PREMIER HOMES, INC. | B= | C | 08/10/2018 | all units complete | LONNYS | LONNYS | | B= | C | 5929843 |
PREMIER HOMES, INC. | B= | P | 08/08/2018 | 5658 , 5664 , 5670 / all units OK pending MEP finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): J2D ELECTRIC, INC. Electrical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 5927211 |
PREMIER HOMES, INC. | B= | P | 08/07/2018 | 5652 final OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): J2D ELECTRIC, INC. Electrical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 5926415 |
PREMIER HOMES, INC. | B= | P | 08/03/2018 | 5646 OK pending MEP finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): J2D ELECTRIC, INC. Electrical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet, R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 5923427 |
PREMIER HOMES, INC. | B= | P | 07/31/2018 | 5634 5640 building finals OK pending MEP finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection UF by CSUAPPSPRM is not Completed yet (Contact: CSU: Contract Admin at 668-8111), J2D ELECTRIC, INC. Electrical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet, R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 5919254 |
PREMIER HOMES, INC. | B= | P | 07/27/2018 | 5610 and 5616 / building finals OK pending MEP finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection UF by CSUAPPSPRM is not Completed yet (Contact: CSU: Contract Admin at 668-8111), JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet, R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet, SPECIAL SYSTEMS DESIGN,LLC Electrical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 5916195 |
PREMIER HOMES, INC. | B= | P | 07/26/2018 | 5622 , 5628 ONLY / building finals OK pending other MEP finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection UF by CSUAPPSPRM is not Completed yet (Contact: CSU: Contract Admin at 668-8111), JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet, R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet, SPECIAL SYSTEMS DESIGN,LLC Electrical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 5914632 |
PREMIER HOMES, INC. | B= | R | 07/23/2018 | field cancelled per site rep TOM - not ready. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), External Agency Inspection UF by CSUAPPSPRM is not Completed yet (Contact: CSU: Contract Admin at 668-8111), JESS' PLBG. & HEATING, INC. Mechanical Final Inspection is not Completed yet, JESS' PLBG. & HEATING, INC. Plumbing Final Inspection is not Completed yet, R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet, SPECIAL SYSTEMS DESIGN,LLC Electrical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | R | 5910685 |
PREMIER HOMES, INC. | BSP | P | 07/13/2018 | 5670 CUT JOIST: received engineer letter for cut floor joist | LONNYS | LONNYS | | BSP | P | 5901864 |
PREMIER HOMES, INC. | BFR | P | 07/11/2018 | 5670, 5664, 5658 FRAME CORRECTIONS: all items corrected | LONNYS | LONNYS | | BFR | P | 5898666 |
