RIVER ROCK CUSTOM HOMES, INC. | B= | C | 10/19/2018 | Items corrected | DAKOTAB | DAKOTAB | | B= | C | 5999877 |
RIVER ROCK CUSTOM HOMES, INC. | B= | P | 10/18/2018 | Emergency escape ladder needed in front basement bedroom -- Schedule a new Building Final when above items are complete. | SHAUN | SHAUN | | B= | P | 5999233 |
RIVER ROCK CUSTOM HOMES, INC. | BLA | C | 07/24/2018 | | DALE | DALE | | BLA | C | 5911773 |
RIVER ROCK CUSTOM HOMES, INC. | BIN | C | 06/11/2018 | | BOBF | BOBF | | BIN | C | 5870499 |
RIVER ROCK CUSTOM HOMES, INC. | BFR | C | 06/08/2018 | | BOBF | BOBF | | BFR | C | 5869276 |
RIVER ROCK CUSTOM HOMES, INC. | BFR | T | 06/07/2018 | PAID (REC#1505957) roof jack not installed / H 3 were only corrected over 1 garage, still need the other garage completed / letter for front porch on file | BOBF | BOBF | | BFR | T | 5867964 |
RIVER ROCK CUSTOM HOMES, INC. | BFR | R | 06/06/2018 | missing pipe jack at rang hood vent / H 3 hardware not installed per detail in garage / h 2' 5 at mid point bearing all b1 and b2 trusses at garage common wall / MTS 12 at west end truss C / seal around pipe going through foundation at north side of basement / need letter for front porch per previous inspection | BOBF | BOBF | | BFR | R | 5866105 |
RIVER ROCK CUSTOM HOMES, INC. | BSP | R | 04/25/2018 | girders landing on inside posts areset on top of posts with BC6 post caps, plans call for girders to be landes in HU610 hangar to side of posts, rest of front porch and posts okay / rear porch and posts okay / garage portal walls okay / st 22 straps per note A okay | BOBF | BOBF | | BSP | R | 5827451 |
RIVER ROCK CUSTOM HOMES, INC. | BFD | C | 03/21/2018 | letter for drain and soils report on file | BOBF | BOBF | | BFD | C | 5794482 |
RIVER ROCK CUSTOM HOMES, INC. | BFT | C | 03/21/2018 | design on file 1500# | BOBF | BOBF | | BFT | C | 5794481 |
RIVER ROCK CUSTOM HOMES, INC. | BFT | P | 03/20/2018 | open hole 1500# and letter for footing, steel and eufer on file / still need foundation design | BOBF | BOBF | | BFT | P | 5793201 |
RIVER ROCK CUSTOM HOMES, INC. | BFN | C | 03/20/2018 | letter for steel and eufer on file | BOBF | BOBF | | BFN | C | 5793196 |
RIVER ROCK CUSTOM HOMES, INC. | BFD | P | 03/19/2018 | AUTHORIZED INSPECTION BY ENGINEER | JLANE | JLANE | JLANE | BFD | P | 5792224 |
RIVER ROCK CUSTOM HOMES, INC. | BFT | P | 03/19/2018 | AUTHORIZED INSPECTION BY ENGINEER | JLANE | JLANE | JLANE | BFT | P | 5792223 |
RIVER ROCK CUSTOM HOMES, INC. | BFN | P | 03/19/2018 | AUTHORIZED INSPECTION BY ENGINEER | JLANE | JLANE | JLANE | BFN | P | 5792222 |
MESA ELECTRIC, LLC. | E= | C | 09/13/2018 | 40 amp a/c | TOMC | TOMC | | E= | C | 5963941 |
MESA ELECTRIC, LLC. | ES | C | 06/08/2018 | Residential Underground: 200 - amp 3 Wire new service, ok to seal meter / | CRAIG | CRAIG | | ES | C | 5869386 |
