CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | C | 12/18/2018 | All other required Final inspections are complete. (This is a computer generated result) | NICK | NICK | | B= | C | 6056226 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 12/18/2018 | . Additional Inspections Required (computer generated): External Agency Inspection UBS by CSUREVIEW is not Completed yet (Contact: 668-3524), External Agency Inspection UWS by CSUREVIEW is not Completed yet (Contact: 668-3524). | NICK | NICK | | B= | P | 6056026 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 12/17/2018 | Complete final grade at front and right of home / Penetrations sealed at AC -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection UBS by CSUREVIEW is not Completed yet (Contact: 668-3524), External Agency Inspection UWS by CSUREVIEW is not Completed yet (Contact: 668-3524). | SHAUN | SHAUN | | B= | P | 6054721 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 12/14/2018 | Need to seal penetrations in exterior at AC / Need to complete final grade at front of house -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection UBS by CSUREVIEW is not Completed yet (Contact: 668-3524), External Agency Inspection UWS by CSUREVIEW is not Completed yet (Contact: 668-3524). | NICK | NICK | | B= | P | 6053265 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BTR | C | 10/12/2018 | Underlayment, batten & flashing OK | RICHB | RICHB | | BTR | C | 5993085 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BLA | C | 09/24/2018 | Lath OK | RICHB | RICHB | | BLA | C | 5974405 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BIN | C | 09/14/2018 | Thermal in walls & roof/ceiling OK per IECC prescriptive indicated in plans | RICHB | RICHB | | BIN | C | 5965645 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFR | C | 09/11/2018 | Framing OK - other Roughs are complete | RICHB | RICHB | | BFR | C | 5961238 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BIN | P | 09/10/2018 | Qualified third party energy inspection documentation must be presented at time of final building (B=) inspection | INTERNET | INTERNET | | BIN | P | 5960023 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 08/14/2018 | engineer letter for master slider on file | LONNYS | LONNYS | | BSP | P | 5932827 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFD | C | 08/03/2018 | | LONNYS | LONNYS | | BFD | C | 5922851 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFN | C | 08/03/2018 | all paperwork on file | LONNYS | LONNYS | | BFN | C | 5922850 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFT | C | 08/03/2018 | open hole on file - 2400PSF - usable | LONNYS | LONNYS | | BFT | C | 5922847 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | R | 08/01/2018 | floor framing OK per previous inspection on 6-29-18 | LONNYS | LONNYS | | BSP | R | 5920184 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFN | R | 07/26/2018 | foundation design already on file / still need open hole | LONNYS | LONNYS | | BFN | R | 5914288 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 07/25/2018 | Need all Eng for footing/foundation / Inspection for shear nailing for portal walls and for structural facia and hardware at facia / Shear wall nailing and foundation strapping OK / Structural facia OK / LS30's and LS70's at porch OK for facia connections | NICK | NICK | | BSP | P | 5913571 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 07/10/2018 | great room and master narrow braced wall drag strutt detail OK - still need to inspect exterior sheathing and fastening | LONNYS | LONNYS | | BSP | P | 5897581 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 06/29/2018 | floor framing OK | LONNYS | LONNYS | | BSP | P | 5889482 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | R | 06/28/2018 | Need to install hangers for double I joists / Need to frame in header and opening in mechanical space to rest of crawl space per approved plans / All other floor framing OK / Still need all Eng for footing/foundation | NICK | NICK | | BSP | R | 5888511 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFD | R | 06/14/2018 | need open hole and soils to complete BFT and BFD / drain is entire to sump - damp proofing oK | LONNYS | LONNYS | | BFD | R | 5874363 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFD | R | 