COLORADO STRUCTURES INC | B= | C | 12/23/2019 | remainder of building / all units and exterior and east breeze way and items from previous B= complete / final OK pending other finals | DANE | DANE | | B= | C | 6435865 |
COLORADO STRUCTURES INC | B= | R | 12/20/2019 | west tower units and breeze ways and all garages only / garage #4 - need to complete protection of 4" PVC at rear corner into floor/ceiling assembly / all units at west tower OK pending other finals | DANE | DANE | | B= | R | 6434396 |
COLORADO STRUCTURES INC | BSP | P | 12/11/2019 | light gauge framing for soffits in garages OK | DANE | DANE | | BSP | P | 6424690 |
COLORADO STRUCTURES INC | BSP | P | 10/04/2019 | rock and attachments at rated assemblies at garages OK / this complete the screw inspections at this building | DANE | DANE | | BSP | P | 6358639 |
COLORADO STRUCTURES INC | BSP | P | 10/02/2019 | rock and attachments of rock OK at all rated assemblies at all first floor units at both towers / still need to inspect all garages | DANE | DANE | | BSP | P | 6355459 |
COLORADO STRUCTURES INC | BSP | P | 10/01/2019 | above ceiling penetrations OK at bathroom drop ceilings at fan coils at all units at all levels at both towers OK and ceiling drop framing OK at same areas | DANE | DANE | | BSP | P | 6353607 |
COLORADO STRUCTURES INC | BSP | P | 09/30/2019 | rock and attachments of rock OK at all units at level 2 at east tower | DANE | DANE | | BSP | P | 6352845 |
COLORADO STRUCTURES INC | BSP | P | 09/26/2019 | rock and attachments at all 2nd floor units at west tower OK / fire tape at prerock at laundry and bath walls in all 1st floor units at both towers OK | DANE | DANE | | BSP | P | 6349207 |
COLORADO STRUCTURES INC | BIN | P | 09/24/2019 | thermal insulation and RC OK at all garages and riser room and storage room | DANE | DANE | | BIN | P | 6346571 |
COLORADO STRUCTURES INC | BSP | P | 09/24/2019 | fire tape at prerock at 2nd floor double walls at bathrooms and laundries OK | DANE | DANE | | BSP | P | 6346569 |
COLORADO STRUCTURES INC | BIN | P | 09/23/2019 | thermal insulation OK at all units at 1st and 2nd floors at both towers | DANE | DANE | | BIN | P | 6344711 |
COLORADO STRUCTURES INC | BSP | P | 09/23/2019 | RC at floor ceiling assemblies at all units at 2nd and 1st floor units OK | DANE | DANE | | BSP | P | 6344706 |
COLORADO STRUCTURES INC | BSP | P | 09/23/2019 | pre rock at bathrooms and laundry rooms at fur out walls at 1st and 2nd floors / 103 - need to screw off prerock at dead space at west bathroom wall / 108 - need to screw off prerock at dead space at east bathroom all other prerock and attachments OK at 1st and 2nd floor fur out walls | DANE | DANE | | BSP | P | 6344704 |
COLORADO STRUCTURES INC | BSP | P | 09/20/2019 | 3RD FLOOR DRYWALL SCREW INSPECTION -- WEST TOWER -- All rated assembly attachment on 3rd floor west tower OK | DAKOTAB | DAKOTAB | | BSP | P | 6343233 |
COLORADO STRUCTURES INC | BFR | P | 09/19/2019 | FRAMING REINSPECTION -- 1ST FLOOR UNITS -- 108 - Still missing fire collar at 4" PVC at chase behind tub -- All other items from previous inspection corrected -- Engineer letter for truss repairs received | DAKOTAB | DAKOTAB | | BFR | P | 6341348 |
COLORADO STRUCTURES INC | BFR | P | 09/18/2019 | GARAGE FRAME INSPECTION -- All garage framing OK -- Engineer letter for truss repairs received | DAKOTAB | DAKOTAB | | BFR | P | 6339529 |
