PRO WALL SYSTEMS LLC | B= | C | 05/30/2018 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 5858900 |
PRO WALL SYSTEMS LLC | B= | P | 05/29/2018 | items corrected / final OK pending other finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), COPPER SMITH ELECTRIC INC Electrical Final Inspection is not Completed yet, CROWN SERVICES INC. Plumbing Final Inspection is not Completed yet, MICK HEATING & SHEET METAL Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 5857702 |
PRO WALL SYSTEMS LLC | B= | R | 05/25/2018 | need single action at all exterior doors except main entrance that is allowed a double key dead bolt with and indicator / need accessible hardware on both pocket doors and hardware at both pocket doors needs to be accessible in the fully open position / need to complete all other finals. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), COPPER SMITH ELECTRIC INC Electrical Final Inspection is not Completed yet, CROWN SERVICES INC. Plumbing Final Inspection is not Completed yet, MICK HEATING & SHEET METAL Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | R | 5856651 |
PRO WALL SYSTEMS LLC | BFR | P | 04/30/2018 | grab bar framing now OK / all framing now OK pending other roughs | DANE | DANE | | BFR | P | 5831112 |
PRO WALL SYSTEMS LLC | BFR | P | 04/27/2018 | need to install all grab bar backing / all other light gauge framing OK pending other roughs / discussed accessible elements | DANE | DANE | | BFR | P | 5830215 |
PRO WALL SYSTEMS LLC | BSP | R | 04/16/2018 | letter needs to be submitted to the plumbing inspector | DANE | DANE | | BSP | R | 5817346 |
COPPER SMITH ELECTRIC INC | E= | C | 05/30/2018 | | BRET | BRET | | E= | C | 5858848 |
COPPER SMITH ELECTRIC INC | E= | P | 05/29/2018 | Lay in fixtures are not clipped to grid---Need to look at all lay in fixtures and grid ceiling areas / | ROB | ROB | | E= | P | 5857874 |
COPPER SMITH ELECTRIC INC | E= | P | 05/25/2018 | gfci protect all receptacles within 6' of sink, gfci protect water cooler, handle ties, panel schedule did not inspect rtu, have ladder available for ceiling inspection tiles installed prior to inspection | BRET | BRET | | E= | P | 5856072 |
COPPER SMITH ELECTRIC INC | ER | P | 05/25/2018 | install clips on light fixtures, box open above duct work, | BRET | BRET | | ER | P | 5856064 |
COPPER SMITH ELECTRIC INC | ES | P | 05/15/2018 | Commercial Service: 200 amp service--Ok to set Meter----NOTE: Need to check for brass tag and branch circuit make up in panel at final / | ROB | ROB | | ES | P | 5844700 |
COPPER SMITH ELECTRIC INC | ES | R | 05/14/2018 | Commercial Service: Need to install brass tag with address at Meter--200 amp / | ROB | ROB | | ES | R | 5844136 |
COPPER SMITH ELECTRIC INC | ER | P | 05/14/2018 | Hard lid bathroom ceilings ok / | ROB | ROB | | ER | P | 5844128 |
COPPER SMITH ELECTRIC INC | ESL | C | 04/27/2018 | conduits from wall to reception desk | BRET | BRET | | ESL | C | 5829590 |
COPPER SMITH ELECTRIC INC | ER | P | 04/27/2018 | walls except reception desk wall | BRET | BRET | | ER | P | 5829588 |
MICK HEATING & SHEET METAL CO. | H= | C | 05/29/2018 | TEST AND BALANCE REPORT RECEIVED. WILL SCAN IN IN MORNING. MECHANICAL FINAL OK. | BENH | BENH | | H= | C | 5858144 |
MICK HEATING & SHEET METAL CO. | HD | C | 05/25/2018 | DUCT ABOVE CEILING AND DIFFUSERS OK, NO ROOF TODAY | BENH | BENH | | HD | C | 5856853 |
MICK HEATING & SHEET METAL CO. | HC | C | 05/15/2018 | PENDING LETTER OF APPROVAL FOR MEDIUM PRESSURE PLEASE RELEASE METER FOR 2 LB SYSTEM THANKS | BENH | BENH | | HC | C | 5845959 |
MICK HEATING & SHEET METAL CO. | HO | C | 05/15/2018 | BY FINAL NEED LETTER OF APPROVAL FOR MEDIUM PRESSURE SYSTEM 10 LB TEST OK, 1" MAIN(MEDIUM PRESSURE) 2 ROOF TOP UNITS | BENH | BENH | | HO | C | 5845958 |
MICK HEATING & SHEET METAL CO. | HD | P | 05/04/2018 | EF-1 OK, EF-2,3 FANS AND DUCT ABOVE HARD LID OK, NO ROOF TRUNK LINES OR LATERALS INSPECTED TODAY | BENH | BENH | | HD | P | 5836676 |
CROWN SERVICES INC. | P= | C | 05/30/2018 | corrections made | JOSEPHD | JOSEPHD | | P= | C | 5858899 |
CROWN SERVICES INC. | P= | P | 05/29/2018 | need power supply to recirculating pump and clearances at toilet, rest ok. | TAYLOR | TAYLOR | | P= | P | 5857124 |
CROWN SERVICES INC. | P= | P | 05/25/2018 | no hot water, need 16-18 inches from from side wall to center of toilet at womens restroom, re- inspect all. | TAYLOR | TAYLOR | | P= | P | 5856395 |
CROWN SERVICES INC. | PTO | C | 04/30/2018 | DWV and water distribution test OK, check water heater at final | SHANEN | SHANEN | | PTO | C | 5831193 |
CROWN SERVICES INC. | PB | C | 04/17/2018 | Engineers letter received see image | SHANEN | SHANEN | | PB | C | 5818450 |
CROWN SERVICES INC. | PB | P | 04/10/2018 | Installed plumbing does not match plans, re-plumb, revise plans or submit engineers approval for installed piping, plans reflect 3" from 6" trunk line to drinking fountain and shows separate tie-ins for bathroom group and drain to drinking fountain, uncover tie-ins to verify, | SHANEN | SHANEN | | PB | P | 5812484 |