06/13/2018 | Need to post address on site for house / Do not know what building is being inspected / Need footing/foundation complete | NICK | NICK | | BFD | R | 5873321 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFD | R | 06/12/2018 | field cancelled per site rep Mike | LONNYS | LONNYS | | BFD | R | 5871388 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 06/12/2018 | foundation design on file 2000PSF / UPDATE: status changed to reject - foundation design already on file - still need soils and open hole | LONNYS | LONNYS | | BSP | P | 5871125 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFN | P | 06/06/2018 | need to complete BFT / foundation wall forms and reinforcing OK | LONNYS | LONNYS | | BFN | P | 5865863 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 06/04/2018 | foundation design on file 2000 PSF / NOTE: still need soils and open hole | LONNYS | LONNYS | | BSP | P | 5862758 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFT | P | 05/31/2018 | need site specific foundation design / need soils and open hole / footer forms and reinforcing OK - ufer observed / pour at own risk | LONNYS | LONNYS | | BFT | P | 5860090 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFT | R | 05/30/2018 | field cancelled per site rep - not ready | LONNYS | LONNYS | | BFT | R | 5859689 |
GONZALES ELECTRIC, LLC | E= | C | 12/12/2018 | | JOHNN | JOHNN | | E= | C | 6050947 |
GONZALES ELECTRIC, LLC | ES | C | 08/29/2018 | Residential Underground: 200-amp 3 Wire service, ok to set meter , new res, | JOHNN | JOHNN | | ES | C | 5949544 |
GONZALES ELECTRIC, LLC | ER | C | 08/29/2018 | need #6cu for inter sys bond, panel not made up, CHECK on final,------------ir ufer, jet tub, | JOHNN | JOHNN | | ER | C | 5949534 |
BESTWAY PLUMBING, INC | H= | C | 12/13/2018 | corrections made | DAVIDH | DAVIDH | | H= | C | 6052108 |
BESTWAY PLUMBING, INC | H= | R | 12/12/2018 | STILL MISSING RAIN SHIELD ON VENT ON ROOF AND STILL NO ACCESS TO GAS CONNECTION ON FIREPLACE | DAVIDH | DAVIDH | | H= | R | 6050780 |
BESTWAY PLUMBING, INC | H= | P | 12/11/2018 | on demand water heater vents not trimmed out, fireplace vents missing rain shields on roof need access to fireplace in great rm can not get to gas line | DAVIDH | DAVIDH | | H= | P | 6049360 |
MESA PLUMBING & HEATING INC. | HC | C | 09/10/2018 | RELEASE METER | DAVIDH | DAVIDH | | HC | C | 5959923 |
MESA PLUMBING & HEATING INC. | HI | C | 09/10/2018 | 10 LB TEST OK NOTE 2" MAIN , 3 FIREPLACES, 1 RANGE, 2 ON DEMAND W/H | DAVIDH | DAVIDH | | HI | C | 5959902 |
BESTWAY PLUMBING, INC | HRR | C | 09/07/2018 | | RANDYB | RANDYB | | HRR | C | 5958453 |
BESTWAY PLUMBING, INC | HRR | R | 09/05/2018 | Great room fireplace vent disconnected above chase. Still need insulation shields around both great room and master bedroom fireplace vents. Master bedroom vent lacks 1" clearance to combustibles. | RANDYB | RANDYB | | HRR | R | 5955524 |
BESTWAY PLUMBING, INC | HRR | P | 08/31/2018 | Provide fireplace installation instructions for master bedroom and great room fireplace. Secure outdoor fireplace and maser bedroom fireplace to framing. Provide insulation shields for master bedroom and great room fireplaces. BY FINAL: Inspect air handlers. Inspect water heater venting throughout crawlspace. NOTES: Conditioned crawlspace. 2 Instantaneous hot water heaters. NO Outside air to furnace return. | RANDYB | RANDYB | | HRR | P | 5953130 |
BESTWAY PLUMBING, INC | HRR | P | 07/05/2018 | UNDER FLOOR OK | DAVIDH | DAVIDH | | HRR | P | 5893838 |
MESA PLUMBING & HEATING INC. | HI | P | 07/03/2018 | 2" main under floor OK, 2 water heater, 3 fireplace, 1 range | SHANEN | SHANEN | | HI | P | 5892756 |
MESA PLUMBING & HEATING INC. | P= | C | 12/13/2018 | Corrections made | MALYNDA | MALYNDA | | P= | C | 6052308 |
MESA PLUMBING & HEATING INC. | P= | P | 12/12/2018 | Unable to locate mixing valves for tubs, secure master shower head, water lines crossed at powder bath lav, T&P installed incorrectly (must be installed per manufacture's instructions), rest ok. Note: no irrigation. | MALYNDA | MALYNDA | | P= | P | 6050363 |
MESA PLUMBING & HEATING INC. | PTO | C | 08/09/2018 | Check water heaters, water entry, and tub mixing valves at final | SHANEN | SHANEN | | PTO | C | 5929389 |
MESA PLUMBING & HEATING INC. | PB | C | 05/24/2018 | | SHANEN | SHANEN | | PB | C | 5854834 |