JAMES PIFER CONSTRUCTION | B= | C | 05/07/2019 | All other required Final inspections are complete. (This is a computer generated result) | NICK | NICK | | B= | C | 6191159 |
JAMES PIFER CONSTRUCTION | B= | P | 05/07/2019 | Unfinished basement. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet, External Agency Inspection N= by WP ENGINEERING is not Completed yet. | NICK | NICK | | B= | P | 6190603 |
JAMES PIFER CONSTRUCTION | BSP | P | 05/07/2019 | Front porch posts OK | NICK | NICK | | BSP | P | 6190602 |
JAMES PIFER CONSTRUCTION | BLA | C | 05/07/2019 | | NICK | NICK | | BLA | C | 6190601 |
JAMES PIFER CONSTRUCTION | BSP | P | 04/25/2019 | 2 piers for front porch OK | NICK | NICK | | BSP | P | 6178617 |
JAMES PIFER CONSTRUCTION | BLA | P | 10/12/2018 | Need to install kick out flashing where side wall flashing installed at west side of house / Need to install flashing over garage service door / All other lath OK | NICK | NICK | | BLA | P | 5993068 |
JAMES PIFER CONSTRUCTION | BFR | C | 10/12/2018 | Letter on file for use of H2.5T for trusses / Still need to check front porch posts | NICK | NICK | | BFR | C | 5992937 |
JAMES PIFER CONSTRUCTION | BIN | C | 10/08/2018 | Insulation OK pending frame complete / Check attic at final | NICK | NICK | | BIN | C | 5988365 |
JAMES PIFER CONSTRUCTION | BFR | P | 10/08/2018 | Kick backs for strong back at gables OK at 48"oc / Still need letter for truss hardware / Still need to inspect front porch posts | NICK | NICK | | BFR | P | 5988356 |
JAMES PIFER CONSTRUCTION | BFR | P | 10/01/2018 | Still need to install kickers for strong back at 48"oc / Need stamped letter stating OK to use H2.5T hardware in place of TBE6 and TBE4 per approved plans / Still need to inspect front porch posts once installed / All other framing OK / Truss fix on file for T05 / OK to insulate | NICK | NICK | | BFR | P | 5981329 |
JAMES PIFER CONSTRUCTION | BSP | P | 10/01/2018 | New foundation design on file showing 2 new 10" piers for front porch area | NICK | NICK | | BSP | P | 5981322 |
JAMES PIFER CONSTRUCTION | BFR | T | 09/12/2018 | PAID (REC#1542765) Need to install T bracing for T03 trusses for lateral bracing called out on truss calcs / Need to install 4 king studs for garage door header / Need to install double TBE6 hangers for garage common wall truss locations / Need to install double king studs for master closet header / Need to splice plans to show new window in master bedroom / Need to install double TBE4's for all T04 trusses / Need to install double TBE4 and HTS20 hangers for all T05 trusses mid point connection / Back porch beam covered prior to inspection / Need to install 2 king studs for header kitchen / Need truss fix for all T05 trusses / Need to install lateral bracing for T05A and T05B / Need to install strong backs for all gable ends over 6' with kick backs at 48" oc / Need anchor bolts with in 12" of sill plate breaks / Approved plans call for 6x12 beam front porch, 2 2x10 installed / Need detail for post to beam connection and beam size front porch / Stopped inspe | NICK | NICK | | BFR | T | 5962635 |
JAMES PIFER CONSTRUCTION | BFD | C | 04/04/2018 | All usable space for drain OK / Damp proof OK / daylights to back of house | NICK | NICK | | BFD | C | 5807147 |
JAMES PIFER CONSTRUCTION | BFN | C | 03/23/2018 | Foundation reinforcement OK per design / Grounding rod OK | NICK | NICK | | BFN | C | 5797214 |
JAMES PIFER CONSTRUCTION | BFT | C | 03/23/2018 | Open hole on file / #4000psf / Drain habitable space | NICK | NICK | | BFT | C | 5797082 |
JAMES PIFER CONSTRUCTION | BFT | P | 03/19/2018 | Footing and pads OK per design on file / Need to Eng open hole report / Grounding rod OK / Poor at own risk | NICK | NICK | | BFT | P | 5792098 |
