEREMYA | JEREMYA | | BSP | P | 6165153 |
COLORADO STRUCTURES INC | BSP | P | 04/08/2019 | main floor west exterior steel stud wall and headers from grid line 1-2.5 at J.5 line okay too cover exterior side, started sheer walk at 3rd floor north missing straps and hold downs per plan, discussed over drilled and notched studs at bearing walls. per details S-060 and plan page S-104A | NATHAN | NATHAN | | BSP | P | 6158844 |
COLORADO STRUCTURES INC | BSP | P | 04/02/2019 | EDIT 5th floor south wing west sheer at exterior not completed, south wing west and north exterior sheer wall nailing per S-060 detail 2. | NATHAN | NATHAN | | BSP | P | 6152216 |
COLORADO STRUCTURES INC | BSP | P | 03/27/2019 | Exterior shear at south and east wings OK // Hold downs at east and south wings OK | JEREMYA | JEREMYA | | BSP | P | 6146800 |
COLORADO STRUCTURES INC | BSP | P | 03/22/2019 | Exterior shear on floors 2-5 OK at west and north walls of north wing // Interior hold downs and shear OK at east wing from north end to center. Still need to see from center to south end | JEREMYA | JEREMYA | | BSP | P | 6141793 |
COLORADO STRUCTURES INC | BSP | P | 03/21/2019 | Interior shear and hold downs at north wing, 2nd floor OK | JEREMYA | JEREMYA | | BSP | P | 6139809 |
COLORADO STRUCTURES INC | BFR | P | 03/21/2019 | Exterior shear at north wing, courtyard, floors 4-5 OK | JEREMYA | JEREMYA | | BFR | P | 6139799 |
COLORADO STRUCTURES INC | BSP | P | 03/21/2019 | Exterior shear at courtyard, north walls, 2nd and 3rd floors OK | JEREMYA | JEREMYA | | BSP | P | 6139211 |
COLORADO STRUCTURES INC | BFR | P | 03/20/2019 | Exterior heavy gage framing at exterior wall along L line OK // Box headers and king studs pre-insulated // Fire safing at T.O.W. OK at 2 line from K to F and E to C // Fire safing OK on C line from 2.7 to 8 // Fire safing OK on K line from 2.7 to 5 | JEREMYA | JEREMYA | | BFR | P | 6137652 |
COLORADO STRUCTURES INC | BSP | P | 02/01/2019 | met with Aaron CSI walked insulation at headers exterior wall ground level, and head of wall at CMU stuff and spray to bottom of 2nd floor embedded pipe at unit 101 in CMU wall needs addressed. discussed continuity of CMU fire barrier south east stair exit passage way through floor. | NATHAN | NATHAN | | BSP | P | 6095341 |
COLORADO STRUCTURES INC | BSP | P | 12/19/2018 | Met on site with supt. Aaron Lavy. Discussed pipe penetrations at podium // Also observed Hilti sleeves through the concrete floor at all locations for penetrating items. | JEREMYA | JEREMYA | | BSP | P | 6056461 |
COLORADO STRUCTURES INC | BSP | P | 12/06/2018 | Site visit to check progress and status. Framing should begin within the next 10 days. Discussed unit sep wall listings. Also discussed accessible items in type A and B units. | JEREMYA | JEREMYA | | BSP | P | 6045181 |
COLORADO STRUCTURES INC | BSP | P | 09/19/2018 | Site visit to determine project schedule. Full permit issue is anticipated within the next couple days. Once that has been established, GC has requested pre-con meeting to follow. | JEREMYA | JEREMYA | | BSP | P | 5970294 |
COLORADO STRUCTURES INC | B16 | P | 08/08/2018 | Upgraded permit to allow Superstructure through 121'-6" only. The horizontal building separation occurs at the floor of Level 2, which is at 121'-6" based on elevation drawings. | JAY | JAY | | B16 | P | 5927864 |
COLORADO STRUCTURES INC | B16 | P | 08/08/2018 | Spoke to Aaron on phone about getting with plan reviewer Dan to look at possible super structure permit. | BERTW | BERTW | | B16 | P | 5927385 |
COLORADO STRUCTURES INC | BSP | P | 08/06/2018 | Site visit to see progress. Met with Project Manager, discussed limitations of "Foundation Only" permit. | JEREMYA | JEREMYA | | BSP | P | 5924175 |
COLORADO STRUCTURES INC | BSP | P | 05/04/2018 | Met on-site with GC. Discussed project progress. Also discussed pre-con meeting to come. Will have date options provided by end of the day. | JEREMYA | JEREMYA | | BSP | P | 5836230 |
COLORADO STRUCTURES INC | BBB | P | 03/08/2018 | Ok to use engineer to do inspections | BERTW | BERTW | | BBB | P | 5784178 |
COLORADO STRUCTURES INC | BFN | P | 03/08/2018 | Ok to use engineer to do inspections | BERTW | BERTW | | BFN | P | 5784175 |
COLORADO STRUCTURES INC | BFT | P | 03/08/2018 | Ok to use engineer to do inspections | BERTW | BERTW | | BFT | P | 5784173 |
BIBLE ELECTRIC, INC. | E= | C | 10/15/2020 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 6742428 |
BIBLE ELECTRIC, INC. | E= | C | 10/15/2020 | parking protection installed / | BRIAN | BRIAN | | E= | C | 6742419 |
BIBLE ELECTRIC, INC. | E= | P | 10/14/2020 | all units ok with gfci protection on the bathrooms / garage protection needs to be mechanically attached to the column and braced solid or pour with concrete | BRIAN | BRIAN | | E= | P | 6740701 |
BIBLE ELECTRIC, INC. | E= | P | 10/09/2020 | phase 3 --- units 116--118--120--122---ok ac units on roof --ok / | BRIAN | BRIAN | | E= | P | 6736093 |
COLORADO ELECTRICAL SYSTEMS, LLC | E= | C | 10/09/2020 | FIRE ALARM INSPECTION: fire alarm--ok | BRIAN | BRIAN | | E= | C | 6736086 |
BIBLE ELECTRIC, INC. | E= | P | 10/08/2020 | phase 3 102--104--106--108--110--112-- 114 -- ok | BRIAN | BRIAN | | E= | P | 6734570 |
BIBLE ELECTRIC, INC. | E= | P | 09/25/2020 | FIRE ALARM INSPECTION: phase 2----ok / notes need 30 amp switch for water heater in club house and gfci breaker for fridge / gfci 6'of sink / verify on phase 3 inspections / | BRIAN | BRIAN | | E= | P | 6719479 |
BIBLE ELECTRIC, INC. | E= | P | 09/24/2020 | PHASE 2 ----2nd floor outdoor area , bbq's / heaters---ok / spa EPO not working / | BRIAN | BRIAN | | E= | P | 6717775 |
BIBLE ELECTRIC, INC. | E= | P | 09/23/2020 | pool equipment room /---ok | BRIAN | BRIAN | | E= | P | 6715956 |
BIBLE ELECTRIC, INC. | E= | P | 09/22/2020 | phase 2------ I inspected units: 231, 233, 224, 235, 237, 239, 226, 241, 228, 230, 243, 232, 245, 247, 234, 236, 249--------units 233, 244, 235, 237, 239, 241, 243, 232, 245 ok------ unit 231: gfci outlet in laundry are------unit 249: missing floor box outlet and re-label water heater breaker---------- re-label all water heaters labeled lights and outlets------------- all units 20 amp a/c breakers except units 237 and 249 have 25 amp breakers | MATTHEW | MATTHEW | | E= | P | 6715308 |
BIBLE ELECTRIC, INC. | E= | P | 09/22/2020 | phase 2----- units -216--218--220--223--225--227--229---ok | BRIAN | BRIAN | | E= | P | 6714019 |
BIBLE ELECTRIC, INC. | E= | P | 09/21/2020 | phase 2------units 215--217--219---221----ok -----still need gfci on mirror circuit / | BRIAN | BRIAN | | E= | P | 6713430 |
BIBLE ELECTRIC, INC. | E= | R | 09/17/2020 | corrections not being made on gfci accessibility in mech rooms / | BRIAN | BRIAN | | E= | R | 6709122 |
BIBLE ELECTRIC, INC. | E= | P | 09/16/2020 | phase 2--- units 204-205-206-207-208-209---mech room gfci not accessible ---rest of units--ok | BRIAN | BRIAN | | E= | P | 6707682 |
BIBLE ELECTRIC, INC. | E= | P | 09/01/2020 | phase 2-----pool light epoxy coating--ok / | BRIAN | BRIAN | | E= | P | 6692220 |
BIBLE ELECTRIC, INC. | E= | P | 08/31/2020 | phase 2---- units 201--202--203---ok / epoxy on pool is not covering the lug completly/ | BRIAN | BRIAN | | E= | P | 6690751 |
BIBLE ELECTRIC, INC. | ER | P | 08/28/2020 | pool bonding on the lights / ok --- still need epoxy inspection / | BRIAN | BRIAN | | ER | P | 6689153 |
BIBLE ELECTRIC, INC. | E= | P | 08/27/2020 | all panels on all floors--ok / | BRIAN | BRIAN | | E= | P | 6687615 |
BIBLE ELECTRIC, INC. | E= | P | 08/26/2020 | phase 1----/ main elect room / generator room / trash room / ---ok | BRIAN | BRIAN | | E= | P | 6685877 |
BIBLE ELECTRIC, INC. | E= | P | 08/25/2020 | phase 1---parking garages ( need to protect the emt to the outlets ) /sales office areas, work out room / main panel room ( need color and voltage labels ) /---ok | BRIAN | BRIAN | | E= | P | 6684641 |
BIBLE ELECTRIC, INC. | E= | P | 08/24/2020 | west entry door: mc hanging at door closer/ water cooler gfci/ right side coffe station gfci not working/ break rm: need gfci's within 6' of sink/ looked at lobby,fitness,break rm,mail, bath rms/ | JOHNN | JOHNN | | E= | P | 6682937 |
BIBLE ELECTRIC, INC. | ER | P | 08/20/2020 | epoxy inspection on the spa lights----ok / | BRIAN | BRIAN | | ER | P | 6679634 |
BIBLE ELECTRIC, INC. | E= | P | 08/20/2020 | phase 1--- generator and room---ok / | BRIAN | BRIAN | | E= | P | 6679632 |
BIBLE ELECTRIC, INC. | ER | P | 08/20/2020 | wet niche bonding in the spa only / not the pool , still need the pool / | BRIAN | BRIAN | | ER | P | 6679627 |
BIBLE ELECTRIC, INC. | E= | P | 08/20/2020 | phase 1--units--502--513--518--522--523--525--527--536--537--549----ok / | BRIAN | BRIAN | | E= | P | 6679618 |
BIBLE ELECTRIC, INC. | E= | P | 08/19/2020 | phase 1---- rest of 3rd floor units / ok ----/ need to verify gfci on mirrors / | BRIAN | BRIAN | | E= | P | 6677998 |
BIBLE ELECTRIC, INC. | E= | P | 08/18/2020 | phase 1--- units--316 --317--318--319--320--321--326--327--329--331--333--335--337--339--341--ok | BRIAN | BRIAN | | E= | P | 6676212 |
BIBLE ELECTRIC, INC. | E= | P | 08/17/2020 | phase 1 -- units 305--306--307--308--309--310--311--312---ok -- still need to verify bath gfci for the lighted mirror / | BRIAN | BRIAN | | E= | P | 6674513 |
BIBLE ELECTRIC, INC. | ER | P | 08/14/2020 | garage ceiling/ lower garage ceiling, center elevator pit---ok | BRIAN | BRIAN | | ER | P | 6674087 |
BIBLE ELECTRIC, INC. | ER | T | 08/14/2020 | PAID (REC#1704668) AFTER-HOURS INSPECTION: $200 From: MATTHEW Brian Maxa will do inspection | MATTHEW | MATTHEW | | ER | T | 6673583 |
BIBLE ELECTRIC, INC. | ER | P | 08/14/2020 | ceiling in the lower parking garage east side and bike storage / | BRIAN | BRIAN | | ER | P | 6673148 |
BIBLE ELECTRIC, INC. | E= | P | 08/14/2020 | phase 1 / units 301--302--303--304 / | BRIAN | BRIAN | | E= | P | 6673138 |
BIBLE ELECTRIC, INC. | EP | P | 08/14/2020 | GFCI TEST REPORT ---OK | BRIAN | BRIAN | | EP | P | 6672601 |
BIBLE ELECTRIC, INC. | E= | P | 08/13/2020 | phase -1 units 401--402--403--404--405--406--407--408---ok all units have ac units | BRIAN | BRIAN | | E= | P | 6671370 |
BIBLE ELECTRIC, INC. | E= | P | 08/12/2020 | phase 1-----units 408--409--410--411--412---ok | BRIAN | BRIAN | | E= | P | 6669680 |
BIBLE ELECTRIC, INC. | E= | P | 08/11/2020 | phase 1 --- units 413--415--416--417--418--419--421--423--425----ok | BRIAN | BRIAN | | E= | P | 6668109 |
BIBLE ELECTRIC, INC. | E= | P | 08/07/2020 | units 420--424--427--429--431--433--435--ok / need gfci breaker for bath light outlet / | BRIAN | BRIAN | | E= | P | 6664940 |
BIBLE ELECTRIC, INC. | E= | P | 08/06/2020 | units -426--428--430--432--441--443--445---ok / still need gfci breaker for the bath light / | BRIAN | BRIAN | | E= | P | 6663315 |
BIBLE ELECTRIC, INC. | ER | P | 08/05/2020 | ceilings in pool equipment room, trash room , generator room / | BRIAN | BRIAN | | ER | P | 6661725 |
BIBLE ELECTRIC, INC. | E= | P | 08/04/2020 | 5th ,and 4th floor halls units 541--526--449--436--447---need the correct size breaker for the bath circuit / verify later / | BRIAN | BRIAN | | E= | P | 6660115 |
BIBLE ELECTRIC, INC. | ER | P | 07/28/2020 | PVC strapping under pavers south side of pool ok / Water jets bonded North side of pool / | LOGANP | LOGANP | | ER | P | 6652262 |
BIBLE ELECTRIC, INC. | ER | P | 07/21/2020 | club house bathrooms ceilings---ok / | BRIAN | BRIAN | | ER | P | 6644179 |
BIBLE ELECTRIC, INC. | ER | P | 07/17/2020 | soffits in club house and 1/2 wall ---ok / | BRIAN | BRIAN | | ER | P | 6640969 |
BIBLE ELECTRIC, INC. | ER | P | 07/14/2020 | club house bathroom walls --ok / | BRIAN | BRIAN | | ER | P | 6636314 |
BIBLE ELECTRIC, INC. | E= | P | 07/14/2020 | units 516-- 517--519--521--524--526--529--531--533--535--539--ok | BRIAN | BRIAN | | E= | P | 6636304 |
BIBLE ELECTRIC, INC. | EUG | P | 07/09/2020 | south west side if sidwalk lighting / | BRIAN | BRIAN | | EUG | P | 6631750 |
BIBLE ELECTRIC, INC. | E= | P | 07/09/2020 | 516--517--519--521--ok / | BRIAN | BRIAN | | E= | P | 6631739 |
BIBLE ELECTRIC, INC. | E= | P | 06/25/2020 | units 509-510-511 512-513-515--need gfci on bath outlets rest ok | BRIAN | BRIAN | | E= | P | 6617204 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 06/19/2020 | FIRE ALARM INSPECTION: parking garage entry area ceilings--/ | BRIAN | BRIAN | | ER | P | 6610826 |
BIBLE ELECTRIC, INC. | ER | P | 06/19/2020 | maintenance area / ceilings in parking garage / | BRIAN | BRIAN | | ER | P | 6610817 |
BIBLE ELECTRIC, INC. | ER | P | 06/11/2020 | FIRE ALARM INSPECTION: 1st floor corridor and parking garage--ok boxes and wire/ | BRIAN | BRIAN | | ER | P | 6601701 |
BIBLE ELECTRIC, INC. | ER | P | 06/11/2020 | 1st floor corridor and grid ceiling on parking garage --ok / | BRIAN | BRIAN | | ER | P | 6601696 |
BIBLE ELECTRIC, INC. | E= | P | 06/09/2020 | units 501--503--504--505--506--507--508--ok / need wr gfci on outside / need gfci protection on all bathroom outlets / verify on next inspection | BRIAN | BRIAN | | E= | P | 6598108 |
BIBLE ELECTRIC, INC. | ER | P | 06/05/2020 | fitness room ceiling--ok / | BRIAN | BRIAN | | ER | P | 6594754 |
BIBLE ELECTRIC, INC. | ER | P | 06/01/2020 | uf feeds for the planters on 2nd floor---ok / | BRIAN | BRIAN | | ER | P | 6588586 |
BIBLE ELECTRIC, INC. | ER | P | 05/22/2020 | rest of the 1st floor units stair walls and kitchen furr outs---ok | BRIAN | BRIAN | | ER | P | 6580833 |
BIBLE ELECTRIC, INC. | EP | P | 05/20/2020 | transformer T-5 and T-6 / panels ELH1-----EHH1---SLH1---SHH1---OK | BRIAN | BRIAN | | EP | P | 6577963 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 05/15/2020 | FIRE ALARM INSPECTION: lobby area ---ok | BRIAN | BRIAN | | ER | P | 6573112 |
BIBLE ELECTRIC, INC. | ER | P | 05/15/2020 | stair walls and kitchen fur outs / units 102--104--106--108--110--ok / hard lids in lobby and guest bathrooms, leasing offices---ok | BRIAN | BRIAN | | ER | P | 6573111 |
BIBLE ELECTRIC, INC. | ER | P | 05/12/2020 | elevator lobby 2,3,4,and 5 floors ---hardlids--ok / spa lights north wall --ok / | BRIAN | BRIAN | | ER | P | 6568620 |
BIBLE ELECTRIC, INC. | ER | P | 05/01/2020 | FIRE ALARM INSPECTION: club house --ok | BRIAN | BRIAN | | ER | P | 6557943 |
BIBLE ELECTRIC, INC. | ER | P | 05/01/2020 | drops in 536--520--ok / rest of wall in club room / | BRIAN | BRIAN | | ER | P | 6557939 |
BIBLE ELECTRIC, INC. | ER | P | 04/30/2020 | 502--513--518--525--520--527--537--549---partial drop soffits / pool club house walls / | BRIAN | BRIAN | | ER | P | 6556531 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 04/30/2020 | FIRE ALARM INSPECTION: roof elevator lobby --ok | BRIAN | BRIAN | | ER | P | 6556513 |
BIBLE ELECTRIC, INC. | ER | P | 04/23/2020 | 110: still need kitchen fur out. | JOHNN | JOHNN | | ER | P | 6549634 |
BIBLE ELECTRIC, INC. | ER | P | 04/17/2020 | FIRE ALARM INSPECTION: units 114--116--118--120--122---ok | BRIAN | BRIAN | | ER | P | 6543667 |
BIBLE ELECTRIC, INC. | ER | P | 04/17/2020 | partial in units --112--114--116--118--120--122---need stair ways and fur outs / | BRIAN | BRIAN | | ER | P | 6543655 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 04/14/2020 | FIRE ALARM INSPECTION: fitness room ceiling / | BRIAN | BRIAN | | ER | P | 6539900 |
BIBLE ELECTRIC, INC. | ER | P | 04/14/2020 | drops in units --227--327--320--427--436---ok / hard lid in the fitness room 1st floor --ok / | BRIAN | BRIAN | | ER | P | 6539842 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 04/06/2020 | FIRE ALARM INSPECTION: units 102--104--106--108---fire alarm only | BRIAN | BRIAN | | ER | P | 6531818 |
BIBLE ELECTRIC, INC. | ER | P | 04/06/2020 | walls and upper hard lids in units 102--104--106--108---still need stair walls when built | BRIAN | BRIAN | | ER | P | 6531817 |
BIBLE ELECTRIC, INC. | ER | P | 03/26/2020 | 1st floor prerock in west corridor / | BRIAN | BRIAN | | ER | P | 6522133 |
BIBLE ELECTRIC, INC. | ER | R | 03/26/2020 | units 403--425 drops and fur out kitchen---ok / | BRIAN | BRIAN | | ER | R | 6522132 |
BIBLE ELECTRIC, INC. | ER | P | 03/16/2020 | bathroom drops and kitchen walls in units --- 412--413--418--420--423--437--449--ok | BRIAN | BRIAN | | ER | P | 6511343 |
BIBLE ELECTRIC, INC. | ER | P | 03/13/2020 | unit 536 walls and prerock / walls on north end 1st floor --see plans --ok / | BRIAN | BRIAN | | ER | P | 6510040 |
BIBLE ELECTRIC, INC. | ER | P | 03/12/2020 | unit 427--ok | BRIAN | BRIAN | | ER | P | 6508766 |
BIBLE ELECTRIC, INC. | ES | C | 03/12/2020 | Commercial Service: ok to set meters in units / 301--302--303--304--305--306--307--308--309--310--311--312--313--315--316--317--318--319--320--321--323--324--325--326--327--328--329--330--331--332--333--334--335--336--337--339--341--343--345--347--349--/ 4th floor / 401--402--403--404--405--406--407--408--409--410--411--412--413--415--416--417--418--420--421--423--424--425--426--427--428--429--430--431--432--433--434--435--436--437--439--441--443--445--447--449 / 5th floor / 501--502--503--504--505--506--507--508--509--510--511--512--513--515--516--517--518--519--520--521--523--524--525--526--527--528--529--530--531--532--533--534--535--536--537--539--541--543--545 / this is all the units / 125 amp 3-w / | BRIAN | BRIAN | | ES | C | 6508752 |
BIBLE ELECTRIC, INC. | ER | P | 03/11/2020 | unit 327 / prerock and walls / | BRIAN | BRIAN | | ER | P | 6507241 |
BIBLE ELECTRIC, INC. | ES | P | 03/11/2020 | Commercial Service: ok to set metetrs in units / 101--102--104--106--108--110--112--114--116--118--120--122 / 201--202--203--204--205--206--207--208--209--210--211--213--215--216--217--218--210--220--221--222-223--224--225--226--227--228--229--230--231--232--233--234--235--236--237--239--241--243--235--247--249 / more inspection to follow / all units are 125 amp 3-w | BRIAN | BRIAN | | ES | P | 6507233 |
BIBLE ELECTRIC, INC. | ER | P | 02/26/2020 | fitness room and bathroom walls --ok / 4'rip at top of walls 1st floor --ok / | BRIAN | BRIAN | | ER | P | 6493047 |
BIBLE ELECTRIC, INC. | ER | P | 02/24/2020 | upper layer of rebar and forming shell light bonds---ok | BRIAN | BRIAN | | ER | P | 6489937 |
BIBLE ELECTRIC, INC. | ER | P | 02/19/2020 | south wing kitchen fur outs and drops --ok -----520--ok ------536 need the wall and stairs installed for roof patio to finish the wiring / | BRIAN | BRIAN | | ER | P | 6485715 |
BIBLE ELECTRIC, INC. | ER | P | 02/18/2020 | kitchen fur outs and bath drops in 2nd floor units --215--216--217--218--219--221--223--224--225--229--231--233--235---ok / | BRIAN | BRIAN | | ER | P | 6484109 |
BIBLE ELECTRIC, INC. | ER | P | 02/13/2020 | 512--503 -----201--202--203--204--205--206--207--208--209--210--211--212--213--ok / kitchen fur out and bathroom drops / | BRIAN | BRIAN | | ER | P | 6481677 |
BIBLE ELECTRIC, INC. | ER | P | 02/06/2020 | 3rd floor drop ceilings and kitchen walls /326-330-332-334-336-337-339-341-343-345-347-349 --ok / | BRIAN | BRIAN | | ER | P | 6475489 |
BIBLE ELECTRIC, INC. | ER | P | 02/05/2020 | hard lid drops and kitchen fur outs / units---313-314-315-316-317- 318-319-321- 324-325-329-331-333-335 | BRIAN | BRIAN | | ER | P | 6474383 |
BIBLE ELECTRIC, INC. | ER | P | 01/24/2020 | 301 through 312 / kitchen and hard lids--ok / | BRIAN | BRIAN | | ER | P | 6463057 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 01/23/2020 | FIRE ALARM INSPECTION: 2nd floor corridor ok / ceilings | BRIAN | BRIAN | | ER | P | 6461517 |
BIBLE ELECTRIC, INC. | ER | P | 01/23/2020 | 2nd floor corridor ceiling ok / 5th floor fire dampers ok / | BRIAN | BRIAN | | ER | P | 6461512 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 01/10/2020 | FIRE ALARM INSPECTION: units 513--518--537--549-- ok / | BRIAN | BRIAN | | ER | P | 6449102 |
BIBLE ELECTRIC, INC. | ER | P | 01/10/2020 | units--518--513--537--549---ok walls and prerock / need fan installed in 520 / ----------4th floor dampers | BRIAN | BRIAN | | ER | P | 6449088 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 01/08/2020 | FIRE ALARM INSPECTION: 502 --523--527 / | BRIAN | BRIAN | | ER | P | 6446400 |
BIBLE ELECTRIC, INC. | ER | P | 01/08/2020 | unit 502 -523--527 / walls and prerock / | BRIAN | BRIAN | | ER | P | 6446398 |
BIBLE ELECTRIC, INC. | ER | P | 01/02/2020 | FIRE ALARM INSPECTION: 5th and 4th floor halls --ok see plans | BRIAN | BRIAN | | ER | P | 6441429 |
BIBLE ELECTRIC, INC. | ER | P | 12/31/2019 | FIRE ALARM INSPECTION: 3rd floor hallway ---ok / | BRIAN | BRIAN | | ER | P | 6440552 |
BIBLE ELECTRIC, INC. | E= | P | 12/31/2019 | 3rd floor hall hard lids--ok | BRIAN | BRIAN | | E= | P | 6440546 |
BIBLE ELECTRIC, INC. | ER | P | 12/31/2019 | fire dampers on north and south tower 3rd floor--ok | BRIAN | BRIAN | | ER | P | 6440519 |
BIBLE ELECTRIC, INC. | ER | P | 12/19/2019 | kitchen wall in unit 501----rip along ceilings in 102--104--106--108--110--112--114---ok | BRIAN | BRIAN | | ER | P | 6432389 |
BIBLE ELECTRIC, INC. | ER | P | 12/11/2019 | FIRE ALARM INSPECTION: 237--239--241--243--245--247--249 | BRIAN | BRIAN | | ER | P | 6423844 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 12/11/2019 | FIRE ALARM INSPECTION: rest of the south tower 2nd floor units --237--239--241--245--247--249 | BRIAN | BRIAN | | ER | P | 6423840 |
BIBLE ELECTRIC, INC. | ER | P | 12/09/2019 | units -- 539--541--543--545--547--526--528--530--532--534-----kitchen walls and bath room drop lids / 2nd floor damper conn. / ok | BRIAN | BRIAN | | ER | P | 6420663 |
