COLORADO STRUCTURES INC | B= | C | 11/27/2019 | north tower units and exterior and corrections from previous inspection OK / final OK pending other finals | DANE | DANE | | B= | C | 6411684 |
COLORADO STRUCTURES INC | B= | R | 11/15/2019 | south tower and garages only / need rated breezeway door at garage 5 / need rated entry doors at units 301 and 302 / unit 104 - grab bars have been installed in the type a unit and are not installed in the correct positions at the rear or side bars. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), HORIZON, LLC Plumbing Final Inspection is not Completed yet. | DANE | DANE | | B= | R | 6401169 |
COLORADO STRUCTURES INC | BSP | P | 11/08/2019 | fire caulking inside soffit and soffit framing around pipe in 2nd from north garage OK / EJ and design received for fire stopping of pipe | DANE | DANE | | BSP | P | 6393687 |
COLORADO STRUCTURES INC | BSP | P | 08/16/2019 | Drywall and attachment at 1st floor units OK -- Still need to check penetrations in garages per previous inspection comment | DAKOTAB | DAKOTAB | | BSP | P | 6304012 |
COLORADO STRUCTURES INC | BSP | P | 08/14/2019 | drywall and attachments at rated assemblies in garages OK - still need to check all penetrations at rated assemblies when penetrations are ready / still need to inspect 1st floor dwelling units | DANE | DANE | | BSP | P | 6300805 |
COLORADO STRUCTURES INC | BSP | P | 08/13/2019 | level 2 rock and attachments at both towers at rated assemblies OK | DANE | DANE | | BSP | P | 6298436 |
COLORADO STRUCTURES INC | BIN | P | 08/07/2019 | 1st floor garages and units in both towers / RC and thermal insulation OK at all garages and 1st floor units and overhangs at cantilevers over garages / rock and fire caulking OK at under side of floor drains at 2nd floor water heater closets / this completes the RC inspections for this building | DANE | DANE | | BIN | P | 6292383 |
COLORADO STRUCTURES INC | BSP | P | 08/07/2019 | above ceiling penetrations and drop ceiling framing OK at 3rd floor fan coils and 1st floor fan coils in both towers and drop in south 1st floor breezeway / this completes the above ceiling inspections for this building | DANE | DANE | | BSP | P | 6292374 |
COLORADO STRUCTURES INC | BIN | P | 08/06/2019 | RC at 2nd floor ceilings OK at all units in both towers / drop ceiling framing, fire taping and all above ceiling penetrations OK at all prerock ceilings at bathrooms with fan coils on than in both towers units on the 2nd floor / thermal insulation OK at all 2nd floor units at both towers | DANE | DANE | | BIN | P | 6290295 |
COLORADO STRUCTURES INC | BSP | P | 08/02/2019 | Rock and attachments at rated assemblies OK at all units at both towers of 3rd floor | DANE | DANE | | BSP | P | 6287310 |
COLORADO STRUCTURES INC | BFR | P | 08/02/2019 | level 2 frame reinspection / all items from previous inspection corrected / truss fixes for F36 and F52 received | DANE | DANE | | BFR | P | 6287299 |
