FAUROT CONSTRUCTION, INC. | B= | C | 08/07/2018 | All other required Final inspections are complete. (This is a computer generated result) | RICHB | RICHB | | B= | C | 5926429 |
FAUROT CONSTRUCTION, INC. | B= | P | 07/13/2018 | Restroom 145A and 146A complete pending other Finals / need to complete Mechanical including verification of smoke damper in A262 / remodel OK otherwise. Additional Inspections Required (computer generated): PROCRAFT MECHANICAL Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5901877 |
FAUROT CONSTRUCTION, INC. | B= | P | 07/09/2018 | Engineering received for smoke damper clarification - Splice on file / need to complete other Finals. Additional Inspections Required (computer generated): PROCRAFT MECHANICAL Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5895903 |
FAUROT CONSTRUCTION, INC. | B= | P | 07/06/2018 | Discussed smoke requirements deletion with Mech Inspector - still need engineering deleting smoke damper requirement at A262 -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): PROCRAFT MECHANICAL Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5894533 |
FAUROT CONSTRUCTION, INC. | B= | P | 07/05/2018 | Need to complete 1st floor restrooms 145A & 146A / discussed state inspection completion / rest of remodel OK to occupy pending other Finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): PROCRAFT MECHANICAL Mechanical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5893757 |
FAUROT CONSTRUCTION, INC. | BFR | P | 06/22/2018 | partial frame inspection for bathrooms 145A and 146A/reviewed accessibility -- framing infills at west stair tower/framing for understair wall ok -- discussed State Plumbing and Electrical inspections/ reviewed final inspection requirements | SCOTTS | SCOTTS | | BFR | P | 5882614 |
FAUROT CONSTRUCTION, INC. | BFR | P | 06/15/2018 | New stair framing on West end OK / discussed intermediate handrail requirements / plans reviewed onsite | RICHB | RICHB | | BFR | P | 5876033 |
FAUROT CONSTRUCTION, INC. | BFR | P | 05/01/2018 | Reviewed engineering onsite - letter eliminates smoke damper requirement from Chemistry Lab A262 (per IBC 509), need copy of letter submitted to PPRBD, plans reviewed onsite | RICHB | RICHB | | BFR | P | 5832949 |
FAUROT CONSTRUCTION, INC. | BFR | P | 03/22/2018 | Framing for new classrooms OK pending other Roughs / discussed State inspection requirements & records / discussed accessible elements / discussed smoke partition requirements (Room A262) / still need to inspect stair reconfiguration / plans reviewed onsite | RICHB | RICHB | | BFR | P | 5796970 |
PROCRAFT MECHANICAL, INC. | H= | C | 08/07/2018 | Smoke damper installed, splice approved to match TAB report and 1st floor bathrooms complete | MARKB | MARKB | | H= | C | 5926428 |
PROCRAFT MECHANICAL, INC. | H= | P | 08/07/2018 | Good Test And Balance Received | MARKB | MARKB | | H= | P | 5925642 |
PROCRAFT MECHANICAL, INC. | H= | P | 07/30/2018 | TAB received did not have Outside air readings, will need a revised TAB report showing outside air readings for RTU's to match ventilation table on permit | MARKB | MARKB | | H= | P | 5917371 |
PROCRAFT MECHANICAL, INC. | HSP | P | 07/09/2018 | After discussion with Jon B. (mechanical senior), Jeremy (building senior), Dale H. (mechanical plan review) and Rich B. (building inspector), the return air transfer opening for chemistry lab needs to resist the passage of smoke and be protected with a smoke damper. Dale H. will be calling engineer. Stopped on site and spoke with Eric (site super) and Procraft mechanical. | MARKB | MARKB | | HSP | P | 5896300 |
PROCRAFT MECHANICAL, INC. | H= | P | 07/05/2018 | FOR FINAL - Further research required on CHEM LAB wall. Can not build duct out of insulation board - lab opening in wall requires duct through the wall. Still need all inspection on added downstairs bathrooms. Provide a TEST AND BALANCE REPORT. EXHAUST HOOD AND PVC DUCT IN LAB INSTALLED PER PLAN. ALL DIFFUSERS IN GYM INSTALLED AND SPLICE PROVIDED. | MARKB | MARKB | | H= | P | 5894292 |
PROCRAFT MECHANICAL, INC. | HD | P | 05/02/2018 | FLEX AND DIFFUSERS INSTALLED. STILL NEED - Smoke damper in transfer and type 2 hood installed in Chem. lab. Plan splice per previous notes. Diffusers installed in gym. Hard lid areas per previous notes. Provide Test And Balance Report. | MARKB | MARKB | | HD | P | 5833862 |
PROCRAFT MECHANICAL, INC. | HD | P | 03/30/2018 | ABOVE CEILING DUCT - SUPPLY MAINS/BRANCHES FOR VAV 4-24, MEDIUM PRESSURE FOR VAV 4-21, ROOM B228 AND SUPPLY/EXHAUST FOR REST ROOMS B244 & B242 INSTALLED PER PLAN OK TO WRAP. Will need access panel provided for volume dampers above hard lids. | MARKB | MARKB | | HD | P | 5803825 |
PROCRAFT MECHANICAL, INC. | HD | P | 03/26/2018 | ABOVE CEILING DUCT - LOW PRESSURE SIDE FOR M111A & M111B SHEETS HIGHLIGHTED IN PINK ON APPROVED SET OK TO WRAP. STILL NEED - MEDIUM PRESSURE DUCTS, EXHAUST, DAMPERS, HOOD, PLAN SPLICE FOR CORRIDORS, FLEX, DIFFUSERS AND ADDRESS PVC PIPING IN ABOVE CEILING PLENUM | MARKB | MARKB | | HD | P | 5798860 |
PROCRAFT MECHANICAL, INC. | XMS | T | 08/07/2018 | PAID (REC#1524825) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised ventilation schedule, VAV schedule and CFM indicated on floor plans | JUSTINC | JUSTINC | | XMS | T | 5925778 |
PROCRAFT MECHANICAL, INC. | XMS | T | 05/29/2018 | PAID (REC#1504879) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: delta 3 | DALEH | DALEH | | XMS | T | 5857161 |
FAUROT CONSTRUCTION, INC. | XBS | T | 05/29/2018 | PAID (REC#1504880) PLAN SPLICE FEE: $50 by: DANM for Construction: Minor revisions throughout including addition of two new restrooms on 1st floor | DANM | DANM | | XBS | T | 5857051 |