BIBLE ELECTRIC, INC. | ER | P | 12/04/2019 | Hard lids in bathrooms units 505, 507, 509, 515, 519, and 531 okay / Hard lids in bathrooms and fured out walls in units 503, 506, 508, 510, 511, 516, 517, 521, 524, 529, 533 okay | CHIPO | CHIPO | | ER | P | 6416032 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 12/03/2019 | FIRE ALARM INSPECTION: no fire alarm to day | BRIAN | BRIAN | | ER | P | 6414221 |
BIBLE ELECTRIC, INC. | ER | P | 12/03/2019 | 4th floor kitchen walls and bath hard lids / 401--403--404--405--406--407--408--409--410--411--415--416--417--419--421--429--431--435--439--441--443--445--447--426--428--430--432--434---ok | BRIAN | BRIAN | | ER | P | 6414214 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 12/02/2019 | FIRE ALARM INSPECTION: units 512--412--420--425--315--309--212--209--- | BRIAN | BRIAN | | ER | P | 6412625 |
BIBLE ELECTRIC, INC. | ER | P | 12/02/2019 | 512--4123--420--425--315--309--212--209---accessible units / | BRIAN | BRIAN | | ER | P | 6412622 |
BIBLE ELECTRIC, INC. | ER | P | 11/25/2019 | FIRE ALARM INSPECTION: units 226, 234, 232, 230, 228, 226 | SHELBY | SHELBY | | ER | P | 6409800 |
BIBLE ELECTRIC, INC. | ER | P | 11/25/2019 | Units 226, 234, 232, 230, 228, 226 OK other than kitchen fur outs | SHELBY | SHELBY | | ER | P | 6409790 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/21/2019 | FIRE ALARM INSPECTION: units ---227--229--231--233--235--237--220--224--- ok | BRIAN | BRIAN | | ER | P | 6406641 |
BIBLE ELECTRIC, INC. | ER | P | 11/21/2019 | units--227--229--231--233--235--237--224--220-----ok walls and prerock ceilings --need kitchen walls / | BRIAN | BRIAN | | ER | P | 6406640 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/20/2019 | FIRE ALARM INSPECTION: 209---211--213--215--217--219--221--223--225--ok | BRIAN | BRIAN | | ER | P | 6405253 |
BIBLE ELECTRIC, INC. | ER | P | 11/20/2019 | units--209--211--213--215--217--219--221--223--225-- ok walls and prerock / | BRIAN | BRIAN | | ER | P | 6405251 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/18/2019 | FIRE ALARM INSPECTION: 202--204--206--208--210--212- / | BRIAN | BRIAN | | ER | P | 6402231 |
BIBLE ELECTRIC, INC. | ER | P | 11/18/2019 | units 202--204--206--208--210--112 / walls and prerock -----need kitchen walls | BRIAN | BRIAN | | ER | P | 6402226 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/15/2019 | FIRE ALARM INSPECTION: 2nd floor elect rooms / units 201--203--205--207 / | BRIAN | BRIAN | | ER | P | 6400423 |
BIBLE ELECTRIC, INC. | ER | P | 11/15/2019 | 2nd floor elect rooms hard lids ok / units 201--203--205--207 / --walls and prerock ceilings ok | BRIAN | BRIAN | | ER | P | 6400410 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | R | 11/12/2019 | FIRE ALARM INSPECTION: not ready | BRIAN | BRIAN | | ER | R | 6395822 |
BIBLE ELECTRIC, INC. | ER | P | 11/12/2019 | south units 1st floor / ok to install rip around the top walls | BRIAN | BRIAN | | ER | P | 6395818 |
BIBLE ELECTRIC, INC. | ER | P | 11/07/2019 | 3rd floor units -- 326-328-330-332-334-336---walls and prerock ceilings ok/ still need kitchen walls | BRIAN | BRIAN | | ER | P | 6391381 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/07/2019 | FIRE ALARM INSPECTION: 3rd floor units -- 326-328-330-332-334-336----ok | BRIAN | BRIAN | | ER | P | 6391360 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/06/2019 | FIRE ALARM INSPECTION: units 337-339-341-343-345-347-349-ok | BRIAN | BRIAN | | ER | P | 6389855 |
BIBLE ELECTRIC, INC. | ER | P | 11/06/2019 | 3rd floor units --337-339-341-343-345-347-349---ok walls and pre rock ceilings | BRIAN | BRIAN | | ER | P | 6389851 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/05/2019 | FIRE ALARM INSPECTION: 327-329-331-333-335--324 / ---ok | BRIAN | BRIAN | | ER | P | 6388342 |
BIBLE ELECTRIC, INC. | ER | P | 11/05/2019 | units--327-329-331-333-335-----324 / --walls and prerock only / | BRIAN | BRIAN | | ER | P | 6388341 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 11/04/2019 | FIRE ALARM INSPECTION: 314-315-316-317-318-319-321-323-325 / ok | BRIAN | BRIAN | | ER | P | 6387125 |
BIBLE ELECTRIC, INC. | ER | P | 11/04/2019 | units 314-315-316-317-318-319-321-323-325----walls and prerock / --need kitchen walls / | BRIAN | BRIAN | | ER | P | 6387122 |
BIBLE ELECTRIC, INC. | ES | P | 11/01/2019 | Commercial Service: 1- 1000 amp 480 volt 4-w / 2- 1600 amp 4-w 208 volt / ----ok for utility to energize /-----------------rbd notes --ok to mains need water gec connected to water line , all branch breakers in mdp's ok / need gfci test report uploaded / | BRIAN | BRIAN | | ES | P | 6385541 |
BIBLE ELECTRIC, INC. | ER | P | 10/23/2019 | 3rd floor units / 302-304-306-308-310-312-314 walls and prerock , need kitchen walls / | BRIAN | BRIAN | | ER | P | 6377596 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 10/23/2019 | FIRE ALARM INSPECTION: 3rd floor units 302-304-306-308-310-312-314----fire alarm | BRIAN | BRIAN | | ER | P | 6377583 |
COLORADO ELECTRICAL SYSTEMS, LLC | E= | P | 10/22/2019 | FIRE ALARM INSPECTION: fire alarm / 301-303-305-307-309-311---ok | BRIAN | BRIAN | | E= | P | 6376259 |
BIBLE ELECTRIC, INC. | ER | P | 10/22/2019 | units 301-303-305-307-309-311---walls and drop ceilings , still need kitchen wall / | BRIAN | BRIAN | | ER | P | 6376258 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 10/08/2019 | FIRE ALARM INSPECTION: units 522-539-541-543-545---wire and boxes | BRIAN | BRIAN | | ER | P | 6361471 |
BIBLE ELECTRIC, INC. | ER | P | 10/08/2019 | 5th floor units /522-539-541-543-545-/ walls and prerock still need kitchen walls / | BRIAN | BRIAN | | ER | P | 6361466 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 10/04/2019 | FIRE ALARM INSPECTION: units -- 516-524-526-528-530-532-534 / boxes and wire | BRIAN | BRIAN | | ER | P | 6357931 |
BIBLE ELECTRIC, INC. | ER | P | 10/04/2019 | units 516-524-526-528-530-532-534/ walls and prerock ceilings , need kitchen walls | BRIAN | BRIAN | | ER | P | 6357926 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 10/01/2019 | FIRE ALARM INSPECTION: units 515-517-519-521-529-531-533 / boxes and wire -ok / | BRIAN | BRIAN | | ER | P | 6353412 |
BIBLE ELECTRIC, INC. | ER | P | 10/01/2019 | units 515-517-519-521-529-531-533 walls and prerock ceilings need kitchens / | BRIAN | BRIAN | | ER | P | 6353407 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 09/24/2019 | FIRE ALARM INSPECTION: units 501 through 511--ok | BRIAN | BRIAN | | ER | P | 6345632 |
BIBLE ELECTRIC, INC. | E= | P | 09/24/2019 | units 501-503-504-505-506-507-508-509-510-511- walls and prerock / need drop lids and kitchen walls / | BRIAN | BRIAN | | E= | P | 6345629 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 08/27/2019 | FIRE ALARM INSPECTION: SOPUTH TOWER - units 426-428-432-434-436 -ok | BRIAN | BRIAN | | ER | P | 6315711 |
BIBLE ELECTRIC, INC. | ER | P | 08/27/2019 | SOUTH TOWER --units 426-428-432-434-436---ok --------------------NOTE-- ACCESSIBLE UNITS HAVE CHANGED PER CONTRACTOR | BRIAN | BRIAN | | ER | P | 6315703 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 08/26/2019 | FIRE ALARM INSPECTION: SOUTH TOWER - units 435-437-439-441-443-445-447-449--ok | BRIAN | BRIAN | | ER | P | 6313701 |
BIBLE ELECTRIC, INC. | ER | P | 08/26/2019 | SOUTH TOWER 4TH FLOOR ---units 435-437-439-441-443-445-447-449---ok prerock and walls | BRIAN | BRIAN | | ER | P | 6313697 |
BIBLE ELECTRIC, INC. | ER | P | 08/23/2019 | 416, 418, 424, 433, 431, 429, 427 | SHELBY | SHELBY | | ER | P | 6312115 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 08/20/2019 | FIRE ALARM INSPECTION: EAST TOWER units 413-415-417-419-421-423-425 / | BRIAN | BRIAN | | ER | P | 6306728 |
BIBLE ELECTRIC, INC. | ER | P | 08/20/2019 | EAST TOWER / units 413-415-417-419-421-423-425---walls and prerock /--need kitchen walls still / | BRIAN | BRIAN | | ER | P | 6306726 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 08/19/2019 | FIRE ALARM INSPECTION: north tower / units 403-405-407-409-411 / ok | BRIAN | BRIAN | | ER | P | 6305117 |
BIBLE ELECTRIC, INC. | ER | P | 08/19/2019 | NORTH TOWER units 403-405-407-409-411 / walls and prerock / Discussed accessibility requirements with contractor / | BRIAN | BRIAN | | ER | P | 6305105 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 08/16/2019 | FIRE ALARM INSPECTION: units / 401-402-404-406-408-410 - ok | BRIAN | BRIAN | | ER | P | 6303372 |
BIBLE ELECTRIC, INC. | ER | P | 08/16/2019 | units on north tower / 401-401-404-406-408-410 / prerock and walls ok , need drops and kitchen wall / Discussed accessibility requirements with contractor / | BRIAN | BRIAN | | ER | P | 6303369 |
BIBLE ELECTRIC, INC. | ESP | P | 07/31/2019 | consultation ---talked about the balcony outlets and fixed panel outlets inside / | BRIAN | BRIAN | | ESP | P | 6283164 |
BIBLE ELECTRIC, INC. | ER | P | 07/03/2019 | walls on corridors on 2nd , 3rd, 4th floors--ok | BRIAN | BRIAN | | ER | P | 6252558 |
BIBLE ELECTRIC, INC. | ER | P | 07/02/2019 | elect rooms on floors 2-5 prerock ceilings--ok | BRIAN | BRIAN | | ER | P | 6250987 |
BIBLE ELECTRIC, INC. | ER | P | 06/28/2019 | see plans/ NOTE NO FIRE ALARM INSTALLED | BRIAN | BRIAN | | ER | P | 6247615 |
BIBLE ELECTRIC, INC. | ER | P | 06/28/2019 | prerock ceilings in 2,3,4th floor corridors --ok / 2,3.4.telecom and trash rooms prerock ceilings--ok | BRIAN | BRIAN | | ER | P | 6247614 |
BIBLE ELECTRIC, INC. | ER | P | 06/27/2019 | partial pre rock inspection on 5th floor hall --see plans / roof ac curbs --ok | BRIAN | BRIAN | | ER | P | 6245962 |
BIBLE ELECTRIC, INC. | ER | P | 06/19/2019 | east couch on south tower ---ac ER --ok | BRIAN | BRIAN | | ER | P | 6236179 |
BIBLE ELECTRIC, INC. | ER | P | 06/06/2019 | nm stubs for a/c's, marked/dated on prints | GARYL | GARYL | | ER | P | 6222081 |
BIBLE ELECTRIC, INC. | ER | P | 05/15/2019 | north ac platform--ok | BRIAN | BRIAN | | ER | P | 6199522 |
BIBLE ELECTRIC, INC. | ER | P | 04/18/2019 | riser room in basement ---walls ok / | BRIAN | BRIAN | | ER | P | 6169913 |
BIBLE ELECTRIC, INC. | ESP | P | 04/10/2019 | this was a consultation | BRIAN | BRIAN | | ESP | P | 6161467 |
BIBLE ELECTRIC, INC. | E= | P | 04/08/2019 | remainder of underground to be called under the building electrical attachment | MATTHEW | MATTHEW | | E= | P | 6158319 |
BIBLE ELECTRIC, INC. | ESL | P | 10/17/2018 | south east pour 2nd floor--ok | BRIAN | BRIAN | | ESL | P | 6158307 |
BIBLE ELECTRIC, INC. | ESL | P | 10/03/2018 | s.west 2nd floor----ok | BRIAN | BRIAN | | ESL | P | 6158306 |
BIBLE ELECTRIC, INC. | EUG | P | 09/24/2018 | north east of 2nd floor---- Discussed accessibility requirements with contractor / | BRIAN | BRIAN | | EUG | P | 6158315 |
BIBLE ELECTRIC, INC. | EUG | P | 08/28/2018 | 2nd level pool bonding, equi-around pool, 7-corner connections from main pool, 4-corner connections from spa, equi-around spa, AND level 2 post tention slab around pool | GARYL | GARYL | | EUG | P | 6158314 |
BIBLE ELECTRIC, INC. | EUG | P | 08/16/2018 | POOL BONDING: 4--CORNERS OF POOL, 4--CORNERS OF HOT TUB | GARYL | GARYL | | EUG | P | 6158313 |
BIBLE ELECTRIC, INC. | EUG | P | 08/09/2018 | slab, marked and dated on prints, 1st floor ceilings, 2nd floor slab | GARYL | GARYL | | EUG | P | 6158312 |
BIBLE ELECTRIC, INC. | EUG | P | 07/26/2018 | from column F - B and 1 - 8 ok only | CRAIG | CRAIG | | EUG | P | 6158311 |
BIBLE ELECTRIC, INC. | EUG | P | 07/11/2018 | marked/dated via Brandon on prints | GARYL | GARYL | | EUG | P | 6158310 |
BIBLE ELECTRIC, INC. | ESL | P | 06/26/2018 | from column J - G and 2 - 8 ok only | CRAIG | CRAIG | | ESL | P | 6158305 |
BIBLE ELECTRIC, INC. | EUG | P | 06/22/2018 | marked/dated on prints, all eug this section | GARYL | GARYL | | EUG | P | 6158309 |
BIBLE ELECTRIC, INC. | ER | P | 06/20/2018 | marked/dated on prints | GARYL | GARYL | | ER | P | 6158304 |
BIBLE ELECTRIC, INC. | ER | P | 06/19/2018 | Marked/dated on prints, | GARYL | GARYL | | ER | P | 6158303 |
BIBLE ELECTRIC, INC. | ER | P | 05/22/2018 | marked and dated on prints----See Brandon | GARYL | GARYL | | ER | P | 6158302 |
BIBLE ELECTRIC, INC. | EUG | P | 04/30/2018 | Ufer okay, G-section eug, marked/dated on electric prints | GARYL | GARYL | | EUG | P | 6158308 |
BRUCE MECHANICAL OF COLORADO, INC | H= | C | 11/18/2020 | VERIFIED WITH BUILDING INSPECTOR RESTRAINT SYSTEM FOR RTU IS COMPLETE | JON | JON | | H= | C | 6780265 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 10/20/2020 | PHASE 3 COMPLETE PENDING GUARD RAIL AT CLUB HOUSE. | JON | JON | | H= | P | 6747161 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 10/15/2020 | NEED PREVIOUS NOTES ADDRESSED FROM LAST INSPECTION NOTES: TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | P | 6742383 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | C | 09/30/2020 | THIS CONTRACTORS SCOPE OF WORK IS COMPLETE. | JON | JON | | H= | C | 6725044 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 09/29/2020 | THIS IS A COMPLETE LIST FOR ALL ITEMS. 1- BALANCE REPORT 2-UNIT 116 AND 120 NEED LAUNDRY MAKE UP AIR. 3- CLUB HOUSE ROOF TOP UNIT NOT 10 FEET FROM ROOF EDGE. 4- CONDENSERS MISSING LABELS FOR 212, 412, 512, 232, 245, 433, 420, 320, EPH 7. 5- REPAIR PVC PROTECTION FOR UNIT 108 UPPER FAN COIL IN RETURN PLENUM. REST OK | JON | JON | | H= | P | 6723702 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 09/25/2020 | PHASE 2 COMPLETE PENDING GUARD RAIL AT CLUB HOUSE RTU.. 5TH FLOOR ROOF TOP CONDENSERS MISSING LABELS ON 212, 412, 512, 232, 245, 433, 420, 320, EPH 7. ALSO NEED ALL EXTERIOR DUCT WORK WEATHER SEALED PROPERLY AT CORRIDOR RTU'S.. NEED UV RATED CANVAS CONNECTORS ON RTU'S OR PROTECT FROM THE SUN. | JON | JON | | H= | P | 6720617 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 09/25/2020 | Phase 2 final ok for this contractor | JON | JON | | H= | P | 6720510 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 09/23/2020 | PHASE 2 2ND FLOOR APARTMENTS UNITS COMPLETE. POOL DECK AND CLUB INSPECTION PHASE 2 OK EXCEPT FOR ONE OF THE RTU'S IS NOT 10 FEET FROM THE ROOF EDGE. WENT OVER OPTIONS WITH ZACH FROM CSI. REST OK WILL NEED AIR BALANCE REPORT ON ENTIRE PROJECT BEFORE FINAL. | JON | JON | | H= | P | 6717096 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 09/23/2020 | INSPECTION FOR 2 FIRE PITS. SEE SCANNED LETTER FROM FIRE PIT MANUFACTURER FOR PROPER VENTILATION OPENINGS. FOR FINAL WILL NEED VENT LIMITING REGULATORS PROTECTED WITH PROPERLY PER MANUFACTURER INSTRUCTIONS FOR OUTSIDE, THIS INCLUDES ROOF TOP UNITS ON CLUBHOUSE. WILL VERIFIY ALL PROPER VENTILATION OPENINGS ON BOTH FIRE PITS. WILL CHECK ACCESS TO FUEL SHUTOFF VALVES. | JON | JON | | H= | P | 6717087 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 09/18/2020 | SNOW MELT BOILER OK. STILL NEED PERMITS AND INSPECTIONS FOR THE 2 CAMP FIRES. 3 BUILT IN BARBECUES ARE INSTALLED IN NON COMBUSTIBLE MATERIALS WITH TIMERS AND SHUT OFF VALVES IN PLACE. STILL NEED TO ADDRESS POOL AND SPA BOILERS AS THE GAS REGULATORS ARE NOT VENTED TO THE OUTSIDE. IF THESE GAS REGULATORS DO NOT ALLOW A VENT LIMITING REGULATOR THE ENGINEER WILL HAVE TO ADDRESS WHERE TO LOCATE THE REGULATOR VENTS AS THE PARKING GARAGE IS NOT CONSIDERED OUTSIDE. REST OK ON POOL BOILERS | JON | JON | | H= | P | 6711332 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 09/17/2020 | PHASE 2 SECOND FLOOR APARTMENTS. 236 NEEDS FIRE DAMPER TO OPERATE PROPERLY. 232 IS MISSING SUPPLY AIR REGISTERS AT REAR SLIDING DOOR. ALL THE REST ARE COMPLETE. | JON | JON | | H= | P | 6710110 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 09/16/2020 | NEED TO RECHECK FIRE DAMPER OPERATION ON 203, 204, 205, 207, 211 REST OK NORTH SIDE ONLY NEXT INSPECTION TO START AT 213 ON EAST WING FOR HVAC FINAL | JON | JON | | H= | P | 6708488 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 09/15/2020 | WATER HEATERS FOR ALL WALK UP UNITS NOW COMPLETE | JON | JON | | H= | P | 6706654 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 09/15/2020 | INSPECTED POOL BOILERS. BOILERS OK EXCEPT FOR GAS REGULATOR VENTS FOR BOILERS ARE NOT PIPED TO THE OUT DOORS OR HAVE VENT LIMITERS IN PLACE. DISCUSSED WITH TONY | JON | JON | | HSP | P | 6706651 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 09/10/2020 | SNOW MELT PIPING TEST AND VISIBLE INSPECTION OK FOR POOL DECK. | JON | JON | | HWP | P | 6702138 |
BRUCE MECHANICAL OF COLORADO, INC | HV | C | 09/10/2020 | BOILER VENTS AND UNIT HEATER VENT COMPLETE. JUST NEED NON COMBUSTIBLE CEILING PANELS IN GENERATOR ROOM FOR UNIT HEATER VENT AND GENERATOR EXHAUST PIPING. | JON | JON | | HV | C | 6703014 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 09/09/2020 | STILL NEED BOILER INSPECTIONS BY NEWCOMER, WENT OVER THAT WITH TONY ON SITE TODAY | JON | JON | | HSP | P | 6700749 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 09/09/2020 | ALL THAT IS LEFT ON THE REZNOR UNIT HEATER IN THE GENERATOR ROOM IS 2 NON COMBUSTIBLE PANELS IN THE CEILING ONE FOR THE UNIT HEATER AND ONE FOR THE GENERATOR EXHAUST. NEED TO CORRECT THE BAROMETRIC DAMPERS FOR THE BOILER VENTS IN THE BOILER ROOM. REST OF BOILER VENTING OK. | JON | JON | | H= | P | 6700744 |
BRUCE MECHANICAL OF COLORADO, INC | HV | P | 09/03/2020 | BOTH BOILERS VENTS ARE COMPLETE, THE UNIT HEATER IN THE GENERATOR ROOM NEEDS INSTALLED TO ITS INSTRUCTIONS. WENT OVER THIS WITH NORMAN, VENT SLOPE PROPER SEALING AT B-VENT CONNECTION AND NEEDS PROPER VENT CAP PER INSTRUCTIONS. | JON | JON | | HV | P | 6699074 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/03/2020 | FIRE DAMPERS COMPLETE AT BOILER ROOM. NEED EXHAUST FAN INSTALLED WITH DUCTS IN BOILER ROOM. | JON | JON | | HD | P | 6699079 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 09/02/2020 | ADDED COMMISSIONING DOCUMENTS TO IMAGES FOR GENERATOR FROM MANUFACTURE. | JON | JON | | HSP | P | 6693994 |
FIREPLACE WAREHOUSE | H= | C | 09/01/2020 | CLOSED PERMIT. WILL NEED A NEW CONTRACTOR FOR FIRE PIT. WILL NOT COMPLETE GAS FINAL FOR GAS CONTRACTOR ON PHASE 2 WITHOUT A PERMIT FOR FIRE PIT. UNLESS FIRE PIT IS SHOWN AS FUTURE. | JON | JON | | H= | C | 6693415 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/27/2020 | PHASE 1 PARTIAL HEAT FINAL COMPLETE FOR THIS CONTRACTOR. | JON | JON | | H= | P | 6688342 |
SCHINDLER ELEVATOR CORPORATION | HE= | C | 08/27/2020 | ALL ELEVATORS COMPLETE | ROBERTV | ROBERTV | | HE= | C | 6688061 |
SCHINDLER ELEVATOR CORPORATION | H= | R | 08/24/2020 | SEE IMAGES FOR DOCUMENT LISTING ITEMS THAT NEED TO BE ADDRESSED FOR ELEVATORS | ROBERTV | ROBERTV | | H= | R | 6683836 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/21/2020 | STILL NEED INTERLOCK ON UNITS 303, 304, 312, 315, 337, 302, REST OF 3RD FLOOR OK. ALL GARAGE CO/NOX SENSORS IN PLACE PER RFI DOCUMENT. ATTACHED RFI TO IMAGES. DOG WASH COMPLETE. FOR PHASE 1 PARTIAL FINAL STILL NEED BOILER ROOM, GENERATOR ROOM AND THE UNITS NOTED ABOVE ON THIRD FLOOR | JON | JON | | H= | P | 6682174 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/20/2020 | ALL THREE GARAGE EXHAUST FANS ARE IN OPERATION. ELEVATOR LOBBIES IN GARAGE AREA COMPLETE. TRASH ROOM COMPLETE. FOR PHASE ONE STILL NEED 3RD FLOOR INTERLOCKS. STILL NEED ALL WORK IN BOILER ROOM COMPLETE. NEED APPROVED PLAN FOR CHANGES TO CO/NOX SENSORS AS NOTED. SIDE NOTE CONTRACTOR STILL WORKING ON CONDENSER LABELING ON ROOF. CALL ROOF INSPECTION WHEN READY. SEE ALL PRIOR NOTES. | JON | JON | | H= | P | 6680629 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 08/20/2020 | WATER HEATERS, GAS AND VENTS FOR ALL 14 WALK UP UNITS ALL COMPLETE. | JON | JON | | H= | P | 6680622 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/19/2020 | ALL OF 4TH AND 5TH FLOORS COMPLETE. STILL NEED 3RD FLOOR INTERLOCKS FOR FAN COIL SHUT DOWN, ONLY FOUND ONE OUT OF THE 4 INTERLOCKS THAT WERE CHECKED TO BE WORKING PROPERLY. REST OK ON 3RD FLOOR. PARKING GARAGE AREA IS PARTIAL PENDING AN RBD PLAN SPLICE APPROVAL FOR REDUCTION AND LOCATION CHANGES FOR CO/NOX DETECTORS IN ALL LEVELS OF GARAGE. WILL NEED TO SEE BOILER COMBUSTION AIR INTAKES OVER CEILING IN G-1 GARAGE AREA TO VERIFY INSULATION HAS BEEN INSTALLED. BOILER VENTS OVER THIS CEILING ARE OK. EXTENSIVELY WENT OVER BOILER VENTING WITH CONTRACTOR TO MAKE SURE THE MAXIMUM VENT DISTANCES DO NOT EXCEED THE 100 FOOT MAXIMUM DISTANCE INCLUDING ALL ELBOW REDUCTIONS. ALL OTHER ROOMS ASSOCIATED WITH PARKING GARAGE TO BE COMPLETED AS PREVIOUSLY NOTED, AS IN ELEVATOR LOBBIES, DOG SPA,TRASH ROOM, BOILER ROOM. ETC WENT OVER THIS WITH AARON WITH CSI AND JOHN Q PROJECT MANAGER FOR BRUCE MECHANICAL. INSPECTOR WAS TOLD BY BRUCE MECHANICAL PM THAT ALL 3 GARAGE EXHAUST FANS SHOULD BE OPERATIONAL BY THE END OF THE DAY TODAY. | JON | JON | | H= | P | 6678826 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 08/18/2020 | PHASE ONE COMPLETE FOR GAS, HYDRONIC PIPING AND WATER HEATER VENTS. | JON | JON | | H= | P | 6677372 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/18/2020 | MISSING CO SENSORS IN GARAGE G1 NORTH AND SOUTH. ALSO MISSING CO SENSOR BY EAST STAIRS G2. 5TH FLOOR MEZZANINE UNITS NOW COMPLETE EXCEPT FOR 515 AND 535. 427 AND 327 NOW COMPLETE, 3RD AND 4TH FLOOR NOW COMPLETE EXCEPT FOR 315,335, 415 AND 435. STILL NEED TO FOLLOW ALL OF THE NOTES FROM 8-15-20 THROUGH TO TODAY. | JON | JON | | H= | P | 6677370 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/17/2020 | THESE NOTES ARE TO BE ADDED TO THE HEAT FINAL INSPECTION HISTORY FROM 8-15-20. NEED ROOF INSPECTION WITH CONDENSERS LABELED AREA SERVED. ALL GARAGE EXHAUST FANS ARE TO BE INSTALLED AND OPERATIONAL. NEED TO WALK WITH CONTRACTOR TO VERIFY ALL CO SENSORS ARE INSTALLED TO PLANS AT ALL GARAGE LEVELS. NEED ALL ELEVATOR LOBBIES AT GARAGE LEVELS TO BE COMPLETED WITH OUTSIDE AIR PER PLANS ALONG WITH PLAN SPLICES FOR ALL CHANGES FOR DUCT ROUTING. AARON WILL HAVE INSPECTION CALLED FOR TUESDAY THE 18TH FOR INTERLOCK INSPECTION FOR ALL FAN COIL UNITS ON FLOORS 2-5. DISCUSSED AGAIN THAT VENT INSPECTIONS ARE TO BE CALLED FOR BOILERS AND UNIT HEATERS AT GARAGE LEVEL 1. STILL MISSING EXHAUST AND MAKEUP AIR FIRE DAMPERS AT BOILER ROOM GARAGE LEVEL 1. NEED AIR BALANCE REPORT. OWNERS WORKING ON PHASE 2 FOR AN ENGINEERED DESIGN FOR THE SNOW MELT SYSTEM INSTALLED ABOVE PODIUM FOR HEATING PANELS UNDER PAVERS AT POOL DECK. | JON | JON | | H= | P | 6675078 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 08/17/2020 | FOR GAS FINAL NEED PLACARDS FOR GENERATOR GAS SERVICE LINE. NEED GAS COMPLETED FOR GENERATOR AND UNIT HEATER. NEED BOILER ROOM GAS PIPING COMPLETED. NEED ROOF INSPECTION FOR CORRIDOR ROOF TOP UNITS. NEWCOMERS PLUMBING IS CALLING THIS PHASE ONE INSPECTION FOR 8-18-20.. SEE PREVIOUS NOTES 8-15-20 FOR WATER HEATER FINALS PHASE ONE. | JON | JON | | H= | P | 6675062 |