BEAR NECESSITY ELECTRIC INC | E= | C | 05/06/2019 | ufer access below main panel, | JOHNN | JOHNN | | E= | C | 6190165 |
BEAR NECESSITY ELECTRIC INC | ES | C | 05/03/2019 | Residential Underground: 200-amp 3 Wire New Residence , meter is set, | JOHNN | JOHNN | | ES | C | 6187185 |
BEAR NECESSITY ELECTRIC INC | E= | R | 05/03/2019 | need ufer access, jet tub needs bond to outlet EGC, smoke det hanging down, fixture missing globe, basement sub panel: missing panel cover screw, need 2 cb blanks, --------------------------notes: 100 amp sub has no branch circuits installed, | JOHNN | JOHNN | | E= | R | 6187169 |
BEAR NECESSITY ELECTRIC INC | EUG | C | 01/18/2019 | from meter to home--4/0 al---#2 al g---ok | BRIAN | BRIAN | | EUG | C | 6082820 |
BEAR NECESSITY ELECTRIC INC | ER | C | 08/23/2018 | rough,ok-----------------will need access to ufer on final, rev ufer---------------check basement panel on final,not made up, | JOHNN | JOHNN | | ER | C | 5944296 |
BEAR NECESSITY ELECTRIC INC | ER | R | 08/20/2018 | ufer not connected, grd outside round boxes, jet tub outlet needs to face access panel, 12/2 nm cable hanging in basement in back, basement sub panel not installed, --------------------------------------- #6al, #2al,feeders not installed, jet tub, unfinished basement, | JOHNN | JOHNN | | ER | R | 5939886 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | H= | C | 05/03/2019 | permit secured prior to January 1 2019 1 fireplace inspected under Hrr. note direct vent furnace and water heater, unfinished basement, no a/c | DAVIDH | DAVIDH | | H= | C | 6186205 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | HC | C | 08/30/2018 | RELEASE METER | DAVIDH | DAVIDH | | HC | C | 5950669 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | HRR | C | 08/30/2018 | | DAVIDH | DAVIDH | | HRR | C | 5950656 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | HRR | R | 08/28/2018 | NO INSULATION SHIELD ON FIREPLACE WAIVED RE-INSPECTION FEE | DAVIDH | DAVIDH | | HRR | R | 5947737 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | HRR | R | 08/23/2018 | exhaust fan upstairs not complete and fireplace not complete note no equip set yet 6"osa unfinished basement | DAVIDH | DAVIDH | | HRR | R | 5943430 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | HI | C | 08/23/2018 | 10 lb test ok note 1 " line 1 furn,w/h,f/p and c/t no equip set yet | DAVIDH | DAVIDH | | HI | C | 5943427 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | P= | C | 05/06/2019 | correction made | JOSEPHD | JOSEPHD | | P= | C | 6187817 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | P= | P | 05/03/2019 | can not see tempering valve for master tub, need to cap future laundry sink dwv, rest ok can upload images note: unfinished basement, no irrigation | JOSEPHD | JOSEPHD | | P= | P | 6187254 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | PTO | C | 08/30/2018 | correction made, image received | SHANEN | SHANEN | | PTO | C | 5950452 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | PTO | P | 08/28/2018 | need mixing valve for master tub note: aav master lav next to tub and main bath lav, CWV for other master lav and laundry sink, dwv rough for basement o.k, unfinished basement | JOEL | JOEL | | PTO | P | 5948426 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | PB | C | 04/17/2018 | | TAYLOR | TAYLOR | | PB | C | 5819376 |
WOODLAND PLUMBING, HEATING & AIR CONDITIONING LLC | PB | P | 04/16/2018 | can not horizontal dry vent floor drain. | TAYLOR | TAYLOR | | PB | P | 5818114 |
JAMES PIFER CONSTRUCTION | XBS | T | 09/26/2018 | PAID (REC#1542767) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised master bedroom; clarified front porch beams. | SHELLEY | SHELLEY | | XBS | T | 5977682 |