RICHMOND AMERICAN HOMES | B= | C | 03/07/2019 | | SCOTTS | SCOTTS | | B= | C | 6126584 |
RICHMOND AMERICAN HOMES | BIN | C | 03/07/2019 | Air Leakage Testing report (Blower Door) Per 2015 IECC Section R402.4.1 on file | SCOTTS | SCOTTS | | BIN | C | 6126570 |
RICHMOND AMERICAN HOMES | BSP | P | 02/25/2019 | 2015 IECC 402.4.1.2/RBC 308.4.15 ACH on file | SCOTTS | SCOTTS | | BSP | P | 6115872 |
RICHMOND AMERICAN HOMES | BIN | P | 02/21/2019 | provide ES report for spray foam insulation per 2015 IRC 316.5.4/spray foam installed at rims | SCOTTS | SCOTTS | | BIN | P | 6112799 |
RICHMOND AMERICAN HOMES | B= | R | 02/21/2019 | documentation provided must be compliant to 2017 RBC for test | SCOTTS | SCOTTS | | B= | R | 6112588 |
RICHMOND AMERICAN HOMES | B= | P | 02/19/2019 | complete BIN -- provide blower door test -- provide builders statement for attic insulation -- crawlspace/no deck -- Schedule a new Building Final when above items are complete. | SCOTTS | SCOTTS | | B= | P | 6110232 |
RICHMOND AMERICAN HOMES | BSP | P | 11/09/2018 | front porch frame and posts ok | DALE | DALE | | BSP | P | 6021388 |
RICHMOND AMERICAN HOMES | BIN | P | 11/07/2018 | still need to have air barrier at crawl space rims | DALE | DALE | | BIN | P | 6018325 |
RICHMOND AMERICAN HOMES | BFR | C | 11/07/2018 | | DALE | DALE | | BFR | C | 6018322 |
RICHMOND AMERICAN HOMES | BFR | L | 11/06/2018 | cancelled by Joe | SCOTTS | SCOTTS | | BFR | L | 6016673 |
RICHMOND AMERICAN HOMES | BIN | L | 11/06/2018 | cancelled by Joe | SCOTTS | SCOTTS | | BIN | L | 6016671 |
RICHMOND AMERICAN HOMES | BIN | P | 10/30/2018 | complete BFR -- seal top plates at first and 2nd floor -- provide air barrier at rims on 1st floor and in crawlspace -- provide air barrier under stairs at enclosed space | SCOTTS | SCOTTS | | BIN | P | 6009952 |
RICHMOND AMERICAN HOMES | BFR | P | 10/30/2018 | still missing post and kickers in crawlspace/rest ok | SCOTTS | SCOTTS | | BFR | P | 6009949 |
RICHMOND AMERICAN HOMES | BFD | C | 10/30/2018 | | SCOTTS | SCOTTS | | BFD | C | 6009698 |
RICHMOND AMERICAN HOMES | BFN | C | 10/30/2018 | foundation design on file | SCOTTS | SCOTTS | | BFN | C | 6009697 |
RICHMOND AMERICAN HOMES | BFR | R | 10/25/2018 | complete bfn bfd / inspect front porch on BSP / install all roof jacks / need strong-back on gable end at 6ft and 45 brace / need 9-2x4 post under beam at garage / missing tele-post at crawl space / no rear deck | DALE | DALE | | BFR | R | 6005596 |
RICHMOND AMERICAN HOMES | BFD | P | 10/25/2018 | complete BFN -- drain observation on file -- this is a 2017 RBC permit | SCOTTS | SCOTTS | | BFD | P | 6005402 |
RICHMOND AMERICAN HOMES | BFN | P | 10/25/2018 | provide foundation design -- foundation observation on file | SCOTTS | SCOTTS | | BFN | P | 6005397 |
RICHMOND AMERICAN HOMES | BSP | P | 10/25/2018 | soils/open hole on file/3000 psf/drain useable/10% | SCOTTS | SCOTTS | | BSP | P | 6005394 |
RICHMOND AMERICAN HOMES | BFT | C | 10/25/2018 | footing observation on file | SCOTTS | SCOTTS | | BFT | C | 6005390 |
RICHMOND AMERICAN HOMES | BSP | P | 09/25/2018 | exterior shear wall corrections noted from previous inspection are okay / note - need to complete foundation inspections | BRIANB | BRIANB | | BSP | P | 5976416 |
RICHMOND AMERICAN HOMES | BSP | R | 09/21/2018 | nail sill plates per schedule -- rest of shear ok | SCOTTS | SCOTTS | | BSP | R | 5972292 |