FIREPLACE WAREHOUSE | H= | P | 08/17/2020 | CALLED FIREPLACE CONTRACTOR FOR THE OK TO ADD AN HEAT FINAL INSPECTION PHASE ONE COMPLETE 1 FIREPLACE IN LOBBY. THIS CONTRACTOR MAY HAVE THE FIRE PITS ON PHASE 2 AS WELL. | JON | JON | | H= | P | 6675056 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/17/2020 | M I101-A G2 NORTH RBD PLAN PAGE 758 ON THE SHARED PLAN HIGH LIGHTED IN RED. NSPECTED UNDERGROUND OUTSIDE AIR DUCT FOR LEVEL G-2 ELEVATOR 1 LOBBY AND INSPECTED DUCT FAN AND HEAT STRIP INSIDE INTO LOBBY, NEED FLEX AND DIFFUSER INSTALLED AND CALLED FOR INSPECTION WHEN READY. | JON | JON | | HD | P | 6674902 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/15/2020 | PARTIAL LIST FOR INSPECTION REQUIREMENTS BUT NOT LIMITED TO THE FOLLOWING: ALSO SEE HEAT FINAL NOTES FROM TODAY. INSPECTION FOR TRASH ROOM FIRE DAMPER. DAMPER RETAINING ANGLES ARE NOT COVERING STRUCTURE BY 1 INCH PER DAMPER INSTRUCTIONS. THERE SHOULD BE NO VISIBLE OPENINGS, CRACKS OR BREECHES AROUND DAMPER AND RETAINING ANGLES. OK TO INSTALL DAMPER BUT NOT THE LOUVER. NEED TO SEE ANNULAR SPACE AROUND DAMPER IN THE SLEEVE. ALSO NEED TO EXPOSE BOILER VENTING FOR INSPECTION ON G1 BEFORE INSPECTION IS REQUESTED WITH ALL INSTRUCTIONS FOR COMBUSTION BLOWERS AND BOILER INSTRUCTIONS AVAILABLE. NEED APPROVED RFI FROM ENGINEER FOR DUCT SIZE, LOUVER SIZE AND FIRE DAMPER SIZE CHANGES FOR GARAGE EXHAUST FAN G2 IN TRASH ROOM. NEED TO FINISH TRASH ROOM EXHAUST FAN. WAITING FOR PICTURES ON UNDERGROUND EXHAUST DUCT AT NORTH END OF BUILDING. ONCE THESE PICTURES ARE SENT OR ATTACHED TO AN INSPECTION REQUEST AN ENTRY WILL BE ADDED TO INSPECTION HISTORY. | JON | JON | | HD | P | 6674106 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/15/2020 | FRONT OFFICE AREA 2ND FLOOR, 3RD FLOOR, 4TH FLOOR 5TH FLOOR PHASE ONE COMPLETE EXCLUDING ALL MEZZANINE UNITS ALONG WITH THE 15,35 AND 27 NUMBERED APARTMENTS STACKED 2ND THROUGH 4TH FLOORS. MUST HAVE RETURN AIR PLENUM ISOLATED FROM WATER HEATER CLOSETS IN THESE UNITS. STILL NEED TO INSPECTIONS ON PARKING GARAGE EXHAUST FANS, CO SENSORS, TRASH ROOM, BOILER ROOMS AND BOILER VENTING IN GARAGE LEVEL ONE. TRANSFORMER ROOM, DOG WASH, NEED VENT INSPECTIONS ON GENERATOR ROOM UNIT HEATER AND VENT WITH GENERATOR INSPECTION WITH INSTRUCTIONS. NEED RFI'S FOR OFFICE AREA FURNACES SWITCHED TO CONCORD BRAND FURNACES AND UNIT HEATER BRAND CHANGE TO REZNOR. NEED ROOF INSPECTION. NEED START UP DOCUMENTATION FROM GENERAC TO VERIFY THE GENERATOR MEETS OPERATION PARAMETERS DUE TO DUCT SIZE CHANGES. NEED AIR BALANCE REPORT. DID DISCUSS WITH AARON A ENGINEER STAMPED BALANCE REPORT COULD SAVE TIME FOR COMPLETION OF HEAT FINAL WHEN READY. NEED ALL OF PHASE 2 INSPECTIONS WHEN READY | JON | JON | | H= | P | 6674105 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 08/15/2020 | NO TRANSFER GRILL FOR 205 WATER HEATER CLOSET. UNIT 231 AND 245 T&P TO BE SECURED OVER PAN AND CONDENSATE DRAIN IS NOT RUN TO FLOOR DRAIN… UNITS 215 AND 235 ISOLATE WATER HEATER CLOSET FROM RETURN PLENUM. THIS IS THE SAME FOR 327,427. ALSO NEED 315.415, 335 AND 435. STILL NEED ALL MEZZANINE UNITS 5TH FLOOR | JON | JON | | H= | P | 6674104 |
BRUCE MECHANICAL OF COLORADO, INC | HD | T | 08/14/2020 | PAID (REC#1704672) AFTER-HOURS INSPECTION: $200 From: TERRI 8/15 sat | TERRI | TERRI | | HD | T | 6673740 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 08/12/2020 | ALL WATER HEATER CSST GAS LINES ARE NOW TESTED AND COMPLETE WITH 10 LB TEST | JON | JON | | HI | P | 6670827 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/12/2020 | 513 HVAC COMPLETE. 5TH, 4TH AND 3RD FLOOR COMM ROOMS, TRASH ROOMS, JANITOR CLOSETS AND RETURN AIR FIRE DAMPERS COMPLETE. NEED TO MAKE SURE ALL I-503 DAMPERS HAVE ACCESS TO RESET FUSIBLE LINKS. | JON | JON | | H= | P | 6670829 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 08/11/2020 | 1ST FLOOR CSST PRESSURE TESTS OK FOR UNITS #102 THROUGH #110 | BILLS | BILLS | | HI | P | 6668823 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 08/11/2020 | 2ND FLOOR NORTH CORRIDOR GAS FINAL WATER HEATERS COMPLETE AT UNITS #201 THROUGH #213 | BILLS | BILLS | | H= | P | 6668822 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 08/06/2020 | CORRIDORS ONLY 2ND THROUGH 5TH FLOORS SUPPLY DIFFUSERS. STILL NEED COM ROOMS, TRASH ROOMS, JANITOR ROOMS AND ALL RETURN AIR DAMPERS ALL FLOORS. WENT OVER THIS WITH NORMAN. ALL DAMPER ACCESS DOORS TO BE LABELED. | JON | JON | | H= | P | 6664433 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/05/2020 | 8-5-20 JON B SEE BLUE BEAM PAGES 762 AND 763 FOR GREEN HIGH LIGHTS AT CORRIDOR DUCTS ALL COMPLETE WITH DIFFUSERS. | JON | JON | | HD | P | 6662679 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 07/29/2020 | INSPECTED THREE BBQ STUBS ON POOL DECK, NEED TO SEE PRESSURE TEST ON ALL THE BBQ PIPING WHEN READY. 10 LB ON CSST PIPING OK FOR 2ND FLOOR UNITS 226,228,230,232,234,236,251,243,255,247 and 249 | JON | JON | | HI | P | 6654964 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 07/29/2020 | INSPECTED ALL OF THIRD FLOOR APARTMENTS. WILL NEED TO GO BACK AND CHECK FOR AUX SENSORS AND SHUTDOWN RELAYS FOR THIRD FLOOR. ALSO STILL NEED 315, 327 AND 335 TO MAKE SURE RETURN AIR PLENUM HAS BEEN ISOLATED FROM WATER HEATER CLOSETS. | JON | JON | | H= | P | 6655046 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 07/29/2020 | 3RD FLOOR GAS FINAL WATER HEATERS COMPLETE EXCEPT FOR 315, 327 AND 335 AS THESE CLOSETS ARE CONNECTED TO THE RETURN AIR PLENUM WHICH NEEDS CORRECTED ON ALL THESE UNITS ON ALL FLOORS. | JON | JON | | H= | P | 6655042 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 07/28/2020 | CSST 10 TESTS OK FOR UNITS- 216,218,219,220,221,223,224,225,227,229,231,233,235,237, and 239 | JON | JON | | HI | P | 6653321 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 07/28/2020 | CONSULTED ON SNOW MELT FOR HEATED POOL DECK ABOVE PODIUM. THIS MAY NEED DESIGNED BY AN ENGINEER. PIPE SIZING, RADIANT PANEL LOCATIONS, ETC. WILL NEED ONE PAVER REMOVED AT EACH RADIANT PANEL TO SEE PIPING CONNECTIONS AND MANIFOLDS WITH PRESSURE TEST ADEQUATE FOR THE SYSTEM. RADIANT PANELS ARE ONLY RATED AT 37 PSI MAX PRESSURE. | JON | JON | | HSP | P | 6653320 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 07/24/2020 | GAS PIPING 10LB TEST ON CSST IN UNITS 201, 202, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, 213, 215, 217. OK | JON | JON | | HSP | P | 6650085 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 07/22/2020 | TEST AND VISUAL INSPECTION OK FOR 4 LINE SETS AND 4 CONDENSERS IN PARKING GARAGE. | JON | JON | | HRP | P | 6646910 |
BRUCE MECHANICAL OF COLORADO, INC | HD | R | 07/21/2020 | LINE SETS ARE NOT ON TEST. PLEASE RECALL INSPECTION | JON | JON | | HD | R | 6644185 |
FIREPLACE WAREHOUSE | HV | P | 07/13/2020 | NEED TO SEE PICTURES OF FRAMING AROUND UNIT. NEED TO MAKE SURE GAS SHUTOFF VALVES HAVE ACCESS, ONE IN WALL AND ONE UNDER UNIT. DID NOT SEE ANY INFORMATION FOR VENT ATTACHMENT TO UNIT. REST OK | JON | JON | | HV | P | 6635659 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/10/2020 | WORKED WITH AARON FROM CSI FOR FIRE DAMPER INSTALLATION AT TRASH ROOM. IT WAS DISCOVERED WE MAY HAVE THE WRONG FIRE DAMPER FOR THIS APPLICATION. IT APPEARS THIS IS A STATIC ONLY DAMPER THAT MAY HAVE TO OPERATE I N A DYNAMIC INSTALLATION. AARON WILL FOLLOW UP WITH BRUCE MECHANICAL AND THE MECHANICAL ENGINEER. | JON | JON | | HSP | P | 6634157 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 07/09/2020 | SNOW MELT BOILER VENT, NEED TO ENSURE PROPER CLEARANCE FOR ONE PIPE TERMINATION UNDER DECK WITH OPERABLE SLIDING DOOR. NEEDS PLAN SPLICE FOR CHANGING LOCATION OF BOILER AND INSTALLING A DIFFERENT BRAND OF BOILER. SCHEDULE PAGE M-002 AND M-102A | JON | JON | | HV | P | 6632804 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 07/07/2020 | 4TH FLOOR HVAC FINALS ALL APARTMENTS OK EXCEPT 415, 435, 427. RETURN AIR PLENUM CANNOT OPEN INTO WATER HEATER CLOSETS. ALSO NEED TO KEEP VENTILATION FOR GAS REGULATORS IN THESE SAME CLOSETS. | JON | JON | | H= | P | 6629650 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 07/01/2020 | UNIT 116 SUPPLY AIR ROUGH DUCT OK WHERE IT PENETRATES WALL INTO THE PARKING GARAGE AND THEN RE-ENTERS THROUGH THE SAME WALL BACK INTO THE UNIT FROM THE PARKING GARAGE. BUILDING INSPECTOR WILL PERFORM INSPECTION ON NEW RATED CONSTRUCTION TO CONCEAL THIS DUCT FOR UNIT 116. NEED RFI FOR ENGINEER FIX FOR RETURN PLENUM 118 AND 122. DUCT INSPECTION OK PENDING RFI FOR 118 AND 122. ROUGH DUCT OK IN CLUBHOUSE FOR 2 RTU'S AND 3 EXHAUST FANS. WILL NEED TO MAKE SURE ROOF TOP ACCESS LADDER CAN BE POSITIONED AT AN AREA THAT IS LESS THAN 16 FEET, OR A PERMANENT LADDER COULD BE REQUIRED. | JON | JON | | HD | P | 6624888 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/01/2020 | TRASH ROOM FIRE DAMPER INSTALLED AND CONCEALED BEFORE INSPECTION. WENT OVER INSPECTION PROCEDURE FOR FIRE DAMPERS WITH JEROME AND AARON. APPEARS DAMPER WILL HAVE TO BE REINSTALLED AND LOWERED DOWN TO GET A CONTINUOUS STRUCTURE ACROSS THE TOP OF THE DAMPER. THIS MAY REQUIRE ENGINEER TO GET INVOLVED TO MAKE SURE THE INTENT OF THE DAMPER INSTRUCTIONS ARE MET. | JON | JON | | HSP | P | 6627942 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 06/30/2020 | WATER HEATER AND GAS FINAL FOR UNITS 502, 513, 518, 523, 525, 527, 536, 537, 549 | JON | JON | | H= | P | 6622903 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 06/30/2020 | 10 LB TEST OK ON CSST IN WATER HEATER CLOSETS AT UNITS 520, 525, 527, 536, 537, 549 | JON | JON | | HSP | P | 6622895 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/26/2020 | 5TH FLOOR: UNITS #513 AND #537-- SLEEVE EXTENSIONS AND ANGLES OK AT THE I-503 DAMPERS OK. UNIT #518--DUCT IN LOWER LEVEL SOFFIT OK. UNIT #523-- SUPPLY AIR PIPE FROM UPPER LEVEL SOFFIT TO LOWER LEVEL BEDROOM OK | BILLS | BILLS | | HD | P | 6618906 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/25/2020 | STILL NEED TO SEE 513 AND 537 DUCT WORK INSTALLED BELOW I-503 DAMPERS. ANGLES OK AT 537... FOR 513 TALKED TO JEFF AT BRUCE HE NEEDS TO SHOW NEXT INSPECTOR THE SCREWS IN THE SLEEVE EXTENSION AND PICTURES OF DAMPER ANGLES AT BOTTOM SIDE OF DAMPER AT UNIT 513. 518 ROUGH DUCT COMPLETE. 502, 525, 536 I-503 DAMPERS AND DUCT COMPLETE. , SEE FIRE DAMPER ACCESS DOOR LABELING BEFORE FINAL. MAY ALSO NEED TO DEMONSTRATE ACCESS TO FUSIBLE LINK RESET BEFORE FINAL. | JON | JON | | HD | P | 6618259 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 06/25/2020 | CSST GAS PIPING FOR UNITS 437, 436, 449 OK 10 LB TEST | JON | JON | | HI | P | 6618257 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 06/24/2020 | 10 LB TEST COMPLETE ON CSST PIPING FOR WATER HEATERS AT 418, 420, 423, 425, 427 | JON | JON | | HI | P | 6616539 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 06/24/2020 | 4TH FLOOR WATER HEATER AND GAS PIPING OK AT ALL UNITS EXCEPT UNITS 415, 427 AND 435 WHICH NEED THE TRANSFER AIR FOR VENT LIMITERS SEALED OFF FROM RETURN AIR PLENUM WITH A NEW TRANSFER GRILL INSTALLED PER RFI.. | JON | JON | | H= | P | 6616533 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/23/2020 | NEED TO RECALL THE INSPECTIONS FOR THE I-503 DAMPER INSTALLATIONS. THE OPENINGS ARE NOT MUDDED AND TAPED PER PRIOR DISCUSSIONS | JON | JON | | HD | P | 6614588 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/18/2020 | 6-18-20 JON B M SHEET 100B BLUIE BEAM PAGE 757 CIRCULATION FANS CF-7 AND TRANSFER FAN 3 INSTALLED GREEN HIGH LIGHT PAGE M-101 A BB PAGE 761 EPH-4, EPH-6, CF- 6, EPH 5, INSTALLED. GREEN HIGH LIGHT. M-SHEET 102A BB PAGE 826 CF-1 AND CF-8, EPH-1 AND EPH- 3 INSTALLED GREEN HIGH LIGHTS. DISUSSED WITH AARON NO HEATER INSTALLED OR SHOWN ON PLNS FOR ABOVE CEILING IN M-102 B BLUE BEAM PAGE 827. AARON HAS RFI TO ENGINEER. ALSO ON PAGE M-102 B ENGINEER TO ADDRESS CIRCULATION FAN IN ROOM WITH NO SIZES SHOWN FOR OPENINGS IN WALLS FROM PARKING GARAGE FOR CIRCULATION FAN CF-3 | JON | JON | | HD | P | 6610173 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/18/2020 | 6-18-20 JON B M SHEET 100B BLUIE BEAM PAGE 757 CIRCULATION FANS CF-7 AND TRANSFER FAN 3 INSTALLED GREEN HIGH LIGHT PAGE M-101 A BB PAGE 761 EPH-4, EPH-6, CF- 6, EPH 5, INSTALLED. GREEN HIGH LIGHT. M-SHEET 102A BB PAGE 826 CF-1 AND CF-8, EPH-1 AND EPH- 3 INSTALLED GREEN HIGH LIGHTS. DISUSSED WITH AARON NO HEATER INSTALLED OR SHOWN ON PLNS FOR ABOVE CEILING IN M-102 B BLUE BEAM PAGE 827. AARON HAS RFI TO ENGINEER. ALSO ON PAGE M-102 B ENGINEER TO ADDRESS CIRCULATION FAN IN ROOM WITH NO SIZES SHOWN FOR OPENINGS IN WALLS FROM PARKING GARAGE FOR CIRCULATION FAN CF-3 | JON | JON | | HD | P | 6610174 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 06/18/2020 | 10 LB GAS TEST ON CSST PIPING IN APARTMENTS 402, 412, 413 COMPLETE | JON | JON | | HI | P | 6610106 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/16/2020 | DAMPER FRMING OK AT MEZZANINE UNIT 537. ALL I-503 DAMPERS ARE FRAMED NOW AND OK. INSPECTED COMPLETED I-503 FIRE DAMPER AT UNITS 502 AND 536, THESE 2 UNITS ARE NOW READY TO INSTALL BOTTOM RETAINING ANGLE AT DAMPERS AND VERIFY ACCESS DOORS IN DRYWALL FOR DAMPERS AND ENSURE THE FUSIBLE LINKS CAN BE RESET. . ALSO INSPECTED WALK UP UNITS 122 AND 118 AND FOUND THERE IS AN ISSUE WITH THE RETURN AIR PATH. THE RETURN AIR PATH CANNOT BE THROUGH THE THE LAUNDRY ROOM TUNING THE LAUNDRY ROOM INTO A RETURN AIR PLENUM, ENGINEER TO ADDRESS THIS ISSUE. UNIT 120 IS OK STILL NEED 116 AND CORRECTIONS WITH 122 AND 118. ALSO INSPECTED SUPPLY DUCT, SUPPLY FAN IN PARKING GARAGE FEEDING ELEVATOR LOBBY IN GARAGE. | JON | JON | | HD | P | 6606918 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 06/16/2020 | HVAC HEATING FINAL COMPLETE FOR ALL UNITS ON 5TH FLOOR EXCEPT MEZZANINE UNITS. ALSO NEED TO ADDRESS 535, 515 WHICH NEED PROPER VENTILATION FOR VENT LIMITING REGULATORS IN THESE 2 CLOSETS. CANNOT CONNECT TO RETURN AIR PLENUMS. WENT OVER THIS WITH KYLE FROM CSI. THIS WILL BE THE SAME FOR ALL THE 35 AND 15 STACKS. | JON | JON | | H= | P | 6606882 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 06/16/2020 | GAS AND WATER HEATING FINAL COMPLETE FOR ALL UNITS ON 5TH FLOOR EXCEPT MEZZANINE UNITS. ALSO NEED TO ADDRESS 535, 515 WHICH NEED PROPER VENTILATION FOR VENT LIMITING REGULATORS IN THESE 2 CLOSETS. CANNOT CONNECT TO RETURN AIR PLENUMS. WENT OVER THIS WITH KYLE FROM CSI. THIS WILL BE THE SAME FOR ALL THE 35 AND 15 STACKS. | JON | JON | | H= | P | 6606881 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 06/12/2020 | 5TH FLOOR: UNIT #535-- PRESSURE TEST FOR WATER HEATER CSST OK | BILLS | BILLS | | HI | P | 6603046 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/11/2020 | REVIEWED PICTURE FOR I-503 DAMPER FRAMING OK FOR UNIT 536 AND OK. SEE AGAIN WHEN DUCTS AND BREAK AWAY ARE COMPLETE AND BEFORE COVER. CHECK DAMPER SLEEVE SUPPLEMENT EXTENSION FROM BOTTOM SIDE BEFORE RETAINING ANGLE IS INSTALLED. | JON | JON | | HD | P | 6601225 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/10/2020 | UNITS 102, 104, 106, 108, 110, 112 COMPLETE FOR ROUGH DUCT. STILL NEED LOWER 114. DAMPER FRAMING OK FOR THE I-503 LISTING IN UNIT 502. | JON | JON | | HD | P | 6600394 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/09/2020 | UNITS 529 AND 520 COMPLETE ON HVAC. | JON | JON | | HD | P | 6598758 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 06/08/2020 | BUILDING INSPECTOR AND MECHANICAL INSPECTOR CONSULTED WITH AARON, JOHN, KYLE FROM CSI FOR THE I503 UL LISTED FLOOR ASSEMBLE FOR THE FLOOR DAMPER IN UNIT 502. RECALL INSPECTION FOR THIS ONE OPENING BEFORE PRECEDING ON TO THE OTHER 4 FLOOR DAMPERS ARE FRAMED TO ENSURE THAT THE INSTALLATION COMPLIES WITH THE INSTRUCTIONS. | JON | JON | | HSP | P | 6597429 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 06/05/2020 | CONSULTATION INSPECTION FOR THE I503 LISTING FOR A FIRE DAMPER LOCATED IN A HORIZONTAL WOOD ASSEMBLY. RECEIVED DAMPER AND I503 INSTRUCTIONS AND DOCUMENTS. REVIEWING THIS WITH BUILDING INSPECTOR. STRUCTURE FRAMING WAS CONCEALED AND THE METAL STUD FRAMING IS ALREADY COMPLETE. CONTRACTOR WILL CALL INSPECTION FOR MONDAY FOR MECHANICAL AND BUILDING TO MEET ON SITE TO REVIEW ONE THAT HAS NOT BE STARTED YET TO MAKE SURE THIS ALL COMPLIES WITH INSTRUCTIONS. | JON | JON | | HSP | P | 6595411 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/05/2020 | ROUGH DUCT OK FOR LOWER LEVEL FAN COILS AT WALK UP UNITS 110-112-114 ONLY. STILL NEED CEILING FRAMING COMPLETED AT ALL FAN COILS FOR DRAIN INSPECTIONS BEFORE DRYWALL. SEE HSP FOR I503 NOTES | JON | JON | | HD | P | 6595378 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | C | 06/04/2020 | 5TH FLOOR: UNITS #502, 513, AND 516-- PRESSURE TEST FOR CSST AT WATER HEATER CLOSETS OK | BILLS | BILLS | | HI | C | 6593529 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 06/03/2020 | 6-3-20 JON B. UNITS 512 AND 515 2- 10 LB TEST FOR CSST FROM REGULATOR TO WATER HEATER. ALSO INSPECTED 10 LB TEST OK FOR GENERATOR GAS PIPING SEE FINAL CONNECTION AND 2" REGULATOR WHEN READY SHEET MG-102A BLUE BEAM PAGE 794 INDICATED WITH RED HIGH LIGHT | JON | JON | | HI | P | 6592709 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 06/02/2020 | WORKED WITH AARON FROM CSI AND NATHAN FOR VENT PENETRATIONS ON RATED WALL IN PARKING GARAGE. NATHAN HAS RECEIVED ENGINEERING JUDGEMENT S FOR THESE PENETRATIONS. BRUCE WILL CALL IN VENT INSPECTIONS FOR BOILERS WHEN READY | JON | JON | | HSP | P | 6591212 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/02/2020 | INSPECTION FOR LOWER FAN COIL UNITS AND DUCTS IN UNITS 102,104,106,108 ONLY. STILL NEED CEILINGS FRAMED UNDER FAN COILS, STILL NEED LINE SET AND DRAIN INSPECTIONS IN ALL UNITS | JON | JON | | HD | P | 6591187 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/01/2020 | 5TH FLOOR: UNITS #518 AND $520-- SECOND LEVEL IN-SOFFIT DUCTWORK OK | BILLS | BILLS | | HD | P | 6588695 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/28/2020 | 5TH FLOOR: UNIT #527--ENGINEER TO ADDRESS CHANGE IN PIPING FROM UPPER LEVEL DUCTWORK TO MAIN LEVEL BEDROOM (TO AVOID THE I-503) CONTRACTOR TO PROCEED AT OWN CAUTION, DUCTWORK IN UPPER LEVEL SOFFIT OK. | BILLS | BILLS | | HD | P | 6585731 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 05/28/2020 | 5TH FLOOR: STILL NEED REMAINDER OF INSPECTIONS AT ALL MEZZANINE UNITS | BILLS | BILLS | | HSP | P | 6585730 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 05/21/2020 | 3RD FLOOR: UNIITS #320 AND #327: 10LB TEST FOR WATER HEATER CLOSET CSST OK. **THIS INSPECTION COMPLETES THE GAS FOR 3RD FLOOR** | BILLS | BILLS | | HI | P | 6579700 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/21/2020 | 1ST FLOOR: DAMPER ANGLES AT CORRIDOR SUPPLY AIRS OK. | BILLS | BILLS | | HD | P | 6579699 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 05/20/2020 | CONSULTED ON GENERATOR DUCTING.THERE WILL NEED TO BE A DESIGN APPROVED BY THE MANUFACTURE TO SIZE, LOCATE, DISCHARGE AND ATTACH TO THE GENERATOR. THE DISCUSSION WAS THAT WHEN THEY WERE DONE WITH THE INSTALLATION THERE WOULD BE A DOCUMENTED TESTING PAPERWORK BY THE MANUFACTURE FOR ACCEPTANCE THAT WILL NOT VOID ANY WARRANTY ON ANY OF THE EQUIPMENT. | JON | JON | | HSP | P | 6579042 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 05/20/2020 | MET WITH MATT FROM NEWCOMERS AND AARON WITH CSI. THERE WILL BE A DESIGN CHANGE FOR SNOW MELT BOILER WHICH WILL MOVE TO THE EXTERIOR OF THE BOILER ROOM ITSELF INTO THE CLOSED OFF AREA WHERE THE CONDENSERS ARE LOCATED.ADVISED THAT THE INSTALLATION INSTRUCTIONS WOULD HAVE TO BE FOLLOWED FROM THE MANUFACTURE AND THE ENGINEER WOULD SHOW THIS CHANGE ON A NEW SPLICE. THE VENT SYSTEM AND COMBUSTION AIR WOULD BE DESIGNED BY THE ENGINEER. DISCUSSED DRAINS AND ANY FREEZE PROTECTION FOR THE BOILER ITSELF, DRAINS AND VENTING MAY BE REQUIRED. ALSO NOTED THAT THE PLUMBING INSPECTOR MAY ALSO REQUIRE SOME DESIGN CHANGES ON THE PLUMBING PAGES. | JON | JON | | HSP | P | 6579037 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/20/2020 | FIRE DAMPERS FOR BOTH CORRIDOR SUPPLY FANS AT WEST SIDE WALK UP UNITS OK. JUST NEED TO SEE RETAINING ANGLES PROPER INSTALLED ON BOTH SIDES OF DAMPERS WITH NO SCREWS INTO THE STRUCTURE X2. BREAK AWAY CONNECTIONS TO ALSO BE PER INSTRUCTIONS. CONTRACTOR HAD INSTALLATION SUPPLEMENT FOR SLEEVE EXTENSIONS AND INSTRUCTIONS WERE FOLLOWED AND OK. | JON | JON | | HD | P | 6579032 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 05/19/2020 | 1ST FLOOR WALK-UP UNITS: LOWER LEVEL FAN COIL HYDRONIC TIE-INS OK AT ALL UNITS (#102 THROUGH #122). | BILLS | BILLS | | HWP | P | 6576243 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 05/18/2020 | Met with Aaron to take a look at walk up unit 116. There will be a supply air duct running into from unit 116 into the parking garage and then back into unit 116 penetrating 2 CMU fire barrier walls. This duct continues into the soffit with fire dampers shown in the soffit. We believe that the soffit might not be rated and the engineer will have to address that along with how to protect the 2 fire barrier duct penetrations. Also consulted on the generator room as the duct configuration will change for the generator radiator exhaust which will need to be re engineered to match the onsite conditions.. | JON | JON | | HSP | P | 6575761 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/18/2020 | 2ND FLOOR THROUGH 5TH FLOOR LOBBY EXHAUST AND MAKE UP AIR COMPLETE. FLOORS 2 THROUGH 4 HAVE HAD THE EXHAUST ELIMINATED FOR TRASH ROOMS. ACCESS TO DAMPERS ARE FROM INSIDE BOTH THE TELECOM AND TRASH ROOMS. | JON | JON | | HD | P | 6575684 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/14/2020 | 1ST FLOOR LOBBY CONDENSATE DRAINS ARE ROUGHED IN ABOVE ALL CEILINGS AT 4 FURNACES. NEED TO SEE ALL DRAIN TERMINATIONS AT APPROVED LOCATIONS PRIOR TO FINAL. | JON | JON | | HD | P | 6571700 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/12/2020 | 5TH FLOOR: UNIT #537- UPPER LEVEL DUCTWORK IN SOFFITS OK 1ST FLOOR: HALLWAY SUPPLY AIR DUCT DAMPER OPENING OK | BILLS | BILLS | | HD | P | 6569324 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/07/2020 | UNIT 536 UNIT MCW-1 DUCT COMPLETE IN SOFFITS AND BOTH FAN COILS ARE INSTALLED. UNIT 502 MCW-1 ALL DUCT COMPLETE IN SOFFITS STILL NEED LOWER FAN COIL INSTALLED. RECEIVED RFI AND IS IN IMAGES FOR 522 H-1A HOTEL UNIT AND OK. UNIT 549 MCW-2 LOWER SOFFITS OK AND FAN COILS OK. NEED ALL ON UPPER LEVEL WORK COMPLETED IN 549. STILL NEED THE I503 FLOOR DAMPER INSTALLED AND INSPECTED AT ALL MEZZANINE UNITS. PLEASE CALL INSPECTION FOR THE MOCK UP ON THE I503 WHEN READY. | JON | JON | | HD | P | 6564922 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 05/06/2020 | 3RD FLOOR: ALL CSST GAS INSPECTIONS AT WATER HEATER CLOSETS EXCEPT FOR UNITS #320 AND 327 OK. | BILLS | BILLS | | HI | P | 6562670 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 05/06/2020 | 5TH FLOOR: VENT CHASE IN WATER HEATER CLOSET OK TO COVER. | BILLS | BILLS | | HSP | P | 6562668 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/06/2020 | 5TH FLOOR: UNIT #549-LOWER LEVEL BELOW PRE-ROCK DUCT IN SOFFITS OK TO COVER. UNIT #522- OK, UNITS #536 AND #502- MISSING RETURN AIR PATHWAYS, MATERIALS IN RETURN AIR PLENUMS NOT RATED FOR THE 25/50 SMOKE AND FLAME SPREAD, NO DRYWALL OK'D . 