COLORADO STRUCTURES INC | B= | C | 08/16/2019 | Items from previous inspection corrected | DAKOTAB | DAKOTAB | | B= | C | 6304016 |
COLORADO STRUCTURES INC | BFR | C | 08/16/2019 | Engineer letter for OSB spacers at top plate received -- Engineer letter for hold down substitutions received -- Engineer letter for truss repairs for RM11 and RSM14 received -- All items from previous inspection corrected | DAKOTAB | DAKOTAB | | BFR | C | 6304014 |
COLORADO STRUCTURES INC | B= | R | 08/08/2019 | need to complete BFR / need to fire tape above ceiling at all sides of all fire barriers / all other items for final inspection are OK pending other finals and BFR. Additional Inspections Required (computer generated): External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977). | DANE | DANE | | B= | R | 6294093 |
COLORADO STRUCTURES INC | BSP | P | 12/10/2018 | Screw patterns at all drywall in maintenance garage OK | JEREMYA | JEREMYA | | BSP | P | 6048232 |
COLORADO STRUCTURES INC | BIN | P | 12/05/2018 | pending other required inspections insulation on east, west and north side of maintenance room okay | BOBF | BOBF | | BIN | P | 6044079 |
COLORADO STRUCTURES INC | BFR | P | 11/30/2018 | frame inspection of remainder of building // at farthest north bay on east side need engineer fix for broken web in RM11 truss (first truss from south wall) / need engineer fix for missing gusset at RM11 over north wall of 2nd bay from north end on east side (missing at east end over east wall) / need stamped copy of drag truss fixes that are over center wall / need engineer for top plates that have OSB stacked on top of them under trusses / all other framing components OK per plan and OK pending other roughs | DANE | DANE | | BFR | P | 6040325 |
COLORADO STRUCTURES INC | BSP | P | 11/30/2018 | FIRE BARRIERS 2ND LAYER / drywall attachments at 2nd layer of rock at all fire barriers OK per WP 3825 that has been spliced in | DANE | DANE | | BSP | P | 6040301 |
COLORADO STRUCTURES INC | BSP | P | 11/21/2018 | first layer of rock at fire barriers OK per WP 3825 pending splice of the WP 3825 into plans | DANE | DANE | | BSP | P | 6032577 |
COLORADO STRUCTURES INC | BFR | R | 11/15/2018 | could not do frame inspection as the scanned in truss details and layout plan are for a 16 bay garage not the 24 bay and there is no truss connection plan / need to revise plans to have correct pages and connection plan / need to remove plumbing from scope of work as there is no plumbing in this building / training with Tim S on R2 and U occ VB construction apartments | DANE | DANE | | BFR | R | 6027397 |
COLORADO STRUCTURES INC | BSP | P | 11/15/2018 | Training with Dane - Discussed rated assembly penetrations - Discussed Corridors vs Breeze ways - Discussed Fire barriers vs Fire partitions - Discussed Engineer judgments and where they are needed or appropriate - Discussed 5A vs 5B construction and its impact on rated assembly requirements | TIMOTHYS | TIMOTHYS | | BSP | P | 6027394 |
COLORADO STRUCTURES INC | BIN | P | 11/14/2018 | insulation OK at fire barrier between maintenance shop and storage area and can be used per GA assembly WP 3825 pending other roughs / this assembly must be spliced into the plans as the plans call for a GA assembly WP 4135 and that assembly does not allow for insulation in the wall | DANE | DANE | | BIN | P | 6025912 |
COLORADO STRUCTURES INC | BFR | P | 11/09/2018 | Frame and OSB shear at (2) interior fire barrier walls OK pending other roughs -- Still need to inspect insulation and firestopping of penetrations before 1st layer of drywall can be installed | DAKOTAB | DAKOTAB | | BFR | P | 6021524 |
