COMITO BUILDING AND DESIGN, LLC | B= | C | 04/19/2019 | | NICK | NICK | | B= | C | 6172149 |
COMITO BUILDING AND DESIGN, LLC | B= | P | 03/27/2019 | Temp CO: extension ( Expires: 4/26/2019 12:00:00 AM) | GITA | GITA | | B= | P | 6145601 |
COMITO BUILDING AND DESIGN, LLC | B= | P | 03/01/2019 | Temp CO: All finals are done or partials ( Expires: 3/31/2019 12:00:00 AM) | GITA | GITA | | B= | P | 6121039 |
COMITO BUILDING AND DESIGN, LLC | B= | P | 02/28/2019 | Need 36" landing installed at exterior side of front door / Need to install 36" landing outside garage service door / Need all other external finals complete / All other aspects of final OK -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982). | NICK | NICK | | B= | P | 6120217 |
COMITO BUILDING AND DESIGN, LLC | BSP | P | 02/15/2019 | Met on site with Riley to review requirements for apply for a TCO | NICK | NICK | | BSP | P | 6108860 |
COMITO BUILDING AND DESIGN, LLC | BLA | C | 11/20/2018 | | NICK | NICK | | BLA | C | 6030906 |
COMITO BUILDING AND DESIGN, LLC | BIN | C | 09/20/2018 | ES report on file for spray foam / Insulation certificate on file | NICK | NICK | | BIN | C | 5971278 |
COMITO BUILDING AND DESIGN, LLC | BFR | C | 09/20/2018 | All frame items completed | NICK | NICK | | BFR | C | 5971277 |
COMITO BUILDING AND DESIGN, LLC | BFR | P | 09/20/2018 | Eng on file for ledger in floor framing / Still need site visit to inspect all other framing items | NICK | NICK | | BFR | P | 5970726 |
COMITO BUILDING AND DESIGN, LLC | BIN | P | 09/18/2018 | Need ES report for spray foam in attic and exterior walls / Need insulation report to verify R values / Need frame complete | NICK | NICK | | BIN | P | 5968559 |
COMITO BUILDING AND DESIGN, LLC | BFR | R | 09/18/2018 | Still need to install shear on both sides of garage per approved plans / Still need to install all hangers for 2x10 dropped shower framing / Still need to install hanger for F1 truss front entry / Still need to bolt 4 ply LVL in basement / Still need Eng for ledger in basement floor framing / All other items completed | NICK | NICK | | BFR | R | 5968556 |
COMITO BUILDING AND DESIGN, LLC | BFR | P | 09/11/2018 | Need to install HTS20 at H8 gerder / Need to install double H2.5T hanger and H7 at stairs / Need to install double H2.5T at H1 girder / Need to shear both sides of garage door framing / Need to install FHA strap for gas line in garage wall top plate / Need to install hanger for F1 at front entry / Need to finish nailing HTS20 for C8 girder / Need to finish nailing hanger for AH / Need to install hangers for 2x10 framing for dropped shower / Need to strap stair landing corners / Need to install hangers for stair joists / Need Eng for ledger installed for floor framing / Need to install bolts for 4 ply LVL basement / Still need to inspect interior shear walls / OK to insulate | NICK | NICK | | BFR | P | 5961339 |
COMITO BUILDING AND DESIGN, LLC | BTR | C | 08/22/2018 | | NICK | NICK | | BTR | C | 5942233 |
COMITO BUILDING AND DESIGN, LLC | BSP | P | 08/03/2018 | All porch framing OK per Eng letter / Deck frame OK | NICK | NICK | | BSP | P | 5923443 |
COMITO BUILDING AND DESIGN, LLC | BSP | P | 08/03/2018 | Eng on file for porch to beam connections | NICK | NICK | | BSP | P | 5922968 |
COMITO BUILDING AND DESIGN, LLC | BSP | R | 07/19/2018 | Inspection for porches and deck frames / Need to install ACE/AC post caps for all post to beam locations per approved plans detail, coil straps and HTS20's installed at front porch, only coil straps installed at side porch location / Single ACE post to beam installed at side deck location, need to be installed in pairs per Simpson requirements / All other framing for porches and deck OK | NICK | NICK | | BSP | R | 5908108 |