1ST FLOOR: LOBBY FIRE DAMPER STILL NOT CORRECT, CONTRACTOR WORKING ON SUPPLEMENT INSTRUCTIONS OR CHANGE OF DAMPER. | BILLS | BILLS | | HD | P | 6562664 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 05/05/2020 | 3RD FLOOR: EAST CORRIDOR--10LB TEST OK FOR CSST AT WATER HEATERS FOR UNITS #314, 316, 317, 318, 319, 321, 322, 323, 325, 329, 331, 333, 335, 337, AND 339 | BILLS | BILLS | | HI | P | 6560990 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/01/2020 | INSPECTED FRONT LOBBY AREA FOR THE 4 FURNACE SYSTEMS. DRAINS NEED COMPLETED BEFORE COVER, ACCESS OPENINGS IN HARD LIDS TO BE MOVED TO PROPER LOCATIONS AND ONE ADDED FOR FIRE DAMPER AT CORRIDOR WALL. WENT OVER THIS WITH JOHN FROM CSI. NEED TO WALK LOBBY AREA AGAIN BEFORE COVER. ALSO DRYWALL IS BEING TAKEN DOWN AT YOGA ROOM BECAUSE OF MORE ELECTRICAL WORK, WHILE DRYWALL IS REMOVED RECALL INSPECTION FOR THAT FURNACE. CHECK RETURN PLENUMS AT ALL 11 WALK UP UNITS UPPER MEZZANINES ONLY. ALL POSITIVE PRESSURE EXHAUST DUCTS AND PVC PIPING THAT IS REQUIRED BY CODE TO BE PROTECTED IS COMPLETE AT ALL 11 UNITS. UPPER MEZZANINE RETURN PLENUMS, WILL CHECK FOR AUX DRAIN PROVISIONS AT FINAL. STILL NEED ALL LOWER LEVEL FAN COIL AND RETURN PLENUMS INSPECTIONS COMPLETED WHEN READY. | JON | JON | | HD | P | 6559075 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 04/30/2020 | 1ST FLOOR WALK-UP UNITS: PIPE INSULATION IN RETURN AIR PLENUMS OK AT ALL WALK-UP UNITS EXCEPT FOR #102 (SEAL DRYWALLED CHASE TO BOTTOM OF PODIUM), #112 (COMPLETE INSULATION ON LOWER LEVEL AT HILTI FIRESTOP), #118 (REPAIR TORN INSULATION AT UPPER LEVEL) | BILLS | BILLS | | HSP | P | 6556625 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/30/2020 | 3RD FLOOR: NORTH CORRIDOR, UNITS #301 THROUGH #315: 10 LB TEST ON CSST IN WATER HEATER CLOSETS OK | BILLS | BILLS | | HI | P | 6556606 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 04/27/2020 | **5TH FLOOR: UNIT #520--WILL REQUIRE PLAN SPLICE SHOWING NEW WATER HEATER LOCATION ALONG WITH REMOVAL PANEL, SERVICE PANEL, GAS REGULATOR VENTILATION, AND GAS LAYOUT CHANGES. INSTALL WATER HEATER AND SERVICE/CLEARANCE OPENINGS AND RE-CALL INSPECTION.** 5TH FLOOR: FAN COIL HYDRONIC TIE-INS OK AT UNITS #502 LOWER, 513 UPPER AND LOWER, 518 UPPER AND LOWER, 523 LOWER, 525 UPPER, 520 UPPER AND LOWER, 527 UPPER, 536 UPPER AND LOWER, 537 UPPER AND LOWER, 549 UPPER AND LOWER. | BILLS | BILLS | | HWP | P | 6552333 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/22/2020 | 1ST FLOOR: LOBBY DAMPER NEEDS TO BE RE-VISITED FOR RETAINAGE ANGLES AND BREAK AWAY FITTINGS AS 1 SIDED RETAINAGE IS NOT ALLOWED. CONSULTATION ON ALL WALK UP UNITS INSPECTION PRECESS FOR UPPER AND LOWER FAN COIL UNITS (PIPE INSULATION, DRYER EXHAUST ISOLATION, 25/50 SMOKE AND FLAME SPREAD, ETC,,) | BILLS | BILLS | | HD | P | 6548063 |
FIREPLACE WAREHOUSE | HV | P | 04/21/2020 | ABOVE CEILING ONLY FIREPLACE VENTING OK IN CHASE (SEPARATION FROM RETURN AIR PLENUM), FIREPLACE TERMINATION OK. FIREPLACE NOT INSTALLED AT THIS TIME. **ATTN: WILL REQUIRE LETTER FROM FIREPLACE MANUFACTURER ALLOWING SELKIRK VENTING.** | BILLS | BILLS | | HV | P | 6546416 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 04/21/2020 | WALK-UP UNITS FAN COILS ARE BEING CONCEALED WITHOUT INSPECTIONS. UNCOVER AND CALL FOR INSPECTION. | BILLS | BILLS | | HSP | P | 6546410 |
FIREPLACE WAREHOUSE | HSP | P | 04/21/2020 | CONVERSATION WITH JOHN FROM CSI ON PLACEMENT OF ACCESS PANEL FOR LOBBY FIREPLACE GAS REGULATOR. | BILLS | BILLS | | HSP | P | 6546399 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/17/2020 | DRYER DUCT ONLY FOR UNITS 114 AND 110 COMPLETE. | JON | JON | | HD | P | 6544507 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/17/2020 | 10 LB TEST OK ON CSST FOR WATER HEATERS CLOSETS AT UNITS 429,431,432,434,443,445 and 447 | JON | JON | | HI | P | 6544480 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 04/16/2020 | 4TH FLOOR: UNIT #436: HYDRONIC TIE-IN TO FAN COIL OK. | BILLS | BILLS | | HWP | P | 6542509 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/16/2020 | 4TH FLOOR: 10 LB TEST OK FOR WATER HEATER CLOSET CSST AT UNITS #416, 417, 419, 421, 433, 435, 439, 426, 428, 430, AND 441. | BILLS | BILLS | | HI | P | 6542500 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/06/2020 | 1ST FLOOR LOBBY: DAMPER AT HALLWAY-- NORTH SIDE ANGLES AND ANNULAR SPACE OK. | BILLS | BILLS | | HD | P | 6531825 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 04/06/2020 | 4TH FLOOR: UNITS #402, 424, AND 427. 3RD FLOOR: UNITS #320 AND 327. 2ND FLOOR: UNIT #227. HYDRONIC TIE-INS AT FAN COILS ALL OK | BILLS | BILLS | | HWP | P | 6531819 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 03/26/2020 | 1ST FLOOR NORTH: PRESSURE TEST OK AT LOBBY FIREPLACE LINE. INSTALLED AS PER PLAN. 4TH FLOOR: PRESSURE TESTS OK FOR CSST AT UNITS #401, 403, 404, 405, 406, 407, 408, 409, 410, 411, AND 415. | BILLS | BILLS | | HI | P | 6522473 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 03/26/2020 | DAMPER FRAMING AT LOBBY/HALLWAY OK. | BILLS | BILLS | | HD | P | 6522466 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 03/25/2020 | IMAGES RECEIVED OF BELOW PRE-ROCK DAMPER ANGLES AT UNITS #227, 320, 327, AND 427 | BILLS | BILLS | | HD | P | 6520555 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 03/24/2020 | 4TH FLOOR: UNIT #427-- SUPPLY AIR DAMPER TO DRYWALL CLEARANCES OK 3RD FLOOR: UNITS #320 AND #327--SUPPLY AIR DAMPER TO DRYWALL CLEARANCES OK 2ND FLOOR: UNIT #227--SUPPLY AIR DAMPER TO DRYWALL CLEARANCES OK | BILLS | BILLS | | HD | P | 6519274 |
FIREPLACE WAREHOUSE | HSP | P | 03/19/2020 | CONSULTATION WITH FIREPLACE CONTRACTOR ON LOBBY FIREPLACE VENTING. AT THIS TIME VENTING WILL NEED TO BE ISOLATED FROM THE RETURN AIR PLENUM, CONTRACTOR TO RESEARCH SPECIAL GAS VENTING. VERIFY ALL LISTINGS AND APPROVALS ARE IN INSTALLATION INSTRUCTIONS. | BILLS | BILLS | | HSP | P | 6515751 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 03/18/2020 | 1ST FLOOR: ABOVE CEILING DUCT OK FOR LOBBY AREA. STILL NEED TO SEE FLEX, DIFFUSERS, AND ACCESS DOORS. 2ND FLOOR: COMM/TRASH ROOMS DAMPER ANGLES OK. 4TH FLOOR: UNITS #423 AND #449: ABOVE CEILING BELOW PRE-ROCK: NAIL PROTECTION, SUPPORTS, CONDENSATE, AND VISUAL INSPECTION OK. 5TH FLOOR: UNIT #522: WILL ACCEPT ENGINEERS STAMPED RFI FOR REGISTER CHANGES AS LONG AS BUILDING DOES NOT REQUIRE A PLAN SPLICE | BILLS | BILLS | | HD | P | 6514443 |
BRUCE MECHANICAL OF COLORADO, INC | HV | P | 03/18/2020 | FURNACE VENTING OK AT FURNACES #1, #2, #3, AND #4 (LOBBY AREA) | BILLS | BILLS | | HV | P | 6514430 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/18/2020 | FIELD CONSULTATION WITH CONTRACTOR AND SITE SUPERINTENDENT AARON ON WALL FRAMING FOR FIRE DAMPER AT LOBBY. | BILLS | BILLS | | HSP | P | 6514425 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 03/17/2020 | 4TH FLOOR: UNITS #402 AND #425: BELOW DRYWALL FIRE DAMPER ANGLES OK AT PLENUM DAMPERS AND AT SECONDARY SUPPLY AIR DAMPERS ADDED DUE TO STRUCTURAL MEMBERS. | BILLS | BILLS | | HD | P | 6512798 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/12/2020 | CONSULTATION WITH CONTRACTOR ON LOBBY AREA FURNACE ACCESS DOORS, FURNACE VENTING (NEED INSTALLATION INSTRUCTIONS ON SITE), AND CORRIDOR DUCTING (CONTRACTOR WILL BE SUPPLYING AN AMM FOR DUCT ROUTING THROUGH MEZZANINE CLOSETS). | BILLS | BILLS | | HSP | P | 6508630 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 03/10/2020 | 5TH FLOOR: UNITS #502 AND #536: RE-LOCATED 2ND LEVEL FAN COIL CONDENSATE LINES OK. (NOW TERMINATE UNDER 1ST LEVEL SINK). 4TH FLOOR: UNITS #402 AND #425 DRYWALL TO DAMPER CLEARANCES OK. OK TO INSTALL DAMPER ANGLES. UNIT #427: ABOVE CEILING DUCTING, BATH AND DRYER EXHAUST OK. 3RD FLOOR: UNIT #327: ABOVE CEILING DUCTING, BATH AND DRYER EXHAUST OK. 1ST FLOOR WALK-UP UNITS: ABOVE CEILING DUCTING, BATH AND DRYER EXHAUST OK AT UNITS #102 AND #104. UNIT #106 AND #108: NEED TO SUPPORT CONDENSATE DRAIN LINES FROM FAN COIL TO WALL, ISOLATE SUPPLY FLEX FROM SPRINKLER LINES. UNIT #110: NOT READY (DRYER EXHAUST). UNIT #112: RE-ATTACH SUPPLY AIR FLEX SUPPORT AT 3RD SUPPLY FROM THE SOUTH. | BILLS | BILLS | | HD | P | 6505642 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/06/2020 | COMPLIMENTARY VISIT TO SITE TO CHECK STATUS AS NO INSPECTIONS HAVE BEEN REQUESTED SINCE 2/24/2020. BRIEF CONVERSATION WITH SITE SUPERINTENDENT AARON. REGULAR INSPECTIONS SHOULD RESUME ON THE FOLLOWING WEEK. | BILLS | BILLS | | HSP | P | 6502423 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/02/2020 | APPROVED SUBMITTAL FOR FURNACE BRAND CHANGE NOW IN IMAGES. | JON | JON | | HSP | P | 6497441 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 02/28/2020 | HEATING WATER PIPING CONNECTIONS TO FAN COILS IN UNITS 412,413,418,420,423, 437 AND 439 ARE COMPLETE. STILL NEED FAN COIL DRAINS, LINE SETS AND DUCT CONNECTIONS WHEN READY BY OTHER CONTRACTOR. | JON | JON | | HWP | P | 6496501 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 02/26/2020 | UPDATED NOTES ON 2-27-20 JB. CONSULTED ON 402 AND 436 FOR REMOVING FIRE DAMPER COMPONENTS FROM LOCATIONS WHERE ASSEMBLIES ARE NOT RATED. THIS PROCEDURE WILL WORK FOR ALL LOCATIONS WHERE RADIATION DAMPERS ARE INSTALLED IN NO RATED AREA'S. | JON | JON | | HD | P | 6493810 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 02/24/2020 | PRESSURE TESTS, NAIL PROTECTION, SUPPORTS, AND VISUAL INSPECTION OK AT UNITS #327 AND #427 | BILLS | BILLS | | HWP | P | 6490137 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 02/24/2020 | WATER HEATER VENTING AT UNITS #327, 427, 513, AND 537 OK | BILLS | BILLS | | HV | P | 6490136 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 02/24/2020 | 4TH FLOOR: PLENUM DAMPER ANGLES AT UNITS #413 AND #449 OK. DAMPER ANGLES AT COMM/TRASH ROOMS OK. 5TH FLOOR: DAMPER ANGLES AT COMM/TRASH ROOMS OK. | BILLS | BILLS | | HD | P | 6490133 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 02/20/2020 | 4TH FLOOR: CORRECTIONS MADE TO DAMPERS AT UNITS #402, 425, AND 437. SIDE-WALL SUPPLY AIR DAMPER BOOTS TO BE REPLACED WITH STANDARD REGISTER BOOTS. UNIT #413: SUPPLY PLENUM DAMPER ANGLES (BELOW PRE-ROCK) OK. COMM/TRASH ROOM SQUARE DAMPER ANGLES OK. COMM ROOM ROUND DAMPERS ANGLES TO BE FASTENED TO WALL AS PER INSTALLATION INSTRUCTIONS. **ATTN: SUPPLY AIR DAMPER BOOTS AT WALK-UP UNITS TO BE REPLACED WITH STANDARD REGISTER BOOTS WHERE NOT INSTALLED IN A RATED ASSEMBLY** | BILLS | BILLS | | HD | P | 6487201 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 02/19/2020 | 4TH FLOOR: PLENUM DAMPER/DRYWALL SPACING OK AT UNITS #412, 413, 420, 423, AND 437. 4TH FLOOR: ADDED DAMPERS AT UNITS #402, 427,AND 436 NEED TO BE LOWERED TO CORRECT HEIGHT IN RATED ASSEMBLY. | BILLS | BILLS | | HD | P | 6485914 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 02/19/2020 | 5TH FLOOR: 10LB TESTS OK FOR CSST AT WATER HEATER CLOSETS AT UNITS #526, 528, 530, 532, 539, 541, 542, 543, 545, AND 547. 4TH FLOOR: 10LB TEST OK FOR WATER HEATER LINE AT UNIT #427. 3RD FLOOR: 10LB TEST OK FOR WATER HEATER LINE AT UNIT #427. | BILLS | BILLS | | HI | P | 6485891 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 02/19/2020 | 5TH FLOOR: NEW WATER HEATER VENTING INSTALLED FOR MEZZANINE UNITS OK FOR LENGTH. STILL NEED TO VERIFY ALL SUPPORTS AND NAIL PROTECTION. | BILLS | BILLS | | HV | P | 6485879 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 02/14/2020 | UNITS- 517,519,521,524,529,531 and 533 10 LB TEST ON CSST OK | JON | JON | | HI | P | 6482750 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 02/13/2020 | 2ND FLOOR: REMAINDER OF ALL FAN COIL HYDRONIC TIE-INS OK EXCEPT FOR UNIT #227. | BILLS | BILLS | | HWP | P | 6481266 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 02/12/2020 | 5TH FLOOR: CONSULTATION ON EXHAUST DUCT SHAFT AT SOUTH CORRIDOR JANITORS CLOSET. SHAFT FROM ROOF TO JANITORS CLOSET WILL BE INSPECTED BY BUILDING INSPECTOR (NATHAN). WILL NEED APPROVED DRAWINGS FOR INSPECTION. MORE NOTES TO FOLLOW AFTER RESEARCH WITH SENIOR MECHANICAL INSPECTOR AND SITE BUILDING INSPECTOR. | BILLS | BILLS | | HSP | P | 6479961 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 02/12/2020 | 2ND FLOOR ABOVE CEILING, BELOW PRE-ROCK: FAN COIL CONNECTIONS, SUPPORTS, NAIL PROTECTION, AND VISUAL INSPECTION OK AT ALL UNITS EXCEPT FOR UNITS #227, 237, 245, AND 247 (NO FRAMING YET). | BILLS | BILLS | | HD | P | 6479948 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 02/11/2020 | 5TH FLOOR: PRESSURE TESTS FOR WATER HEATER CSST OK FOR UNITS #503, 504, 505, 506, 507, 508, 509, 510, AND 511 | BILLS | BILLS | | HI | P | 6478661 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 02/11/2020 | NEED TO COMPLETE ALL INSULATION AT DRAIN, WASTE, AND VENT PIPES. NEED TO CONFIRM PLENUM RATINGS FOR PEX ELBOWS AND ALL FURNACE/AIR HANDLER VENTING. | BILLS | BILLS | | HSP | P | 6478660 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 02/05/2020 | 2ND FLOOR: NORTH CORRIDOR AND NORTH END OF EAST CORRIDOR. HYDRONIC TIE-INS AT FAN COILS OK AT UNITS #202 THROUGH #218 | BILLS | BILLS | | HWP | P | 6474389 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 02/04/2020 | 1ST FLOOR: UNIT #114 VENT CHASE CLEARANCES OK | BILLS | BILLS | | HV | P | 6473346 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 02/04/2020 | CONSULTATION ON WATER HEATER VENTING (75K UNITS). NEED TO VERIFY ALL 75K WATER HEATER VENT LENGTHS ON ENTIRE PROJECT FOR MAXIMUM VENT LENGTHS. | BILLS | BILLS | | HSP | P | 6473343 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 02/04/2020 | 4TH FLOOR. UNIT #449: LEVEL AND SQUARE PLENUM DAMPER. UNIT #437: CORRECTIONS MADE (MECHANICAL COMPONENTS IN CONTACT WITH FIRE SPRINKLER PIPING). UNIT #420: EXHAUST FANS INSTALLED. | BILLS | BILLS | | HD | P | 6473326 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 01/30/2020 | 5TH FLOOR: GAS LINES AT UNITS #513, 518, AND 537 OK. CONNECTIONS TIFFED (LIVE SYSTEM) | BILLS | BILLS | | HI | P | 6469038 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 01/30/2020 | 60LB TEST, NAIL PROTECTION, SUPPORTS, AND VISUAL INSPECTION OK AT FAN COIL HYDRONIC LINES FOR UNITS #513, 537, 114, 116, 118, 120, AND 122. | BILLS | BILLS | | HWP | P | 6469032 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/29/2020 | 3RD FLOOR: ABOVE CEILING, BELOW PRE-ROCK FAN COIL HYDRONICS, CONDENSATE DRAINS, NAIL PROTECTION, AND VISUAL INSPECTION OK AT ALL UNITS EXCEPT FOR #349, 336, 341, 337, 335, 327, 320, AND 313. | BILLS | BILLS | | HD | P | 6467482 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 01/27/2020 | 3RD FLOOR. UNIT #302: ALL 3/4" RIGID CONNECTIONS FROM WALL PENETRATION TO DELIVERY SIDE OF SHUT OFF VALVE TIFFED OK. | BILLS | BILLS | | HI | P | 6464332 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/23/2020 | 2ND FLOOR: ALL UNITS EXCEPT FOR #227: PLENUM DAMPER ANGLES BELOW PRE-ROCK OK. | BILLS | BILLS | | HD | P | 6461740 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 01/23/2020 | ALL CSST GAS LINES TO BE PRESSURE TESTED. | BILLS | BILLS | | HSP | P | 6461726 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 01/23/2020 | 3RD FLOOR: ALL UNITS EXCEPT FOR #320, 327, AND 337: ALL HYDRONIC CONNECTIONS AT FAN COILS OK. | BILLS | BILLS | | HWP | P | 6461719 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/22/2020 | 5TH FLOOR: UNITS #520 AND #525,, IN WALL DRYER, BATH, AND 2ND LEVEL FAN COIL CONDENSATE OK. STILL NEED ALL OTHER INSPECTIONS. 4TH FLOOR: UNIT #425,, DRYER EXHAUST OK (RE-ROUTED TO IN-WALL VERTICAL FOR WALL FIRE PROTECTION). 2ND FLOOR: ALL UNITS EXCEPT FOR #227 (NO DRYWALL), ALL PLENUM DAMPER/DRYWALL CLEARANCES OK. OK TO INSTALL PLENUM DAMPER ANGLES. | BILLS | BILLS | | HD | P | 6459932 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/17/2020 | 2- RETURN AIR FIRE SMOKE DAMPERS AT 5TH FLOOR NORTH AND 5TH FLOOR SOUTH SHAFTS INSTALLED TO INSTRUCTIONS. SEE AGAIN BEFORE RETURN AIR GRILLS ARE INSTALLED. | JON | JON | | HD | P | 6457169 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/15/2020 | 5TH FLOOR: IN WALL BATH AND DRYER EXHAUST, IN WALL CONDENSATE LINES FOR 2ND LEVEL FAN COILS OK AT UNITS #549, 536, 537, AND 527. UNITS #518 AND 523 ALSO EXCEPT FOR NO 2ND LEVEL FAN COILS. STILL NEED ALL INSPECTIONS FOR DUCTWORK, PIPING, DAMPERS, ETC... UNIT #535: ABOVE CEILING, BELOW PRE-ROCK HYDRONICS, LINESET, CONDENSATE, AND NAIL PROTECTION AT FAN COIL OK. 5TH FLOOR NORTH AND SOUTH CORRIDOR RETURN AIR DAMPER FRAMING OK. | BILLS | BILLS | | HD | P | 6453417 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/10/2020 | 4TH FLOOR NORTH AND SOUTH CORRIDOR RETURN AIR DAMPER INSTALLATION OK. 5TH FLOOR. UNIT #513 IN WALL AND ABOVE CEILING BATH AND DRYER EXHAUST OK. IN WALL CONDENSATE FOR UPPER FAN COIL OK. GARAGE LEVEL #1 NORTH. ROOM #157 (COMM ROOM) MINI-SPLIT HEAD AND CONDENSER OK | BILLS | BILLS | | HD | P | 6449059 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 01/07/2020 | 4TH FLOOR NORTH AND SOUTH CORRIDOR RETURN AIR DAMPER FRAMING AT SHAFT'S OK. 5TH FLOOR UNIT #536: IN WALL AND ABOVE CEILING BATH AND DRYER EXHAUST OK. IN WALL CONDENSATE FOR UPPER FAN COIL UNIT OK. | BILLS | BILLS | | HD | P | 6445259 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 01/03/2020 | 3RD FLOOR HYDRONIC TIE-INS AT FAN COILS OK AT UNIT #301, 302, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, AND 313 | BILLS | BILLS | | HWP | P | 6442289 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 01/03/2020 | 4TH FLOOR WATER HEATER VENT CONNECTION TIE-INS OK AT UNITS #403, 404, 405, 406, 407, 408, 409, 410, AND 411. | BILLS | BILLS | | HV | P | 6442283 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/30/2019 | 3RD FLOOR PLENUM DAMPER ANGLES OK AT ALL UNITS EXCEPT FOR UNITS #327 AND #320 (NO DRYWALL AS OF YET) | BILLS | BILLS | | HD | P | 6439387 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/30/2019 | 3RD FLOOR NORTH AND SOUTH CORRIDOR RETURN AIR DAMPER INSTALLATION OK. NEXT INSPECTION FOR THESE DAMPERS ARE FOR THE SECONDARY WALLS/RETURN AIR EXTENSIONS. | BILLS | BILLS | | HD | P | 6439381 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 12/19/2019 | 60LB TEST, NAIL PROTECTION, SUPPORTS, AND VISUAL INSPECTION OK AT UNITS #549, 536, 527, 525, 523, 522, 520, AND 518. SEE PLAN PAGES M105.A&B, BDA #251 & 252 | BILLS | BILLS | | HWP | P | 6432332 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/18/2019 | UNIT #512: ABOVE CEILING HVAC DAMPERS, DRYER, EXHAUST OK. BELOW PRE-ROCK, ABOVE CEILING HYDRONICS, NAIL PROTECTION, AND CONDENSATE OK AT WEST FAN COIL (COMBINED UNIT) UNITS #420, 437, AND 449 FAN COIL PLENUM DAMPER RAILS OK WALK-UP UNITS: NEED CLARIFICATION ON PENETRATIONS AT RATED ASSEMBLIES FOR ALL DUCTS AND ROUND PIPING. SUPPORT ALL DUCTING TO CODE.