COLORADO STRUCTURES INC | BSP | P | 09/18/2019 | DRYWALL SCREW INSPECTION -- 3RD FLOOR -- EAST TOWER -- All drywall and attachment on 3rd floor west tower OK | DAKOTAB | DAKOTAB | | BSP | P | 6339525 |
COLORADO STRUCTURES INC | BFR | P | 09/18/2019 | Engineer letter for hole drilled in LVL and strongbacks at floor trusses on file | DAKOTAB | DAKOTAB | | BFR | P | 6338891 |
COLORADO STRUCTURES INC | BFR | P | 09/17/2019 | level 2 frame reinspection at all units at both towers / all items at level 2 units corrected / truss fixes received for F02 F18 F12 F12 F12 F03 F04 F12 F12 / all truss repairs OK | DANE | DANE | | BFR | P | 6338223 |
COLORADO STRUCTURES INC | BFR | P | 09/16/2019 | frame inspection at all 1st floor units / 103 - need fix for F02A with drilled top cord in 2 places over pantry - missing squash blocks at point load over header at interior bearing wall / 104 - missing anchor bolt at plate break at hall to bath across from door to bathroom - need fix for F11 over mech room with drilled top cord over interior bearing wall end - need to fire protect wires at fire barrier left of door after they are reinstalled to light switch / 107 - need to fix penetration at wire in fire barrier above door / 108 - misisng putty pads at light and outlet boxes at fire barrier at stud bay left of range outlet - wrong strap used at top plate to bottom of floor truss at corner of exterior walls at center bedroom - missing point load squash blocks above header at interior bearing wall - missng 2x8 block between studs at interior bearing wall under truss with no stud under it at bathroom - missing collar at 4" PVC at east bathroom dead space / need letter for drilled LVL's in breezeway floors / still need to inspect all garages | DANE | DANE | | BFR | P | 6336611 |
COLORADO STRUCTURES INC | BSP | P | 09/16/2019 | 3rd floor fire tape and fire stopping OK at all prerock at walls in bathrooms and laundry rooms in all units at both towers | DANE | DANE | | BSP | P | 6336569 |
COLORADO STRUCTURES INC | BSP | P | 09/13/2019 | rock and attachments of rock at all prerock at bathroom ceilings for air handlers and all fur out walls at laundry and bathrooms OK at all 3rd floor units at both towers | DANE | DANE | | BSP | P | 6334702 |
COLORADO STRUCTURES INC | BSP | P | 09/12/2019 | RC OK at all bathroom ceilings at all units at all floors at both towers OK where air handlers are to be installed | DANE | DANE | | BSP | P | 6333758 |
COLORADO STRUCTURES INC | BIN | P | 09/12/2019 | Thermal insulation at all 3rd floor units OK and RC at all 3rd floor units OK | DANE | DANE | | BIN | P | 6333750 |
COLORADO STRUCTURES INC | BFR | P | 09/12/2019 | all items from previous inspection at 3rd floor at both towers corrected OK | DANE | DANE | | BFR | P | 6333739 |
COLORADO STRUCTURES INC | BFR | P | 09/12/2019 | frame inspection for 2nd floor east tower units only / 205 - need fix for F12 trusses with loose or missing gussets at fire barrier end / need to complete fire tape of fire barrier at north end above ceiling / 206 - need fixes for (4) F03 trusses with missing gussets at fire barrier end in kitchen - missing 2x8's under trusses in interior load bearing wall - RC not installed right at prerock in east bathroom - need fix for F04 over east closet wall with drilled bottom cord / 207 - need fixes for (2) F12 trusses over living room that both have 2 breaks each / 208 - RC at prerock at east bathroom not installed right / truss fixes received for R05 F02 F01 F12 F03 and F18 | DANE | DANE | | BFR | P | 6333735 |