PREMIER HOMES, INC. | BSP | P | 07/09/2018 | Training with PPRBD inspector Lonny / VB construction / R2 occupancy / reviewed 2hr U375 rated American Gyp assembly and details on sheet A11 of the approved design / discussed inspection scheduling for apartments | BRIANB | BRIANB | | BSP | P | 5896113 |
PREMIER HOMES, INC. | BIN | P | 07/09/2018 | 5658,5664,5670: insulation OK in all units pending BFR and other MEP roughs | LONNYS | LONNYS | | BIN | P | 5896111 |
PREMIER HOMES, INC. | BFR | P | 07/09/2018 | 5658,5664,5670 FRAME REINSPECTION / fire block incomplete at tubs and bottom plates all units / 5670 cut top flange of TGI joist lower S bedroom | LONNYS | LONNYS | | BFR | P | 5896108 |
PREMIER HOMES, INC. | BSP | R | 07/09/2018 | gyp fastening inspection not required as it is not part of rated assembly at unit separation wall | LONNYS | LONNYS | | BSP | R | 5896102 |
PREMIER HOMES, INC. | BFR | R | 07/03/2018 | 5658,5664, and 5670 FRAMING / all units missing mineral wool fire block at rims / 5664 - missing roof jack to dry in - lower level bedroom wall framing incomplete / 5670 - missing roof jack to dry in - lower lever load bearing wall over drilled at under stair laundry - all fire blocking incomplete / through penetrations OK in all units | LONNYS | LONNYS | | BFR | R | 5892586 |
PREMIER HOMES, INC. | BFR | P | 07/02/2018 | 5646 FRAME ONLY / all frame items OK / inspection status changed to partial - still need to complete frame inspections for last 3 units | LONNYS | LONNYS | | BFR | P | 5890830 |
PREMIER HOMES, INC. | BFR | P | 06/29/2018 | 5646 and 5652 FRAME REINSPECT / 5646 still has putty pads at electric penetrations in unit sep. wall / all other items OK | LONNYS | LONNYS | | BFR | P | 5889702 |
PREMIER HOMES, INC. | BIN | P | 06/28/2018 | 5646 and 5652 - insulation OK | LONNYS | LONNYS | | BIN | P | 5888210 |
PREMIER HOMES, INC. | BSP | P | 06/27/2018 | met with site rep Tom and discussed installation of H2.5 clip attachment questions | LONNYS | LONNYS | | BSP | P | 5886965 |
PREMIER HOMES, INC. | BFR | P | 06/26/2018 | FRAME INSPECTION FOR 5646 AND 5652 ONLY / missing roof jacks both units to dry in / fire block incomplete at tubs and rims between upper and lower levels both units / putty pad used at electric bundle penetrations both units / unit 5652 has over drilled stud in load bearing wall at under stair laundry / frame inspection pending other roughs | LONNYS | LONNYS | | BFR | P | 5885367 |
PREMIER HOMES, INC. | BFN | C | 06/26/2018 | | LONNYS | LONNYS | | BFN | C | 5885039 |
PREMIER HOMES, INC. | BFT | C | 06/26/2018 | all paperwork on file | LONNYS | LONNYS | | BFT | C | 5885038 |
PREMIER HOMES, INC. | BFN | P | 06/22/2018 | still need to complete BFT / need foundation design / engineer letter for foundation on file - ufer noted | LONNYS | LONNYS | | BFN | P | 5882430 |
PREMIER HOMES, INC. | BSP | P | 06/21/2018 | 5610,5616,5622,(5628-east wall) GYP. FASTENING FOR UPPER LEVEL PRESCRIPTIVE WALL- all gyp fastening and 5/8" type X gyp OK per spliced in unit separation wall detail for upper level of 3 units only | LONNYS | LONNYS | | BSP | P | 5881408 |