| BILLS | BILLS | | HD | P | 6430938 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/17/2019 | UNIT #420: NEED CORRECT ANGLES INSTALLED AT FAN COIL PLENUM DAMPER UNIT #437: NEED CORRECT ANGLES INSTALLED AT FAN COIL PLENUM DAMPER UNIT #449: NEED CORRECT ANGLES INSTALLED AT FAN COIL PLENUM DAMPER AND CORRECTIONS FROM INSPECTION DATED 12/4/19 | BILLS | BILLS | | HD | P | 6429577 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/17/2019 | 3RD FLOOR NORTH AND SOUTH RETURN AIR DAMPER FRAMING AT SHAFTS OK. RE-CALL INSPECTION AFTER DRYWALL AND DAMPER INSTALLATION. SEE PLAN PAGES M104.A&B, BDA #249 & #250 | BILLS | BILLS | | HD | P | 6429571 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 12/16/2019 | CONSULT WITH CONTRACTOR AND BUILDER ON DAMPER FRAMING AT SHAFTS. CORRECTIONS TO BE MADE AND INSPECTION RE-CALLED | BILLS | BILLS | | HSP | P | 6428382 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/13/2019 | UNIT #502: DRYER AND BATH EXHAUST COMPLETE THROUGH WALLS AND THROUGH ROOF. STILL NEED ALL OTHER INSPECTIONS UNIT #522: BATH EXHAUST COMPLETE THROUGH ROOF. STILL NEED ALL OTHER INSPECTIONS. ABOVE CEILING HVAC DUCT, DAMPERS, DRYER, AND BATH EXHAUSTS OK AT UNITS #412, #320, #212, #220,AND #243. SE PLAN PAGES M104.A&B, 103.A&B, PLAN PAGES #247,#248, #249, AND #250 | BILLS | BILLS | | HD | P | 6427419 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/11/2019 | THIS INSPECTION IS FOR ANGLES ON 3RD FLOOR FAN COIL PLENUM DAMPERS. ANGLES ARE COMPLETE AND OK TO HANG FAN COILS ON ALL UNITS EXCEPT FOR #325, #327, AND #337 **UNABLE TO ACCESS PLANS, WILL UPDATE ON THE FOLLOWING MORNING** | BILLS | BILLS | | HD | P | 6423592 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 12/11/2019 | GROUND LEVEL WALK-UP UNITS: 10LB TEST OK AT UNITS #110 AND #112. PLAN PAGE M102.B, BDA #246 | BILLS | BILLS | | HWP | P | 6423591 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/10/2019 | UNIT #502: CONSULT ON BATH AND DRYER EXHAUST. WILL UPDATE INSPECTION COMMENTS AFTER MEETING WITH BUILDING INSPECTOR ON POSSIBLE CORRECTIONS TO BATH EXHAUST IN "DEAD" SPACE. UNIT #522: BATH EXHAUST RAN UP THROUGH CEILING INTO "DEAD" SPACE ABOVE, NOT COMPLETED AT TIME OF INSPECTION, NO APPROVED PLANS AS OF YET. PROCEED AT OWN CAUTION. UNIT #412/414: ROUGH DUCT ONLY, NO APPROVED PLANS AS OF YET, PROCEED AT OWN CAUTION. REMOVE ALL SCREWS IMPEDING DAMPER OPERATION AND RE-CALL INSPECTION. UNITS #437, #437, AND #449: STILL NEED TO INSPECT CORRECTIONS FROM INSPECTION DATED 12/4/19. | BILLS | BILLS | | HD | P | 6422376 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/09/2019 | THIS INSPECTION IS FOR ANGLES ON 3RD FLOOR FAN COIL PLENUM DAMPERS. ANGLES ARE COMPLETE AND OK TO HANG FAN COILS ON NORTH AND EAST UNITS ONLY. EXCLUDING 302, 312, 318, 327, 335, 336, 349. ON NEXT INSPECTION NEED TO START WITH 326 ON SOUTH WING FOR ANGLE INSPECTION. | JON | JON | | HD | P | 6420788 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 12/09/2019 | 4TH FLOOR. HYDRONIC CONNECTIONS TO FAN COIL UNITS OK AT ALL UNITS EXCEPT FOR 402, 412, 418, 420, 436, 437, AND 449 | BILLS | BILLS | | HWP | P | 6420503 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/09/2019 | 4TH FLOOR ABOVE CEILING, BELOW PRE-ROCK AT FAN COILS: NAIL PROTECTION, LINESET INSULATION AND CONDENSATE DRAINS. ALL UNITS EXCEPT--405, 407, 411,421, NEED ADDITIONAL NAIL PROTECTION AT CONDENSATE DRAINS. UNITS 402, 412, 418, 420, 427, 436, 437, AND 449 NOT READY FOR INSPECTION. **CONFIRM AUXILIARY COIL CONDENSATE PROTECTION BY FINAL** | BILLS | BILLS | | HD | P | 6420502 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/06/2019 | 4TH FLOOR CURSORY WALK WHILE ON SITE TO CHECK STATUS AT FAN COIL ROOMS. MOST ROOMS ARE COMPLETE, ADDITIONAL NAIL PROTECTION REQUIRED AT CONDENSATE LINES AT SOME UNITS. | BILLS | BILLS | | HD | P | 6418745 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 12/06/2019 | 60LB TEST, NAIL PROTECTION, AND VISUAL INSPECTION OK AT UNITS #102, 104, 106, 108. LOW TEST AT UNITS #110, AND 112. SEE PLAN PAGES M102.A&B, BDA 244 and 245 | BILLS | BILLS | | HWP | P | 6418718 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/05/2019 | 3RD FLOOR FAN COIL DAMPER INSPECTION ALL OK TO INSTALL ANGLES AT ALL APARTMENT UNITS ON 3RD FLOOR EXCEPT 320-327-337. CALL BACK FOR AN ANGLE INSPECTION BEFORE INSTALLING FAN COILS. | JON | JON | | HD | P | 6418233 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 12/05/2019 | 10LB TEST OK. LINE RAN FROM UNIT #418 UP TO #518 OK SEE PLAN PAGE MG105.A, BDA #229 | BILLS | BILLS | | HI | P | 6417120 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/04/2019 | CONTRACTOR TO CONTACT DAMPER MANUFACTURER FOR DIRECTION AND INFORMATION ON CUTTING DAMPER SLEEVE AT BOTH 2ND FLOOR RETURN AIR DAMPERS. UNIT #449: SUPPLY AIR FLEX AND LINESET IN CONTACT WITH FIRE SPRINKLER LINES, LINESET COPPER IN CONTACT WITH DAMPER RAILS. UNIT #436: RE-INSPECT ALL. SUPPLY AIR DUCT PENETRATING RATED MEMBRANE IN 2 LOCATIONS WITHOUT DAMPERS. WILL NEED PLAN REVISION. UNIT #437: SUPPLY AIR FLEX IN CONTACT WITH FIRE SPRINKLER LINES. DAMPER TO DRYWALL CLEARANCES OK AT UNITS #304, 306, 307, 309, 317, 319, 321, 331, 335, AND 339. OK TO INSTALL BELOW DRYWALL RETAINING ANGLES AT PLENUM RADIATION DAMPER | BILLS | BILLS | | HD | P | 6415725 |
BRUCE MECHANICAL OF COLORADO, INC | H= | P | 12/04/2019 | INSPECTION CALLED IN BY MISTAKE, NOT READY FOR FINAL | BILLS | BILLS | | H= | P | 6415502 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 12/03/2019 | UNIT #536 GAS LINE VISUAL INSPECTION OK. CONNECTIONS TIFFED (LINES UNDER GAS PRESSURE). SEE PLAN PAGE MG105.B, BDA #230 | BILLS | BILLS | | HI | P | 6414168 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 12/02/2019 | 2ND FLOOR NORTH SHAFT RETURN DAMPER FRAMING NEEDS TO BE RE-INSPECTED (NO DAMPER INSTALLATION INSTRUCTIONS AVAILABLE). 3RD FLOOR PLENUM ANGLES INSPECTION AT ALL FAN COILS TO BE RE-CALLED FOR DRYWALL TO RADIATION DAMPER CLEARANCES BEFORE RETAINING ANGLES ARE RE-INSTALLED. 2ND FLOOR CORRIDOR SUPPLY DUCT WRAP OK, STILL NEED RUN-OUTS | BILLS | BILLS | | HD | P | 6412532 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/20/2019 | 2ND FLOOR NORTH AND SOUTH CORRIDOR DUCTING AND CORRIDOR SIDE BREAK-AWAY CONNECTIONS OK. OK TO WRAP. STILL NEED TAPS AND RUN-OUTS. SEE PLAN PAGES M103.A&B,, BDA PAGES #247&248 | BILLS | BILLS | | HD | P | 6405135 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 11/20/2019 | INSPECTED 1ST RETURN AIR DAMPER FRAMING ON 2ND FLOOR SOUTH. OK TO PROCEED WITH THE REST OF HE SHAFT CONSTRUCTION AFTER VERIFICATION FROM BUILDING INSPECTOR THAT THIS PORTION OF FACE WALL IS A NON RATED WALL. NEED DAMPER INSTALLED AND INSPECTED BEFORE ANY MORE WORK ON SHAFT IS COMPLETED TO SEE DAMPER TIE IN AND DAMPER SUPPORT. | JON | JON | | HSP | P | 6404913 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 11/20/2019 | UNIT 502 GAS RISER UP FROM 202 TESTED AND COMPLETE | JON | JON | | HI | P | 6404905 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 11/14/2019 | DISCUSSED RETURN AIR DAMPERS AT SHAFT WALLS WITH BRUCE MECHANICAL AND CSI. WILL NEED TO SEE 1 DAMPER INSTALLED PER MANUFACTURERS INSTALLATION INSTRUCTIONS AND MOCKED UP FOR INSPECTION. | BILLS | BILLS | | HSP | P | 6399161 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/14/2019 | NORTH AND SOUTH SHAFTS, ALL DUCT COMPLETE (SUPPLY, RETURN AND EXHAUST AIR. ALL DAMPERS EXCEPT RETURN AIRS COMPLETE. SEE PLAN PAGES M104 A&B, BDA #746 &747 | BILLS | BILLS | | HD | P | 6399155 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/12/2019 | 11-12-19 JB ...SUPPLY AND RETURN DROPS 3RD FLOOR SOUTH OK. SUPPLY DAMPER OK. STILL NEED ALL RETURN DAMPERS INSPECTED AT SHAFT WALLS ALL FLOORS AT SHAFTS. RED HIGH LIGHT BOX BLUE BEAM PAGE746 M-104B | JON | JON | | HD | P | 6396990 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/11/2019 | 11-11-19 JB ...SUPPLY AND RETURN DROPS 4TH FLOOR SOUTH OK. SUPPLY DAMPER OK. STILL NEED ALL RETURN DAMPERS INSPECTED AT SHAFT WALLS ALL FLOORS AT SHAFTS. GREEN HIGH LIGHT BOX BLUE BEAM PAGE746 M-104B | JON | JON | | HD | P | 6395346 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/08/2019 | 11-8-19 JB SUPPLY, RETURN DROPS FROM 2ND FLOOR AND DAMPER CONNECTIONS OK. PAGE 247 SEE SOLID RED HIGH LIGHTED BOX M-103A..FIRE DAMPER ANGLES AT TRANSFORMER ROOM OK PROCEEDING AT OWN RISK NO APPROVED PLANS FOR THIS EXHAUST SYSTEM, FAN AND DAMPER. 2ND FLOOR NORTH SUPPLY AND RETURN OK DOWN FROM 3RD FLOOR AND BREAK AWAY CONNECTION TO DAMPER OK. | JON | JON | | HD | P | 6393692 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/07/2019 | UP DATE JOB SITE PLANS NEXT TRIP..11-7-19 JB NORTH SHAFT SUPPLY AND RETURN DROPS AND DAMPER CONNECTIONS FROM ROOF DOWN THROUGH 3RD FLOOR OK. SEE LIGHT BLUE HIGH LIGHT ON BLUE BEAM PAGE 745 | JON | JON | | HD | P | 6392217 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/05/2019 | DAMPER INSPECTION - ANNULAR SPACE AROUND 120 X 40 FIRE DAMPER OK FOR TRANSFORMER ROOM 171 ON G1 LEVEL 1 NORTH SPLICE PENDING APPROVAL - CONTINUE AT OWN RISK WITH ANGLES.
SHAFT DUCT - SUPPLY AIR DUCT INSTALLED IN NORTH SHAFT FROM LEVEL 5 DOWN TO LEVEL 4 TIED INTO LEVEL 4 DAMPER WITH BREAK AWAY OK TO WRAP. | MARKB | MARKB | | HD | P | 6388394 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/04/2019 | ----PLAN SPLICE REQUIRED FOR EXHAUST IN SOUTH SHAFT NOT SHOWN ON PLANS---- 5TH FLOOR SOUTH SHAFT - SUPPLY DUCT INSTALLED FROM ROOF TO FLOOR LEVEL TIED INTO DAMPER WITH BREAK AWAY CONNECTION OK FOR SUPPORT AND SEALING.
3RD FLOOR ABOVE PRE-ROCK ROUGH DUCT - SUPPLY/EXHAUST/DRYER/DAMPER DUCT COMPLETE FOR SOUTH UNITS 336 & 334 AND NORTH UNIT 302. | MARKB | MARKB | | HD | P | 6387198 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 11/01/2019 | 1ST SECTION OF SUPPLY DUCT INSIDE NORTH SHAFT FROM ROOF. THIS DUCT HAS TO BE INSTALLED FIRST BEFORE RETURN DROP IS INSTALLED BLOCK ACCESS FOR INSPECTION. THIS PROCESS WILL CONTINUE ALL THE WAY DOWN TO 2ND FLOOR. RETURN FIRE SMOKE DAMPERS AT EACH FLOOR LEVEL WILL NEED A CONSULTATION FOR INSPECTION PROCESS.. | JON | JON | | HD | P | 6386427 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/31/2019 | 10-31-19 JON B NORTH EXHAUST RISERS AND BREAK AWAY DAMPER INSPECTIONS COMPLETE FOR EXHAUST DUCT FROM 5TH FLOOR DOWN TO 2ND FLOOR ALL COMPLETE BLUE BEAM PAGE 747 GREEN HIGHLIGHT.. OK TO START SUPPLY DUCT IN SHAFTS AND CALL INSPECTIONS WHEN READY. WENT OVER PLAN SPLICES IN CSI JOB SITE OFFICE. | JON | JON | | HD | P | 6385193 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 10/31/2019 | WALK UP UNIT 14 NEEDS TO HAVE WATER HEATER VENT ENCLOSED IN A CHASE TO CHECK NAIL PROTECTION. REST OF ROUGH WATER HEATER VENTS OK IN ALL WALK UP UNITS. | JON | JON | | HV | P | 6385191 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 10/28/2019 | ADDED DOCUMENT TO PERMIT IMAGES ON THE PVC/CPVC GLUE AND PRIMER CONNECTIONS | BILLS | BILLS | | HSP | P | 6381614 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/25/2019 | 5TH FLOOR FAN COIL ABOVE CEILING TIE-INS, NAIL PROTECTION, CONDENSATE DRAINS, LINESET INSULATION, AND SEALANT OK AT ALL UNITS EXCEPT MEZZANINE, COMBINED, AND HOTEL UNITS. UNABLE TO MARK SITE PLANS, WILL UPDATE AT NEXT INSPECTION. | BILLS | BILLS | | HD | P | 6380284 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 10/23/2019 | CHANGED INSPECTION TO HSP. CONSULT WITH CONTRACTOR ON REQUIREMENTS FOR RETURN AIR PLENUMS AT FAN COILS ( ISOLATE WOOD AT RETURN AND TRANSFER AIR OPENINGS, NAIL PROTECTION AT LINESETS, CONDENSATE, AND HYDRONIC LINES, DUCT ACCESS DOORS, SEALANT AT SUPPLY DUCT/DAMPER DUCT JOINT, LINESET INSULATION COMPLETION, AND SUPPLY AIR DUCT SUPPORTS. ALSO NEED TO VERIFY ALL DAMPER ANGLES BEFORE FAN COIL DUCT INSTALLATION. | BILLS | BILLS | | HSP | P | 6377737 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 10/21/2019 | CONSULT WITH CONTRACTOR AT TRANSFORMER ROOM DAMPER.*** NO APPROVED PLANS FOR NEW DESIGN AVAILABLE. PROCEED AT OWN CAUTION***. NEED CLARITY FROM DAMPER MANUFACTURER (GREEN HECK) ON DAMPER EXPANSION ROOM AND RETAINAGE FOR SIZE OF DAMPER (2 SIDED RETAINAGE DUE TO SIZE), AND/OR REDUCTION OF EXPANSION ROOM OR ALLOWING 1 SIDED RETAINAGE. | BILLS | BILLS | | HSP | P | 6374775 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 10/21/2019 | GAS LINES AT GENERATOR ROOM UNIT HEATER, POOL AND SPA BOILERS, AND SNOW MELT BOILER OK. NEED TO VERIFY CORRECT HANGER SPACING AT SNOW MELT LINE BETWEEN MAIN LINE AND BOILER ROOM. GAS LINE AT UNIT #549 OK. SEE PLAN PAGES MG103. A, BDA #223, MG105.B,, BDA #230 | BILLS | BILLS | | HI | P | 6374755 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 10/18/2019 | ***UPDATED 10/21/19 BY BILL S. NEED TO CONFIRM NAIL PROTECTION AT ALL WALK-UP UNITS** GARAGE LEVEL WALK-UP UNITS. ALL WATER HEATER CONCENTRIC VENTING OK AT ALL WALK-UP UNITS. SEE PLAN PAGES M102.A & B, BDA PAGES #245 & #246 | BILLS | BILLS | | HV | P | 6373111 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 10/17/2019 | 2ND AND 3RD FLOOR SOUTH UNITS #237 AND #337 PRESSURE TEST, NAIL PROTECTION, SUPPORTS AND VISUAL INSPECTION OF FAN COIL HYDRONIC LINES OK. SEE PLAN PAGE M103.B, BDA #248 , M1O4.B, BDA #250 | BILLS | BILLS | | HWP | P | 6371733 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/17/2019 | 3RD FLOOR SOUTH CORRIDOR SUPPLY AIR DUCT AND CORRIDOR SIDE DAMPER BREAK-AWAY CONNECTION OK. OK TO WRAP. SEE PLAN PAGE M104.B,, BDA #250 | BILLS | BILLS | | HD | P | 6371731 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 10/16/2019 | 2RD FLOOR SOUTH PRESSURE TEST, NAIL PROTECTION, SUPPORTS AND VISUAL INSPECTION OF FAN COIL HYDRONIC LINES OK FOR ALL UNITS EXCEPT FOR #237. SEE PLAN PAGE M103.B, BDA #248 | BILLS | BILLS | | HWP | P | 6370342 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/16/2019 | 5TH FLOOR DAMPER ANGLES AT JANITORS CLOSET CMU SHAFT WALL ALL OK. CORRECTION MADE TO 4TH FLOOR NORTH SUPPLY AIR DAMPER ALSO. | BILLS | BILLS | | HD | P | 6370309 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 10/15/2019 | CANCELLED AT CALL AHEAD BY TONY | BILLS | BILLS | | HV | P | 6368336 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/15/2019 | DAMPER ANGLES AT JANITORS CLOSET CMU SHAFT WALLS AT 2ND, 3RD, AND 4TH FLOORS ALL OK EXCEPT FOR 4TH FLOOR NORTH SUPPLY DAMPER WEST SIDE ANGLE LACKS 1" COVERAGE. WILL UPDATE SITE PLANS AND BLUE BEAM ON THE FOLLOWING MORNING | BILLS | BILLS | | HD | P | 6368331 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 10/15/2019 | 3RD FLOOR SOUTH PRESSURE TEST, NAIL PROTECTION, SUPPORTS AND VISUAL INSPECTION OF FAN COIL HYDRONIC LINES OK FOR ALL UNITS EXCEPT FOR #337 (NO ACCESS). SEE PLAN PAGE M104.B, BDA #250 | BILLS | BILLS | | HWP | P | 6368318 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/14/2019 | 3RD FLOOR NORTH AND EAST CORRIDOR SUPPLY AIR AND CORRIDOR SIDE BREAK AWAY CONNECTION OK. OK TO WRAP. STILL NEED FLEX AND DIFFUSERS. SEE PLAN PAGE M104.A, BDA #249 **ATTN. ENGINEER STILL TO ADDRESS THE REMOVAL OF CORRIDOR RADIATION DAMPERS BELOW RATED CEILING** | BILLS | BILLS | | HD | P | 6366939 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 10/14/2019 | NEED VERIFICATION ON ALL RETURN AIR PLENUM CONFIGURATIONS AT WALK UP UNITS (PLENUM RATED MATERIALS, PROTECTION, ETC) | BILLS | BILLS | | HSP | P | 6366938 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 10/11/2019 | CONSULT WITH CONTRACTOR ON FIRE DAMPER AT TRANSFORMER ROOM/PARKING GARAGE WALL. NO APPROVED PLANS ON FILE. WENT OVER OPTIONS OF RETAINAGE AND BREAK-AWAY CONNECTIONS FOR GREENHECK DAMPER | BILLS | BILLS | | HSP | P | 6366098 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/09/2019 | 1ST FLOOR SOUTH. ABOVE CEILING SUPPLY AIR, EXHAUST AIR, AND DRYER EXHAUST OK AT UNITS #116, 118, 120, AND 122. SEE PLAN PAGE M102.B,, BDA #2456 GREEN LINES | BILLS | BILLS | | HD | P | 6362894 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 10/09/2019 | 5TH FLOOR EAST. STACK VENTS AT 17 AND 33 UNITS SIZED AT 4" TO MEET LENGTH REQUIREMENTS. SEE PLAN PAGE M105.B, BDA #252 | BILLS | BILLS | | HV | P | 6362881 |
BRUCE MECHANICAL OF COLORADO, INC | HV | P | 10/07/2019 | WENT OVER FURNACE VENT INSTRUCTIONS FOR CPVC AND PVC VENTING WITH SAM. SAM WILL PROVIDE INFORMATION FROM CONCORD TO ENSURE THAT THE FLUE COLLARS ARE NOT CONSTRUCTED OF ABS. CONTRACTOR TO FOLLOW INSTALLATION INSTRUCTIONS FOR PROPER PRIMER AND GLUE FOR ALL VENT JOINTS. LISTING NUMBERS FOR PRIMERS AND GLUES ARE TO BE VERIFIED AND INSTALLED TO INSTRUCTIONS FOR ALL VENT JOINTS. THE INSTRUCTIONS FROM THE PRIMER AND GLUE CANS ARE TO BE VERIFIED AND ON SITE FOR INSPECTION WHEN READY. | JON | JON | | HV | P | 6360802 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/04/2019 | 4TH FLOOR. REMAINDER OF FAN COIL DAMPER ANGLE OK. STILL NEED ALL MEZZANINE UNITS INSPECTED. SEE PLAN PAGES M104.A&B, BDA PAGES #251 & #252 GREEN EX'S | BILLS | BILLS | | HD | P | 6357746 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 10/03/2019 | NEED PLAN SPLICE FOR THE REMOVAL OF THE WATER HEATERS AT THE HOTEL UNITS ON PLAN PAGES MG103.A & B, SEE GREEN CLOUDS. 10LB TEST OK FOR UNITS #520 AND #522. PLAN PAGE MG105.B BLUE LINES | BILLS | BILLS | | HI | P | 6356824 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 10/02/2019 | 4TH FLOOR. ALL DAMPER ANGLES OK EXCEPT FOR MEZZANINE UNITS AND THE FOLLOWING: #401, 405, 406, 407. 408, 409, 412, 419, 435, 441. PLAN PAGES M105.A & B, BDA #251 &252. UNABLE TO UPDATE SITE PLANS IN JOB TRAILER DUE TO MEETING, WILL UPDATE SITE PLANS ON NEXT VISIT | BILLS | BILLS | | HD | P | 6355076 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/27/2019 | ABOVE PRE-ROCK ROUGH DUCT AND DAMPERS, HVAC, EXHAUST, AND DRYER OK FOR UNITS #516, 534, 539, 543, AND 545. PLAN PAGES M105.A &B, BDA PAGES #251 & #252 GREEN CROSSES | BILLS | BILLS | | HD | P | 6350245 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 09/25/2019 | ALL APARTMENT WATER HEATER VENTING ABOVE PODIUM OK EXCEPT FOR 33 AND 17 UNITS STACK VENTS (OVER LENGTH), STILL NEED ALL MEZZANINE VENT INSPECTIONS 5TH FLOOR UNITS EXCEPT FOR #549. SEE PLAN PAGE M-105B BB PAGE 25 | BILLS | BILLS | | HV | P | 6347730 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 09/25/2019 | CHANGED TO AN HSP. WENT OVER DRYWALL AND SHAFT OPENINGS. CONTRACTOR TO ENSURE ALL DRYWALL WRAP AT WOOD WALLS, INSTALL ALL DAMPERS AT CMU WALLS WITH 1 SIDED ANGLES AND CALL FOR INSPECTION | BILLS | BILLS | | HSP | P | 6347722 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 09/20/2019 | LOOKED AT WATER HEATER VENTS COMING UP FROM 302 AND 402 UP THROUGH 5TH FLOOR CORRIDOR. NEED VENTS FRAMED IN AT 5TH FLOOR CORRIDOR AND NEED VENT SUPPORT ADDED IN ATTIC AT 4 FOOT SPACING. UNIT 549 NEEDS ALL VENTING SUPPORTED IN THIS MEZZANINE UNIT. CONTRACTOR WILL CALL ALL UNITS IN THAT HAVE VENTS PENETRATING MULTIPLE FLOORS NEXT WEEK. | JON | JON | | HV | P | 6343192 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HC | C | 09/20/2019 | METER RELEASE OK AND READY FOR TEMPORARY HEAT. ALL MAINS HAVE BEEN TESTED AT 60 LBS FOR WELDED AND 10 LBS FOR LOW PRESSURE. THE " RBD HI " INSPECTION WILL REMAIN OPEN FOR MORE INSPECTIONS ON SMALL LOW PRESSURE PIPING AT WALK UP AND MEZZANINE UNITS. ALL OTHER BRANCH LINES ARE VALVED AND CAPPED OR CONNECTED TO VENTED APPLIANCES. | JON | JON | | HC | C | 6342327 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 09/18/2019 | CONSULTED ON ALL WOOD AND MASONRY DAMPER PENETRATIONS, CONTRACTOR WILL INSTALL ALL DAMPERS IN MASONRY OPENING'S ATTACH DAMPER ANGLES FOR ONE SIDED SUPPORT AND CALL INSPECTION. CSI IS WORKING BUILDING INSPECTOR TO DISCUSS OPPOSITE SIDE OF MASONRY WALLS FOR ANY ADDED FILL MATERIALS. | JON | JON | | HSP | P | 6339957 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | L | 09/18/2019 | WATER HEATER VENT INSPECTIONS, JB 9-18-19, EAST AND SOUTH WINGS FOR WATER HEATER VENTS CLOSETS ONLY NO VERTICAL RISER VENTS YET FROM OTHER FLOOR. THIS EXCLUDES THESE 8 UNITS 518, 520, 523, 525, 527, 537, 549 536. BLUE CROSS HIGH LIGHTS ON PLANS. .B.B PAGE 251 AND 252 | JON | JON | | HV | L | 6339902 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/18/2019 | DUCT INSPECTION JB 9-18-19 INSPECTED APARTMENT ROUGH BATH FAN, DRYER, AND HVAC DUCTS NOW COMPLETE IN UNIT 434 B.B. PAGE 250 SOLID YELLOW CLOUD | JON | JON | | HD | P | 6340598 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 09/17/2019 | CONSULTATION WITH CONTRACTOR ON DAMPER OPENINGS, DRYWALL WRAP, RETAINING ANGLES, AND ANNULAR SPACING AT SHAFTS, TELLECOM, AND TRASH ROOMS. RE-INSPECT ALL | BILLS | BILLS | | HSP | P | 6337749 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 09/13/2019 | 4TH FLOOR SOUTH: 60 PSI PRESSURE TEST, NAIL PROTECTION AND SUPPORT FOR SUPPLY/RETURN PIPING FROM WATER HEATER TO FCU OK FOR UNITS 424, 426, 428, 430, 432, 434, 439, 441, 443, 445, 447 HIGHLIGHTED ON M-104.B WITH PURPLE CIRCLES. Blue Beam page 250 | MARKB | MARKB | | HWP | P | 6334360 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/12/2019 | 5TH FLOOR SOUTH AND EAST CORRIDOR SUPPLY AIR COMPLETION FROM UNIT #541 TO EAST STAIRWAY CORRIDOR OK. OK TO WRAP. SEE PLAN PAGE M105.B (BDA #252) | BILLS | BILLS | | HD | P | 6332820 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 09/12/2019 | 5TH FLOOR SOUTH CORRIDOR. ALL UNITS EXCEPT FOT #536, 537, AND 549. 60LB PRESSURE TEST, NAIL PROTECTION, AND VISUAL INSPECTION OK FOR FAN COIL HYDRONIC LINES. SEE PLAN PAGE M105.B (BDA #252) | BILLS | BILLS | | HWP | P | 6332819 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 09/11/2019 | FIELD CANCELLED BY CONTRACTOR AT CALL AHEAD | BILLS | BILLS | | HWP | P | 6330997 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/10/2019 | 5TH FLOOR NORTH CORRIDOR SUPPLY AIR DUCT COMPLETION OK. OK TO WRAP. SEE PLAN PAGE M105.A (BDA #251). 5TH FLOOR SOUTH CORRIDOR SUPPLY AIR DUCT FROM JANITORS CLOSET TO UNIT #541 OK. OK TO WRAP. SEE PLAN PAGE M105.B (BDA #252) 4TH AND 5TH FLOORS SOUTH CORRIDOR DAMPERS AT JANITORS CLOSETS /SHAFT WALLS ANGLES AND ANNULAR SPACING OK. SEE PLAN PAGES M104.B AND M105.B (BDA #250 AND #252) | BILLS | BILLS | | HD | P | 6329470 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/05/2019 | ENGINEER TO ADDRESS THE REMOVAL OF THE CEILING RADIATION DAMPERS IN ALL CORRIDORS IF NOT RATED. CONVERSATION WITH CONTRACTOR THAT THESE DAMPERS WERE TO BE REMOVED. 5TH FLOOR NORTH CORRIDOR. CORRIDOR SUPPLY AIR FROM DAMPER AT JANITORS CLOSET TO UNIT #523 INSTALLED PER PLAN AND OK TO WRAP. SEE PLAN PAGE M105.A (BDA #251) | BILLS | BILLS | | HD | P | 6324830 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 09/05/2019 | 4TH FLOOR ALL UNITS EXCEPT FOR #402 ALL IN- WALL AND CEILING LINESETS OK FOR NAIL PROTECTION AND VISUAL INSPECTION. SEE PLAN PAGES M104.A&B (BDA #249 AND #250) | BILLS | BILLS | | HRP | P | 6324817 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 09/04/2019 | 10LB TEST OK FOR UNITS #336 AND #436. SEE PURPLE LINES AT PLAN PAGES MG104.B (BDA #228) | BILLS | BILLS | | HI | P | 6323226 |