COLORADO STRUCTURES INC | BFR | R | 09/11/2019 | level 2 west tower only / 201 - need to remove foam from floor ceiling assembly - missing collar at pipe in dead space at bathroom - missing stud at north wall of west bathroom / 202 - need fix for F12 over entry - need to remove foam from floor ceiling assembly - nix hole in fire barrier above ceiling by wire - need stamped fix for F18 over bedroom - missing putty pad at box by entry door / 203 - need to remove foam from floor ceiling assembly - need fix for F02 with drilled bottom cord over low volt panel - missing collar at pipe in west bathroom / 204 - need to remove foam from floor ceiling assembly - fix fire caulk at fire barrier above ceiling left of door - need to hook up dryer vent - need fix for farthest south F12 broken in 2 places over living room - missing portion of top plate and strap at plate break at west corner of south bedroom wall - missing stud at vanity wall - missing collar at pipe in dead space at kitchen / truss fixes received for F18 F02 F03 F02 ans F12 | DANE | DANE | | BFR | R | 6332250 |
COLORADO STRUCTURES INC | BFR | P | 09/10/2019 | framing at floor ceiling assembly above bathrooms where air handlers will go OK at all 1st and 2nd level units in both towers | DANE | DANE | | BFR | P | 6330478 |
COLORADO STRUCTURES INC | BFR | P | 09/09/2019 | 3rd floor frame inspection -- Need to label fire barrier above all units doors through out --302 - Missing puddy pad at 3 gang box next to front door -- 303 -- Need engineer repair for R05 truss -- 304 - Studs next to front door not at 16" OC -- Missing puddy pad at 3 gang box next to front door -- 305 - Studs next to front door not 16" OC -- Missing puddy pad at 3 gang box next to front door -- 307 - Missing puddy pad at 3 gang box next to front door -- Engineer letters for truss repairs received, repairs OK | DAKOTAB | DAKOTAB | | BFR | P | 6328825 |
COLORADO STRUCTURES INC | BSP | P | 04/19/2019 | DRYWALL SCREW INSPECTION -- BREEZEWAYS -- All drywall attachment at breezeways OK per GA WP 8105 | DAKOTAB | DAKOTAB | | BSP | P | 6172028 |
COLORADO STRUCTURES INC | BSP | P | 03/26/2019 | revised drywall wrap design for ledger on file | DANE | DANE | | BSP | P | 6144044 |
COLORADO STRUCTURES INC | BSP | P | 01/31/2019 | exterior shear and straps OK | DANE | DANE | | BSP | P | 6094168 |
COLORADO STRUCTURES INC | BFN | C | 12/05/2018 | engineer observation on file / open hole on file | DANE | DANE | | BFN | C | 6043014 |
COLORADO STRUCTURES INC | BFT | C | 12/05/2018 | engineer observations for footing and foundation and interior slab on file | DANE | DANE | | BFT | C | 6043008 |
COLORADO STRUCTURES INC | BFT | P | 07/12/2018 | Authorized 3rd party engineer inspection with all observation paperwork-ufer letter,soils and open hole letter to be picked up by inspector @ BFI or BFD inspection | DANE | DANE | | BFT | P | 5900144 |
BIBLE ELECTRIC, INC. | E= | C | 12/04/2019 | | RANDY | RANDY | | E= | C | 6415884 |
BIBLE ELECTRIC, INC. | E= | P | 12/02/2019 | units and garages ok, | BRET | BRET | | E= | P | 6412888 |
BIBLE ELECTRIC, INC. | E= | P | 11/21/2019 | 3rd floor units corridor and 208 ok pending breaker locks for heaters | BRET | BRET | | E= | P | 6406677 |
BIBLE ELECTRIC, INC. | E= | P | 11/20/2019 | 2nd floor pendant lights not working in 208 could not do 3rd floor because of painting | BRET | BRET | | E= | P | 6406005 |
BIBLE ELECTRIC, INC. | E= | P | 11/19/2019 | 2nd floor west units, 2nd and 3rd corridors, missing screws in panel cover 203 | BRET | BRET | | E= | P | 6403832 |