MESA ELECTRIC, LLC. | ES | R | 06/04/2018 | Residential Underground: gec to ufer must land on neutral bar at main, inside wiring for well not installed, verify front porch receeptacle | BRET | BRET | | ES | R | 5863747 |
MESA ELECTRIC, LLC. | ER | C | 06/04/2018 | #6 cu x3, #8 cu a/c, no mcc,no vac, #2 al sub. | BRET | BRET | | ER | C | 5863743 |
MESA ELECTRIC, LLC. | EUG | C | 04/10/2018 | 3/w 4/0 al | CRAIG | CRAIG | | EUG | C | 5812647 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | C | 10/16/2018 | NOTES: CONDITIONED CRAWLSPACE, 1 SUPPLY 1 RETURN, OUTSIDE AIR TO RETURN, A/C COMPLETE | BENH | BENH | | H= | C | 5995552 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | H= | P | 10/01/2018 | NEED 6" CLEARANCE FROM COMBUSTIBLES ON WATER HEATER VENT, NEED GAS FLEX INSTALLED TO WATER HEATER, NEED SUPPORT FURNACE EXHAUST VENT EVERY 5 FEET, SECURE CONDENSATE DRAIN, A/C CONDENSER NEEDS 30" SERVICE CLEARANCE FROM WINDOW WELL NOTES: CONDITIONED CRAWLSPACE, 1 SUPPLY 1 RETURN, OUTSIDE AIR TO RETURN, A/C COMPLETE | BENH | BENH | | H= | P | 5981265 |
ALPHALETE MECHANICAL LLC | HC | C | 06/05/2018 | RELEASE METER | BENH | BENH | | HC | C | 5864857 |
ALPHALETE MECHANICAL LLC | HI | C | 06/05/2018 | 10 LB TEST OK 1 1/2" MAIN, 1 FURNACE, 1 WATER HEATER, 1 FIREPLACE, 1 COOK TOP, 1 DRYER | BENH | BENH | | HI | C | 5864830 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | C | 06/01/2018 | BY FINAL FURNACE EXHAUST VENT NEEDS TO BE SPACED EVERY 5 FT AND COMBUSTION AIR INTAKE AT FURNACE NEEDS A 90 DEGREE ELBOW ON IT | BENH | BENH | | HRR | C | 5861768 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | L | 05/30/2018 | LOCKED: ARRIVED AT 11:15 AND DOORS WERE LOCKED | BENH | BENH | | HRR | L | 5858838 |
CAPITAL VIEW GENERAL CONSTRUCTION, INC. | HRR | P | 05/25/2018 | NEED NAIL PROTECTION FOR B VENT ON MAIN LEVEL, NEED INSULATION SHIELD FOR B VENT IN ATTIC, HANGERS FOR FURNACE EXHAUST NEEDS TO BE EVERY 5 FT, BY FINAL INTAKE FOR FURNACE NEEDS ELBOW ON IT NOTES: CONDITIONED CRAWLSPACE/FINISHED BASEMENT, OUTSIDE AIR TO RETURN, A/C ROUGH COIL AND LINE SET | BENH | BENH | | HRR | P | 5855837 |
KROME GAS AND PLUMBING CO., INC. | P= | C | 10/17/2018 | certificate of potable water sent to scanning. | TAYLOR | TAYLOR | | P= | C | 5997559 |
KROME GAS AND PLUMBING CO., INC. | P= | P | 10/12/2018 | need the following ( backflow for irrigation, certificate of potable water, 6 inches of clearance from pex to single wall vent above water heater ), rest ok, finished basement. | TAYLOR | TAYLOR | | P= | P | 5993779 |
CLARK PLUMBING & HEATING | PTO | C | 05/24/2018 | finished basement, VTR, aav at kitchen, check water service and ejector tie in's by final. | TAYLOR | TAYLOR | | PTO | C | 5855307 |
HOMEOWNER | PWO | C | 05/24/2018 | need potable water certificate by final. | TAYLOR | TAYLOR | | PWO | C | 5855165 |
CLARK PLUMBING & HEATING | PB | C | 03/21/2018 | Bathroom group and floor drain to lift station, test OK | SHANEN | SHANEN | | PB | C | 5794824 |