BRUCE MECHANICAL OF COLORADO, INC | HWP | P | 09/04/2019 | 4TH FLOOR ALL UNITS IN-WALL CONDENSATE OK. SEE PURPLE LINES AT PLAN PAGES M104.A & B, (BDA #249 #250) | BILLS | BILLS | | HWP | P | 6323192 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 09/04/2019 | 4TH AND 5TH FLOORS NORTH JANITORS CLOSET/SHAFT WALL (CMU) DAMPER ANGLES AND ANNULAR SPACING OK. SEE PURPLE CLOUDS AT PLAN PAGES M104.A/M105.A (BDA #249 & #251) | BILLS | BILLS | | HD | P | 6323161 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 08/29/2019 | 10LB TEST OK FOR 2" MAIN AT GRID LINE"D". FEEDS UNITS #110, 112, AND 236. POOL DECK SOUTH FIRE PIT, AND BBQ.*** PLAN PAGE MG102.B (BDA #224) ORANGE LINES.*** 10LB TEST OK FOR 2" MAIN AT GRID LINE "G". FEEDS UNITS #102, 104, 106, 108, 1" MAIN TO RTU'S #3 &4, POOL DECK NORTH FIRE PIT, CLUB HOUSE FIREPLACE, AND FUTURE USE OVEN ***PLAN PAGE MG102.A (BDA #223) ORANGE LINES*** | BILLS | BILLS | | HI | P | 6318524 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 08/26/2019 | 5TH FLOOR EAST CORRIDOR. 60LB TEST AND VISUAL INSPECTION OK FOR FAN COIL UNITS AT UNITS #515, 516, 517, 519, 521, 529, 531, 533, & 535. SEE ORANGE CLOUDS AT PLAN PAGES M105.A&B, BLUE BEAM PAGES #251&252 | BILLS | BILLS | | HWP | P | 6313789 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 08/23/2019 | FIELD CANCELLED BY CONTRACTOR | BILLS | BILLS | | HWP | P | 6311797 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/22/2019 | ENGINEER TO ADDRESS THE REMOVAL OF THE CEILING RADIATION DAMPERS IN ALL CORRIDORS IF NOT RATED. CONVERSATION WITH CONTRACTOR THAT THESE DAMPERS WERE TO BE REMOVED. 4TH FLOOR NORTH, EAST, AND SOUTH CORRIDORS SUPPLY AIR DUCT WRAP OK. SEE ORANGE HIGHLIGHTED DUCTS ON PLAN PAGES M104.A&B, BLUE BEAM PAGES #249 ú. | BILLS | BILLS | | HD | P | 6310225 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 08/22/2019 | 4TH FLOOR EAST CORRIDOR. 60LB TEST AND VISUAL INSPECTION OK FOR FAN COIL HYDRONIC LINES AT UNITS #415, 416, 417, 419, 421, 423, 429, 431, 433, AND 435. MARKED WITH GREEN CLOUDS. PLAN PAGES M104.A&B, BLUE BEAM PAGES #249 & #250 | BILLS | BILLS | | HWP | P | 6310190 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/16/2019 | ENGINEER TO ADDRESS THE REMOVAL OF THE CEILING RADIATION DAMPERS IN ALL CORRIDORS IF NOT RATED. CONVERSATION WITH CONTRACTOR THAT THESE DAMPERS WERE TO BE REMOVED. 4TH FLOOR NORTH AND SOUTH CORRIDORS SUPPLY AIR DUCT AND PIPE OK TO WRAP. SEE ORANGE LINES. BLUE BEAM PAGES #251 ü,, PLAN PAGES M105.A & M105.B | BILLS | BILLS | | HD | P | 6303331 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 08/16/2019 | 5TH FLOOR SOUTH AND EAST. ABOVE CEILING LINESET VISUAL INSPECTION AND IN-WALL CONDENSATE DRAIN LINES ALL OK EXCEPT FOR UNITS #520, 522, 524, 526, 527, 536, 537, AND 549 SEE BLUE LINES, BLUE BEAM PAGE #252, PLAN PAGE M105.B | BILLS | BILLS | | HRP | P | 6303329 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 08/15/2019 | NEED ALL DESIGN CHANGES FOR FRESH AIR TO BE SPLICED BEFORE INSPECTION FOR F-2 AND F-4 (WRAP AT OWN RISK). MISSING SUPPLY AIR RUN OUTS AT F-3 AND F-4 DUE TO FLOOR PLAN CHANGES. NEED SPLICE BEFORE INSPECTION (WRAP AT OWN RISK) SEE ORANGE CLOUDS, BLUE BEAM PAGE #245, PLAN PAGE M102.A | BILLS | BILLS | | HSP | P | 6302144 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/15/2019 | ALL ITEMS IN RETURN AIR PLENUM TO BE PROTECTED OR MEET THE 25/50 SMOKE/FLAME SPREAD. NEED RFI FOR ALLIED/CONCORD EQUIPMENT INSTALLED. NEED REMOVAL ACCESS FOR ALL 4 FURNACES WITH PROPER AMOUNT OF ACCESS DOORS FOR REMOVAL AND CONTROL MOTORS. AUXILIARY DRAINS TO BE CODE COMPLIANT FOR ALL FURNACES AND COILS (CHECK AT VENT INSPECTION). ALL GREEN HIGHLIGHTED DUCT OK TO COVER (SUPPLY, RETURN, AND OUTSIDE AIR) OK TO WRAP BDA PAGE #245, PLAN PAGE M102.A | BILLS | BILLS | | HD | P | 6302133 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 08/15/2019 | 5TH FLOOR EAST AND SOUTH CORRIDORS, LINESET SUPPORT AND VISUAL INSPECTION OK EXCEPT FOR LINESET BANK AT SOUTH JANITOR CLOSET WALL (SEVERAL BREAKS IN INSULATION) | BILLS | BILLS | | HRP | P | 6302108 |
NEWCOMER'S PLUMBING AND HEATING, INC. | H= | P | 08/13/2019 | INSPECTION CALLED IN BY MISTAKE | JON | JON | | H= | P | 6299077 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 08/08/2019 | NEED ALL UPDATED PLANS BROUGHT THROUGH PLAN REVIEW FOR CHANGES BEFORE INSPECTION CAN TAKE PLACE IN THOSE AREA'S (REMOVAL OF CORRIDOR RADIATION DAMPERS, JANITOR CLOSET EXHAUST AIR, TRASH ROOM CHANGES EQUIPMENT SCHEDULES, AND ANY OTHER KNOWN CHANGES). AFTER CONVERSATION WITH SENIOR BUILDING INSPECTOR, CONTRACTOR TO WORK WITH ENGINEER FOR A REPAIR/REPLACEMENT OF DAMAGED CMU BLOCKS AT MECHANICAL SHAFTS PER BUILDING SENIOR. | BILLS | BILLS | | HSP | P | 6292943 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 08/07/2019 | 5TH FLOOR SOUTH. 10LB TEST AND VISUAL INSPECTION OK FOR ALL SOUTH UNITS EXCEPT FOR UNITS #537 AND #549 | BILLS | BILLS | | HI | P | 6291375 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/06/2019 | 2ND AND 3RD FLOORS, NORTH AND SOUTH JANITORS CLOSET SUPPLY AIR DAMPER OPENINGS DRYWALL WRAP OK. SEE PLAN PAGES M103.A & B, M104.A & B, BDA PAGES # 247, 248, 249, AND 250 | BILLS | BILLS | | HD | P | 6289714 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/05/2019 | 4TH FLOOR SOUTH JANITORS CLOSET SUPPLY AIR DAMPER ANNULAR SPACING OK. PLAN PAGE M104.B, BDA PAGE #250 | BILLS | BILLS | | HD | P | 6287944 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/02/2019 | 5TH FLOOR NORTH AND SOUTH JANITORS CLOSET SUPPLY AIR DAMPER ANNULAR SPACING OK. 4TH FLOOR NORTH JANITORS CLOSET SUPPLY AIR DAMPER ANNULAR SPACING OK PLAN PAGES M104.A, M105A &B. BDA PAGES #249, #251, AND #252 | BILLS | BILLS | | HD | P | 6286348 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 08/02/2019 | 60LB TEST AND VISUAL INSPECTION OK ON ALL EAST UNITS EXCEPT FOR #322. MARKED WITH ORANGE LINE. PLAN PAGE M104.A AND M104.B, BDA PAGE #249 AND #250 | BILLS | BILLS | | HWP | P | 6286323 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 08/01/2019 | 4TH FLOOR NORTH AND SOUTH FIRE DAMPER OPENING (SUPPLY AIR) DRYWALL WRAP OK AT JANITORS CLOSETS, PLAN PAGES M104.A AND M104.B, BDA PAGES #249 AND #250 | BILLS | BILLS | | HD | P | 6284885 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 08/01/2019 | 4TH FLOOR SOUTH. 10LB TESTS AND VISUAL INSPECTION OK FOR UNITS #426, 428, 430, 432, 434, 437, 441, 443, 445, 447, 449, AND RTU RISER AT #449. PLAN PAGE MG-104, BDA PAGE #228 | BILLS | BILLS | | HI | P | 6284864 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 08/01/2019 | 2ND FLOOR EAST 60LB PRESSURE TEST AND VISUAL INSPECTION OK FOR UNITS #215, 216, 217, 218, 219, 220, 221, 223, 225, 227, 229, 231, 233, AND 235. PLAN PAGES M-103A AND M-103B, BDA PAGES #247 AND #248 | BILLS | BILLS | | HWP | P | 6284845 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 07/31/2019 | DRY WALL WRAP INSIDE JANITORS CLOSETS WOOD WALLS OK NORTH AND SOUTH 2 DAMPER HOLES ONLY 5TH FLOOR SEE BLUE BEAM PAGES 252 AND 251 | JON | JON | | HD | P | 6284009 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 07/31/2019 | ALL REFRIGERATION PIPING FOR CONDENSERS AT SOUTH EAST AND SOUTH EQUIPMENT COUCHES TEST COMPLETE ON ROOF. ALL LINE SETS IN CORRIDORS ON SOUTH AND SOUTH EAST SIDES. WILL NEED NAIL PROTECTION AND LINE INSPECTIONS IN ALL WALLS STARTING AT 5TH FLOOR DOWN THROUGH ALL FLOORS TO GARAGE LEVELS. WHEN READY. | JON | JON | | HRP | P | 6283989 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 07/30/2019 | 2ND FLOOR NORTH: 60 PSI PRESSURE TEST, NAIL PROTECTION AND SUPPORT FOR SUPPLY/RETURN PIPING FROM WATER HEATER TO FCU OK FOR UNITS 201-214 HIGHLIGHTED ON M-103.A WITH PURPLE CIRCLES. Blue Beam page 225 | MARKB | MARKB | | HWP | P | 6281435 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 07/29/2019 | 3RD FLOOR NORTH. ALL UNITS #301 THROUGH #314. HWP TEST AND VISUAL INSPECTION OK. PLAN PAGE M-104.A, BDA PAGE #249. MARKED WITH ORANGE LINE | BILLS | BILLS | | HWP | P | 6279911 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 07/29/2019 | 3RD FLOOR SOUTH. 10LB TESTS OK FOR UNITS #326, 328, 330, 332, 334, 337, 339, 341, 343, 345, 347, 349, AND THE RTU RISER IN #349. PLAN PAGE MG104.B, BDA PAGE #228. MARKED WITH AN ORANGE LINE. GARAGE LEVEL 1 NORTH FURNACE #1 TO BE RE-CALLED WITH PRESSURE TEST. | BILLS | BILLS | | HI | P | 6279868 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 07/26/2019 | ADDED APPROVED RFI FROM DESIGN TEAM FOR WATER HEATER CHANGES IN IMAGES, PLAN SPLICES TO GO THROUGH RBD PLAN REVIEW FOR APPROVAL WHEN READY. | JON | JON | | HSP | P | 6281993 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 07/26/2019 | 4TH FLOOR NORTH CORRIDOR. ALL UNITS ( #401 THROUGH #414) HWP TEST AND VISUAL INSPECTION OK. PLAN PAGE M-104.A, BDA PAGE #249. MARKED WITH A GREEN LINE. | BILLS | BILLS | | HWP | P | 6278033 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | P | 07/25/2019 | 5TH FLOOR NORTH CORRIDOR, ALL UNITS EXCEPT #502 AND #513 HWP TEST AND VISUAL INSPECTION OK. PLAN PAGE M.105.A, BDA PAGE #251. MARKED WITH BLUE LINE | BILLS | BILLS | | HWP | P | 6277077 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/23/2019 | DISCUSSED TRASH ROOM AND EXHAUST SYSTEMS, WAITING ON NEW DESIGN. ALSO DISCUSSED GARAGE LEVEL ONE RETURN AIR PLENUM AT OFFICES AS ALL MATERIALS IN PLENUM ARE TO BE PLENUM RATED | JON | JON | | HSP | P | 6273617 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 07/23/2019 | ALL FIRE DAMPER ANGLES ON FAN COILS OK 5TH FLOOR NORTH AND SOUTH EXCEPT FOR ALL MEZZANINE UNITS. FIRE SMOKE DAMPER FRAMING OK AT FIFTH FLOOR JANITOR/STORAGE ROOMS WOOD WALLS ONLY NORTH AND SOUTH 2 DAMPERS. SEE YELLOW CLOUDS ON SHEETS M-105 A AND M-105B BLUE BEAM PAGES 251 AND 252 | JON | JON | | HD | P | 6273607 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 07/22/2019 | GROUND FLOOR NORTH: 10 PSI PRESSURE TEST ON BRANCHES TO FRN-2, 3 &4 OK INSTALLED PER PLAN HIGHLIGHTED IN PURPLE DASH SHEET MG-102.A BLUE BEAM PAGE 223 | MARKB | MARKB | | HI | P | 6271808 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 07/22/2019 | ----ENGINEER TO ADDRESS WATER HEATER BRAND AND MODEL NUMBER BEING INSTALLED IN APARTMENTS IS NOT LIST AS AN ACCEPTABLE MODEL----- 5TH FLOOR NORTH: WATER HEATER VENTS COMPLETE THROUGH ROOF FOR UNITS 501, 514. vENTS FOR UNITS 402 & 302 OK ON 5TH FLOOR ONLY. Still need to hook up to equipment and complete termination caps per manufacturer instructions. HIGHLIGHTED ON M-105.A B.B. PAGE 251 WITH PURPLE CLOUD. | MARKB | MARKB | | HV | P | 6271540 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HWP | L | 07/22/2019 | NOT READY | MARKB | MARKB | | HWP | L | 6271537 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 07/17/2019 | 5TH FLOOR NORTH: DAMPERS - FCU DAMPER ANGLES BELOW PRE-ROCK OK FOR UNITS 501, 503, 505, 507, 509, 511, 514, 515, 516, 517 & 521 HIGHLIGHTED WITH BLUE SQUARE ON M-105.A SHEET. | MARKB | MARKB | | HD | P | 6267009 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 07/16/2019 | 5TH FLOOR NORTH: DAMPER ANGLES FOR FCU'S BELOW PRE ROCK OK FOR UNITS 504, 506, 508 & 510 HIGHLIGHTED WITH YELLOW SQUARE ON SHEET M-105.A BLUE BEAM 251 | MARKB | MARKB | | HD | P | 6264696 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/12/2019 | CONSULTED ON FAN COIL DAMPERS. THESE DAMPERS NEED TO HAVE THE DRYWALL UP TIGHT TO THE DAMPER PER THE DAMPER INSTRUCTIONS WITHIN 1/8TH OF AN INCH. BEFORE THE ANGLES ARE INSTALLED. THIS WILL REQUIRE AN INSPECTION AFTER DRYWALL AT ALL RADIATION DAMPERS BEFORE GRILLS AND FAN COIL PLENUMS ARE INSTALLED. AFTER FIRE DAMPER ANGLES ARE INSTALLED WILL REQUIRE ONE MORE INSPECTION BEFORE THE PLENUM IS INSTALLED AT THE FAN COIL. WENT OVER THIS WITH SAM ON SITE. | JON | JON | | HSP | P | 6262534 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/12/2019 | CONSULTED ON CPVC DRAIN LINES FOR FAN COILS AND TRAPS. MANUFACTURE ASKED FOR MINIMUM 1 1/2" DEEP TRAPS. CONTRACTOR TO PROVIDE INFORMATION TO ENSURE CPVC IS ALLOWED IN RETURN PLENUMS, WILL NEED INSPECTIONS ON ALL CONDENSATE PIPING WHEN READY AT ALL APARTMENT UNITS BEFORE COVER. | JON | JON | | HSP | P | 6262504 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 07/11/2019 | 10 PSI PRESSURE TEST ON GAS PIPING FROM UNIT 501 TO RTU-1 ON ROOF HIGHLIGHTED IN PURPLE ON SHEET MG105.A BLUE BEAM PAGE 229. Still need final connection to RTU | MARKB | MARKB | | HI | P | 6260069 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/11/2019 | LEVEL 5 NORTH: FCU MOCK UP IN UNIT 512 OK HIGHLIGHTED IN PURPLE CIRCLE SHEET M105.A BLUE BEAM PAGE 251. At this point contractors on site do not know who is installing condensate drains for FCU'S - Secondary protection will be a switch installed in the pan. | MARKB | MARKB | | HSP | P | 6260041 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 07/11/2019 | BATH, DRYER AND HVAC DUCTS ONLY.. RADIATION DAMPERS INCLUDED FOR UNITS 201, 222, 224, 226, 227, 228, 232, 234, 236,237, 239, 241, 245, 247, 249 . INDICATED BY PURPLE CIRCLES. BLUE BEAM PAGE 248 M-103B
| MARKB | MARKB | | HD | P | 6260034 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 07/03/2019 | Checked mock up fan coil damper on 5th floor to discuss drywall clearance at damper. must have maximum 1/8" clearance and then install second set of 1 x 1 angles after drywall. this will be a 2 step inspection process on fan coil dampers before fan coil and duct is installed. | JON | JON | | HSP | P | 6252229 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/28/2019 | COLOR PLANS NEXT TRIP...INSPECTED FIRE DAMPER FRAMING AND ALL OK AT 5TH, 4TH, 3RD, 2ND FLOOR TELCOM AND TRASH ROOMS 3 DAMPERS PER FLOOR. SEE BLUE HIGH LIGHTS. DAMPER FRAMING OK FOR JANITOR CLOSETS AT NORTH AND SOUTH 4TH, 3RD, AND 2ND FLOORS. WOOD WALLS ONLY SEE BLUE HIGH LIGHTS FOR DAMPER FRAMING SEE AGAIN AFTER DRYWALL IS APPLIED. | JON | JON | | HD | P | 6248751 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/28/2019 | SAM WILL RESCHEDULE THIS HVAC INSPECTION | JON | JON | | HD | P | 6248436 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 06/28/2019 | STILL NEED UNIT 236. ALL SOUTH UNITS 2ND FLOOR 237,239,226,241,228,230,243,232,245,234,247,249 AND RTU LINE IN THIS UNIT 249. 2" AND 1 1/2" MAIN GARAGE LEVEL ONE SOUTH AND ALL BRANCHES ON THIS . INCLUDING 116,118,120,122. MG-102 A AND MG-102B FOR UNIT 101 FOR REPIPE NORTH WALK UP UNIT. PURPLE HIGH LIGHTS | JON | JON | | HI | P | 6248426 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 06/27/2019 | BLUE BEAM PAGE 251 5TH FLOOR NORTH 11 WATER HEATER CONCENTRIC VENTS 503 THROUGH 515 . 513 NOT READY YET. GREEN CLOUDS ON PLANS. | JON | JON | | HV | P | 6246678 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 06/26/2019 | GREEN HIGH LIGHTS ON BLUE BEAM PAGE 247 SHEET M-103A. FIRE SMOKE DAMPER FRAMING OK FOR 2 DAMPERS AT TELECOM ROOM AND ONE TRANSFER DAMPER AT TRASH ROOM. STILL NEED DRYWALL APPLIED IN DAMPER OPENINGS AND EXPANSION INSPECTIONS WHEN READY. NEED PLANS REVISED FOR CHANGES AT TRASH ROOM AND WILL NOT BE ABLE TO PERFORM INSPECTIONS FOR DESIGN CHANGES WITHOUT ENGINEER INVOLVEMENT AND AN APPROVED SPLICE. PLANS SHOW 4 DAMPERS 2 IN TELECOM AND 2 IN TRASH ROOM WHERE ONLY ONE IS FRAMED IN TRASH ROOM FOR A TOTAL OF 3. | JON | JON | | HSP | P | 6245563 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 06/25/2019 | CONSULTED ON FIRE DAMPERS FOR 5TH FLOOR NORTH AND 5TH FLOOR SOUTH JANITOR CLOSETS. THESE DAMPERS MUST HAVE HEADERS TIED INTO VERTICAL STUDS FLOOR TO CEILING ON BOTH SIDES OF DAMPER TO INSTRUCTIONS. ALSO MET WITH AARON FROM CSI AND SAM FROM BRUCE MECHANICAL FOR 2 DAMPERS OVER SINGLE WIDE DOORS AT ELECTRICAL ROOMS. TOP AND BOTTOM HEADERS MUST BE TIED INTO SIDE VERTICAL STUDS PER INSTRUCTIONS. NEED TO SET UP ANOTHER MOCK UP FOR INSPECTION. ALSO SENT CODE INFORMATION TO AARON AND SAM FOR CORRIDORS AT THE WALK UP UNITS FOR REQUIREMENTS AND EXCEPTIONS FOR ELIMINATING DAMPERS AT THESE FIRE BARRIERS AND FIRE PARTITIONS. | JON | JON | | HSP | P | 6243289 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 06/24/2019 | 5TH FLOOR LINESETS - LOOKED AT LINESET INSULATION AND ROUTING FOR CORRIDORS SERVING AND UNIT #'S 501-516, 519 & 521. HIGHLIGHTED AND DATED ON PLANS IN PURPLE SHEET M105A (B.B. page 251) | MARKB | MARKB | | HRP | P | 6241132 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/18/2019 | UNABLE TO HIGH LIGHT PLANS IN SHARED FILE / ONSITE PLANS HAVE BEEN HIGH LIGHTED IN YELLOW THIS INSPECTION WAS FOR THE FOLLOWING - 3TD FLOOR ABOVE PRE ROCK - F/D - SA DUCTS - DRYER - FANS OK IN THE FOLLOWING UNITS - 315 - 317 - 319 - 321 - 316 - 323 - 318 - 325 - 320 - 322 - 327 - 329 - 331 - 333 - 324 - 335 - 337 - 339 - 326 - 341 - 328 - 330 - 343 - 332 - 345 - 347 - 349 | JERRYF | JERRYF | | HD | P | 6235271 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 06/14/2019 | THIS INSPECTION WAS FOR LINE SET PRESSURE TESTS AT COUCHES 3 AND 4 - 32 TESTS OK - STILL NEED LINE SET INSPECTIONS | JERRYF | JERRYF | | HRP | P | 6232046 |
BRUCE MECHANICAL OF COLORADO, INC | HRP | P | 06/12/2019 | DATE OF INSPECTION 6/12/ 19 - PRESSURE TESTS ONLY ON CONDENSERS PADS 1 AND 2 - STILL LINE SET INSPECTIONS - UNIT 511 LOST TEST - 43 OTHER TESTS OK | JERRYF | JERRYF | | HRP | P | 6228463 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/11/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 4TH EAST AND SOUTH ABOVE PRE ROCK - F/D - DRY - FAN - SA DUCTS OK IN THE FOLLOWING UNITS HIGH LIGHTED IN ORANGE - 420 - 422 - 427 - 421 - 423 - 425 - 429 - 431 - 433 - 435 - 439 - 426 - 441 - 428 - 430 - 443 - 432 - 445 - 447 | JERRYF | JERRYF | | HD | P | 6227096 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/04/2019 | NOTES ADDED ON 6/5 NEED TO HIGH LIGHT ONSITE PLANS - THIS INSPECTION WAS FOR THE FOLLOWING - 4TH FLOOR FIRE DAMPERS // SA DUCT / FANS /DRYER VENTS ABOVE PRE ROCK IN THE FOLLOWING UNITS OK - 401 - 413 - 415 - 417 - 419 - 416 - 423 - 418 | JERRYF | JERRYF | | HD | P | 6219537 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 06/03/2019 | INSPECTION FOR UNIT 503 ONLY SEE BLUE BEAM PAGE 252 105A. ALSO SEE BLUE PAGE PAGE 253 105B FOR UNITS 541, 526, 528,530, 532. GREEN HIGH LIGHTS ALL ROUGH DUCT COMPLETE IN THESE UNITS FOR HVAC, DRYER AND BATH EXHAUST WITH RADIATION DAMPERS GREEN CLOUDS FOR TODAY | JON | JON | | HD | P | 6219602 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 05/29/2019 | 1 WATER HEATER VENT 3RD FLOOR UNIT 324 ONLY OK. BLUE BEAM PAGE 250 GREEN CLOUD | JON | JON | | HV | P | 6213435 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 05/28/2019 | BLUE BEAM PAGE 229 AND 230 GREEN CLOUDS 10 LB TEST OK FOR 5TH FLOOR RISERS AT 14,15, 16,17,19, 21 AND 24,29, 33,35 | JON | JON | | HI | P | 6212422 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/23/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 5TH FLOOR EAST UNITS - ABOVE PRE ROCK - F/D - DRYER - FANS - SA DUCTS OK IN THE FOLLOWING UNITS - 515 - 517 - 519 - 521 - 529 - 531 - 535 - 524 - 535 | JERRYF | JERRYF | | HD | P | 6208906 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/22/2019 | HVAC, BATH EXHAUST AND DRYER DUCTS OK AT THE YELLOW CLOUDED UNITS. INCLUDES RADIATION DAMPERS. 