PEAK PROFESSIONAL CONTRS INC | B= | C | 06/14/2019 | | NICK | NICK | | B= | C | 6231028 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 04/16/2019 | Building final OK pending all other finals complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 6167736 |
PEAK PROFESSIONAL CONTRS INC | BFN | C | 04/12/2019 | Compaction results on file with Eng stamp | NICK | NICK | | BFN | C | 6163441 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 04/09/2019 | Still need to install guard rail at south exit landing where fall over 30" / Need stamped copy of compaction results / All other items completed -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 6160655 |
PEAK PROFESSIONAL CONTRS INC | BFT | P | 04/09/2019 | Need compaction results to have Eng stamp, please re upload compaction results with Eng stamp | NICK | NICK | | BFT | P | 6159623 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 04/04/2019 | Still need compaction report for new strip footings / Need to install hand rails for all exterior stairs / Need to install guard at south exit landing where fall over 30" / Need to install cover over plumbing for restrooms on west side main level / All other aspects of final OK / Need all other finals complete -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Mechanical Final Inspection is not Completed yet, LANDMARK PLUMBING & HEATING, INC. Plumbing Final Inspection is not Completed yet. | NICK | NICK | | B= | P | 6154906 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 04/04/2019 | 2nd layer rock for under stair storage OK / All penetrations OK through rated wall | NICK | NICK | | BFR | P | 6154905 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 03/15/2019 | 1st layer of 5/8 type X for lid of mechanical room per approved plans OK, still need to inspect 2nd layer 5/8 type X rock for lid / All fir framing at elevators OK for 1st and 2nd floors / Dropped lids at elevators OK / Rock for P 1.13 wall per U379 OK at mechanical closet / Need to inspect penetrations at this wall | NICK | NICK | | BFR | P | 6134274 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 02/27/2019 | All dropped lid framing for upper level OK | NICK | NICK | | BFR | P | 6119248 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 02/19/2019 | All dropped ceiling framing for main level OK except at elevator / Reviewed splice with contractor for new rated ceiling listing at exterior mechanical closet | NICK | NICK | | BFR | P | 6110878 |
PEAK PROFESSIONAL CONTRS INC | BIN | C | 01/22/2019 | All insulation OK for lower and upper level / Reviewed rated assemblies with contractor | NICK | NICK | | BIN | C | 6085128 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 01/16/2019 | Eng letter on file for framing items / Frame OK pending all MEP's complete | NICK | NICK | | BFR | P | 6079451 |
PEAK PROFESSIONAL CONTRS INC | BIN | P | 01/15/2019 | 1st floor insulation inspection / Missing insulation in woman's restroom south side / All other exterior walls on 1st floor OK / All exterior rigid R-5 OK | NICK | NICK | | BIN | P | 6079118 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 01/11/2019 | still need clarification on S1.02 note 6 and header frame at 1st floor north not on plan, remaining items corrected as inspected | NATHAN | NATHAN | | BFR | P | 6076431 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 01/09/2019 | bottom level frame with completed required inspections, reviewed accessible elements on bottom level, address note 6 S1.02 plywood and header in wall not on plan, strap top plates at plate breaks and ends of walls where needed, north wall under moment frame missing nuts and washers, NW wall missing foundation bolts. | NATHAN | NATHAN | | BFR | P | 6073947 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 12/12/2018 | All shear walls OK per approved plans | NICK | NICK | | BSP | P | 6051193 |