COLORADO ELECTRICAL SYSTEMS, LLC | E= | C | 11/18/2019 | FIRE ALARM INSPECTION: FA ok / | ROB | ROB | | E= | C | 6403004 |
BIBLE ELECTRIC, INC. | E= | P | 11/18/2019 | Third level west tower, corridor recpt not working / Need breaker lockouts for heater breakers / res ok / | ROB | ROB | | E= | P | 6403002 |
BIBLE ELECTRIC, INC. | ER | C | 10/01/2019 | corridor and bath lids ok | BRET | BRET | | ER | C | 6353467 |
COLORADO ELECTRICAL SYSTEMS, LLC | ER | C | 06/26/2019 | FIRE ALARM INSPECTION: rough complete | BRET | BRET | | ER | C | 6244817 |
BIBLE ELECTRIC, INC. | EP | P | 06/26/2019 | unit panels except 103 | BRET | BRET | | EP | P | 6244816 |
BIBLE ELECTRIC, INC. | ER | P | 06/26/2019 | unit, garages and corridors except drop bath lids | BRET | BRET | | ER | P | 6244815 |
BIBLE ELECTRIC, INC. | ES | C | 06/13/2019 | Commercial Service: 2- 600 amp 3 wire services / Ok to set 1 house meter and 20 meters for units / Note: Check water pipe ground when water line installed / | ROB | ROB | | ES | C | 6230918 |
HORIZON LLC OF SOUTH CAROLINA | H= | C | 12/18/2019 | BUILDING 9. GAS FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6431216 |
LDI MECHANICAL, INC. | H= | C | 12/17/2019 | BUILDING 9. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6429790 |
HORIZON LLC OF SOUTH CAROLINA | H= | P | 12/17/2019 | BUILDING 9. GAS FINAL OK EXCEPT 103, 108, 201, 203, 206, 208, 301, 303, 306 AND 308: F891 CELL CORE IS NOT PERMITTED FOR WATER HEATER VENTING. | DUSTINS | DUSTINS | | H= | P | 6429788 |
LDI MECHANICAL, INC. | H= | P | 12/16/2019 | BUILDING 9. WEST TOWER MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | P | 6428406 |
HORIZON LLC OF SOUTH CAROLINA | H= | P | 12/16/2019 | BUILDING 9. WEST TOWER GAS FINAL OK EXCEPT 302 AND 304 MISSING CONDENSATE NEUTRALIZERS FOR WATER HEATERS. | DUSTINS | DUSTINS | | H= | P | 6428404 |
LDI MECHANICAL, INC. | H= | P | 12/13/2019 | BUILDING 9. MECHANICAL FINAL OK EXCEPT: ALL APARTMENTS NEED TO INSTALL HOSE CLAMPS ON CONDENSATE DRAIN TUBING UNDER SINKS. | DUSTINS | DUSTINS | | H= | P | 6427079 |
HORIZON LLC OF SOUTH CAROLINA | HSP | P | 12/09/2019 | GAS AND ELECTRIC METER VERIFICATION LETTER RECEIVED. | DUSTINS | DUSTINS | | HSP | P | 6420039 |
LDI MECHANICAL, INC. | H= | P | 12/06/2019 | BUILDING 9. MECHANICAL FINAL OK EXCEPT: ALL APARTMENTS NEED TO INSTALL HOSE CLAMPS ON CONDENSATE DRAIN TUBING UNDER SINKS. 301, 302, 304, 202, 204, AND 104: NEED TO SEE INSIDE FAN COIL UNITS. 304: NEED TO CONFIRM INTERLOCK SHUT DOWN WITH FIRE ALARM. | DUSTINS | DUSTINS | | H= | P | 6419057 |
LDI MECHANICAL, INC. | H= | P | 12/05/2019 | BUILDING 9. EAST TOWER MECHANICAL FINAL OK EXCEPT ALL EAST TOWER APARTMENTS NEED TO INSTALL HOSE CLAMPS ON CONDENSATE DRAIN TUBING UNDER SINKS. STILL NEED TO SEE WEST TOWER AND OUTSIDE. | DUSTINS | DUSTINS | | H= | P | 6417483 |
LDI MECHANICAL, INC. | HD | C | 11/06/2019 | BUILDING 9. ALL APARTMENTS GAPS AROUND SUPPLY OUTLETS TO SHEET ROCK OK. | DUSTINS | DUSTINS | | HD | C | 6390595 |
LDI MECHANICAL, INC. | HD | P | 10/30/2019 | CANCELLED AT CALL AHEAD PER JESSICA WITH CSI, NOT READY. | DUSTINS | DUSTINS | | HD | P | 6383711 |
HORIZON LLC OF SOUTH CAROLINA | HWP | C | 09/17/2019 | BUILDING 9. ALL HOT WATER SUPPLY/RETURN PIPING OK. CHECK CONNECTIONS TO EQUIPMENT AT FINAL. | DUSTINS | DUSTINS | | HWP | C | 6337936 |
LDI MECHANICAL, INC. | HD | P | 07/12/2019 | BUILDING 9. MECHANICAL ROUGH ABOVE CEILING OK. STILL NEED TO SEE GAPS AROUND SUPPLY OUTLETS AFTER SHEET ROCK INSTALLED. | DUSTINS | DUSTINS | | HD | P | 6261818 |
