JAMES COMPANY ENTERPRISES, LTD. | B= | C | 03/25/2019 | All other required Final inspections are complete. (This is a computer generated result) | CHUCK | CHUCK | | B= | C | 6142679 |
JAMES COMPANY ENTERPRISES, LTD. | B= | P | 03/04/2019 | Bldg final re-inspection OK / All items completed. / 12" clearance for restroom only required with closer and latch (only latch present). / Accessible restroom signs posted in compliant locations. / Address posted on street side of building. / Bar and hangers at rear exit door removed. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982). | CHUCK | CHUCK | | B= | P | 6123193 |
JAMES COMPANY ENTERPRISES, LTD. | B= | R | 02/22/2019 | Bldg final inspection - interior remodel - change of occupancy - 2009 IEBC / Need address posted on street side of building / Accessible restroom tactile signs to be posted on the latch side of the door or as per 703.3.11 of the 2003 A117.1 / Maneuvering clearance at manual swinging door at Women's Restroom for hinge approach, push side shall be a min. of 12" as per detail (e) in Figure 404.2.3.1 of the 2003 A117.1 / Rear egress exit door shall not provide use of a steel barricade to secure the door. Approved locks and latches are required per IBC 1008.1.9.3. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982). | CHUCK | CHUCK | | B= | R | 6114232 |
JAMES COMPANY ENTERPRISES, LTD. | BLA | C | 10/15/2018 | | NATHAN | NATHAN | | BLA | C | 5994493 |
JAMES COMPANY ENTERPRISES, LTD. | BSP | P | 08/16/2018 | inspection of drywall attachment not needed unless the wall is being used for sheer or part of a listed assembly. | NATHAN | NATHAN | | BSP | P | 5935976 |
JAMES COMPANY ENTERPRISES, LTD. | BIN | C | 08/03/2018 | | NATHAN | NATHAN | | BIN | C | 5923197 |
JAMES COMPANY ENTERPRISES, LTD. | BFR | C | 08/02/2018 | items corrected | NATHAN | NATHAN | | BFR | C | 5921717 |
JAMES COMPANY ENTERPRISES, LTD. | BFR | P | 08/01/2018 | THIS IS A 2009 IEBC PERMIT, address headroom 7'4" finished by final, restroom backing, complete roof repair for RTU 2-2x12 sistered rafter does not count, Reviewed Accessible Elements / Plans reviewed electronically / reviewed doors and hardware. | NATHAN | NATHAN | | BFR | P | 5920553 |
LENZ ELECTRIC, INC. | E= | C | 01/08/2019 | grid eyelets installed / all else okay | CHIPO | CHIPO | | E= | C | 6071848 |
LENZ ELECTRIC, INC. | ES | C | 01/08/2019 | Commercial Service: 200 Amp 3 wire service--no action needed / feeders match plans and neutral from weather head changed out. | CHIPO | CHIPO | | ES | C | 6071836 |
LENZ ELECTRIC, INC. | ES | P | 12/28/2018 | Commercial Service: PRE RELEASE ONLY | BRIAN | BRIAN | | ES | P | 6064406 |
LENZ ELECTRIC, INC. | ES | R | 12/12/2018 | Commercial Service: needs to match the plans --have 4/0- 4/0- 2/0 al installed up to main plans show 3/0 cu ---label panel---complete reinspect | BRIAN | BRIAN | | ES | R | 6050749 |
LENZ ELECTRIC, INC. | E= | R | 12/12/2018 | need to remove all the ceiling tile for ceiling insp----strap the light up with grid wires with grid eyelets not screws---complete reinspect | BRIAN | BRIAN | | E= | R | 6050743 |
LENZ ELECTRIC, INC. | ER | P | 07/30/2018 | walls only | GARYL | GARYL | | ER | P | 5917377 |
LENZ ELECTRIC, INC. | ES | P | 07/19/2018 | Commercial Service: PRE RELEASE OK / | MIGUEL | MIGUEL | | ES | P | 5907471 |
ANYTHING HVAC, LLC. | H= | C | 01/07/2019 | TAB REPORT RECEIVED AND THERMOSTAT IS COMPLETE | JERRYF | JERRYF | | H= | C | 6069626 |
ANYTHING HVAC, LLC. | H= | P | 12/20/2018 | AFTER CONSULT WITH SENIOR INSPECTOR RTU WILL NEED TO BE CLAIMED ON PERMIT - NEED THERMOSTAT AND TAB REPORT | JERRYF | JERRYF | | H= | P | 6058718 |
ANYTHING HVAC, LLC. | H= | P | 12/19/2018 | NEED FURTHER RESEARCH ON EXISTING RTU MORE NOTES TO FOLLOW ON 12/20 - NEED THE FOLLOWING TO COMPLETE FINAL - TAB REPORT - PICTURE OF THERMOSTAT PER ADA REQUIREMENT OR INSTALL LOCK BOX | JERRYF | JERRYF | | H= | P | 6058105 |
ANYTHING HVAC, LLC. | HSP | P | 07/16/2018 | BY FINAL ADD RTU TO PERMIT REST OF HVAC IS OK AT THIS TIME. | JERRYF | JERRYF | | HSP | P | 5902989 |
ANYTHING HVAC, LLC. | HD | P | 07/13/2018 | NEED CONSULT WITH SENIOR INSPECTOR ON RTU LOCATION MAY NEED SAFETY RAILING INSTALLED ABOVE CEILING SA - RA MAINS OK - AT FINAL CONFIRM THERMO PAN HAS BEEN REPLACED WITH METAL AT MAIN RETURN GRILLE | JERRYF | JERRYF | | HD | P | 5902507 |
BM PLUMBING INC | P= | C | 02/13/2019 | Corrections made, received engineer letter for pex and water heater. | DANR | DANR | | P= | C | 6105957 |
BM PLUMBING INC | P= | P | 01/09/2019 | women's toilet needs to flush to open side - caulk lavs - support water new water lines to mop sink - need break room sink installed - need flooring installed to check drinking fountain knee clearance - need engineer approval for pex and 40 gallon electric water heater (drawing shows 20 gallon), rest ok. | DANR | DANR | | P= | P | 6072803 |
BM PLUMBING INC | PTO | C | 07/16/2018 | Correction made. | DANR | DANR | | PTO | C | 5903199 |
BM PLUMBING INC | PTO | P | 07/13/2018 | Need proper drainage fitting drinking fountain. | DANR | DANR | | PTO | P | 5901626 |
BM PLUMBING INC | PTO | P | 07/12/2018 | Drinking fountain s-trapped, need engineer letter approving pex piping, rest ok. Note: by final support mop sink water lines, check water heater at final. | DANR | DANR | | PTO | P | 5901276 |
BM PLUMBING INC | PB | C | 07/11/2018 | Ok, | DANR | DANR | | PB | C | 5898821 |