COLORADO STRUCTURES INC | BFR | P | 08/01/2019 | frame reinspection at 2nd and 1st floors at both towers / 201 - still need fix for F52 - fix not done per design not taken / 203 - still need fix for F36 that is not done per eng fix that was not taken / 208 - engineer letter for lack of bearing received but fix not done per engineering - need 2x4 to extend from girder in laundry to flooring below with 28 10D nails to post / all other items at both levels corrected / truss fixes received for F58 F57 F55 F55 F36 F33 F18 F12 F18 F62 FB12 FB10 and FB08 // Training with Justin L | DANE | DANE | | BFR | P | 6285924 |
COLORADO STRUCTURES INC | BSP | P | 08/01/2019 | Training with PPRBD inspector Dane S on fire barriers - Fire partitions - membrane penetrations - Pre rock - Types of construction ( difference between 5A and 5B construction ) - Occupancy type ( R2 ) - Code interpretation and application | JUSTINL | JUSTINL | | BSP | P | 6285876 |
COLORADO STRUCTURES INC | BSP | P | 07/31/2019 | FIRETAPE INSPECTION AT PRE-ROCK -- BOTH TOWERS -- ALL FLOORS -- All fire tape at all pre-rock at plumbing walls OK
RATED ASSEMBLY ATTACHMENT -- BREEZEWAYS -- 3RD FLOOR -- All rated assembly attachment at 3rd floor breezeways OK | DAKOTAB | DAKOTAB | | BSP | P | 6284030 |
COLORADO STRUCTURES INC | BSP | P | 07/29/2019 | level 2 and level 3 prerock at unit separation walls and bathroom ceilings OK at all units except at tubs that back up to unit separation walls where no screws have been installed behind the tubs / discussed OK to fire tape all other areas and can check fire tape after above ceiling penetrations have been corrected after fan coils are installed | DANE | DANE | | BSP | P | 6280609 |
COLORADO STRUCTURES INC | BFR | P | 07/26/2019 | 1st floor frame -- 104 - Need to firecaulk penetrations at pre-rock -- Garage 5 - Need engineer letter to show repair on right side of truss for F08 -- Garage 10 - Need engineer repair for FB10 -- Engineer letter for truss repairs received for F08, F12A, F42, F48, and F51 -- Reviewed Accessible Elements | DAKOTAB | DAKOTAB | | BFR | P | 6279065 |
COLORADO STRUCTURES INC | BIN | P | 07/26/2019 | R/C and insulation on 3rd floor OK | DAKOTAB | DAKOTAB | | BIN | P | 6279047 |
COLORADO STRUCTURES INC | BSP | P | 07/25/2019 | ABOVE LID IN BATHROOM INSPECTION -- R/C AND DRYWALL SCREW INSPECTION -- 1ST FLOOR -- All R/C and drywall screws at above lid in bathrooms OK
PRE-ROCK AT PLUMBING WALLS -- Pre-rock at pllumbing walls in units 104 and 107 OK | DAKOTAB | DAKOTAB | | BSP | P | 6277324 |
COLORADO STRUCTURES INC | BSP | P | 07/24/2019 | RC at ceiling pre-rock areas at 2nd floor bathrooms OK pending other roughs at all 2nd floor units | DANE | DANE | | BSP | P | 6275942 |
COLORADO STRUCTURES INC | BFR | R | 07/24/2019 | frame 201 through 208 / need fix for cut F57 over pantry bearing wall - missing 1 king at entry door at 3 gang box - putty pad not installed correctly at 3 gang box - fix rock at fire barrier above pantry / 203 - need fix for 2 F55's over pantry - need fix for F52 over kitchen not done per engineering - need fix for F36 drilled at top and bottom over electric panel - need to fire ftop 2" PVC pipe and blank hole at bottom of plate in bearing wall - loose