RAINE BUILDING LLC. | B= | C | 11/12/2018 | All other required Final inspections are complete. (This is a computer generated result) | CHUCK | CHUCK | | B= | C | 6022701 |
RAINE BUILDING LLC. | B= | P | 10/18/2018 | Bldg final - Greiner Electric sub-permit has not been completed yet. The building permit will automatically complete once the sub-permit has been completed. Additional Inspections Required (computer generated): GREINER ELECTRIC, LLC. Electrical Final Inspection is not Completed yet. | CHUCK | CHUCK | | B= | P | 5998138 |
RAINE BUILDING LLC. | B= | P | 08/22/2018 | Complete pending other Finals / training with Chuck - accessible elements, scope of work limitations & egress requirements. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), GREINER ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, JOHNSON BROTHERS PLUMBING & HEATING Mechanical Final Inspection is not Completed yet, JOHNSON BROTHERS PLUMBING & HEATING Plumbing Final Inspection is not Completed yet, SPECIAL SYSTEMS DESIGN,LLC Electrical Final Inspection is not Completed yet. | RICHB | RICHB | | B= | P | 5941940 |
RAINE BUILDING LLC. | BFR | P | 07/03/2018 | with completed required inspections frame okay, Reviewed Accessible Elements / | NATHAN | NATHAN | | BFR | P | 5892237 |
GREINER ELECTRIC, LLC. | E= | C | 11/12/2018 | training room okay / splice provided for 14 new circuits | CHIPO | CHIPO | | E= | C | 6022700 |
GREINER ELECTRIC, LLC. | ER | C | 11/12/2018 | | CHIPO | CHIPO | | ER | C | 6022699 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 08/22/2018 | FIRE ALARM INSPECTION: FA ok / | MIGUEL | MIGUEL | | E= | C | 5943036 |
GREINER ELECTRIC, LLC. | E= | P | 08/22/2018 | pending addition of 14 new circuits to training room and splice to plans indicating such / | MIGUEL | MIGUEL | | E= | P | 5943035 |
SPECIAL SYSTEMS DESIGN,LLC | E= | P | 08/20/2018 | FIRE ALARM INSPECTION: FA pending offices 122,123 / | MIGUEL | MIGUEL | | E= | P | 5939110 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 08/20/2018 | FIRE ALARM INSPECTION: FA rough ok pending offices 122, 123 / | MIGUEL | MIGUEL | | ER | P | 5939106 |
GREINER ELECTRIC, LLC. | ER | P | 08/17/2018 | ceilings marked on plans / | MIGUEL | MIGUEL | | ER | P | 5937379 |
GREINER ELECTRIC, LLC. | ER | P | 08/14/2018 | ceilings marked in purple on plans / | MIGUEL | MIGUEL | | ER | P | 5934196 |
GREINER ELECTRIC, LLC. | ER | P | 07/19/2018 | walls for training room and unisex bathroom ok. Also checked frog eye marked on plans in purple. Discussed accessibility device heights with contractor. | DEAN | DEAN | | ER | P | 5907329 |
GREINER ELECTRIC, LLC. | ER | P | 07/12/2018 | walls marked in orange on plans ok---no floor boxes installed yet / | MIGUEL | MIGUEL | | ER | P | 5901371 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | C | 08/29/2018 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 5948930 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | P | 08/16/2018 | PARTIAL PENDING TAB REPORT - ALL SA / RA GRILLES AND EXHAUST FAN ARE COMPLETE | JERRYF | JERRYF | | H= | P | 5936722 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | P | 07/10/2018 | AT FUTURE INSPECTION VERIFY ALL PVC ABOVE RESTROOM HAS BEEN PROTECTED TO 25/50 - ALL SA MAINS AND RUN OUTS ARE OK | JERRYF | JERRYF | | HD | P | 5898169 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | P= | C | 08/23/2018 | Correction made, image from contractor uploaded. | DANR | DANR | | P= | C | 5943107 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | P= | P | 08/22/2018 | Toilet handle needs to be on open side of room (picture ok), rest ok. | DANR | DANR | | P= | P | 5941936 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | P= | P | 08/21/2018 | Not ready, re-inspect all. | DANR | DANR | | P= | P | 5940299 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | C | 08/14/2018 | OK. Note: At final check copper pipes by water heater and 4" cast in ceiling for wrap (touching steel pipe), - add hanger ceiling 2" and 4" drain line, - check 4" drain connection. | DANR | DANR | | PTO | C | 5933147 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | P | 07/17/2018 | Need shower and valve installed, need under floor piping inspection, rest ok for dwv and domestic water in wall and over head ok. Note: check water heater at final. | DANR | DANR | | PTO | P | 5904567 |
GREINER ELECTRIC, LLC. | XES | T | 10/26/2018 | PAID (REC#1551257) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: As - built drawings. | BERTHA | BERTHA | | XES | T | 6007241 |
RAINE BUILDING LLC. | XBS | T | 08/22/2018 | PAID (REC#1529550) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised storage areas to office | SHELLEY | SHELLEY | | XBS | T | 5941893 |