LDI MECHANICAL, INC. | HD | P | 06/26/2019 | BUILDING 9. EAST TOWER MECHANICAL ROUGH ABOVE CEILING OK EXCEPT 207: LIVING ROOM CEILING RADIATION DAMPER IS BROKEN FROM THE SPOT WELDS AND WILL NEED TO BE REPLACED. STILL NEED TO SEE GAP AROUND ALL SUPPLY OUTLETS IN THIS BUILDING. | DUSTINS | DUSTINS | | HD | P | 6245591 |
LDI MECHANICAL, INC. | HD | P | 06/25/2019 | BUILDING 9. WEST TOWER MECHANICAL ROUGH ABOVE CEILING OK. STILL NEED TO SEE GAP AROUND SUPPLY OUTLETS AFTER SHEET ROCK IS INSTALLED AND STILL NEED TO SEE EAST TOWER. | DUSTINS | DUSTINS | | HD | P | 6242981 |
LDI MECHANICAL, INC. | HSP | P | 02/12/2019 | LETTER FROM ENGINEER APPROVING CFD-15 IN RATED ASSEMBLIES RECEIVED, SEE IMAGES. | DUSTINS | DUSTINS | | HSP | P | 6104159 |
LDI MECHANICAL, INC. | HSP | P | 01/30/2019 | LETTER FROM ENGINEER ADDRESSING GAP AROUND DAMPERS RECEIVED, SEE IMAGES. | DUSTINS | DUSTINS | | HSP | P | 6091815 |
HORIZON LLC OF SOUTH CAROLINA | HC | C | 01/17/2019 | OK TO SET TWENTY METERS AT THIS ADDRESS. | DUSTINS | DUSTINS | | HC | C | 6081351 |
HORIZON LLC OF SOUTH CAROLINA | HI | C | 01/17/2019 | BUILDING 9. TWENTY 10 LB TEST OK. PIPING PER PLAN. CHECK CONNECTIONS TO EQUIPMENT AT FINAL. | DUSTINS | DUSTINS | | HI | C | 6081345 |
LDI MECHANICAL, INC. | HSP | P | 11/06/2018 | LETTER FROM ENGINEER APPROVING CEILING RADIATION DAMPERS IN DYNAMIC SYSTEM RECEIVED, SEE IMAGES. | DUSTINS | DUSTINS | | HSP | P | 6018008 |
HORIZON LLC OF SOUTH CAROLINA | P= | C | 12/18/2019 | | TAYLOR | TAYLOR | | P= | C | 6430789 |
HORIZON LLC OF SOUTH CAROLINA | P= | P | 12/17/2019 | all ok minus units 202, 204, 207 and water entry room. | TAYLOR | TAYLOR | | P= | P | 6429614 |
HORIZON LLC OF SOUTH CAROLINA | P= | P | 12/16/2019 | west tower ok. | TAYLOR | TAYLOR | | P= | P | 6428520 |
HORIZON LLC OF SOUTH CAROLINA | PTO | C | 08/20/2019 | all corrections made. | TAYLOR | TAYLOR | | PTO | C | 6306966 |
HORIZON LLC OF SOUTH CAROLINA | PB | C | 08/13/2019 | | JOHNS | JOHNS | | PB | C | 6299478 |
HORIZON LLC OF SOUTH CAROLINA | PTO | P | 08/13/2019 | OK for dwv and accessible measurements MINUS @ 2nd west garage back grade, @ 4th east garage back grade @ kitchen, @ 5th east garage back grade @ bath group, @ 6th east garage back grade @ bath group, @ 4th west garage back grade @ kitchen, secure all first floor flanges, @ 104 back grade @ kitchen for uppr, @ 103 slope @ hall bath for uppr, @ 203 back grade @ kitchen stub out and nail pro @ washer trap, @ 201(?) back grade @ kitchen stub out and slope @ hall lav for uppr, @ 204 slope @ lav for uppr, @ 207 low test @ kitchen, @ 205 back grade @ kitchen stub out, @ 206 low test @ mech aav, add straps @ kitchen for upr, slope @ hall lav for upr, low test @ mstr, and need slope @ mstr lav for upr, @ 208 slope / strap kitchen for upr, slope @ hall lav stub out, low test @ mstr, re attach strap @ mstr water closet for uppr, @ 301 back grade @ right mstr lav, @ 303 back grade @ kitchen stub out and slope @ left mstr lav, re test @ all areas where couplings will be added for slope corrections, rest ok
**STILL NEED ABOVE CORRECTIONS | JOHNS | JOHNS | | PTO | P | 6299477 |
HORIZON LLC OF SOUTH CAROLINA | PTO | P | 08/09/2019 | BLDG 9 TYPE 1 ok for main distro / unit waters. NOTE: vtr, all ground floor units TYPE B (HALL BATHS COMPLY), aav @ water entry, all 1st and 2nd floor lavs (up high in cab), 108 / 104 / 103 / 201 / 202 / and 206 mech rooms, check water htrs / water entry @ final, concelable hammer arrestors @ all hot kitchens lines, unit shut offs @ laundry room | JOHNS | JOHNS | | PTO | P | 6295870 |