RICHMOND AMERICAN HOMES | BSP | P | 09/06/2018 | Foundation waterproofing OK / interior crawl space drain to pit / need engineer reports for soil and footing/foundation observation. | CHUCK | CHUCK | | BSP | P | 5957203 |
RICHMOND AMERICAN HOMES | BFD | P | 08/29/2018 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFD | P | 5950113 |
RICHMOND AMERICAN HOMES | BFT | P | 08/29/2018 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFT | P | 5950112 |
RICHMOND AMERICAN HOMES | BFN | P | 08/29/2018 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFN | P | 5950111 |
DELMARK ELECTRIC INC | E= | C | 01/31/2019 | E= OK ---- 30-amp A/C ok / | GREGM | GREGM | | E= | C | 6093265 |
DELMARK ELECTRIC INC | E= | R | 01/29/2019 | all can fixtures need to be trimmed and lamped for testing before final | CHIPO | CHIPO | | E= | R | 6091205 |
DELMARK ELECTRIC INC | E= | R | 01/18/2019 | not ready yet | CHIPO | CHIPO | | E= | R | 6082615 |
DELMARK ELECTRIC INC | ES | C | 10/24/2018 | Residential Underground: 200 amp 3/w new res | CRAIGS | CRAIGS | | ES | C | 6004445 |
DELMARK ELECTRIC INC | ER | C | 10/24/2018 | | CRAIGS | CRAIGS | | ER | C | 6004444 |
DELMARK ELECTRIC INC | ES | R | 10/23/2018 | Residential Underground: use proper clamp on the ufer , clamp not rated to have a lug bolted to it ----200 amp 3/w | CRAIGS | CRAIGS | | ES | R | 6002815 |
DELMARK ELECTRIC INC | ER | R | 10/23/2018 | use proper ufer clamp ---make up master bedroom closet light --- need a box and make up laundry room light -- move radon gas fan receptacle up out of the insulation and install trim plate --no multi --- crawler -- no central vac -- | CRAIGS | CRAIGS | | ER | R | 6002812 |
DELMARK ELECTRIC INC | ES | R | 10/19/2018 | Residential Underground: NOT READY | CRAIG | CRAIG | | ES | R | 6000753 |
DELMARK ELECTRIC INC | ER | R | 10/19/2018 | NOT READY | CRAIG | CRAIG | | ER | R | 6000749 |
TOM JOHNSON, INC. | H= | C | 02/15/2019 | | RANDYB | RANDYB | | H= | C | 6109373 |
TOM JOHNSON, INC. | H= | P | 02/14/2019 | Debris blocking water heater exhaust at termination behind screen. NOTES: Continuous whole house ventilation being achieved via outside air duct to furnace return with motorized damper, Control switch is located within furnace closet. Conditioned crawlspace. Outside air to furnace return with motorized damper. Direct vent furnace. High low transfers to water heater closet. A/C Complete. | RANDYB | RANDYB | | H= | P | 6107052 |
TOM JOHNSON, INC. | H= | R | 02/13/2019 | Cancelled per conversation with Bee with Allied Heating. Pictures rejected, no corrections made. | RANDYB | RANDYB | | H= | R | 6105626 |
TOM JOHNSON, INC. | H= | P | 02/08/2019 | Where is whole house ventilation switch located? Provide water heater installation instructions to verify proper screen within termination, Need passive transfer from crawlspace to living area per 2015 IRC R408.3. Locate furnace/A/C condensate drain piping vent standpipe no higher than the bottom of the furnace collector box per page 19 of furnace installation instructions. Terminate furnace intake vent with fittings per page 16 of furnace installation instructions. NOTES: Crawlspace with mechanical exhaust. Outside air to furnace return with motorized damper used for whole house ventilation. Direct vent furnace. High low transfers to water heater closet. A/C Complete. | RANDYB | RANDYB | | H= | P | 6102399 |
TOM JOHNSON, INC. | H= | P | 02/07/2019 | RECEIVED DUCT LEAKAGE REPORT FROM CONTRACTOR, SEE IMAGES | MATTM | MATTM | | H= | P | 6100143 |
SPRINGS GAS, INC. | HC | C | 10/15/2018 | RELEASE METER | ANDREWP | ANDREWP | | HC | C | 5995157 |
