COLORADO COMMERCIAL CONSTRUCTION, INC. | B= | C | 02/25/2019 | final OK pending other finals | DANE | DANE | | B= | C | 6115980 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | B= | P | 02/25/2019 | final OK pending other finals / stamper letter of compliance for welding and bolting on file | DANE | DANE | | B= | P | 6115814 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | B= | P | 02/21/2019 | pending completion of mech final building okay. Additional Inspections Required (computer generated): R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6113529 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | B= | P | 02/14/2019 | Still need eng letter for welded canopy, need to complete ramp on west exterior doorway / need address posted on building / need to complete mech final -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): R & R HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6107213 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BIN | C | 10/24/2018 | | BOBF | BOBF | | BIN | C | 6004260 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BIN | P | 10/15/2018 | need to complete insulation at areas where stucco is not installed, rest of exterior walls okay | BOBF | BOBF | | BIN | P | 5994320 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BFR | P | 09/13/2018 | need eng letter for welded canopy framing, pending other required inspections rest of framing okay, R38 insulation installed at roof | BOBF | BOBF | | BFR | P | 5964063 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BLA | C | 09/07/2018 | | BOBF | BOBF | | BLA | C | 5958289 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BFR | P | 08/09/2018 | pending other required inspections, walls and joists okay, conditioned space / roof decking not installed | BOBF | BOBF | | BFR | P | 5929136 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BFI | C | 06/18/2018 | R10 installed / | BOBF | BOBF | | BFI | C | 5877204 |
COLORADO COMMERCIAL CONSTRUCTION, INC. | BFT | P | 06/18/2018 | footing okay pending receipt of stamped open hole | BOBF | BOBF | | BFT | P | 5877175 |
EL PASO ELECTRIC, LLC. | E= | C | 02/05/2019 | install main breaker in panel. | BRET | BRET | | E= | C | 6098520 |
EL PASO ELECTRIC, LLC. | ER | C | 02/05/2019 | | BRET | BRET | | ER | C | 6098515 |
EL PASO ELECTRIC, LLC. | EUG | P | 06/18/2018 | ufer n.e corner of building | BRET | BRET | | EUG | P | 5877240 |
R & R HEATING & AIR CONDITIONING, INC. | H= | C | 02/06/2019 | MECHANICAL FINAL OK. TEST AND BALANCE REPORT NOT REQUIRED. | DUSTINS | DUSTINS | | H= | C | 6099531 |
R & R HEATING & AIR CONDITIONING, INC. | H= | P | 01/17/2019 | AIR HANDLERS, LINE SETS, COILS AND FRESH AIR OK. NEED TO WEATHER PROOF LOUVERS AND NEED TO SEE CONDENSERS ON ROOF, NO ACCESS TODAY. PROVIDE TEST AND BALANCE REPORT FOR FINAL. | DUSTINS | DUSTINS | | H= | P | 6081116 |