gussets at bottom plates of 2 F33's over south closet - missing strap at top plate by water heater closet / 204 - fix rock at fire barrier at scab truss / 205 - need fix for F12 over entry / 206 - rock at fire barrier is not continuous to OSB at inside or outside by entry door - replace cut stud at 3 gang box at interior bearing wall by hall - stud shoes not installed correctly at over bored stud by tub at sprinkler head - girder over laundry is not bearing enough at post by bathroom / 207 - fix hole in fire barrier at scab truss / rock not continuous to OSB at fire barrier at outside of entry door / truss fixes received for F18 F52 F12 F68 F67 and F12 | DANE | DANE | | BFR | R | 6275890 |
COLORADO STRUCTURES INC | BFR | P | 07/23/2019 | Engineer truss fixes for R61 and R84 in units 302 and 303 received, repairs OK | DAKOTAB | DAKOTAB | | BFR | P | 6273959 |
COLORADO STRUCTURES INC | BSP | P | 07/22/2019 | framing at prerock areas at bathroom ceilings and plumbing fur out walls at all 1st and 2nd floor units OK pending other roughs / floor truss repair received for F58 over unit 201 bathroom - repair OK | DANE | DANE | | BSP | P | 6272477 |
COLORADO STRUCTURES INC | BSP | P | 07/22/2019 | stamped letters for holes drilled in breeze way LVL's and for standard fixes for missing gussets | DANE | DANE | | BSP | P | 6271223 |
COLORADO STRUCTURES INC | BFR | P | 07/19/2019 | 3rd floor north tower reinspection of truss fixes / all fixes at north tower OK / truss fixes received for R92GE R85G R86G R102 and R102 / still need to inspect all items from inspection dated 7/18/19 for south tower in rooms 302 and 303 | DANE | DANE | | BFR | P | 6270811 |
COLORADO STRUCTURES INC | BFR | P | 07/18/2019 | 3RD FLOOR -- 302 - R84 calls for 2 rows of nails at gusset repair -- 303 - Damaged bottom cord at bearing location for R61 -- 305 - Missing gusset on R92GE-2 -- Other gusset repairs at R92GE-2 not done per engineering -- R86G missing 2nd row of nails -- R85G calls for 3 rows of nails at repair -- 306 - R102A nailing pattern not complete per engineering -- 308 - R102 nailing pattern not complete per engineering -- Engineer letter for truss repairs received for R65G, R67G, R49D, R92GE, R131G, and R116 | DAKOTAB | DAKOTAB | | BFR | P | 6269182 |
COLORADO STRUCTURES INC | BSP | P | 04/19/2019 | Drywall wrap at ledger in breezeways OK per splice | DAKOTAB | DAKOTAB | | BSP | P | 6172027 |
HORIZON LLC OF SOUTH CAROLINA | BSP | T | 04/04/2019 | PAID (REC#1591735): ADDITIONAL PLAN REVIEW TIME: $50 From: DALEH splice delta 1 | DALEH | DALEH | | BSP | T | 6155671 |
COLORADO STRUCTURES INC | BSP | P | 03/26/2019 | revised drywall wrap design for ledger on file | DANE | DANE | | BSP | P | 6144041 |
COLORADO STRUCTURES INC | BSP | P | 02/28/2019 | exterior side of breezeway fire barriers / need to remove drywall backing at roof truss plain need to be over the drywall / all other rock and attachments OK at exterior sides of breezeways | DANE | DANE | | BSP | P | 6120672 |
COLORADO STRUCTURES INC | BSP | R | 02/27/2019 | inspection site canceled - not ready per super and drywall contractor | DANE | DANE | | BSP | R | 6119501 |