PEAK PROFESSIONAL CONTRS INC | BSP | P | 12/05/2018 | Shear inspection / Need to install 8d nails at 3" oc for north exterior wall per approved plans / Need to install 8d nails at 4" oc for west exterior wall / All interior shear walls OK / All hold downs OK per approved plans / South exterior wall OK | NICK | NICK | | BSP | P | 6044031 |
PEAK PROFESSIONAL CONTRS INC | BBB | C | 10/03/2018 | Top of wall bond beam OK per approved design | NICK | NICK | | BBB | C | 5985044 |
PEAK PROFESSIONAL CONTRS INC | BFN | P | 10/02/2018 | All foundation walls OK per previous inspection / Need compaction results for new interior strip footings and pads | NICK | NICK | | BFN | P | 5983276 |
PEAK PROFESSIONAL CONTRS INC | BFT | C | 10/02/2018 | All interior pads and strip footings OK per approved design | NICK | NICK | | BFT | C | 5983267 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 09/26/2018 | Top of wall bond beam OK with 2 #5 bars | NICK | NICK | | BBB | P | 5977668 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 09/21/2018 | 2 #5 bars per detail 8/S2.01 OK for bond beam | NICK | NICK | | BBB | P | 5973417 |
PEAK PROFESSIONAL CONTRS INC | BFI | P | 09/19/2018 | All rigid insulation for foundation walls OK | NICK | NICK | | BFI | P | 5970415 |
PEAK PROFESSIONAL CONTRS INC | BFN | P | 09/14/2018 | All exterior foundation reinforcement OK per design / 2nd half of open hole report on file / Still need to inspect all interior strip footings and pads once installed | NICK | NICK | | BFN | P | 5965364 |
PEAK PROFESSIONAL CONTRS INC | BFN | P | 09/07/2018 | All exterior footings OK per design / Need 2nd half of open hole report for 2nd half of footing / Still need to inspect all interior pads and strip footings | NICK | NICK | | BFN | P | 5958825 |
PEAK PROFESSIONAL CONTRS INC | BBB | P | 08/28/2018 | 2 #5 bars per detail 15/S1.02 and 16/S1.02 OK for elevator shaft CMU walls | NICK | NICK | | BBB | P | 5948521 |
PEAK PROFESSIONAL CONTRS INC | BFT | P | 08/23/2018 | Partial Open hole on file / Eng on file for use of #4 bar in footing | NICK | NICK | | BFT | P | 5943151 |
PEAK PROFESSIONAL CONTRS INC | BFI | P | 08/21/2018 | Rigid insulation at pored sections foundation OK | NICK | NICK | | BFI | P | 5941607 |
PEAK PROFESSIONAL CONTRS INC | BFN | P | 08/13/2018 | Foundation reinforcement OK per design for areas specified in footing inspection / Still need open hole report | NICK | NICK | | BFN | P | 5932586 |
PEAK PROFESSIONAL CONTRS INC | BFT | P | 08/01/2018 | Need open hole report / Partial footing inspection / All north and east wall footings OK per design / Footing for elevator shaft OK at south side of building up to grid line 5 / Still need to inspect all other footings and interior pads / Poor at own risk / Trusses pending | NICK | NICK | | BFT | P | 5921126 |
SYSTEMS ELECTRIC, INC. | E= | C | 06/05/2019 | corrections made / | MIGUEL | MIGUEL | | E= | C | 6220996 |
SYSTEMS ELECTRIC, INC. | E= | C | 06/03/2019 | FIRE ALARM INSPECTION: FA complete / | MIGUEL | MIGUEL | | E= | C | 6217329 |
SYSTEMS ELECTRIC, INC. | E= | C | 06/03/2019 | FIRE ALARM INSPECTION: FA complete / | MIGUEL | MIGUEL | | E= | C | 6217327 |
SYSTEMS ELECTRIC, INC. | ER | C | 06/03/2019 | FIRE ALARM INSPECTION: FA complete / | MIGUEL | MIGUEL | | ER | C | 6217326 |