2ND FLOOR EAST WING EXCEPT NUMBER 227 WILL HAVE ANOTHER HEAT RUN AND DAMPER INSTALLED AFTER RFI IS APPROVED BLUE BEAM PAGE 247 AND 248 M-103 A AND M-103 B | JON | JON | | HD | P | 6207648 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 05/20/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 3TD AND 4TH FLOOR WATER HEATER VENTS WHERE RELOCATED TO CORRIDORS AT THE FOLLOWING UNITS 302 - 402 - 336 - 436 AND WILL NEED PLAN REVISIONS APPROVED THROUGH PPRBD - FROM UNITS THROUGH TO 5TH FLOOR CEILING | JERRYF | JERRYF | | HV | P | 6204395 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 05/20/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 4TH EAST HI AND PRESSURE TEST OK ON THE FOLLOWING UNITS - 414 - 415 - 416 - 417 - 418 - 419 - 420 - 421 - 422 - 423 - 424 - 425 - 427 - 429 - 431 - 433 - 435 | JERRYF | JERRYF | | HI | P | 6204380 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/14/2019 | 2ND FLOOR NORTH SIDE CORRIDOR 201,203,205,207,209,211,213 DRYER, BATH EXHAUST, HVAC DUCTS AND RADIATION DAMPERS OK. ORANGE CLOUDS AND BLUE BEAM PAGE 247 M-103 A | JON | JON | | HD | P | 6198745 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 05/14/2019 | 3RD FLOOR SOUTH WATER HEATER VENTS IN 326, 328, 330, 332, 334, 349, 347, 345, 343, 341 339 YELLOW CLOUDS BLUE BEAM PAGE 250 M-104 B | JON | JON | | HV | P | 6198529 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/13/2019 | GREEN CLOUDS 3RD FLOOR DRYER, HVAC AND BATH FAN DUCTS WITH RADIATION DAMPERS OK ..301,303,305,307,309,311,313,314 | JON | JON | | HD | P | 6196774 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 05/10/2019 | WENT OVER MOVING OF ALL PREVIOUSLY INSPECTED RADIATION DAMPERS DUE TO THE R/C CHANNEL DEPTH CHANGE AND HAVING TO MOVE ALL THE RADIATION DAMPERS. ALSO DISCUSSED KEEPING TRACK OF OF DRYER DUCT LENGTHS FOR ALL APARTMENTS AS TO HAVE PROPER PLACARDS POSTED IN LAUNDRY ROOMS FOR ACTUAL DRYER DUCT LENGTHS BY FINAL. ALL DRYER DUCTS ARE OVER 35 FEET IN LENGTH. | JON | JON | | HSP | P | 6195246 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 05/09/2019 | THIS INSPECTION WAS FOR 4TH EAST - FLOOR EAST AND SOUTH WATER HEATER VENTS - THE FOLLOWING UNITS ARE OK - 414 - 415 - 417 - 418 - 425 - 420 - 422 - 427 - 429 - 431 - 433 - 424 - 435 - 437 - SOUTH - 439 - 426 - 441 - 428 - 430 - 443 - 432 - 445 - 434 - 447 - 449 - VERIFY FINAL CONNECTIONS AT WATER HEATER AT FUTURE INSPECTION | JERRYF | JERRYF | | HV | P | 6193920 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 05/09/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 3TD FLOOR EAST PRESSURE TESTS AND PIPING OK IN THE FOLLOWING UNITS OK - 335 - 324 - 333 - 331 - 329 - 327 - 322 - 320 - 325 - 318 - 323 - 316 - 321 - 319 - 317 - 314 - 315 | JERRYF | JERRYF | | HI | P | 6193914 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/08/2019 | THIS INSPECTION WAS FOR THE FOLLOWING 4TH FLOOR NORTH UNITS HIGH LIGHTED IN ORANGE ON PLANS - THE FOLLOWING UNITS ABOVE PRE ROCK INCLUDING DRYERS / FANS / RAD. DAMPERS AND SUPPLY DUCTS - UNITS 411 - 414 - 412 - 409 - 410 - 408 - 407 - 406 - 405 - 404 - 403 | JERRYF | JERRYF | | HD | P | 6193119 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 05/07/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 5TH FLOOR NORTH UNITS - RAD. DAMPERS - DRY - FANS - SA DUCT - NEED DRYER COMPLETED IN UNIT 503 - NOTES: THE FOLLOWING UNITS ARE OK - 514 - 511 - 509 - 507 - 505 - 501 - 504 - 506 - 508 - 510 - 512 | JERRYF | JERRYF | | HD | P | 6190842 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 05/07/2019 | THIS INSPECTION WAS FOR THE FOLLOWING - 3RD FLOOR EAST WATER HEATER VENTS ABOVE PRE ROCK - THE FOLLOWING UNITS ARE OK - 315 - 317 - 319 - 321 - 323 - 325 - 320 - 322 - 327 - 318 - 329 - 331 - 333 - 324 - 335 - 337 | JERRYF | JERRYF | | HV | P | 6190816 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/30/2019 | THIS INSPECTION WAS FOR 5TH FLOOR NORTH UNITS AND RTU 1 RISER - 12 PRESSURE TESTS OK ON THE UNITS - 501 - 503 - 504 - 505 - 506 - 507 - 508 - 509 - 510 - 511 - 512 - RTU 1 RISER FROM GARAGE TO 5TH FLOOR | JERRYF | JERRYF | | HI | P | 6182454 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 04/25/2019 | THIS INSPECTION WAS FOR THE FOLLOWING ABOVE PRE ROCK - 2ND FLOOR WATER HEATER VENTS IN THE FOLLOWING UNITS - 217 AND 233 FROM 2ND FLOOR THROUGH TO 5TH FLOOR OK - THE FOLLOWING UNITS ARE CONCENTRIC THROUGH SIDE WALL - 219 - 221 - 223 - 229 - 231 - ALL OK - HIGH LIGHTED IN PURPLE ON CSI PLANS | JERRYF | JERRYF | | HV | P | 6177925 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 04/24/2019 | CONSULTATION FOR DEPTH CHANGE FOR R/C CHANNEL ON RATED ASSEMBLIES. ALL RADIATION BOOTS AND PLENUM DAMPERS INCLUDING THE ONES THAT HAVE ALREADY BEEN INSPECTED WILL BE RAISED AND NEW SUPPORT RAILS ADDED TO BOTTOM OF TRUSS ASSEMBLY. CONTRACTOR WILL RECALL ALL PREVIOUSLY INSPECTED UNITS WHEN WORK IS READY FOR INSPECTION. | JON | JON | | HSP | P | 6177214 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/19/2019 | FIELD CANCELLED BY SAM | JON | JON | | HD | P | 6171908 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/19/2019 | 1- GAS RISER AT 206, 306, 406, 10 LB TEST OK YELLOW FOR 206, BLUE FOR 306 AND GREEN FOR 406. MG-104 A, 306, MG-104A AND 206 ON MG-103 A BLUE BEAM 225 AND 227 | JON | JON | | HI | P | 6171904 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/18/2019 | BATH, DRYER AND HVAC DUCTS ONLY.. RADIATION DAMPERS INCLUDED FOR FOR NORTH TOWER UNITS 304,306, 308, 310, 312 U-1 APARTMENTS. SHEET M104-A BLUE BEAM PAGE 249. | JON | JON | | HD | P | 6170371 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/18/2019 | GREEN BOXES ARE FOR 4TH FLOOR. 201-205 AND 207 - 213.10 LB OK. ALSO 10 LB TEST ON RTU RISER AT 401. INCLUDES UNIT 302 RISER 10 LB TEST BLUE BOX MG-104 A BLUE BEAM PAGE 227 | JON | JON | | HI | P | 6170328 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/15/2019 | BATH, DRYER AND HVAC DUCTS ONLY.. RADIATION DAMPERS INCLUDED FOR FOR NORTH TOWER UNITS 208, 210, 212, 214 U-1 APARTMENTS BLUE BEAM PAGE 247 M- 103A SEE BLUE CLOUD HIGH LIGHTS | JON | JON | | HD | P | 6166167 |
BRUCE MECHANICAL OF COLORADO, INC | HD | P | 04/10/2019 | BATH, DRYER AND HVAC DUCTS ONLY.. RADIATION DAMPERS INCLUDED FOR UNITS 204 AND 206 U-I APARTMENTS SAWTOOTH. INDICATED BY RED CLOUDS STILL NEED HRP INSPECTIONS IN UNITS BEFORE COVER. BLUE BEAM PAGE 247 M-103A | JON | JON | | HD | P | 6162206 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/10/2019 | SEE BLUE BEAM PAGE 227 FOR MG-104 FOR ALL BUT 2 APARTMENTS FOR GAS RISERS. NORTH WING BLUE HIGHLIGHTS 10 POUND TEST OK. | JON | JON | | HI | P | 6162205 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 04/08/2019 | WENT OVER ROUGH INSPECTION PROTOCOL FOR DRYER, BATH EXHAUST AND HVAC DUCTS ABOVE HARD LID CEILINGS IN ALL APARTMENTS. AFTER A ROUGH INSPECTION IS DOCUMENTED, THERE WILL NEED TO BE AN INSPECTION FOR R/C CHANNEL TO MAKE SURE CHANNELS ARE NOT AFFECTING RADIATION DAMPERS IN ANY WAY AND PROPER CLEARANCE IS OBTAINED FROM THE R/C CHANNEL TO THE DAMPER PER INSTRUCTIONS. THIS WILL BE ANOTHER INSPECTION AFTER THE DRYWALL IS INSTALLED TO ENSURE THAT THE DRYWALL CLEARANCE FOR THE DAMPER IS TO THE INSTRUCTIONS. AFTER DRYWALL ON THE FAN COIL DAMPERS AND CLEARANCE HAS BEEN VERIFIED THERE WILL BE ANOTHER RETAINING ANGLE THAT HAS TO BE VERIFIED TO SANDWICH THE SHEET TO THE R/C CHANNEL THEN THE FAN COIL AND SUPPLY PLENUM CAN BE INSTALLED. ALSO SPOKE AGAIN ABOUT LISTINGS AND DAMPER APPROVALS. ALL DRYER AND BATH FAN EXHAUST TERMINATIONS ARE TO BE 36" FROM OPERABLE OPENINGS. DISCUSSED DRYER PLACARDS FOR DRYER DUCTS BY FINAL. DISCUSSED RETURN AIR PLENUM FOR EXPOSED MATERIALS IN THE PLENUM AREA. DISCUSSED HRP (REFRIGERATION LINE SETS) INSPECTIONS MUST BE INSPECTED PRIOR TO SHEET ROCK IN ALL UNITS. WILL FOLLOW UP WITH CONTRACTOR FOR ANY MAKEUP AIR REQUIREMENTS NEEDED NEXT INSPECTION. | JON | JON | | HSP | P | 6159182 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 04/04/2019 | NEED SPLICE FOR ADDED INDEPENDENT RTU PIPING FROM GARAGE LEVEL TO ROOF THIS LINE TESTED FROM LEVEL 2 DOWN TO 2 INCH IN GARAGE LEVEL.. M SHEET MG-103A BLUE BEAM PAGE 225. STILL NEED 206 AS IT WAS NOT READY, ALL OTHER NORTH 2ND FLOOR WITH YELLOW HIGH LIGHTED SQUARES GAS RISERS COMPLETE TO TOP OF CLOSET 10 LB TEST OK. | JON | JON | | HI | P | 6155802 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 04/03/2019 | WATER HEATER VENTS ON 4TH FLOOR BOTH SIDES OF NORTH CORRIDOR OK ONLY. SEE RED COLORED BOXES ON SHEET M-104 A. BLUE BEAM PAGE 249. | JON | JON | | HV | P | 6154270 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 04/02/2019 | 3RD FLOOR NORTH WING WATER HEATER VENTS THROUGH CONCEALED SPACE OK .. STILL NEED 305 AND 302 ON NORTH WING. SEE BLUE BEAM PAGE 249 M-104A FOR PURPLE BOX HIGHLIGHTS | JON | JON | | HV | P | 6152912 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 04/02/2019 | SPOKE WITH SAM ABOUT SOME INSPECTION PROCEDURES AND HE WILL CALL FOR A CONSULTATION INSPECTION ON MONDAY OF NEXT WEEK. | JON | JON | | HSP | P | 6152212 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 03/29/2019 | 3-29-19 WATER HEATER VENTS ON UNITS MARKED WITH PURPLE BOX HIGHLIGHTS STILL NEED VENT INSPECTIONS FOR UNITS 17,19,21,22,23,29,31,33,49. M-SHEETS 103 A AND 103 B BLUE BEAM PAGES 247 AND 248..ALL OTHER UNITS ON ENTIRE SECOND FLOOR VENTS COMPLETE SEE CONNECTIONS TO WATER HEATERS WHEN READY | JON | JON | | HV | P | 6149690 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/20/2019 | WENT OVER DAMPER INSTRUCTIONS AND ASSEMBLY LISTING WITH AARON FROM COLORADO STRUCTURES. NEED INSTRUCTIONS AVAILABLE WHEN INSPECTIONS ARE READY IN EACH UNIT. SUPPLY AIR PLENUM DAMPER IS LARGER THAN THE MAX OPENING SIZE ALLOWED PER THE UL LISTING. A MAX OPENING SIZE OF 180 SQUARE INCHES IS INDICATED AND THE DAMPER OPENINGS ARE 196 SQUARE INCHES. AARON WILL WORK WITH UL AND DESIGN TEAM FOR A RESOLUTION. | JON | JON | | HSP | P | 6139047 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 03/20/2019 | SEE INSPECTION NOTES FROM HSP THAT WAS ADDED ON THE 20TH FOR WATER HEATER VENTS CALLED CONTRACTOR | JON | JON | | HV | P | 6139046 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HSP | P | 03/20/2019 | CONSULTATION FOR SAWTOOTH UNITS TO CHECK WATER HEATER VENTING. RHEEM WATER HEATERS NOT ON SITE AT THIS TIME. WORKING OFF OF RHEEM MANUAL AND WILL HAVE TO VERIFY WATER HEATERS ONCE ON SITE. VENT DISTANCES ON ROUGH INSPECTION WILL BE INSPECTED ON EACH 65K RHEEM HEATERS NOT TO EXCEED 50 FEET INCLUDING ALL THE FITTINGS AND PIPE THAT WILL BE REQUIRED TO DROP DOWN AND CONNECT THE HEATERS. WENT OVER THIS WITH AARON AND TONY ON SITE. | JON | JON | | HSP | P | 6139041 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/18/2019 | WENT OVER DRYER VENT REQUIREMENTS AND DRYER PLACARD BY FINAL FOR ANYTHING OVER 35 FEET. ALL FIRE DAMPERS ARE TO BE INSTALLED TO PROPERLY FINISH WHERE REQUIRED WITH R/C CHANNEL.. ALL DAMPER ARE TO BE INSTALLED LEVEL AND FUNCTION PROPERLY. MUST NOT HAVE ANY SCREWS IN THE PATH OF THE DAMPER. ALL FASTENERS ARE THE SIZE AND TYPE SPECIFIED BY THE MANUFACTURE. MUST HAVE ALL THE INSTALLATION INSTRUCTIONS FOR THE RIGHT DAMPER APPLICATION. DUCT SYSTEMS MUST BE INSTALLED PER APPROVED PLANS. NEED PROPER SEALING OF ALL DUCT JOINTS. MUST HAVE ALL DUCTS COMPLETED TO X-VENTS. SPOKE ABOUT DAMPER ACCESS DOORS AT FAN COILS. ALSO DISCUSSED AND CHECKED WITH BUILDING INSPECTOR FOR FHA STRAP REQUIREMENTS A DRYER DUCTS AND DUCT PENETRATIONS FOR FIRE CALUK AS SOME HOLES APPEAR TO BE TO LARGE AT THIS TIME. | JON | JON | | HSP | P | 6136198 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/18/2019 | ADDED NOTE FROM LAST INSPECTION. BUILDING RATED HORIZONTAL ASSEMBLIES HAVE CHANGED TO A L574 FLOOR/CEILING AND A P545 ROOF/ CEILING ASSEMBLY. ALERTED BUILDING INSPECTOR FOR THE PROPER PLAN CHANGES | JON | JON | | HSP | P | 6138339 |
BRUCE MECHANICAL OF COLORADO, INC | HSP | P | 03/13/2019 | WORKED WITH BRENDAN ON SITE.. WENT OVER INSPECTION TYPES AND PROCEDURES. WENT OVER UL LISTING AND ASSEMBLIES FOR DAMPER APPROVALS. CONTRACTOR TO VERIFY ALL LISTINGS WITH DAMPERS. WENT OVER FAN COIL SHUT DOWN SYSTEM FOR RADIATION DAMPERS. PERMIT REQUIREMENTS FOR POOL BOILERS AND VENTING. PERMIT SCOPE TO ADD FURNACE VENTS AND POSSIBLY BOILER VENTS. NEED TO GET WITH BUILDING INSPECTOR FOR BOILER VENT PENETRATIONS IN RATED WALLS. | JON | JON | | HSP | P | 6132901 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 03/12/2019 | BLUE HIGHT LIGHTS ON SHOP DRAWING IN CSI OFFICE. EAST SIDE 2ND FLOOR RISERS FROM 4" MAIN UP TO TP OF SECOND FLOOR CLOSETS ONLY. TEST AND VISUL INSPECTION OK FOR RISERS TO 214 THROUGH 225 AND 227, 229. 231, 233, 235. 17-10 LB TEST'S OK. | JON | JON | | HI | P | 6132388 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 03/08/2019 | INSPECTED VENTS AT 201, 202,,203 OK. UNIT 205 IS 4" AND NEED VERIFICATION OF 90 FEET FOR TOTAL VENT LENGTH. NEED PROPER INSTRUCTION MANUAL FOR THE PRO SERIES HEATERS. 207, 209, 211, 213 OK. ALSO SPOKE WITH KYLE AND TONY ABOUT THE SAWTOOTH UNITS BECAUSE THE VENT LENGTHS ARE SO CLOSE TO THE MAXIMUM TONY WILL LABEL THE VENTS IN THE MECHANICAL ROOM WITH THE ACTUAL VENT LENGTHS TO THAT POINT TO MAKE SURE THAT AFTER THE ADDED PIPING AND WITH MORE FITTINGS WHEN WATER HEATERS ARE ON SITE THE VENT LENGTHS ARE NOT EXCEEDED. | JON | JON | | HV | P | 6128927 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HV | P | 02/07/2019 | CONSULTED ON WATER HEATER VENTING. WENT OVER WATER HEATER INSTRUCTIONS AND IT APPEARS THERE MAY BE SOME CONCERNS WITH THE 3" VENT SIZING EXCEEDING THE LENGTH ALLOWANCE OF 30 FEET AFTER ELBOWS AND OFFSET FITTINGS. CONTRACTOR IS REVIEWING. | JON | JON | | HV | P | 6101022 |
NEWCOMER'S PLUMBING AND HEATING, INC. | HI | P | 02/06/2019 | 60 LB TEST ON EAST 4" MAIN WELDED PIPING, BETWEEN COLUMN LINES 6 AND 7. TWENTY TWO WELDOLET'S AND BALL VALVES INSTALLED FOR RISERS. WILL ADD NOTES FOR BLUE BEAM AT NEXT INSPECTION. | JON | JON | | HI | P | 6100166 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | C | 01/12/2021 | All Plan Splices and Corrections approved. | SAMH | SAMH | | P= | C | 6833736 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 01/12/2021 | Main level sink corrections made. Need further review with previous inspector concerning Plan Splices. - Will update notes after review. | SAMH | SAMH | | P= | P | 6833705 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 10/20/2020 | phase 3 ok for TCO, still need corrections as noted | JOEL | JOEL | | P= | P | 6747129 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 10/05/2020 | ok for all of club house
STILL need 1st floor public bath correction | JOHNS | JOHNS | | P= | P | 6729705 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/29/2020 | Drinking fountain by pool only: freeze protection?. | DANR | DANR | | P= | P | 6722546 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/25/2020 | ok for club house mop sink and kitchen
still need d.f,. water htr, hot water, tempering to fixtures and verify all roof drain membranes removed | JOHNS | JOHNS | | P= | P | 6719554 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/23/2020 | ok for club house bths only minus tempering @ both lavs STILL NEED membranes and remainder of clubhouse | JOHNS | JOHNS | | P= | P | 6716190 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PBP | P | 09/18/2020 | WATTS LF009M2QT rp. NOTE: this complete pool bfp only | JOHNS | JOHNS | | PBP | P | 6710627 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/18/2020 | membranes
ok for --Phase 1-- 315. NOTE: 3rd floor complete ok for --Phase 2-- 209. NOTE: 2nd floor complete ok for --Phase 2-- remainder of first floor, pool bfp, pool indirect waste, and water entry. NOTE: 1st floor complete
STILL NEED : --Phase 2-- club house | JOHNS | JOHNS | | P= | P | 6710619 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/17/2020 | membranes
ok for--Phase 1-- 522, 420, and 425. NOTE: 4th and 5th floor complete
STILL NEED : --Phase 1-- 3rd floor hand shwr --Phase 2-- 2nd floor unit 209 --Phase 2-- remainder of 1st floor to include unisex bath correction, mech room, common areas, indirect waste @ pool, and pool bfp --Phase 2-- club house | JOHNS | JOHNS | | P= | P | 6709715 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/16/2020 | membranes
--Phase 2-- ok for rms 102, 104, 106, 108, 110 , and 112
STILL NEED : --Phase 1-- 5th floor accessible unit --Phase 1-- 4th floor hand shwr (x2) --Phase 1-- 3rd floor hand shwr --Phase 2-- 2nd floor unit 209 --Phase 2-- remainder of 1st floor to include unisex bath correction, mech room, common areas, and pool bfp --Phase 2-- club house | JOHNS | JOHNS | | P= | P | 6707905 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/15/2020 | membranes
need non positive shut offs for all hand held shwrs
STILL NEED all areas / phases noted on last inspection | JOHNS | JOHNS | | P= | P | 6706522 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/10/2020 | STILL NEED revisions and roof membranes corrections
--Phase 2-- ok for 219, 114, 116, 118, 120, and 122
STILL NEED : --Phase 1-- 5th floor accessible unit --Phase 1-- 4th floor hand shwr (x2) --Phase 1-- 3rd floor hand shwr --Phase 2-- 2nd floor unit 209 --Phase 2-- remainder of 1st floor to include unisex bath correction, mech room, and pool bfp --Phase 2-- club house | JOHNS | JOHNS | | P= | P | 6701572 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 09/02/2020 | STILL NEED revisions
--Phase 2 -- ok for 2nd floor units @ 226, 228, 230, 232, 234, 236, 237, 239, 241, 243, 245, 247, and 249
STILL need --Phase 1-- 5th floor accessible unit --Phase 1-- 4th floor hand shwr (x2) --Phase 1-- 3rd floor hand shwr --Phase 2-- 2nd floor unit 219 --Phase 2-- remainder of 1 st floor to include unisex bath correction, mech room, and pool bfp --Phase 2-- club house | JOHNS | JOHNS | | P= | P | 6694627 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/28/2020 | STILL NEED REVISIONS
--Phase 2-- ok for rooms 215-221 MINUS 219, 223-225, 227, 229, 233, and 235
STILL NEED --Phase 2-- RM 219 and remainder of 2nd floor roof drain membrane --Phase 1-- 5th floor accessible unit --Phase 1-- 4th fllor hand shwr (x2) --Phase 1-- 3rd floor hand shwr --Phase 2-- remainder of 2nd floor --Phase 2-- remainder of 1st floor to include mech room and pool --Phase 2-- club house | JOHNS | JOHNS | | P= | P | 6689360 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/27/2020 | --Phase 1-- OK FOR 518, 525, AND 527
--Phase 2-- ist floor unisex barh w/ shwr lacks 5" side clearance to counter top
STILL NEED remaing areas noted on 8/25
ins note only: roof membrane and revisions | JOHNS | JOHNS | | P= | P | 6687741 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/26/2020 | --Phase 2-- ok for lobby water htr / mop sink, G-1 maintenance room, and dog wash only
STILL need remainder of 1st floor, all previous corrections from last inspection, and remainder | JOHNS | JOHNS | | P= | P | 6685882 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/25/2020 | --PHASE 2-- ok for 2nd floor @ units 201-212 MINUS @ 209 need hand shwr, VERIFY SPLICES W/ GC @ following inspections
STILL NEED 5th floor accessible unit and remaining 3 units --PHASE 1-- 4th floor hand shwr (x2), --PHASE 1-- 3rd floor hand shwr --PHASE 1-- remainder of 2nd floor --PHASE 2-- remainder of ist floor to include units ,common areas, water entry and mech --PHASE 2-- club house --PHASE 2-- | JOHNS | JOHNS | | P= | P | 6684712 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/21/2020 | STILL NEED revisions
ok for 301, 313, 1st floor public baths (x2), and mop sinks (x2). MINUS need hand shwr @ common bath, need expansion @ mop sink waer htr, mop sink cant be temepered, rest ok
STILL NEED previous corrections for 8/20/20, and remainder | JOHNS | JOHNS | | P= | P | 6681486 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/20/2020 | STILL NEED revisions complete
NEED engineers letter addressing vent terminations for all 5th floor units with roof top observation decks
ok for rms 502, 513, 520, 523, 537, 536, and 549
STILL NEED remainder of 5th, 4h, 3rd floor, previous corrections @ 522 hand shwr, 420 and 425 hand shwr and water closets side clearance, and 324 bath, and remainder | JOHNS | JOHNS | | P= | P | 6679513 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/17/2020 | The following 3rd floor rooms ok: 326 -328 - 330 - 332 - 334 - 336 - 337 - 339 - 341 - 343 - 345 - 347 - 349. | DANR | DANR | | P= | P | 6674463 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/12/2020 | ok for rms 522, 420, 425, 314-327,329,331,333,335 MINUS @ 522 need hand shwr, @ 420 and 425 need hand shwr and water closet side clearance, and @ 324 need bath inspected
still need remainder of 3rd floor and remainder | JOHNS | JOHNS | | P= | P | 6670572 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 08/11/2020 | ok for rooms 301- 313 MINUS 301 and 313 kitchens
STILL NEED remainder of 3rd, 4th, 5th, and remaining floors | JOHNS | JOHNS | | P= | P | 6668164 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 07/14/2020 | contractor to verify all revisions / e letters are complete
ok for 4th floor south wing, elevator sumps (x3), and trap seal @ s/o interceptor
still need 5th and 4th floor remainder | JOHNS | JOHNS | | P= | P | 6636975 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 06/25/2020 | ok for 4th floor @ rm#'s 416 - 418, 421, 423, 424, 427, 429, 431, 433, and 435 only
STILL need remainder to include 5th floor | JOHNS | JOHNS | | P= | P | 6617662 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 06/24/2020 | entered results off site due to computer issues
ok for 4th floor @ rm#'s 401 - 411 and 415 only
STILL need remainder to include 5th floor | JOHNS | JOHNS | | P= | P | 6615774 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 06/17/2020 | 520 and 522 not ready, will verify roof drain membranes @ next inspection, contractor to verify all revisions / e letters (if applicable)
ok for 5th floor @ rms 524, 526, 528, 529, 530-535, 539, 541, 543, 545, and 547
STILL NEED remainder | JOHNS | JOHNS | | P= | P | 6607819 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 06/16/2020 | entered results off site due to internet connection
will start to verify all revisions / e letters @ next inspection, contractor to verify all revisions and e letters needed (if applicable)
ok for 5th floor rooms @ 501, 503-512, 515-517, 519, and 521 only
STLL NEED remainder of 5th floor | JOHNS | JOHNS | | P= | P | 6606301 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 05/08/2020 | partial pending plan revision still needed
ok for club house corrections. NOTE: verify drain down valves for drinking fountain.