COLORADO STRUCTURES INC | BSP | P | 01/07/2019 | exterior shear nailing and straps OK | DANE | DANE | | BSP | P | 6070607 |
COLORADO STRUCTURES INC | BSP | R | 01/07/2019 | duplicate request | DANE | DANE | | BSP | R | 6070597 |
COLORADO STRUCTURES INC | BFN | P | 11/13/2018 | Engineer letter for foundation on file -- Eufer noted -- Engineer letter for interior slab on file | DAKOTAB | DAKOTAB | | BFN | P | 6023405 |
COLORADO STRUCTURES INC | BFT | P | 11/13/2018 | Engineer letter for footing on file -- Open hole on file -- 2000 PSF | DAKOTAB | DAKOTAB | | BFT | P | 6023397 |
COLORADO STRUCTURES INC | BFT | P | 07/11/2018 | Authorized 3rd party engineer inspection with all observation paperwork-ufer letter,soils and open hole letter to be picked up by inspector @ BFI or BFD inspection | DANE | DANE | | BFT | P | 5898754 |
BIBLE ELECTRIC, INC. | E= | C | 11/01/2019 | | RANDY | RANDY | | E= | C | 6386169 |
BIBLE ELECTRIC, INC. | E= | P | 10/31/2019 | garages locked have lighting exterior lighting on , 107,108 ok | BRET | BRET | | E= | P | 6384647 |
COLORADO ELECTRICAL SYSTEMS, LLC | E= | C | 10/31/2019 | FIRE ALARM INSPECTION: | BRET | BRET | | E= | C | 6384639 |
BIBLE ELECTRIC, INC. | E= | P | 10/29/2019 | unit 103,104, 102 locked | RANDY | RANDY | | E= | P | 6382769 |
BIBLE ELECTRIC, INC. | E= | P | 10/23/2019 | 2nd fl units and corridor ok | RANDY | RANDY | | E= | P | 6377690 |
BIBLE ELECTRIC, INC. | E= | P | 10/21/2019 | 305, 306, 307,308 need lock out on breaker for HWH heater / 305,307 20/2 for CU's / 306, 308 25/2 for CU's / | ROB | ROB | | E= | P | 6375772 |
BIBLE ELECTRIC, INC. | E= | P | 10/18/2019 | 2nd fl units and corridor | RANDY | RANDY | | E= | P | 6373281 |
BIBLE ELECTRIC, INC. | E= | P | 10/17/2019 | 3rd fl units and corridor | RANDY | RANDY | | E= | P | 6371928 |
BIBLE ELECTRIC, INC. | ER | C | 08/07/2019 | bath lids and corridor ok | BRET | BRET | | ER | C | 6291576 |
BIBLE ELECTRIC, INC. | ER | P | 08/06/2019 | 301,302,303 bath drop ceilings | BRET | BRET | | ER | P | 6289703 |
BIBLE ELECTRIC, INC. | ES | C | 06/25/2019 | Commercial Service: 2-600 amp 3 wire / Ok to set 1 house meter and 20 apartment meters /---------------------------NOTE: Check water pipe GEC's | ROB | ROB | | ES | C | 6243879 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | C | 05/29/2019 | FIRE ALARM INSPECTION: | BRET | BRET | | ER | C | 6213106 |
BIBLE ELECTRIC, INC. | ER | P | 05/29/2019 | 205,208 corridors except south 1st floor (ser soffit) | BRET | BRET | | ER | P | 6213098 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | P | 05/23/2019 | FIRE ALARM INSPECTION: Rough ok for 107,108,205,206,207,208,305,306,307,308 / | ROB | ROB | | ER | P | 6209338 |
BIBLE ELECTRIC, INC. | ER | P | 05/23/2019 | Box broke and not made up on north kitchen wall in 205 / Lights, recpts, and comm. box not complete in 308 master bath / Rough and panels ok in 107,108,206,207,208,305,306,307 / Panels ok in205,308,Rough ok for breezeway on north end / | ROB | ROB | | ER | P | 6209332 |