PREMIER HOMES, INC. | BSP | P | 06/21/2018 | 5640, 5634, 5628 PENETRATIONS ONLY - all penetrations OK | LONNYS | LONNYS | | BSP | P | 5881401 |
PREMIER HOMES, INC. | BSP | R | 06/20/2018 | 5610 -5640 UNIT SEPARATION WALL PENETRATIONS / penetration fire caulk incomplete at units 5628-5640 / need to verify puddy pad product used for electric penetrations for all units | LONNYS | LONNYS | | BSP | R | 5879984 |
PREMIER HOMES, INC. | BIN | P | 06/20/2018 | 5634 and 5640 / insulation OK pending other roughs | LONNYS | LONNYS | | BIN | P | 5879846 |
PREMIER HOMES, INC. | BFR | P | 06/15/2018 | 5634 and 5640 FRAMING / need to to complete fire caulk at unit separation wall penetrations both units / mineral wool fire blocking missing at top and bottom of upper level floor framing both units / OK to insulate pending other roughs | LONNYS | LONNYS | | BFR | P | 5875702 |
PREMIER HOMES, INC. | BIN | P | 06/13/2018 | 5628 INSULATION - insulation is OK upon further review / ES report for spray foam insulation on file | LONNYS | LONNYS | | BIN | P | 5872811 |
PREMIER HOMES, INC. | BSP | P | 06/12/2018 | 5670 LEDGER LAG REINSPECT / ledger lags OK | LONNYS | LONNYS | | BSP | P | 5871503 |
PREMIER HOMES, INC. | BIN | P | 06/12/2018 | 5622 AND 5628 INSULATION / 5628 upper level west bedroom missing batt next to access to over framing - may upload picture upon completion / NOTE - need ES report for spray foam used in ceilings | LONNYS | LONNYS | | BIN | P | 5871499 |
PREMIER HOMES, INC. | BFI | C | 06/12/2018 | engineer letter for foundation insulation on file | LONNYS | LONNYS | | BFI | C | 5871161 |
PREMIER HOMES, INC. | BSP | P | 06/11/2018 | density test on file | LONNYS | LONNYS | | BSP | P | 5869785 |
PREMIER HOMES, INC. | BFT | P | 06/11/2018 | need footing observations / soils and open hole on file 2400 PSF - no drain - 5% | LONNYS | LONNYS | | BFT | P | 5869780 |
PREMIER HOMES, INC. | BIN | P | 06/08/2018 | 5610-5616 INSULATION - insulation OK pending other roughs / NOTE: R11 observed at upper level unit separation walls | LONNYS | LONNYS | | BIN | P | 5868968 |
PREMIER HOMES, INC. | BSP | P | 06/07/2018 | HARD WEAR INSPECTION PRIOR TO SPRAY FOAM INSULATION AT ROOF - UNITS 5646,5652,5658,5664,5670 / unit 5670 missing lags at lower lever ledger / all other hard wear in all units OK | LONNYS | LONNYS | | BSP | P | 5867468 |
PREMIER HOMES, INC. | BFR | P | 06/07/2018 | 5622 and 5628 FRAME INSPECTION - fire block incomplete at top plate and tubs / all other framing OK | LONNYS | LONNYS | | BFR | P | 5867462 |
PREMIER HOMES, INC. | BIN | R | 06/07/2018 | site cancelled per on site rep TOM | LONNYS | LONNYS | | BIN | R | 5867421 |
PREMIER HOMES, INC. | BFR | P | 06/05/2018 | FRAME INSPECTION 5610 -5616 / need to complete all foundation inspections / need engineering detail for unit separation wall penetrations / corrections to C track at unit separation wall not completed - H stud used in lieu of C track at horizontal joints / need to complete foam and fire stop for top plate penetrations - tub drains - top and middle of unit separation wall / frame pending all other roughs | LONNYS | LONNYS | | BFR | P | 5864737 |