SYSTEMS ELECTRIC, INC. | E= | P | 04/30/2019 | need labels on panel / bond metal skin on building / verify intersystem bond / loose sealtight at walkway gate / add ground rod at power pedestal / need to have elevator tech available to access elevator to verify disconnecting means and ampacity requirements for motor / | MIGUEL | MIGUEL | | E= | P | 6182942 |
SYSTEMS ELECTRIC, INC. | EUG | C | 04/22/2019 | rest of underground ok / | MIGUEL | MIGUEL | | EUG | C | 6173690 |
SYSTEMS ELECTRIC, INC. | EUG | P | 04/17/2019 | pvc for walk way lights and power pedestal / lack last 10' at power pedestal / | MIGUEL | MIGUEL | | EUG | P | 6168859 |
SYSTEMS ELECTRIC, INC. | E= | C | 04/02/2019 | FIRE ALARM INSPECTION: FA ok / | MIGUEL | MIGUEL | | E= | C | 6152214 |
SYSTEMS ELECTRIC, INC. | E= | P | 04/02/2019 | still need to inspect donor room and deck / work room / condensers and split unit / exterior restrooms / elevator / install breaker locks on hand dryers / install panel labels / need proper working clearance in front of panels / power pedestal / Lance 726-0434 | MIGUEL | MIGUEL | | E= | P | 6152190 |
SYSTEMS ELECTRIC, INC. | ER | C | 03/18/2019 | elevator lobbies and FA ok / | MIGUEL | MIGUEL | | ER | C | 6135661 |
SYSTEMS ELECTRIC, INC. | ER | P | 02/27/2019 | FIRE ALARM INSPECTION: lack elevator lobbys / | MIGUEL | MIGUEL | | ER | P | 6119075 |
SYSTEMS ELECTRIC, INC. | ER | P | 02/27/2019 | will need access for boxes in 1st floor restrooms,check on next inspection / still need ceilings in elevators lobbys and hall / FA ok / | MIGUEL | MIGUEL | | ER | P | 6119063 |
SYSTEMS ELECTRIC, INC. | ER | P | 02/19/2019 | 1st floor lids-102-107, 109, 111, hallway w/ exception of elevator lobby / verify placement of register for box access in 107, 111 / 207 lid ok / need to attach fire alarm permit before next inspection request / FA ok in same areas before mentioned / | MIGUEL | MIGUEL | | ER | P | 6110533 |
SYSTEMS ELECTRIC, INC. | ER | P | 01/11/2019 | 2nd floor walls ok / | MIGUEL | MIGUEL | | ER | P | 6076417 |
SYSTEMS ELECTRIC, INC. | ER | P | 12/26/2018 | 1st floor walls ok / | MIGUEL | MIGUEL | | ER | P | 6062923 |
SYSTEMS ELECTRIC, INC. | ES | C | 12/07/2018 | Commercial Service: NEW 600A 4w service ok to set CTs and meter----RBD note 400A ED up to main only / | MIGUEL | MIGUEL | | ES | C | 6046636 |
SYSTEMS ELECTRIC, INC. | ES | P | 11/19/2018 | Commercial Service: pre release only ---temp to power the sky jack for the weekend---- | BRIAN | BRIAN | | ES | P | 6030015 |
SYSTEMS ELECTRIC, INC. | ESL | C | 10/18/2018 | in slab ok / | MIGUEL | MIGUEL | | ESL | C | 5999466 |
SYSTEMS ELECTRIC, INC. | EUG | P | 10/18/2018 | waiting on feeders south of structure, rest ok | MIGUEL | MIGUEL | | EUG | P | 5999465 |
AIRTECH MECHANICAL, INC. | H= | C | 04/22/2019 | PATIO HEATER IS KMI 20 ALL OK | JERRYF | JERRYF | | H= | C | 6173418 |
AIRTECH MECHANICAL, INC. | H= | P | 04/17/2019 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | P | 6167927 |
AIRTECH MECHANICAL, INC. | H= | P | 04/15/2019 | THIS INSPECTION WAS FOR RADIANT HEATER ONLY - UNIT IS STILL TO HIGH SEE PAGE 10 CIRCLED NOTE OF INSTALL MANUAL | JERRYF | JERRYF | | H= | P | 6165960 |
LANDMARK PLUMBING AND HEATING, INC. | H= | C | 04/15/2019 | THIS CONTRACTORS SCOPE OF WORK IS COMPLETE | JERRYF | JERRYF | | H= | C | 6165959 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | C | 04/03/2019 | ELEVATOR COMPLETE | ERIC | ERIC | | HE= | C | 6154572 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 04/02/2019 | PATIO HEATER REQUIRES 24" CLEARANCE TO TOP OF UNIT / CIRCLED ON PAGE 10 OF INSTALL MANUAL NOTES: 2 GAS STUBS ARE FOR FUTURE PATIO HEATERS AT WEST PATIO - ALL OTHER CONNECTIONS ARE COMPLETE | JERRYF | JERRYF | | H= | P | 6151972 |