LDI MECHANICAL, INC. | H= | C | 11/12/2019 | BUILDING 8. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6396814 |
HORIZON LLC OF SOUTH CAROLINA | H= | C | 11/12/2019 | BUILDING 8. GAS AND ELECTRIC METER VERIFICATION RECEIVED, GAS FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6396813 |
HORIZON LLC OF SOUTH CAROLINA | H= | P | 11/11/2019 | BUILDING 8. GAS FINAL OK EXCEPT 104: CONTRACTOR STATING WATER HEATER IS BEING CHANGED, NEED TO VERIFY VENT AND GAS CONNECTIONS. NEED METER VERIFICATION LETTER. | DUSTINS | DUSTINS | | H= | P | 6394943 |
LDI MECHANICAL, INC. | H= | P | 11/11/2019 | BUILDING 8. MECHANICAL FINAL OK EXCEPT 108: COMPLETE CONDENSATE DRAIN LINE UNDER SINK. | DUSTINS | DUSTINS | | H= | P | 6394942 |
HORIZON LLC OF SOUTH CAROLINA | H= | P | 11/07/2019 | BUILDING 8. NORTH TOWER GAS FINAL OK. STILL NEED TO SEE SOUTH TOWER AND OUTSIDE. NEED METER VERIFICATION LETTER. | DUSTINS | DUSTINS | | H= | P | 6392213 |
LDI MECHANICAL, INC. | H= | P | 11/01/2019 | BUILDING 8. MECHANICAL FINAL OK EXCEPT 108: COMPLETE CONDENSATE DRAIN LINE UNDER SINK. 205: MISSING FIRE DAMPER STICKER ON ACCESS DOOR. 207: MISSING FIRE DAMPER STICKER ON ACCESS DOOR. | DUSTINS | DUSTINS | | H= | P | 6386244 |
LDI MECHANICAL, INC. | H= | P | 10/29/2019 | BUILDING 8. NORTH TOWER: NEED TO SEE INSIDE ALL FAN COIL UNITS. 108: NEED TO COMPLETE CONDENSATE DRAIN LINE UNDER SINK. 205: MISSING FIRE DAMPER STICKER ON ACCESS DOOR. 207: MISSING FIRE DAMPER STICKER ON ACCESS DOOR. STILL NEED TO CONFIRM INTERLOCKS FOR EQUIPMENT SHUTDOWN. SOUTH TOWER: 103 AND 104: NEED TO SEE INSIDE FAN COIL UNITS. STILL NEED TO SEE 2ND AND 3RD FLOORS IN SOUTH TOWER AND OUTSIDE. | DUSTINS | DUSTINS | | H= | P | 6382783 |
LDI MECHANICAL, INC. | HD | C | 09/17/2019 | BUILDING 8. ALL GAPS AROUND SUPPLY OUTLETS TO SHEET ROCK OK. | DUSTINS | DUSTINS | | HD | C | 6337991 |
LDI MECHANICAL, INC. | HD | P | 09/12/2019 | BUILDING 8. ALL GAPS AROUND SUPPLY OUTLETS TO SHEET ROCK OK EXCEPT 103, 201, 203, 301 AND 303 IN THE MASTER BATHROOMS. | DUSTINS | DUSTINS | | HD | P | 6333540 |
HORIZON LLC OF SOUTH CAROLINA | HWP | C | 07/08/2019 | BUILDING 8. ALL APARTMENTS HOT WATER SUPPLY/RETURN PIPING OK. CHECK CONNECTIONS TO EQUIPMENT AT FINAL. | DUSTINS | DUSTINS | | HWP | C | 6255777 |
LDI MECHANICAL, INC. | HD | P | 05/13/2019 | BUILDING 8. NORTH TOWER MECHANICAL ROUGH ABOVE CEILING OK. STILL NEED TO SEE GAP AROUND SUPPLY OUTLETS TO SHEET ROCK. | DUSTINS | DUSTINS | | HD | P | 6197050 |
LDI MECHANICAL, INC. | HD | P | 05/06/2019 | BUILDING 8. SOUTH TOWER MECHANICAL ROUGH ABOVE CEILING OK. STILL NEED TO SEE GAP AROUND SUPPLY OUTLETS TO SHEET ROCK, | DUSTINS | DUSTINS | | HD | P | 6190184 |
LDI MECHANICAL, INC. | HSP | P | 02/12/2019 | LETTER FROM ENGINEER APPROVING CFD-15 IN RATED ASSEMBLIES RECEIVED, SEE IMAGES. | DUSTINS | DUSTINS | | HSP | P | 6104158 |
LDI MECHANICAL, INC. | HSP | P | 01/30/2019 | LETTER FROM ENGINEER ADDRESSING GAP AROUND DAMPERS RECEIVED, SEE IMAGES. | DUSTINS | DUSTINS | | HSP | P | 6091813 |
HORIZON LLC OF SOUTH CAROLINA | HC | C | 01/09/2019 | OK TO SET 20 METERS AT THIS ADDRESS. | DUSTINS | DUSTINS | | HC | C | 6073650 |