PREMIER HOMES, INC. | BSP | P | 06/05/2018 | ALL UNITS - shaft liner end caps OK | LONNYS | LONNYS | | BSP | P | 5864729 |
PREMIER HOMES, INC. | BSP | P | 05/17/2018 | 5628-5640 LOWER AND UPPER ROOF HARD WEAR CONNECTION BEFORE SPRAY INSULATION and SHAFTLINER END CAPS / all units hard wear connections OK / 5628-5640 shaftliner end caps OK / NOTE: discussed application of shaftliner smoke tight joint at roof sheathing | LONNYS | LONNYS | | BSP | P | 5848255 |
PREMIER HOMES, INC. | BSP | P | 05/08/2018 | 5610-5616 SHAFTLINER END CAPS INSPECTION / shaft liner end caps OK between 5610 and 5616 / shaft liner end caps OK between 5616 and 5622 | LONNYS | LONNYS | | BSP | P | 5838462 |
PREMIER HOMES, INC. | BSP | R | 05/07/2018 | field cancelled per site rep TOM / NOTE: discussed installation requirements for vertical C tracks at each end of H-stud area separation wall | LONNYS | LONNYS | | BSP | R | 5837109 |
PREMIER HOMES, INC. | BSP | P | 05/02/2018 | Training with PPRBD inspector Lonny / R2 occupancy - VB construction / reviewed 2hr rated separation wall per U375 and American Gyp separation wall system manual / went over H-stud requirements - C-runner track requirements and AWS clip requirements per the approved listing and American Gyp manual / went over separation wall details per sheet A11 of the approved design / also met with Premier superintendent Tom - went over inspection scheduling and processes | BRIANB | BRIANB | | BSP | P | 5833416 |
PREMIER HOMES, INC. | BSP | P | 05/02/2018 | Training with inspector Brian B / reviewed UL design U375 - American Gyp separation wall system manual - including proper c track installation and lap at joints - reviewed H stud installation and location / reviewed types of gyp to be used / reviewed fire blocking requirements, locations and types / reviewed gyp fastening for interior walls / reviewed AWS clip locations and fastening / did meet and greet with site rep Tom concerning inspection request , site plan and time line | LONNYS | LONNYS | | BSP | P | 5833415 |
PREMIER HOMES, INC. | BSP | R | 05/02/2018 | ROOF TRUSS CONNECTIONS FOR UNITS 5610, 5616, 5622 -- need to tie in upper level top plates in all three units / 5610 - need to roll block floor joists lower level on LVL / 5622 - upper level missing several H2.5s / footing and foundation observation letters to follow / UPDATE: observed C channel was not installed at horizontal joints per UL U375 listing and american gyp manual | LONNYS | LONNYS | | BSP | R | 5833393 |
PREMIER HOMES, INC. | BSP | T | 04/06/2018 | PAID (REC#1497546): ADDITIONAL PLAN REVIEW TIME: $50 From: SHELBY Revise service lateral | SHELBY | SHELBY | | BSP | T | 5810621 |
PREMIER HOMES, INC. | BFN | P | 03/30/2018 | Authorized 3rd party engineer inspection with all observation paperwork-ufer letter,soils and open hole letter to be picked up by inspector @ BFI or BFD inspection | BERTW | BERTW | | BFN | P | 5804387 |
