TRI-STAR MASONRY, INC. | B= | C | 02/13/2019 | All other required Final inspections are complete. (This is a computer generated result) | CHUCK | CHUCK | | B= | C | 6105561 |
TRI-STAR MASONRY, INC. | B= | P | 02/06/2019 | Bldg final inspection - shell only OK / Corrections from previous final inspection completed / Engineer's letter dated 1.16.19 for steel structure bolting and welding on file. / Partial pending completion of plumbing final inspection. | CHUCK | CHUCK | | B= | P | 6099296 |
TRI-STAR MASONRY, INC. | B= | R | 02/06/2019 | Bldg final re-inspection - shell only / Weld paperwork submitted does not address welding/bolting of structure. / Need to complete items listed in previous final inspection / Need to complete plumbing final inspection. Additional Inspections Required (computer generated): GRANT DRUMMOND II Plumbing Final Inspection is not Completed yet. | CHUCK | CHUCK | | B= | R | 6098959 |
TRI-STAR MASONRY, INC. | B= | P | 02/05/2019 | Need 3rd party welding/bolting observations -- Need to seal exterior penetrations at west side of building -- Missing exterior door at southeast corner of building -- Need to complete all other finals -- Reviewed accessible elements -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): GRANT DRUMMOND II Plumbing Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 6098693 |
TRI-STAR MASONRY, INC. | BFN | C | 01/28/2019 | Eufer verified by RBD electric inspector Craig K. | JEREMYA | JEREMYA | | BFN | C | 6089591 |
TRI-STAR MASONRY, INC. | BBB | C | 01/23/2019 | Bond beam observations received | RICHB | RICHB | | BBB | C | 6085384 |
TRI-STAR MASONRY, INC. | BFN | P | 01/23/2019 | Foundation wall observations received - need ufer observation to complete BFT & BFN | RICHB | RICHB | | BFN | P | 6085383 |
TRI-STAR MASONRY, INC. | BFT | P | 01/23/2019 | Overexcavation, excavation & backfill observations received - densities and 2200 psf OK per plans // footing observation received - need ufer observation to complete BFT | RICHB | RICHB | | BFT | P | 6085382 |
TRI-STAR MASONRY, INC. | BFI | P | 04/24/2018 | Need to meet with Contractor to discuss Third Party inspection requirements - foundation appears complete / 2" R-10 applied vertically to inside face of foundation, down to top of footing / plans reviewed electronically (none onsite) | RICHB | RICHB | | BFI | P | 5825986 |
ELECTRIC TECH INC. | E= | C | 01/31/2019 | core and shell okay | CHIPO | CHIPO | | E= | C | 6093832 |
ELECTRIC TECH INC. | ES | C | 01/17/2019 | Commercial Service: 100 amp commercial 4w service ok to set meter / Power is for House panel only / Notes: By final verify that contractor has poured a pad at the service in order to keep disconnect below 6 foot 7 inches. | JOSEPH | JOSEPH | | ES | C | 6080980 |
ELECTRIC TECH INC. | ES | R | 01/15/2019 | Commercial Service: need to pull meter / disconnect off of wall to get clearance of gutter | CRAIG | CRAIG | | ES | R | 6078958 |
ELECTRIC TECH INC. | ES | R | 01/14/2019 | Commercial Service: Not Ready | CRAIG | CRAIG | | ES | R | 6077416 |
ELECTRIC TECH INC. | ER | P | 01/11/2019 | wall paks only ok | CRAIG | CRAIG | | ER | P | 6076557 |
DRUMMOND PLUMBING LLC | H= | C | 02/04/2019 | FINAL CONNECTIONS COMPLETE | MARKB | MARKB | | H= | C | 6096766 |