HORIZON LLC OF SOUTH CAROLINA | HI | C | 01/09/2019 | BUILDING 8. TWENTY 10 LB TEST OK. PIPING PER PLAN. CHECK CONNECTIONS TO EQUIPMENT AT FINAL. | DUSTINS | DUSTINS | | HI | C | 6073632 |
LDI MECHANICAL, INC. | HSP | P | 11/06/2018 | LETTER FROM ENGINEER APPROVING CEILING RADIATION DAMPERS IN DYNAMIC SYSTEM RECEIVED, SEE IMAGES. | DUSTINS | DUSTINS | | HSP | P | 6018007 |
HORIZON LLC OF SOUTH CAROLINA | P= | C | 11/19/2019 | | TAYLOR | TAYLOR | | P= | C | 6403516 |
HORIZON LLC OF SOUTH CAROLINA | P= | P | 11/15/2019 | all ok minus unit 103. | TAYLOR | TAYLOR | | P= | P | 6400746 |
HORIZON LLC OF SOUTH CAROLINA | P= | P | 11/12/2019 | unit 203 ok. | TAYLOR | TAYLOR | | P= | P | 6396019 |
HORIZON LLC OF SOUTH CAROLINA | P= | P | 11/11/2019 | 2nd and 3rd floors ok at south tower minus unit 203. | TAYLOR | TAYLOR | | P= | P | 6394592 |
HORIZON LLC OF SOUTH CAROLINA | P= | P | 11/07/2019 | north tower ok minus hi- loop at dishwasher for unit 107, need to inspect all of unit 108. | TAYLOR | TAYLOR | | P= | P | 6391328 |
HORIZON LLC OF SOUTH CAROLINA | PTO | C | 06/19/2019 | corrections made. NOTE: this completes all PTO phases | JOHNS | JOHNS | | PTO | C | 6237273 |
HORIZON LLC OF SOUTH CAROLINA | PTO | C | 06/19/2019 | correction made. NOTE: this completes all PTO phases | JOHNS | JOHNS | | PTO | C | 6237271 |
HORIZON LLC OF SOUTH CAROLINA | PTO | P | 06/18/2019 | ok for previous corrections and accessible measurements MINUS @ 107 still need freeze pro @ looped garage water line | JOHNS | JOHNS | | PTO | P | 6234781 |
HORIZON LLC OF SOUTH CAROLINA | PTO | P | 06/14/2019 | ok for test / design @ dwv MINUS, @ 108 check slope for upper @ hall bath and missing nail protection, @ 203 need slope @ right mstr lav, rest ok **STILL NEED water corrections and all accessible measurements | JOHNS | JOHNS | | PTO | P | 6231743 |
HORIZON LLC OF SOUTH CAROLINA | PTO | L | 06/13/2019 | cancelled via text from contractor | JOHNS | JOHNS | | PTO | L | 6229836 |
HORIZON LLC OF SOUTH CAROLINA | PTO | P | 06/05/2019 | ok for BLDG 8 TYPE 2 main waters and units waters MINUS need freeze pro @ all looped underground garage main waters, and dis similar metals @ all garage looped main waters, rest ok NOTE: ALL GROUND FLOOR UNITS = TYPE B (HALL BATH COMPLIES) MINUS 103 AND 108 = TYPE A (HALL BATH COMPLIES, HAND SHWRS W/ NON POSITIVE SHUT OFFS @ TUBS), vtr, aav @ water entry, @ 108 aav @ w.h. closet, @ 104 aav @ w.h. closet, aav @ all 1st and 2nd floor lavs (up high in cab), @ 202, 203, and 206 aav @ w.h. closet, unit shut offs @ laundry or front closet, concealable hammer arrestors @ all hot kitchen lines, check water htrs and water entry @ final | JOHNS | JOHNS | | PTO | P | 6221099 |
HORIZON LLC OF SOUTH CAROLINA | PB | P | 08/15/2018 | all ok minus water service. | TAYLOR | TAYLOR | | PB | P | 5934699 |
COLORADO STRUCTURES INC | XBS | T | 04/25/2019 | PAID (REC#1615080): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise rated assembly details. | MICHAELA | MICHAELA | | XBS | T | 6177977 |
