ELDER CONSTRUCTION, INC. | B= | C | 03/07/2019 | All other required Final inspections are complete. (This is a computer generated result) | NATHAN | NATHAN | | B= | C | 6126220 |
ELDER CONSTRUCTION, INC. | B= | P | 03/06/2019 | . Additional Inspections Required (computer generated): PEAK HEATING & AIR COND, INC. Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6125525 |
ELDER CONSTRUCTION, INC. | BFR | P | 10/25/2018 | in fill framing of 2 openings and added double door framing only okay with completed required inspections. | NATHAN | NATHAN | | BFR | P | 6005804 |
ELDER CONSTRUCTION, INC. | BFR | P | 09/21/2018 | walls between rooms 5/7/8 okay with completed required inspections. / / / watch door swing at gym for final | NATHAN | NATHAN | | BFR | P | 5972689 |
EL PASO ELECTRIC, LLC. | E= | C | 12/20/2018 | | BRIAN | BRIAN | | E= | C | 6060213 |
EL PASO ELECTRIC, LLC. | E= | R | 12/19/2018 | need panel sch---open j box above the panel to the right in ceiling--ko plugs----- | BRIAN | BRIAN | | E= | R | 6058780 |
EL PASO ELECTRIC, LLC. | ER | P | 12/14/2018 | basement corridor --ok except 2 lights at entry to large room----leave tile out on final to verify these---- | BRIAN | BRIAN | | ER | P | 6053321 |
EL PASO ELECTRIC, LLC. | ER | P | 11/20/2018 | wall with the panels --ok-----need ep inspection on next inspection ---- | BRIAN | BRIAN | | ER | P | 6030594 |
EL PASO ELECTRIC, LLC. | E= | P | 10/15/2018 | phase 1 ok-----see plans---- | BRIAN | BRIAN | | E= | P | 5994298 |
EL PASO ELECTRIC, LLC. | ER | P | 10/15/2018 | phase 1 ok----- | BRIAN | BRIAN | | ER | P | 5994295 |
EL PASO ELECTRIC, LLC. | ER | P | 09/21/2018 | partial walls --see plans | BRIAN | BRIAN | | ER | P | 5972514 |
EL PASO ELECTRIC, LLC. | ER | R | 09/20/2018 | missing the HR to wall outlets--- | BRIAN | BRIAN | | ER | R | 5970932 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 03/07/2019 | DAMPER ANGLES ARE COMPLETE - SEE IMAGES | JERRYF | JERRYF | | H= | C | 6126219 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 02/21/2019 | TAB REPORT RECEIVED - STILL NEED PICTURES OF DAMPER RETAINAGE | JERRYF | JERRYF | | H= | P | 6112547 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 02/07/2019 | PARTIAL PENDING PICTURES PER HD NOTES AND TAB REPORT | JERRYF | JERRYF | | H= | P | 6100835 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 02/07/2019 | OK FOR DAMPER RETAINAGE - CONTRACTOR CAN ATTACH PICTURES OF DAMPER GAP AND RETAINAGE TO NEXT INSPECTION REQUEST | JERRYF | JERRYF | | HD | P | 6100832 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 01/15/2019 | DAMPER INSTALL BASEMENT CORRIDOR - Need to repair drywall around damper, re install damper angles and recall for inspection. | MARKB | MARKB | | HD | P | 6079054 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 01/11/2019 | FRAMING AT DAMPER OK - AT NEXT INSPECTION VERIFY RETAINAGE AND ACCESS DOORS | JERRYF | JERRYF | | HD | P | 6076393 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 01/10/2019 | NEED DAMPER FRAMED CORRECTLY - STOPPED INSPECTION | JERRYF | JERRYF | | HD | P | 6075071 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 11/27/2018 | ABOVE CEILING SA MAINS / RUN OUTS AND BOXES OK - STILL SMOKE DAMPER FRAMING INSPECTION AND DAMPER INSTALLED | JERRYF | JERRYF | | HD | P | 6035285 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 11/16/2018 | ABOVE CEILING SA MAINS - RUN OUTS - BOXES AND TIE INS OK - AT FUTURE INSPECTION VERIFY TRANSFER DUCTS | JERRYF | JERRYF | | HD | P | 6028266 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 10/11/2018 | THIS INSPECTION WAS FOR BASEMENT - ABOVE CEILING MAINS AND RUN OUTS IN THE FOLLOWING AREA'S OK - BIG STORAGE - WORK ROOM - SMALL STORAGE - WOMEN'S AND MENS LOCKER ROOMS - MAINT. OFFICE - SEATING AREA | JERRYF | JERRYF | | HD | P | 5992102 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 02/28/2019 | water heater added to scope, splice in for drinking fountain | JOSEPHD | JOSEPHD | | P= | C | 6119635 |
FRONTIER MECHANICAL SYSTEMS INC | P= | P | 01/25/2019 | need to add electric water heater to scope of work, water heater ok, plans splice in for change of location at drinking fountain, can complete once water heater is added | JOSEPHD | JOSEPHD | | P= | P | 6088775 |
FRONTIER MECHANICAL SYSTEMS INC | P= | P | 01/17/2019 | need plan splice for drinking fountain location change rest ok | JOSEPHD | JOSEPHD | | P= | P | 6081629 |
FRONTIER MECHANICAL SYSTEMS INC | PB | C | 11/26/2018 | Need revisions to reflect installed location and drain tie-in, test OK | SHANEN | SHANEN | | PB | C | 6033306 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 11/26/2018 | Need revisions to reflect installed location, test OK, VTR | SHANEN | SHANEN | | PTO | P | 6033305 |
FRONTIER MECHANICAL SYSTEMS INC | XPS | T | 01/24/2019 | PAID (REC#1571684) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 1-24-2019 relocate drinking fountain | TCRIPPEN | TCRIPPEN | | XPS | T | 6087379 |
ELDER CONSTRUCTION, INC. | XPS | T | 09/10/2018 | PAID (REC#1538922) PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: plumbing splice 9-10-18 | TCRIPPEN | TCRIPPEN | | XPS | T | 5959393 |
ELDER CONSTRUCTION, INC. | XES | T | 09/07/2018 | PAID (REC#1538922) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Added Work Room and Storage to scope. Revised Gym. | BERTHA | BERTHA | | XES | T | 5957814 |
ELDER CONSTRUCTION, INC. | XBS | T | 08/27/2018 | PAID (REC#1538922) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Add to scope of work | MICHAELA | MICHAELA | | XBS | T | 5945921 |