COMITO BUILDING AND DESIGN, LLC | BFI | C | 06/01/2018 | R-10 at 2' OK | NICK | NICK | | BFI | C | 5862055 |
COMITO BUILDING AND DESIGN, LLC | BFD | C | 06/01/2018 | Drain of entire structure OK / Damp proof OK / Daylights to east | NICK | NICK | | BFD | C | 5862031 |
COMITO BUILDING AND DESIGN, LLC | BFN | C | 06/01/2018 | Eng letter of observation on file / Soils on file | NICK | NICK | | BFN | C | 5862030 |
COMITO BUILDING AND DESIGN, LLC | BFT | C | 06/01/2018 | Eng letter of observation on file / Open hole on file / #2600psf / Drain entire structure | NICK | NICK | | BFT | C | 5862026 |
COMITO BUILDING AND DESIGN, LLC | BFT | P | 04/20/2018 | AUTHORIZED INSPECTION BY ENGINEER | GITA | GITA | GITA | BFT | P | 5822384 |
COMITO BUILDING AND DESIGN, LLC | BFN | P | 04/20/2018 | AUTHORIZED INSPECTION BY ENGINEER | GITA | GITA | GITA | BFN | P | 5822383 |
HOMERUN ELECTRONICS, INC. | E= | C | 02/21/2019 | | JOHNN | JOHNN | | E= | C | 6113534 |
HOMERUN ELECTRONICS, INC. | E= | R | 02/15/2019 | 2 drivers in mech rm: need nm connectors, co/smoke det basement, no power, --------------------------------no hot tub installed, prewire only, 25 amp a/c,ok | JOHNN | JOHNN | | E= | R | 6109068 |
HOMERUN ELECTRONICS, INC. | ER | C | 09/06/2018 | | JOHNN | JOHNN | | ER | C | 5957067 |
HOMERUN ELECTRONICS, INC. | ES | C | 09/05/2018 | Residential Underground: 200-amp 3 Wire service, ok to set meter, new res. | JOHNN | JOHNN | | ES | C | 5955551 |
HOMERUN ELECTRONICS, INC. | ER | R | 09/05/2018 | cables on garage ceiling need to be 1.25" back from face of rafter, 2 cables on the sides of the garage doors need to be inside of the wall, as is, they will be under sheet rock, add 1 outlet in kitchen per 6'/12' spacing, living room fireplace: need proper nm connector, ---------------------------------------main panel:ir ufer, no mcc,#6al, 100 amp sub:no mcc,2#6cu,1#6al, | JOHNN | JOHNN | | ER | R | 5955545 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | H= | C | 04/02/2019 | completed | DAVIDH | DAVIDH | | H= | C | 6152274 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | HO | C | 04/02/2019 | 10 lb test ok note future firepit | DAVIDH | DAVIDH | | HO | C | 6152269 |
A & Z MECHANICAL, INC. | H= | C | 02/12/2019 | finished basement , direct vent furns , louver door for water heaters a/c x 1 | DAVIDH | DAVIDH | | H= | C | 6105083 |
A & Z MECHANICAL, INC. | HC | C | 09/06/2018 | RELEASE METER | RANDYB | RANDYB | | HC | C | 5957520 |
A & Z MECHANICAL, INC. | HRR | C | 09/06/2018 | | RANDYB | RANDYB | | HRR | C | 5957424 |
A & Z MECHANICAL, INC. | HRR | P | 08/28/2018 | TWO FIREPLACES NOT SECURED TO FRAMING , LINE SET WILL REQUIRE A PRESSURE TEST PRIOR TO HOOK UP . DIRECT VENT FURNS. A/C X 1 , FINISHED BASEMENT. 6" OSA TO BOTH FURNS. | DAVIDH | DAVIDH | | HRR | P | 5948151 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | HI | C | 08/22/2018 | 10 lb test ok 1 1/2" main 2 furn,2 w/h,1 bbq,3 f/p and 1 future firepit | DAVIDH | DAVIDH | | HI | C | 5942392 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | P= | C | 02/11/2019 | Ok, | DANR | DANR | | P= | C | 6103778 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | PTO | C | 08/21/2018 | Finished basement, no irrigation stub, aav island sink, powder room lav and bar sink. | SHANEN | SHANEN | | PTO | C | 5941140 |
ROCKY MOUNTAIN RADIANT HEATING & PLUMBING, INC. | PB | C | 06/11/2018 | | SHANEN | SHANEN | | PB | C | 5870179 |