PEAK PROFESSIONAL CONTRS INC | B= | C | 02/21/2019 | core shell permit L50261 complete | BRIANB | BRIANB | | B= | C | 6113112 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 02/15/2019 | still pending completion of final inspection for core and shell -- Schedule a new Building Final when above items are complete. | BRIANB | BRIANB | | B= | P | 6108100 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 02/14/2019 | corrections okay / pending other final inspections - including core and shell final inspection -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 6107468 |
PEAK PROFESSIONAL CONTRS INC | B= | P | 02/01/2019 | missing restroom signage / missing door hardware at stock room door / need to complete other final inspections / note - core and shell permit final inspection is partial -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 6095601 |
PEAK PROFESSIONAL CONTRS INC | BFR | P | 12/14/2018 | partial framing inspection -- framing including demising walls on both sides of unit constructed per plan -- reviewed accessibility | SCOTTS | SCOTTS | | BFR | P | 6053645 |
ELECTRIC TECH INC. | E= | C | 01/31/2019 | | RANDY | RANDY | | E= | C | 6093703 |
ELECTRIC TECH INC. | ES | P | 12/27/2018 | Commercial Service: 400amp 4wire--Ok to energize /---------------------One line needs to be spliced to the existing 3000 amp service dated 12.12.2018 / | ROB | ROB | | ES | P | 6064073 |
ELECTRIC TECH INC. | ER | P | 12/14/2018 | north and south main walls okay---except bathrooms not ready | CHIPO | CHIPO | | ER | P | 6053796 |
ELECTRIC TECH INC. | ER | P | 11/29/2018 | East and West exterior walls ok / | ROB | ROB | | ER | P | 6038040 |
ELECTRIC TECH INC. | ESL | C | 11/28/2018 | ESL ok for 2 power conduits and 1 data conduit / | ROB | ROB | | ESL | C | 6036554 |
ELECTRIC TECH INC. | ER | P | 11/28/2018 | Rough in ok for recpts. in both demising walls / | ROB | ROB | | ER | P | 6036550 |
AIRTECH MECHANICAL, INC. | H= | C | 02/15/2019 | TEST AND BALANCE REPORT RECEIVED ( SEE IMAGES ) | LIDO | LIDO | | H= | C | 6108084 |
AIRTECH MECHANICAL, INC. | H= | P | 02/01/2019 | PARTIAL PENDING: NEED TEST AND BALANCE REPORT. | LIDO | LIDO | | H= | P | 6095199 |
AIRTECH MECHANICAL, INC. | H= | P | 12/13/2018 | MISSING SUPPLY GRILL IN ROOM STOCK ROOM 101 / BROKEN ELBOW ON SAME BRANCH LINE. NEED BATHROOM GRILLS INSTALLED , MISSING THERMOSTAT, NEED TO SEE DUCT DETECTOR INSTALLED FOR RTU-5 .SUPPLY AIR GRILLS OK, NEED TEST AND BALANCE REPORT. | LIDO | LIDO | | H= | P | 6052261 |
AIRTECH MECHANICAL, INC. | HD | P | 12/13/2018 | SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK./ NEED TO VERIFY DUCT DETECTORS | LIDO | LIDO | | HD | P | 6052249 |
AIRTECH MECHANICAL, INC. | HD | P | 12/12/2018 | BUILDING BLOCKED NO ACCESS. | LIDO | LIDO | | HD | P | 6051250 |
MIDWAY PLUMBING LLC | P= | C | 02/01/2019 | tenant finish | TED | TED | | P= | C | 6095185 |
MIDWAY PLUMBING LLC | PTO | C | 12/21/2018 | test and design ok | TED | TED | | PTO | C | 6061263 |
MIDWAY PLUMBING LLC | PB | C | 11/27/2018 | Ok. | DANR | DANR | | PB | C | 6034886 |
ELECTRIC TECH INC. | XES | T | 01/30/2019 | PAID (REC#1573034) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised one-line. | BERTHA | BERTHA | | XES | T | 6092892 |
ELECTRIC TECH INC. | XES | T | 12/18/2018 | PAID (REC#1565819): PLAN SPLICE FEE: $50 by: MATTHEW for Electrical: added new panel A and changed service lateral size | MATTHEW | MATTHEW | | XES | T | 6056188 |