AIRTECH MECHANICAL, INC. | HRP | P | 03/27/2019 | 3 PRESSURE TEST OK | JERRYF | JERRYF | | HRP | P | 6145704 |
AIRTECH MECHANICAL, INC. | HRP | P | 03/25/2019 | QUESTION THE FOLLOWING - SERVICE ACCESS TO DISCONNECTS AND 175# TEST ON 1 LINE - 2 OTHER TESTS SHOW OVER 300# | JERRYF | JERRYF | | HRP | P | 6142816 |
AIRTECH MECHANICAL, INC. | HV | C | 03/07/2019 | FURNACE VENTS OK - AT FINAL VERIFY DRAINS | JERRYF | JERRYF | | HV | C | 6126441 |
AIRTECH MECHANICAL, INC. | HD | P | 03/06/2019 | NEED DUCT ACCESS DOORS AT LOWER FURNACE | JERRYF | JERRYF | | HD | P | 6125247 |
AIRTECH MECHANICAL, INC. | HV | P | 03/06/2019 | NEED APPROVED PLAN REVISION FOR NEW LOCATIONS OF FURNACE EXHAUSTS - NEED EXHAUST COMPLETED AT LOWER FURNACE AND INSPECTION CALLED | JERRYF | JERRYF | | HV | P | 6125239 |
AIRTECH MECHANICAL, INC. | HD | P | 03/01/2019 | ABOVE CEILING SA AND EXHAUST MAINS AND RUN OUTS IN WEST RESTROOMS OK | JERRYF | JERRYF | | HD | P | 6121070 |
AIRTECH MECHANICAL, INC. | HD | P | 02/19/2019 | NEED BREAKAWAY CONNECTION CORRECTED - CONTRACTOR TO SUPPLY PICTURES OF CORRECTIONS AT NEXT INSPECTION NOTES: DAMPER INSTALL OK | JERRYF | JERRYF | | HD | P | 6110741 |
AIRTECH MECHANICAL, INC. | HD | P | 02/07/2019 | 2 DAMPER OPENINGS OK | JERRYF | JERRYF | | HD | P | 6100713 |
AIRTECH MECHANICAL, INC. | HD | R | 02/06/2019 | NEED BOTH SIDES OF OPENINGS FIRE TAPED | JERRYF | JERRYF | | HD | R | 6099400 |
LANDMARK PLUMBING AND HEATING, INC. | HC | C | 02/04/2019 | RELEASE METER | JERRYF | JERRYF | | HC | C | 6096571 |
LANDMARK PLUMBING AND HEATING, INC. | HI | C | 02/04/2019 | AT FUTURE INSPECTION VERIFY ALL FINAL CONNECTIONS - NEED PLAN REVISED PER PREVIOUS NOTES | JERRYF | JERRYF | | HI | C | 6096541 |
LANDMARK PLUMBING AND HEATING, INC. | HI | P | 02/01/2019 | COUNTER STRIKE PIPING TO PATIO OK / CONTRACTOR WILL SUPPLY PICTURES OF SUPPORT AND PRESSURE TEST AT NEXT INSPECTION - NEED PLAN REVISED SHOWING COUNTER STRIKE WHERE PLAN CALLS FOR MEATL PIPE | JERRYF | JERRYF | | HI | P | 6094612 |
AIRTECH MECHANICAL, INC. | HD | P | 01/25/2019 | NEED DAMPERS REMOVED TO VERIFY FIRE TAPE INSIDE HOLES AND RECALL INSPECTION / LEAVE DAMPERS OUT UNTIL AFTER INSPECTION | JERRYF | JERRYF | | HD | P | 6088158 |
LANDMARK PLUMBING AND HEATING, INC. | HI | P | 01/25/2019 | NEED PRESSURE TEST INSPECTION FOR 3/4" COUNTER STRIKE IN WALL AND ABOVE CEILING AT PATIO - PIPING OK AT THIS TIME PENDING PRESSURE TEST - NEED PLAN REVISED SHOWING COUNTER STRIKE WHERE RIGID PIPE IS SHOWN ON PLAN | JERRYF | JERRYF | | HI | P | 6088153 |
AIRTECH MECHANICAL, INC. | HV | P | 01/24/2019 | THIS INSPECTION WAS FOR 2ND FLOOR FURNACE VENT - INSTALL MANUAL DOES NOT WALL TERMINATION STYLE / MANUAL SHOWS AS USING CONCENTRIC CONE STYLE??? - NEED LETTER FROM MANUFACTURE SHOWING THIS STYLE OF TERMINATION IS APPROVED | JERRYF | JERRYF | | HV | P | 6087146 |
AIRTECH MECHANICAL, INC. | HD | P | 01/16/2019 | OK TO SEND PICTURES OF SHEET ROCK LINING DAMPER OPENINGS, ATTACH TO INSPECTION REQUEST. | NANCY | NANCY | | HD | P | 6079488 |
AIRTECH MECHANICAL, INC. | HD | P | 01/11/2019 | ABOVE CEILING SA / RA MAINS AND RUN OUTS OK - STILL NEED EXHAUST COMPETED AT 2ND FLOOR AND MAIN ROOM 111 - FIRE DAMPER FRAMING OK STILL NEED TO SHEET ROCK LINING IN DAMPER HOLES BEFORE DAMPER INSTALL - NEED TO VERIFY ALL PLASTIC PIPING INCLUDING PLUMBING / WATER HEATER AND FURNACE FLUES ARE PROTECTED TO 25 / 50 FLAME SPREAD - NEED PLAN REVISIONS FOR ALL DUCT WORK CHANGES | JERRYF | JERRYF | | HD | P | 6075992 |
LANDMARK PLUMBING AND HEATING, INC. | HO | P | 01/10/2019 | CHANGED INSPECTION TO HO - UNDER GROUND MAIN LINE OK TO BURY - 1" WITH TRACER | JERRYF | JERRYF | | HO | P | 6074749 |