AIRTECH MECHANICAL, INC. | H= | C | 01/22/2019 | UNIT HEATERS COMPLETE | MARKB | MARKB | | H= | C | 6084970 |
DRUMMOND PLUMBING LLC | HSP | P | 01/17/2019 | Need unit heaters permitted and inspected. | MARKB | MARKB | | HSP | P | 6081190 |
DRUMMOND PLUMBING LLC | HC | C | 01/16/2019 | RELEASE METER - OK FOR BOTH METERS. GAS SYSTEM IS ENGINEERED FOR 14" W.C. | MARKB | MARKB | | HC | C | 6079446 |
DRUMMOND PLUMBING LLC | HI | C | 01/16/2019 | 10 PSI PRESSURE TEST OK. PIPING PER PLAN. NOTE: ENGINEERED GAS SYSTEM FOR 14" W.C. | MARKB | MARKB | | HI | C | 6079445 |
AIRTECH MECHANICAL, INC. | HD | R | 12/04/2018 | Splice not found in computer or on site. | MARKB | MARKB | | HD | R | 6042493 |
AIRTECH MECHANICAL, INC. | HD | R | 11/26/2018 | Need approved tenant finish plans on file with RBD to do inspection - core and shell has no duct on it. RTU'S not set at this time. | MARKB | MARKB | | HD | R | 6033556 |
DRUMMOND PLUMBING LLC | P= | C | 02/13/2019 | splice complete on water piping | TED | TED | | P= | C | 6105560 |
DRUMMOND PLUMBING LLC | P= | P | 02/06/2019 | need water piping splice | TED | TED | | P= | P | 6099036 |
DRUMMOND PLUMBING LLC | PTO | C | 02/05/2019 | water piping for shell | TED | TED | | PTO | C | 6097575 |
DRUMMOND PLUMBING LLC | PTO | L | 02/04/2019 | Field cancel. | DANR | DANR | | PTO | L | 6096659 |
DRUMMOND PLUMBING LLC | P= | L | 02/04/2019 | Field cancel. | DANR | DANR | | P= | L | 6096651 |
DRUMMOND PLUMBING LLC | PB | C | 08/14/2018 | water stub to images | TED | TED | | PB | C | 5932776 |
DRUMMOND PLUMBING LLC | PB | P | 05/01/2018 | ok for dwv only **STILL NEED WATER STUBBED IN** | JOHNS | JOHNS | | PB | P | 5831953 |
DRUMMOND PLUMBING LLC | XPS | T | 02/11/2019 | PAID (REC#1575819): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 2/11/19: Delta 5 revisions revised water pipe size analysis data, resized 1 1/2" water piping to 1 1/4" | SHANEN | SHANEN | | XPS | T | 6103636 |
ELECTRIC TECH INC. | XES | T | 01/14/2019 | PAID (REC#1569448): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised one-line diagram. | BERTHA | BERTHA | | XES | T | 6077602 |
AIRTECH MECHANICAL, INC. | XMS | P | 01/14/2019 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: delta 4 | DALEH | DALEH | | XMS | P | 6076989 |
TRI-STAR MASONRY, INC. | XBS | T | 12/11/2018 | PAID (REC#1567916) PLAN SPLICE FEE: $50 by: DANM for Construction: Revise lintel angle sizes | DANM | DANM | | XBS | T | 6048864 |
TRI-STAR MASONRY, INC. | XES | T | 11/13/2018 | PAID (REC#1567916) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised Available Fault Current for House Panel and service location. | BERTHA | BERTHA | | XES | T | 6024400 |
TRI-STAR MASONRY, INC. | XMS | P | 11/07/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: delta 1 | JUSTINC | JUSTINC | | XMS | P | 6019346 |
TRI-STAR MASONRY, INC. | XES | P | 11/07/2018 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised entire scope - changed one-line and interior for core and shell. | BERTHA | BERTHA | | XES | P | 6019308 |
TRI-STAR MASONRY, INC. | XBS | T | 11/07/2018 | PAID (REC#1567916) PLAN SPLICE FEE: $50 by: DANM for Construction: Added openings with related structural revisions | DANM | DANM | | XBS | T | 6019236 |