SUB NOTE: check all water entry, pool equipment , and water htrs, verify membrane cut away @ roof drains | JOHNS | JOHNS | | PTO | P | 6565335 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | P | 05/08/2020 | partial status due to plan revisions needed
rest ok for prd / ord, @ G2 and ok for area drains @ pool deck | JOHNS | JOHNS | | PRD | P | 6565310 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 04/21/2020 | need freeze protection - drain down for outside drinking fountain, rest ok for clubhouse only
STILL NEED pool area drains inspected | JOHNS | JOHNS | | PTO | P | 6546564 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 04/16/2020 | ok for tubs @ 114, 513, and 537
ok for side clearances only @ club house only, still need remainder of club house
still need area drain @ pool deck, and any other areas / corrections previously noted | JOHNS | JOHNS | | PTO | P | 6542625 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 03/13/2020 | ok for tubs @ 102, 110, 112, 327, and 427
still need remainder and clubhouse pto corrections | JOHNS | JOHNS | | PTO | P | 6510035 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | P | 03/13/2020 | ok for club house PRD only
still need remainder | JOHNS | JOHNS | | PRD | P | 6510008 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/28/2020 | club house
low test @ kitchen water gauge, need walls built in bath for side clearance measurements, rest ok
still need PRD | JOHNS | JOHNS | | PTO | P | 6495911 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/24/2020 | ok for added baths in rms 327 and 427 only MINUS tubs set and tested, will measure accessibility once tubs are in. NOTE: aav - all lavs and @ washer boxes (high left side) | JOHNS | JOHNS | | PTO | P | 6490573 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/19/2020 | CLUB HOUSE
still need prd
need freeze protection on all outside wall water lines, need waters to mop sink and kitchen sink, need to see water tie ins at club house bath, pop vent, will verify side clearances on water closets on next inspection, rest ok. NOTE: vtr (1), verify clean outs for water closet vents on final, aav at kitchen, check water htr on final
| JOHNS | JOHNS | | PTO | P | 6486352 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/13/2020 | ok for tubs at 104, 106, 108, 110, 112, 114, 116, 118, 120, and 122 MINUS still need upper tub for 114, need tub for 112, and leak at 110 | JOHNS | JOHNS | | PTO | P | 6482100 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/04/2020 | ok for freeze protection @ garage unit walls
ok for tubs at 513 and 537, STILL need loft area tubs at both 513 and 537 | JOHNS | JOHNS | | PTO | P | 6473435 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 01/30/2020 | 114 h20 test o.k, still need freeze protection for all garage wall units, 513 and 537 dwv o.k | JOEL | JOEL | | PTO | P | 6469879 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 01/23/2020 | water in units 513, 537, 116, 118, 120, 122 test o.k will need to verify freeze protection on garage walls. | JOEL | JOEL | | PTO | P | 6462432 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 01/03/2020 | Tubs: 220,224,226,227,228,229,230,231,232,233,234,235,236,237,239, 241,243,245,247,249 o.k discussed water heater location and piping will need proper clearance and access, check valves will need to be properly installed | JOEL | JOEL | | PTO | P | 6442527 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/26/2019 | Tubs tests in units 502/513/518/520/523/525/527/536/537/549 o.k | JOEL | JOEL | | PTO | P | 6436860 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/19/2019 | H2o units 101-112 o.k, dwv units 536/549/502 o.k | JOEL | JOEL | | PTO | P | 6432277 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/17/2019 | UNITS 122/120/114 DWV O.K 118 LOW TEST UPPER BATH, 116 LOW TEST WASHER BOX | JOEL | JOEL | | PTO | P | 6430124 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/13/2019 | dwv units 518/523/525/520/527 o.k h20 units 518/549/536/502/449/436 | JOEL | JOEL | | PTO | P | 6426964 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/12/2019 | still low h20 test @ 436/ 449/ 502/ 536/ and 549, 518 water not on test
ok for tubs @ 201-213 and 218-225 | JOHNS | JOHNS | | PTO | P | 6426269 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/11/2019 | h2o piping for units 523/525/520/522/527 o.k 502/536/436/549/449 low test | JOEL | JOEL | | PTO | P | 6424340 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/06/2019 | Washer boxes units 101- 114 o.k and 112 retest o.k | JOEL | JOEL | | PTO | P | 6419482 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/05/2019 | west side units 101/102/104/106/108/110/114 dwv o.k, 112 lost test and all washer boxes in these units still need air test | JOEL | JOEL | | PTO | P | 6417851 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 11/12/2019 | unit 412 tub o.k | JOEL | JOEL | | PTO | P | 6396782 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 10/16/2019 | 2nd floor south corridor nail protection o.k. Tub valves in all Type ''A'' units need to be lowered | JOEL | JOEL | | PTO | P | 6370614 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 10/15/2019 | water piping and nail protection in units 324/339/326/341/328/330/343/332/345/347/334/336/349 2nd floor water piping 224/239/226/241/228/230/243/232/245/234/247/236/249 o.k still need nail protection | JOEL | JOEL | | PTO | P | 6368513 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/30/2019 | tubs ok @ rm#'s 334, 336, 345, 347, and 349
still need tubs @ 412 and 420 (from previous inspection) | JOHNS | JOHNS | | PTO | P | 6352287 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/27/2019 | reinspected tubs 305/308/311/321/323 o.k south corridor 3rd floor tubs o.k, still need 345/334/347/336/349 | JOEL | JOEL | | PTO | P | 6350641 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/26/2019 | Tubs for 301/302/303/304/306/307/310/309/312/313/315/317/319/316/318/325 o.k leaks at 305/308/311/321/323 | JOEL | JOEL | | PTO | P | 6348805 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/20/2019 | east and south 4th floor corridor tubs o.k, still need 412 and 420 tubs | JOEL | JOEL | | PTO | P | 6343179 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/18/2019 | still need east tub @ 412 (combined unit)
rest ok for tubs @ 401-425 | JOHNS | JOHNS | | PTO | P | 6339787 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/13/2019 | 4th and 5th floor south wing h2o strapping o.k south wing 5th floor vents thru roof o.k | JOEL | JOEL | | PTO | P | 6334820 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | R | 09/12/2019 | no inspection until plan slice is complete for all storm drain system | JOEL | JOEL | | PRD | R | 6333688 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/12/2019 | Water pipe and nail protection 426/441/428/430/443/432/445/434/447/526/541/528/530/543/534/547 tests o.k will need to verify all strapping in each unit | JOEL | JOEL | | PTO | P | 6333629 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/11/2019 | Tubs: 524/525/534/545 o.k | JOEL | JOEL | | PTO | P | 6331366 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 09/04/2019 | dwv mops sinks south corridor o.k, dwv 347 and 334 up thru 5th floor top plates o.k reinspect: 328 washer box stack up thru 5th o.k, 324 grade for 3'' o.k tubs: 532/539/526/541/528/530/543/545 o.k | JOEL | JOEL | | PTO | P | 6324200 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/30/2019 | Tubs in units 512/516/531 o.k | JOEL | JOEL | | PTO | P | 6320154 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/29/2019 | 324 dwv above ceiling bath group and laundry lacks grade, wb stack in 328-528 lost test, 335 kitchen and washer box dwv o.k 339/326/341/330/343/332/345/ up thru 5th floor top plate o.k Tubs: 503/504/507/508/510/509/515/517/519/521/522/529/533/535 o.k | JOEL | JOEL | | PTO | P | 6319287 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/28/2019 | ok for 5th floor north wing tubs @ rm #'s 501, 504, 503, 505, 506, 507, 508, 509, 510, 511, 512
minus @ 504 not on test, 503 leak @ tub shoe, 507 not on test, and @ 509 need slope and re attach strap @ tub drain | JOHNS | JOHNS | | PTO | P | 6316844 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | P | 08/23/2019 | ok for south wing 4" prd / ord @ G-1 up to 5th floor mezzanine
MINUS remainder of ord @ this area
still need to see tie in point @ trash area | JOHNS | JOHNS | | PRD | P | 6312446 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | L | 08/22/2019 | field cancelled | JOHNS | JOHNS | | PRD | L | 6310175 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/22/2019 | MINUS mezzanine and units skipped, ok for main water and unit waters @ 415, 417, 419, 421, 416, 423, 425, 429, 431, 433, and 435 315, 317, 319, 321, 316, 323, 318, 325, 320, 327, 329, 331, 333, and 335 215, 217, 219, 221, 216, 223, 218, 225, 227, 229, 231, 233, and 235 | JOHNS | JOHNS | | PTO | P | 6310169 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P16 | P | 08/21/2019 | PLAN SPLICES NEEDED: 3) revise plans to show south wing 6" roof drains in lieu of 4"
4) revise plans to show unit 220 , 320, and 420 units combined
5) revise plans to show 4" ord from mezzanine down to G-1 tied into other 4" ord @ G-1
6) revise plans to show (1)- 19 gal water htr @ mop sink in lieu of 10 gal water htr, removing 10 gal water htr @ kitchenette, and installing recirc pump @ CLUB HOUSE | JOHNS | JOHNS | | P16 | P | 6308341 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/21/2019 | dwv for units 420, 427, 431, 433, and 435 stubbed up into ceiling, 529, 531, 533, 535 and vtr @ these 5th floor rooms, MINUS mezzanine units. NOTE: aav @ all washer boxes (up high) and all lavs, dbl lavs = aav / cwv @ either | JOHNS | JOHNS | | PTO | P | 6308340 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | P | 08/21/2019 | south wing 5th floor corridor and @ 541, 543, 547, and 549 MINUS ord's @ theses rooms, 6" stubbed down into g-1, still need tie in point | JOHNS | JOHNS | | PRD | P | 6308339 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P16 | P | 08/15/2019 | PLAN SPLICES NEEDED: 1) G-1 area drains need to show pipe discharging to G-2 north end floor. And perimeter drain tie-in from ejector pit to sand oil drain.
2) plan revision for overflow drains in 507 and 503 that tie together .
| JOEL | JOEL | | P16 | P | 6302358 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/13/2019 | fixed grade from previous inspection 8/8/19, units 230/232/234/236/243/245/247/249 dwv up thru 3rd floor stubbed into ceiling o.k | JOEL | JOEL | | PTO | P | 6299180 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/08/2019 | 235 washer box stack o.k, 237/239/224/224/226/241/243 all lack grade above bathrooms, test up thru 3rd floor top plate o.k | JOEL | JOEL | | PTO | P | 6293971 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/06/2019 | DWV IN G1 SOUTH BELOW UNITS 236/249/247/245/234/232/243/230/228/241/226/239/237/224 THRU THE FLOOR O.K | JOEL | JOEL | | PTO | P | 6290742 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 08/01/2019 | dwv 315/316/317/318/319/321/323/325 o.k dwv 415/416/417/418/419/421/423/425 o.k less 417 and 416 dwv above bathrooms lack grade, dwv 515/516/517/519/521 o.k thru roof | JOEL | JOEL | | PTO | P | 6285797 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 07/18/2019 | water pipe 207 ok | JOSEPHD | JOSEPHD | | PTO | P | 6268297 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 07/17/2019 | inspection for water pipe only, still need to see 513,502 completed, low test at 207, north side corridor units 2nd,3rd,4th,5th ok | JOSEPHD | JOSEPHD | | PTO | P | 6266700 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 07/01/2019 | reviewed accessible requirements for type "b" units 2003 ANSI standard | JOEL | JOEL | | PTO | P | 6249819 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | P | 06/27/2019 | north end corridor roof drains o.k down to ceiling of garage, 5th floor mezzanine primary drains not ready, 6'' primary o.k to room 212 and 4'' primary o.k to room 215 revise plans to show 507 and 503 overflow drains tied together and rerouted 6'' in east corridor | JOEL | JOEL | | PRD | P | 6247027 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 06/05/2019 | 220/320, 222/322, 224/324, 227/327, 229/329, 231/331, 233/333, 235/335 DWV o.k from garage up to 3rd floor ceiling | JOEL | JOEL | | PTO | P | 6221434 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 05/29/2019 | rooms 215/217/219/216/223/218/220 dwv o.k 221 has leak on 3'' above waher box, change wet vent for 225 in garage. rooms 315-325 dwv o.k | JOEL | JOEL | | PTO | P | 6212851 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 05/14/2019 | 311/312/314 dwv up thru roof o.k 315 kitchen and laundry stacks up thru roof o.k, check toilet side clearances when tubs are installed | JOEL | JOEL | | PTO | P | 6198179 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 05/07/2019 | fixed all leaks from previous inspection, 304/403/509/505 | JOEL | JOEL | | PTO | P | 6191389 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 05/06/2019 | 301-310 up thru 4th and fifth floors thru roof o.k less 302-502 not ready, 304 leak on 4'' stack behind bathtub, 403 leak at 3x2 wye above toilet, 509 leak on 3'' vent, 505 low test laundry and kitchen stacks | JOEL | JOEL | | PTO | P | 6188404 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 03/25/2019 | east side north tower 2nd and 3rd floor dwv ok | JOSEPHD | JOSEPHD | | PTO | P | 6143383 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 03/22/2019 | north tower dwv 201-208 and 301-308 o.k h2o main test north garage o.k | JOEL | JOEL | | PTO | P | 6141049 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/27/2019 | Consultation for above garages dwv, need plan splice for area drain terminations in g-2 and perimeter drain tie in from ejector pit to sand oil drain | JOEL | JOEL | | PTO | P | 6119169 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/07/2019 | west side basement main test ok | JOSEPHD | JOSEPHD | | PTO | P | 6100808 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/06/2019 | north end 6" dwv main in parking garage test ok will need plan splice for added 4" stack to up stairs near floor clean out | JOSEPHD | JOSEPHD | | PTO | P | 6099574 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 12/18/2018 | Consultation: discussed dwv layout on garage 2nd level with contractor, remove all stacks from went vents, Still need splice for perimeter drain tied into sand oil line | JOEL | JOEL | | PTO | P | 6056054 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 08/29/2018 | north east area ok plans marked, | JOSEPHD | JOSEPHD | | PB | P | 5949130 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PRD | P | 06/21/2018 | 10" and 6" roof drains east side of building ok inspected on 6/15/18 | JOSEPHD | JOSEPHD | | PRD | P | 5881112 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 06/21/2018 | bottom floor units dwv south end of building ok plans marked | JOSEPHD | JOSEPHD | | PB | P | 5881109 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 06/15/2018 | looked at section 4 center of building sand & grease ok plans marked note: also checked 10" and 6" brd east side of building | JOSEPHD | JOSEPHD | | PB | P | 5875589 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 05/31/2018 | 6" main and stack and elevator floor sink east side ok plans marked | JOSEPHD | JOSEPHD | | PB | P | 5860001 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 05/10/2018 | lower lvl sand & grease drains north west side ok plans marked | JOSEPHD | JOSEPHD | | PB | P | 5840693 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 04/26/2018 | vents for S.O. interceptor ok, 4 inch S.O. ok minus trench drain at garage 3 south. | TAYLOR | TAYLOR | | PB | P | 5827895 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PB | P | 04/24/2018 | partial 4 inch S.O. ok at garage 3 south. | TAYLOR | TAYLOR | | PB | P | 5825033 |
BRUCE MECHANICAL OF COLORADO, INC | XMS | T | 08/27/2020 | PAID (REC#1710096): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: New return grill and electric heater | JUSTINC | JUSTINC | | XMS | T | 6688356 |
BIBLE ELECTRIC, INC. | XES | P | 08/27/2020 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Added electric wall heater. | BERTHA | BERTHA | | XES | P | 6688215 |
BIBLE ELECTRIC, INC. | XES | P | 08/27/2020 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Added electric wall heater. | BERTHA | BERTHA | | XES | P | 6688213 |
NEWCOMER'S PLUMBING AND HEATING, INC. | XMS | T | 08/19/2020 | PAID (REC#1707668): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Snow melt boiler revisions | JUSTINC | JUSTINC | | XMS | T | 6677559 |
BIBLE ELECTRIC, INC. | XES | P | 08/13/2020 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Revise unit heaters | SHELBY | SHELBY | | XES | P | 6671397 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 08/13/2020 | PAID (REC#1705134): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Added garage heaters | JUSTINC | JUSTINC | | XMS | T | 6671326 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 06/30/2020 | PAID (REC#1692309): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Unit layout revision | JUSTINC | JUSTINC | | XMS | T | 6622081 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 06/18/2020 | PAID (REC#1689508): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised unit duct layout | JUSTINC | JUSTINC | | XMS | T | 6610164 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 05/15/2020 | PAID (REC#1690141): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised mezzanine unit layout | JUSTINC | JUSTINC | | XMS | T | 6572938 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 05/04/2020 | PAID (REC#1678783): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Layout revisions | JUSTINC | JUSTINC | | XMS | T | 6560068 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 01/29/2020 | PAID (REC#1663198): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Gas at BBQ's | JUSTINC | JUSTINC | | XMS | T | 6467240 |
BIBLE ELECTRIC, INC. | XES | P | 01/23/2020 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: As builts | SHELBY | SHELBY | | XES | P | 6462358 |
NEWCOMER'S PLUMBING AND HEATING, INC. | XPS | T | 01/22/2020 | PAID (REC#1657451): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: 1/22/20: Delta 14 revisions P-002 revised schedules, P-003 added details, P-008 and P-010 new page, P-100.B drawing notes 6 & 7, P-102.A drawing note 5, P-103.A drawing note 3, P-103.B drawing note 1 | SHANEN | SHANEN | | XPS | T | 6460422 |
COLORADO STRUCTURES INC | XBS | T | 12/20/2019 | PAID (REC#1651918): PLAN SPLICE FEE: $100 by: DANM for Construction: Various revisions throughout architectural and structural sheets | DANM | DANM | | XBS | T | 6433741 |
COLORADO STRUCTURES INC | XBS | T | 12/16/2019 | PAID (REC#1650811): PLAN SPLICE FEE: $200 by: DANM for Construction: Various revisions throughout architectural and structural drawings including addition of roof patios at mezzanine units | DANM | DANM | | XBS | T | 6428328 |
SCHINDLER ELEVATOR CORPORATION | XMS | T | 12/12/2019 | PAID (REC#1651077): PLAN SPLICE FEE: $79.17 by: JUSTINC for Mechanical: Revised room layouts | JUSTINC | JUSTINC | | XMS | T | 6425068 |
NEWCOMER'S PLUMBING AND HEATING, INC. | XPS | T | 12/10/2019 | PAID (REC#1649569) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: 12/10/19: Delta 13 revisions see Plumbing Addendum #3 Revisions on pages P-413, P-414, P-418, P-419, P-420, P-425 | SHANEN | SHANEN | | XPS | T | 6422996 |
BIBLE ELECTRIC, INC. | XES | P | 12/09/2019 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Dwelling unit changes | SHELBY | SHELBY | | XES | P | 6420542 |
NEWCOMER'S PLUMBING AND HEATING, INC. | XPS | T | 11/21/2019 | PAID (REC#1647684) PLAN SPLICE FEE: $200 by: TCRIPPEN for Plumbing: new plumbing splice see new narrative notes | TCRIPPEN | TCRIPPEN | | XPS | T | 6406575 |
BIBLE ELECTRIC, INC. | XES | T | 11/18/2019 | PAID (REC#1645463): PLAN SPLICE FEE: $150 by: SHELBY for Electrical: Revised feeders to include AL equipment grounds///revised CU on E102.A///revised unit electrical layouts | SHELBY | SHELBY | | XES | T | 6403136 |
COLORADO STRUCTURES INC | XBS | T | 10/30/2019 | PAID (REC#1641094): PLAN SPLICE FEE: $112.5 by: DANM for Construction: Revisions throughout both architectural and structural sheets including increase of upper floor mezzanines to 50% per 2018 IBC | DANM | DANM | | XBS | T | 6384023 |
COLORADO STRUCTURES INC | XBS | T | 05/07/2019 | PAID (REC#1597937): PLAN SPLICE FEE: $50 by: DANM for Construction: Deferred floor and roof trusses | DANM | DANM | | XBS | T | 6191728 |