HORIZON LLC OF SOUTH CAROLINA | PB | P | 10/15/2018 | Need dwv completed and test floor drain room 103, need water stub, rest ok for dwv. | DANR | DANR | | PB | P | 5994664 |
COLORADO STRUCTURES INC | XBS | T | 04/25/2019 | PAID (REC#1617295): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise rated assembly details. | MICHAELA | MICHAELA | | XBS | T | 6177985 |
LDI MECHANICAL, INC. | XMS | T | 04/04/2019 | PAID (REC#1591731): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: delta 1 | DALEH | DALEH | | XMS | T | 6155675 |
BIBLE ELECTRIC, INC. | XES | T | 03/28/2019 | PAID (REC#1591732): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revised site lighting and luminaire schedule. | SHELBY | SHELBY | | XES | T | 6148406 |
COLORADO STRUCTURES INC | XBS | T | 03/27/2019 | PAID (REC#1591733): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revisions to ANSI units added clarifications per RFIs | MICHAELA | MICHAELA | | XBS | T | 6145732 |
HORIZON LLC OF SOUTH CAROLINA | XPS | T | 03/26/2019 | PAID (REC#1591734): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 3/26/19: Delta 10 revisions - updated materials schedule | SHANEN | SHANEN | | XPS | T | 6145169 |
COLORADO STRUCTURES INC | XBS | T | 03/19/2019 | PAID (REC#1584874): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Arch. and Strc. updates | MICHAELA | MICHAELA | | XBS | T | 6137080 |
COLORADO STRUCTURES INC | XBS | T | 01/28/2019 | PAID (REC#1573062): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: v | MICHAELA | MICHAELA | | XBS | T | 6089918 |
BIBLE ELECTRIC, INC. | XES | T | 01/25/2019 | PAID (REC#1573063): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised site lighting and luminaire schedule. | BERTHA | BERTHA | | XES | T | 6088028 |
COLORADO STRUCTURES INC | XBS | T | 01/22/2019 | PAID (REC#1573065): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Truss uplift connections and fire engineering judgements | MICHAELA | MICHAELA | | XBS | T | 6085198 |
COLORADO STRUCTURES INC | XBS | T | 12/17/2018 | PAID (REC#1567176): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Truss hardware | MICHAELA | MICHAELA | | XBS | T | 6054649 |
COLORADO STRUCTURES INC | XBS | P | 12/10/2018 | PLAN SPLICE: (No Fee) by: MICHAELA for Construction: Truss hardware | MICHAELA | MICHAELA | | XBS | P | 6047135 |
COLORADO STRUCTURES INC | XBS | P | 11/30/2018 | PLAN SPLICE: (No Fee) by: MICHAELA for Construction: Revise some rated assemblies | MICHAELA | MICHAELA | | XBS | P | 6039217 |
BIBLE ELECTRIC, INC. | XES | T | 10/25/2018 | PAID (REC#1561165): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised luminaire, panel schedules, site plan and dwelling units. | BERTHA | BERTHA | | XES | T | 6006559 |
HORIZON LLC OF SOUTH CAROLINA | XPS | T | 10/17/2018 | PAID (REC#1561166): PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 10-17-18 | TCRIPPEN | TCRIPPEN | | XPS | T | 5996908 |
COLORADO STRUCTURES INC | XBS | T | 10/12/2018 | PAID (REC#1561167): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise some assemblies an elevations | MICHAELA | MICHAELA | | XBS | T | 5993047 |
COLORADO STRUCTURES INC | XBS | T | 08/13/2018 | PAID (REC#1526879): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Floor and roof trusses | MICHAELA | MICHAELA | | XBS | T | 5931417 |