SPRINGS GAS, INC. | HI | C | 10/15/2018 | 10 LB TEST OK , 1 1/4 INCH MAIN , 1 FURNACE , 1 WATER HEATER , 1 FIRE PLACE , 1 RANGE | ANDREWP | ANDREWP | | HI | C | 5995151 |
TOM JOHNSON, INC. | HRR | C | 10/10/2018 | BY FINAL: Called and spoke with Sean of Tom Johnson, verify location of whole house ventilation switch installed within furnace closet. | RANDYB | RANDYB | | HRR | C | 5991499 |
TOM JOHNSON, INC. | HRR | P | 10/08/2018 | 3" Bath exhaust duct on main level is undersized per 2015 IRC Table M1506.2. Mechanically fasten dryer exhaust with fasteners protruding not more than 1/8 of an inch per 2015 IRC G2439.7.2. Where will the whole house ventilation switch be located? FYI: High low transfers to water heater closet will not meet the 100 square inch free area minimum requirement once grilles are installed. NOTES: Whole house ventilation requirements will be met via the 6" outside air duct with motorized damper connected to the furnace return. All bath exhaust fans are 50 CFM. Conditioned crawlspace. Outside air to furnace return through roof with motorized damper. Direct vent furnace. A/C Rough coil only. | RANDYB | RANDYB | | HRR | P | 5989198 |
TOM JOHNSON, INC. | HSP | P | 10/02/2018 | 10-02-2018.... had conversation with Shaun of Allied Heating about HRR notes for 10-02-2018 and 10-01-2018. Shaun says there should be a fan in the furnace room for whole house ventilation (WILL NEED TO VERIFY FAN AND SWITCH). | PAULO | PAULO | | HSP | P | 5983182 |
TOM JOHNSON, INC. | HRR | P | 10/02/2018 | NEEDED BY FINAL-- DUCT LEAKAGE REPORT, ACCESS TO CRAWL SPACE TO VERIFY EXHAUST FOR CONDITIONED CRAWL SPACE. REVISED NOTES FOR 2017 CODE: correct size and material for bath fan exhaust duct on main level, properly support and fasten dryer exhaust duct per the IRC G2439.7.2, provide CFM's for bath exhaust per the IRC 1506.2 (NEED TO VERIFY EXHAUST LENGTH-- how are we providing whole house ventilation? and where is the control switch being located? per the IRC M1507., IF PROVIDING COMBUSTION AIR TO BOTH WATER HEATER AND FURNACE CLOSETS- NEED TO SEE THE 2015 IECC R402.4.4. note: crawl space, high combustion air to furnace closet, direct vent furnace, outside air to water heater closet, indirect vent water heater, a/c rough only- no line set. | PAULO | PAULO | | HRR | P | 5982500 |
TOM JOHNSON, INC. | HRR | P | 10/01/2018 | MAIN FLOOR BATHROOM EXHAUST TO BE CORRECT SIZE PER 2015 IR , REMOVE VERTICAL TRANSFER AIR DUCT FROM ATTIC TO FURNACE CLOSET, MECHANICAL FASTEN DRYER EXHAUST DUCT PER IRC G2439 .7.2 ,
NEEDED BY FINAL : ACCESS TO CRAWL SPACE TO VERIFY EXHAUST DUCT FOR CONDITIONING , VERIFY SOLID DOOR WITH SELF CLOSING HINGES AND SEALED TO WATER HEATER CLOSET , DUCT LEAKAGE REPORT. NOTES: DIRECT VENT FURNACE , INDIRECT VENT WATER HEATER , CRAWL SPACE , OUTSIDE AIR TO WATER HEATER CLOSET , AC ROUGH ONLY NO LINE SET TRAINING WITH PAUL O | ANDREWP | ANDREWP | | HRR | P | 5982301 |
CONFIDENCE PLUMBING CO., INC | P= | C | 01/28/2019 | correction made | TED | TED | | P= | C | 6089625 |
CONFIDENCE PLUMBING CO., INC | P= | P | 01/23/2019 | No correction made. | DANR | DANR | | P= | P | 6085940 |
CONFIDENCE PLUMBING CO., INC | P= | P | 01/22/2019 | install dishwasher drain at standpipe, leak at water entry room, rest ok, pvb installed, crawl space. | TAYLOR | TAYLOR | | P= | P | 6084904 |
CONFIDENCE PLUMBING CO., INC | PTO | C | 10/05/2018 | Test ok, irrigation stub. | DANR | DANR | | PTO | C | 5987908 |