PREMIER HOMES, INC. | BFT | P | 03/30/2018 | Authorized 3rd party engineer inspection with all observation paperwork-ufer letter,soils and open hole letter to be picked up by inspector @ BFI or BFD inspection / | BERTW | BERTW | | BFT | P | 5804385 |
J2D ELECTRIC, INC. | E= | C | 08/09/2018 | Correction complete, 20 amp AC installed / | ROB | ROB | | E= | C | 5928803 |
J2D ELECTRIC, INC. | E= | P | 08/08/2018 | 5670 lower bath fan not working---------------5658 complete, 20 amp AC Installed----5664 complete, 20 amp AC installed / | ROB | ROB | | E= | P | 5927371 |
J2D ELECTRIC, INC. | E= | P | 08/03/2018 | 5652 complete, 20 amp AC-----5658 Need to check kitchen, rest ok, 20 amp AC-----5646 complete, 20 amp AC / | ROB | ROB | | E= | P | 5923055 |
J2D ELECTRIC, INC. | E= | R | 08/02/2018 | 5646: still ready,kitchen missing outlets,complete re inspect, 5652: hood outlet not mounted, plate on G/D, frig cb not tripping at cb, ------------20 amp a/c ok, 5658: need counters installed, nm cable feeding furnace needs protection at floor, upstairs bath rm fan guts missing, | JOHNN | JOHNN | | E= | R | 5921934 |
J2D ELECTRIC, INC. | E= | R | 08/01/2018 | 5646,5652 not ready, outlets missing, complete reinspect. | JOHNN | JOHNN | | E= | R | 5920517 |
J2D ELECTRIC, INC. | E= | P | 07/31/2018 | 5634,5640 complete | JOHNN | JOHNN | | E= | P | 5919019 |
J2D ELECTRIC, INC. | E= | R | 07/30/2018 | 5634 and 5640 both units missing porch light, 20 amp a/c units installed | BRET | BRET | | E= | R | 5917385 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 07/30/2018 | FIRE ALARM INSPECTION: could not locate red card | BRET | BRET | | E= | C | 5917384 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 07/30/2018 | FIRE ALARM INSPECTION: | BRET | BRET | | ER | C | 5917380 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 07/30/2018 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 5917381 |
SPECIAL SYSTEMS DESIGN,LLC | E= | R | 07/24/2018 | FIRE ALARM INSPECTION: See ER comments / | ROB | ROB | | E= | R | 5911743 |
SPECIAL SYSTEMS DESIGN,LLC | ER | R | 07/24/2018 | FIRE ALARM INSPECTION: Need SCH 80 PVC above grade--Need to strap ground wire / | ROB | ROB | | ER | R | 5911741 |
J2D ELECTRIC, INC. | E= | P | 07/20/2018 | Correction Complete / for unit 5628 | ROB | ROB | | E= | P | 5909039 |
J2D ELECTRIC, INC. | E= | R | 07/19/2018 | 5628: a/c on 30 amp cb, dryer on 20 amp cb, upper bath: outlet has large dry wall gap around box, | JOHNN | JOHNN | | E= | R | 5908283 |
J2D ELECTRIC, INC. | ER | C | 07/06/2018 | 5664,5670:ok----------------all units complete. | JOHNN | JOHNN | | ER | C | 5895033 |
J2D ELECTRIC, INC. | ER | R | 07/02/2018 | all units must have address # clearly marked outside of each unit or there will not be an inspection, confirm that outlets in bath rms will be 3' from sink, 5670:switch near panel has no cables installed, 5664: framing not complete in 1st floor bed rm, rest of unit ok, 5658,ok---------all units:no mcc,3#8al,panels,ok | JOHNN | JOHNN | | ER | R | 5891046 |
J2D ELECTRIC, INC. | ER | P | 06/26/2018 | Rough in ok for 5646,5652-- #8 AL to A/C / #8 AL to oven/range / # 8 to dryer/ no mcc's / Panels ok / | ROB | ROB | | ER | P | 5885680 |