BIBLE ELECTRIC, INC. | XES | P | 03/28/2019 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Revised site lighting and luminaire schedule. | SHELBY | SHELBY | | XES | P | 6148405 |
COLORADO STRUCTURES INC | XBS | T | 03/27/2019 | PAID (REC#1591736): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revisions to ANSI units | MICHAELA | MICHAELA | | XBS | T | 6145726 |
HORIZON LLC OF SOUTH CAROLINA | XPS | T | 03/26/2019 | PAID (REC#1591737): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 3/26/19: Delta 10 revisions - updated materials schedule | SHANEN | SHANEN | | XPS | T | 6145159 |
COLORADO STRUCTURES INC | XBS | T | 03/19/2019 | PAID (REC#1584869): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Arch. and Strc. updates | MICHAELA | MICHAELA | | XBS | T | 6137073 |
HORIZON LLC OF SOUTH CAROLINA | XPS | T | 03/06/2019 | PAID (REC#1584871): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 3/6/19: Added hub drain riser diagram detail. | SHANEN | SHANEN | | XPS | T | 6125133 |
COLORADO STRUCTURES INC | XBS | T | 01/28/2019 | PAID (REC#1579005): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise UL floor listing | MICHAELA | MICHAELA | | XBS | T | 6089916 |
BIBLE ELECTRIC, INC. | XES | T | 01/25/2019 | PAID (REC#1579006): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised site lighting and luminaire schedule. | BERTHA | BERTHA | | XES | T | 6088027 |
COLORADO STRUCTURES INC | XBS | T | 01/22/2019 | PAID (REC#1579008): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Truss uplift connections and fire engineering judgements | MICHAELA | MICHAELA | | XBS | T | 6085193 |
COLORADO STRUCTURES INC | XBS | T | 12/17/2018 | PAID (REC#1567164): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Truss hardware | MICHAELA | MICHAELA | | XBS | T | 6054640 |
COLORADO STRUCTURES INC | XBS | T | 12/10/2018 | PAID (REC#1567169): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Truss hardware | MICHAELA | MICHAELA | | XBS | T | 6047133 |
COLORADO STRUCTURES INC | XBS | T | 11/30/2018 | PAID (REC#1567170): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Stairs | MICHAELA | MICHAELA | | XBS | T | 6039903 |
COLORADO STRUCTURES INC | XBS | T | 11/30/2018 | PAID (REC#1567171): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise some rated assemblies | MICHAELA | MICHAELA | | XBS | T | 6039215 |
BIBLE ELECTRIC, INC. | XES | T | 10/22/2018 | PAID (REC#1555723): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised luminaire schedule, panel schedules, removed trash compactor. | BERTHA | BERTHA | | XES | T | 6001256 |
HORIZON LLC OF SOUTH CAROLINA | XPS | T | 10/16/2018 | PAID (REC#1555724): PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 10-16-18 | TCRIPPEN | TCRIPPEN | | XPS | T | 5996598 |
COLORADO STRUCTURES INC | XBS | T | 10/12/2018 | PAID (REC#1555726): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise some assemblies an elevations | MICHAELA | MICHAELA | | XBS | T | 5993040 |
COLORADO STRUCTURES INC | XBS | T | 08/15/2018 | PAID (REC#1527379): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Floor and roof trusses | MICHAELA | MICHAELA | | XBS | T | 5934396 |