LANDMARK PLUMBING AND HEATING, INC. | HI | P | 12/28/2018 | PRESSURE TEST OK AND PIPING OK ON 1ST FLOOR ONLY - STILL NEED 2ND FLOOR - NEED PLAN REVISED SHOWING NEW LOCATION OF LINE AT EXTERIOR | JERRYF | JERRYF | | HI | P | 6064552 |
LANDMARK PLUMBING AND HEATING, INC. | HO | P | 10/02/2018 | 3/4" PE WITH TRACER OK TO BURY UNDER ROAD - STILL CONTINUATION TO BUILDING | JERRYF | JERRYF | | HO | P | 5983383 |
LANDMARK PLUMBING AND HEATING, INC. | P= | C | 04/10/2019 | letter for aav received in images | JOSEPHD | JOSEPHD | | P= | C | 6160919 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 04/05/2019 | still need engineer letter for aav @ P4 sink, rest ok | JOSEPHD | JOSEPHD | | P= | P | 6156538 |
LANDMARK PLUMBING AND HEATING, INC. | P= | P | 04/02/2019 | need to see lavs in mens bathroom 1st floor, need breakroom sink 1st and 2nd floor set, check RP drain, rest ok | JOSEPHD | JOSEPHD | | P= | P | 6152627 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | C | 01/11/2019 | shower valve relocated to correct position | JOSEPHD | JOSEPHD | | PTO | C | 6075698 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 01/09/2019 | need to splice accessible shower to plans, accessible shower lacking accessible requirements, rest ok, test on elevator sump pipe ok | JOSEPHD | JOSEPHD | | PTO | P | 6072841 |
LANDMARK PLUMBING AND HEATING, INC. | PTO | P | 12/28/2018 | **please add (1) water htr to scope of work, **need engineers letter allowing aav in lieu of vtr @ P4 sink, **need to revise plans to show added accessible shwr @ upr level bath, rest ok for test / design for dwv and water MINUS (2) WALL HYDRANTS, (1) WOMENS WATER CLOSET, ADDED ACCESSIBLE SHWR @ UPR LEVEL BATH, AND ELEVATOR PIT PIPING. NOTE: aav @ P4 (upr level sink), vtr (1 4" @ east side), check water entry and water htr @ final | JOHNS | JOHNS | | PTO | P | 6064459 |
LANDMARK PLUMBING AND HEATING, INC. | PB | C | 10/17/2018 | corrections made | JOHNS | JOHNS | | PB | C | 5996910 |
LANDMARK PLUMBING AND HEATING, INC. | PB | P | 10/16/2018 | hydrolic jump @ south bath, missing washing machine drain, rest ok for test / design. NOTE: water stubbed into water entrty | JOHNS | JOHNS | | PB | P | 5995577 |
PEAK PROFESSIONAL CONTRS INC | XBS | T | 04/30/2019 | PAID (REC#1594491) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised exiting from second story | SHELLEY | SHELLEY | | XBS | T | 6182473 |
SYSTEMS ELECTRIC, INC. | XES | T | 02/20/2019 | PAID (REC#1577582) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised lighting and power - first floor. | BERTHA | BERTHA | | XES | T | 6112326 |
PEAK PROFESSIONAL CONTRS INC | XBS | T | 01/29/2019 | PAID (REC#1572695) PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: Revised detail for ceiling assembly. | BPHILLIPS | BPHILLIPS | | XBS | T | 6091414 |
PEAK PROFESSIONAL CONTRS INC | XBS | T | 01/09/2019 | PAID (REC#1568303) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised floor plan | SHELLEY | SHELLEY | | XBS | T | 6073059 |
LANDMARK PLUMBING AND HEATING, INC. | XMS | P | 12/20/2018 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised exhaust fan CFM | JUSTINC | JUSTINC | | XMS | P | 6059842 |
LANDMARK PLUMBING AND HEATING, INC. | XPS | P | 12/20/2018 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Plumbing splice 12/20/18 Delta 5 revisions | SHANEN | SHANEN | | XPS | P | 6059787 |
PEAK PROFESSIONAL CONTRS INC | XBS | T | 10/01/2018 | PAID (REC#1543142) PLAN SPLICE FEE: $50 by: LBENNETT for Construction: trusses | LBENNETT | LBENNETT | | XBS | T | 5982135 |