COLORADO STRUCTURES INC | BFR | P | 10/31/2018 | exterior sheer OK | DANE | DANE | | BFR | P | 6012305 |
COLORADO STRUCTURES INC | BFN | C | 08/22/2018 | Engineers observation Letter on file / Eufer noted | DANE | DANE | | BFN | C | 5941773 |
COLORADO STRUCTURES INC | BFT | C | 08/22/2018 | Engineers observation Letter on file / Soils report on file | DANE | DANE | | BFT | C | 5941768 |
COLORADO STRUCTURES INC | BSP | T | 08/06/2018 | PAID (REC#1526029): ADDITIONAL PLAN REVIEW TIME: $50 From: SHELLEY TRUSSES | SHELLEY | SHELLEY | | BSP | T | 5924259 |
COLORADO STRUCTURES INC | BFT | P | 07/05/2018 | Authorized 3rd party engineer inspection with all observation paperwork - ufer letter and open hole letter to be picked up by inspector @ BFI or BFD inspection or uploaded to online inspection request / met on site with superintendent and discussed job progress | DANE | DANE | | BFT | P | 5894410 |
BIBLE ELECTRIC, INC. | E= | C | 05/01/2019 | | BRET | BRET | | E= | C | 6183687 |
BIBLE ELECTRIC, INC. | ES | C | 03/21/2019 | Commercial Service: 400 amp service with 300 amp main breaker for maintenance garage with detached garages | BRET | BRET | | ES | C | 6140121 |
BIBLE ELECTRIC, INC. | ER | P | 11/06/2018 | ok except surface mount panel, sheet rock needs to be installed before panel can be install and cables landed | BRET | BRET | | ER | P | 6017165 |
LDI MECHANICAL, INC. | H= | C | 08/12/2019 | INSPECTED WHEN ON SITE FOR PERMIT L50043, WAS JUST NEEDING MECHANICAL CONTRACTOR ATTACHED TO THIS PERMIT. ONE ELECTRIC HEATER OK. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6296236 |
HORIZON LLC OF SOUTH CAROLINA | P= | C | 08/08/2019 | no plbg installed per plan splice @ plan page 518 | JOHNS | JOHNS | | P= | C | 6292903 |
BIBLE ELECTRIC, INC. | XES | T | 03/28/2019 | PAID (REC#1594575): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revised site lighting and luminaire schedule. | SHELBY | SHELBY | | XES | T | 6148404 |
COLORADO STRUCTURES INC | XBS | T | 03/27/2019 | PAID (REC#1594576): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Clarify fire wall construction and continuity | MICHAELA | MICHAELA | | XBS | T | 6145635 |
COLORADO STRUCTURES INC | XBS | T | 03/19/2019 | PAID (REC#1583898): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Sub-facia change | MICHAELA | MICHAELA | | XBS | T | 6136317 |
BIBLE ELECTRIC, INC. | XES | T | 01/25/2019 | PAID (REC#1583900): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised site lighting and luminaire schedule. | BERTHA | BERTHA | | XES | T | 6087964 |
COLORADO STRUCTURES INC | XBS | T | 12/10/2018 | PAID (REC#1583901): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Truss hardware | MICHAELA | MICHAELA | | XBS | T | 6047131 |
COLORADO STRUCTURES INC | XBS | T | 11/30/2018 | PAID (REC#1560004): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise uplift connections | MICHAELA | MICHAELA | | XBS | T | 6038880 |
COLORADO STRUCTURES INC | XBS | T | 11/21/2018 | PAID (REC#1560001): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Trusses and revised assemblies | MICHAELA | MICHAELA | | XBS | T | 6032086 |
HORIZON LLC OF SOUTH CAROLINA | XPS | P | 11/19/2018 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Plumbing: plumbing splice 11-19-18 | TCRIPPEN | TCRIPPEN | | XPS | P | 6028919 |
BIBLE ELECTRIC, INC. | XES | T | 10/01/2018 | PAID (REC#1552235): PLAN SPLICE FEE: $50 by: SHELBY for Electrical Revise one line and panel schedules. | SHELBY | SHELBY | | XES | T | 5982197 |
COLORADO STRUCTURES INC | XBS | T | 09/21/2018 | PAID (REC#1552236): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised roof pitch, wall height, architectural details and structural revisions | SHELLEY | SHELLEY | | XBS | T | 5972557 |