J2D ELECTRIC, INC. | ES | P | 06/19/2018 | Commercial Service: new commercial, 600 amp,3w, ok to set ct's/energize, --------------------check AIC labeling on final | JOHNN | JOHNN | | ES | P | 5878278 |
J2D ELECTRIC, INC. | ES | R | 06/18/2018 | Residential Underground: Not per one line for 5610-5670--It appears to be sized for other building / Complete re-inspect / | ROB | ROB | | ES | R | 5877433 |
J2D ELECTRIC, INC. | ER | P | 06/13/2018 | 1/0 cu ufer in apt 5610 north wall ok / | ROB | ROB | | ER | P | 5872947 |
J2D ELECTRIC, INC. | ER | P | 06/08/2018 | 5634 and 5640: Electrical Rough ok /Make sure bathroom recpt is within 3' of sink / #8 AL to A/C / #8 AL to oven/range / #8 AL to dryer / no mcc's / Panels ok / | ROB | ROB | | ER | P | 5868706 |
J2D ELECTRIC, INC. | ER | P | 06/07/2018 | THESE UNITS ONLY!!! 5610, 5616, 5622, 5628, No mcc's, no vac, | GARYL | GARYL | | ER | P | 5868204 |
J2D ELECTRIC, INC. | ER | R | 06/04/2018 | need feeders pulled, -------------------------------see Shelby's notes for accessibility, | JOHNN | JOHNN | | ER | R | 5863182 |
R & R HEATING & AIR CONDITIONING, INC. | H= | C | 08/09/2018 | ALL UNITS ARE COMPLETE | JERRYF | JERRYF | | H= | C | 5929672 |
JESS' PLUMBING & HEATING, INC | H= | C | 08/09/2018 | ALL UNITS ARE COMPLETE | JERRYF | JERRYF | | H= | C | 5929670 |
JESS' PLUMBING & HEATING, INC | H= | P | 08/08/2018 | W/H AND GAS COMPLETE | DAVIDH | DAVIDH | | H= | P | 5928069 |
JESS' PLUMBING & HEATING, INC | H= | P | 08/07/2018 | 5652 complete | DAVIDH | DAVIDH | | H= | P | 5926818 |
JESS' PLUMBING & HEATING, INC | H= | P | 08/06/2018 | NEED DRAIN SECURED AT PVC AT WATER HEATER UNIT 5642 IS OK | JERRYF | JERRYF | | H= | P | 5925379 |
R & R HEATING & AIR CONDITIONING, INC. | H= | P | 08/03/2018 | THE FOLLOWING UNITS ARE COMPLETE 5646 - 5652 - 5658 - HIGH / LOW GRILLES | JERRYF | JERRYF | | H= | P | 5923958 |
JESS' PLUMBING & HEATING, INC | H= | P | 07/31/2018 | 5610-5640 COMPLETED | DAVIDH | DAVIDH | | H= | P | 5918775 |
R & R HEATING & AIR CONDITIONING, INC. | H= | P | 07/31/2018 | 5610-5640 COMPLETED | DAVIDH | DAVIDH | | H= | P | 5918769 |
R & R HEATING & AIR CONDITIONING, INC. | H= | P | 07/27/2018 | NEED TO INSTALL DOUBLE WALL VENT ALL THE WAY TO THE FURNACE,5610 5616,5622,5634 AND 5640. | DAVIDH | DAVIDH | | H= | P | 5916853 |
JESS' PLUMBING & HEATING, INC | H= | P | 07/27/2018 | NEED MEDIUM PRESSURE STICKERS ON THE (CSST) FEEDING THE WATER HEATERS | DAVIDH | DAVIDH | | H= | P | 5916801 |
R & R HEATING & AIR CONDITIONING, INC. | H= | P | 07/20/2018 | ALL BED RM DOORS NEED UNDER CUT 1" FOR RETURN AIR PATH OR R/A GRILLS INSTALLED 5610,5616,5622 AND 5628 BY FINAL | DAVIDH | DAVIDH | | H= | P | 5909511 |
JESS' PLUMBING & HEATING, INC | HC | C | 06/27/2018 | RELEASE METER | JERRYF | JERRYF | | HC | C | 5887730 |
JESS' PLUMBING & HEATING, INC | HI | C | 06/27/2018 | CHECK ALL FINAL CONNECTIONS AT FINAL FOR ALL UNITS | JERRYF | JERRYF | | HI | C | 5887726 |
JESS' PLUMBING & HEATING, INC | HV | P | 06/26/2018 | WATER HEATER VENTS THROUGH OK IN UNITS 5658 - 5662 - 5670 - STILL NEED ALL VENT CONNECTIONS AT WATER HEATERS | JERRYF | JERRYF | | HV | P | 5886308 |
JESS' PLUMBING & HEATING, INC | HI | P | 06/26/2018 | NEED ALL LINES CAPPED IN 5658 - 5662 - 5670 BEFORE METER RELEASE NOTES: PRESSURE TEST OK AND PIPING PER PLAN FOR UNITS 5658 - 5662 - 5670 | JERRYF | JERRYF | | HI | P | 5886304 |
R & R HEATING & AIR CONDITIONING, INC. | HRR | C | 06/22/2018 | NEED B VENT COMPLETED TO MECHANICAL ROOM IN 5670 - THE FOLLOWING UNITS ARE COMPLETE - 5646 0- 5652 - 5658 - 5664 - BY FINAL REMOVE ALL OUTSIDE AIR FROM PLANS | JERRYF | JERRYF | | HRR | C | 5882772 |
R & R HEATING & AIR CONDITIONING, INC. | HRP | C | 06/22/2018 | PRESSURE TEST AND PIPING OK IN THE FOLLOWING UNITS - 5646 - 5652 - 5658 - 5664 - 5670 | JERRYF | JERRYF | | HRP | C | 5882755 |
JESS' PLUMBING & HEATING, INC | HI | P | 06/18/2018 | THE WAY PIPE IS RUN QUARTER STRIKER PLATES WILL NOT WORK WILL NEED FULL STRIKER PLATES INSTALLED AND USE SCREWS ALSO TO ATTACH SEND PICTURES OF REPAIRS 6/19/18 corrections made | DAVIDH | DAVIDH | | HI | P | 5877776 |
JESS' PLUMBING & HEATING, INC | HV | P | 06/15/2018 | 5634,5640,5646 AND 5652 | DAVIDH | DAVIDH | | HV | P | 5876477 |
JESS' PLUMBING & HEATING, INC | HI | R | 06/15/2018 | UNITS 5634 AND 5652 NEEDS CSST NAIL PLATE OVER STAIRWELL FOR NAIL PROTECTION, 5640 AND 5646 OK 10 LB TEST OK FURN AND W/H | DAVIDH | DAVIDH | | HI | R | 5876476 |
R & R HEATING & AIR CONDITIONING, INC. | HRR | P | 06/08/2018 | HRR ON 5610 ,5616 AND 5622 | DAVIDH | DAVIDH | | HRR | P | 5869657 |
R & R HEATING & AIR CONDITIONING, INC. | HRR | P | 06/06/2018 | hrr per plans a/c pressure test on 5628,5634 and 5640 ok | DAVIDH | DAVIDH | | HRR | P | 5866098 |
JESS' PLUMBING & HEATING, INC | HV | P | 06/05/2018 | CHECKED VENT ON 5610,5616,5622 AND 5628 VENTS CORRECTED | DAVIDH | DAVIDH | | HV | P | 5864903 |
JESS' PLUMBING & HEATING, INC | HV | P | 05/24/2018 | CANNOT VERIFY 2 STEP PROCESS AT VENT CONNECTIONS ABOVE TERMINATION WYES IN 5610 - 5616 - 5622 - 5628 | JERRYF | JERRYF | | HV | P | 5855490 |
JESS' PLUMBING & HEATING, INC | HI | P | 05/24/2018 | PRESSURE TEST AND PIPING OK PER PLAN FOR THE FOLLOWING UNITS - 5610 - 5616 - 5622 - 5628 | JERRYF | JERRYF | | HI | P | 5855482 |
R & R HEATING & AIR CONDITIONING, INC. | HD | L | 05/24/2018 | STOPPED INSPECTION SEVERAL FLEX DUCTS ARE FILLED WITH WATER - 5628 NOT READY - NEED DUCT FRAMED IN AND SA DROPS COMPLETED - RE INSPECT ALL - NEED PLAN REVISED TO MATCH INSTALLED | JERRYF | JERRYF | | HD | L | 5855478 |
R & R HEATING & AIR CONDITIONING, INC. | HRR | L | 05/22/2018 | NEED CONSULT WITH SENIOR INSPECTOR ON PLANS NOT MATCHING INSTALLED - NEED INSULATION SHIELDS INSTALLED AT B VENTS - DROP HEAT RUNS IN SOFFIT - NOT READY - STOPPED INSPECTION - RE INSPECT ALL | JERRYF | JERRYF | | HRR | L | 5851924 |
JESS' PLUMBING & HEATING, INC | P= | C | 08/09/2018 | revised plans ok. | TAYLOR | TAYLOR | | P= | C | 5929391 |
JESS' PLUMBING & HEATING, INC | P= | P | 08/08/2018 | 5658, 5664 OK, still need revised plan or engineers letter per base notes | SHANEN | SHANEN | | P= | P | 5927900 |
JESS' PLUMBING & HEATING, INC | P= | P | 08/07/2018 | 5652 OK | SHANEN | SHANEN | | P= | P | 5926419 |
JESS' PLUMBING & HEATING, INC | P= | P | 08/03/2018 | unit 5646 ok. | TAYLOR | TAYLOR | | P= | P | 5923338 |
JESS' PLUMBING & HEATING, INC | P= | P | 08/02/2018 | units 5634 and 5640 ok. | TAYLOR | TAYLOR | | P= | P | 5922183 |
JESS' PLUMBING & HEATING, INC | P= | P | 07/31/2018 | need hi- loops at dishwashers and air gaps at T&P drains for units 5634 and 5640. | TAYLOR | TAYLOR | | P= | P | 5919395 |
JESS' PLUMBING & HEATING, INC | P= | P | 07/27/2018 | 5610, 5616, 5622, 5628 OK | SHANEN | SHANEN | | P= | P | 5916683 |
JESS' PLUMBING & HEATING, INC | PTO | C | 07/09/2018 | | SHANEN | SHANEN | | PTO | C | 5896952 |
JESS' PLUMBING & HEATING, INC | PTO | P | 06/28/2018 | units 5652, 5658, and 5664 ok. | TAYLOR | TAYLOR | | PTO | P | 5888731 |
JESS' PLUMBING & HEATING, INC | PTO | P | 06/21/2018 | 5646 DWV test OK | SHANEN | SHANEN | | PTO | P | 5881782 |
JESS' PLUMBING & HEATING, INC | PTO | P | 06/20/2018 | Units 5634, 5640, 5646 water distribution test OK | SHANEN | SHANEN | | PTO | P | 5880842 |
JESS' PLUMBING & HEATING, INC | PTO | P | 06/14/2018 | Units 5628, 5634, 5640 DWV test OK | SHANEN | SHANEN | | PTO | P | 5874621 |
JESS' PLUMBING & HEATING, INC | PTO | P | 06/04/2018 | 5610/5616/5622/5628 h2o o.k / changed to partial by JW to allow further inspections | JOEL | JOEL | | PTO | P | 5863599 |
JESS' PLUMBING & HEATING, INC | PTO | P | 05/22/2018 | 5610, 5616, 5622 DWV test OK, need test on water distribution design OK, water to be tested when mains are completed | SHANEN | SHANEN | | PTO | P | 5852264 |
JESS' PLUMBING & HEATING, INC | PB | C | 04/17/2018 | unit 5670 ok, note: need engineers letter or revise plans by final. | TAYLOR | TAYLOR | | PB | C | 5818789 |
JESS' PLUMBING & HEATING, INC | PB | P | 04/13/2018 | units 5658 and 5664 ok. | TAYLOR | TAYLOR | | PB | P | 5816212 |
JESS' PLUMBING & HEATING, INC | PB | P | 04/11/2018 | unit 5652 ok. | TAYLOR | TAYLOR | | PB | P | 5813729 |
JESS' PLUMBING & HEATING, INC | PB | P | 04/09/2018 | 5610 ok. | TAYLOR | TAYLOR | | PB | P | 5811041 |
JESS' PLUMBING & HEATING, INC | PB | P | 04/06/2018 | unit 5646 ok, can not use no hub cast iron bands at unit 5610. | TAYLOR | TAYLOR | | PB | P | 5809998 |
JESS' PLUMBING & HEATING, INC | PB | P | 04/05/2018 | units 5634 and 5640 ok. | TAYLOR | TAYLOR | | PB | P | 5808840 |
JESS' PLUMBING & HEATING, INC | PB | P | 04/02/2018 | units 5616, 5622, 5628 ok, note: need engineers letter or revise plans to show 3 inch trunk lines. | TAYLOR | TAYLOR | | PB | P | 5804842 |
PREMIER HOMES, INC. | XBS | T | 06/12/2018 | PAID (REC#1506859) PLAN SPLICE FEE: $50 by: DANM for Construction: Calculated fire rating for unit separation wall to show min. 1-hr rating for units 5610, 5616 and 5622 Lion Tracks upper level only | DANM | DANM | | XBS | T | 5872302 |
JESS' PLUMBING & HEATING, INC | XMS | T | 06/05/2018 | PAID (REC#1505870): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised duct layout and sizes | JUSTINC | JUSTINC | | XMS | T | 5865186 |