ELDER CONSTRUCTION, INC. | B= | C | 10/19/2020 | All other required Final inspections are complete. (This is a computer generated result) | NATHAN | NATHAN | | B= | C | 6745227 |
ELDER CONSTRUCTION, INC. | B= | P | 07/20/2020 | doors corrected. Additional Inspections Required (computer generated): EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, FRONTIER MECHANICAL SYSTEMS INC Mechanical Final Inspection is not Completed yet, PEAK HEATING & AIR COND, INC. Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6643254 |
ELDER CONSTRUCTION, INC. | B= | P | 03/22/2019 | need door 1 in room 1 waiting room to swing in direction of travel, rooms 1,2 and 9-20 with completed required inspections okay this is phase 1 only see phasing plan in images -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, FRONTIER MECHANICAL SYSTEMS INC Mechanical Final Inspection is not Completed yet, PEAK HEATING & AIR COND, INC. Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6141133 |
ELDER CONSTRUCTION, INC. | BFR | P | 01/09/2019 | With completed required inspections frame okay, one core floor penetration at open area break room sink to be inspected for firestop through penetration. Reviewed Accessible Elements plumbing permit and inspection needed prior to work starting. | NATHAN | NATHAN | | BFR | P | 6073216 |
EL PASO ELECTRIC, LLC. | E= | C | 07/30/2020 | | JOHNN | JOHNN | | E= | C | 6655249 |
EL PASO ELECTRIC, LLC. | E= | C | 07/30/2020 | pic accepted/ | JOHNN | JOHNN | | E= | C | 6655228 |
EL PASO ELECTRIC, LLC. | E= | P | 07/24/2020 | pics of light --ok / still need pic of the support of the emt / | BRIAN | BRIAN | | E= | P | 6648700 |
EL PASO ELECTRIC, LLC. | E= | P | 07/17/2020 | need to support the 1 1/2" emt / ok to upload pics / | BRIAN | BRIAN | | E= | P | 6641131 |
EL PASO ELECTRIC, LLC. | E= | C | 06/16/2020 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 6606012 |
EL PASO ELECTRIC, LLC. | ER | C | 06/16/2020 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | ER | C | 6606004 |
EL PASO ELECTRIC, LLC. | ER | P | 06/16/2020 | ceiling---need to support the emt for the panel / need j box over the cord for the pendant with 6" or less of cord above the ceiling / | BRIAN | BRIAN | | ER | P | 6605997 |
EL PASO ELECTRIC, LLC. | E= | P | 03/22/2019 | FIRE ALARM INSPECTION: phase 1 ok ----scope is from the entry door to the suit to the north / phase 2 is south of the entry door | BRIAN | BRIAN | | E= | P | 6140805 |
EL PASO ELECTRIC, LLC. | E= | P | 03/21/2019 | FIRE ALARM INSPECTION: phase 1 / north side of the suit entry door --ok | BRIAN | BRIAN | | E= | P | 6139543 |
EL PASO ELECTRIC, LLC. | E= | P | 03/21/2019 | random outlets not working on the north half / phase one label panel with room #'s --- need to see correction before they move in / | BRIAN | BRIAN | | E= | P | 6139537 |
EL PASO ELECTRIC, LLC. | ER | P | 03/08/2019 | ceilings in phase 1--ok -----from entry door north / | BRIAN | BRIAN | | ER | P | 6128081 |
EL PASO ELECTRIC, LLC. | ER | P | 03/07/2019 | FIRE ALARM INSPECTION: partial ceiling --phase 1 (the north half of the suit ) is ok | BRIAN | BRIAN | | ER | P | 6126539 |
EL PASO ELECTRIC, LLC. | ER | P | 03/07/2019 | need to tape the mc / light whips where they touch the sprinkler / rest of the area ok | BRIAN | BRIAN | | ER | P | 6126525 |
EL PASO ELECTRIC, LLC. | ER | P | 01/09/2019 | WALLS OK | BRIAN | BRIAN | | ER | P | 6073056 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 10/19/2020 | TAB REPORT ATTACHED, SEE IMAGES | BENH | BENH | | H= | C | 6745226 |
FRONTIER MECHANICAL SYSTEMS INC | H= | C | 07/22/2020 | CORRECTION MADE SEE IMAGES | JERRYF | JERRYF | | H= | C | 6645350 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 07/17/2020 | PARTIAL PENDING PLAN REVISION FOR CONDENSATE DRAIN AT IT ROOM - NEED PICTURES OF DRAIN ATTACHED TO TAB REPORT | JERRYF | JERRYF | | H= | P | 6641554 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 07/17/2020 | CANNOT HAVE OPEN DRAIN TRAP IN RETURN AIR PLENUM AT CONDENSATE DRAIN - NEED DRAIN INSTALLED PER DETAIL ON NEW PLUMBING PAGE P1.1 - STILL NEED THIS PAGE SPLICED INTO PERMIT SET FOR DRAIN NOTES: REST OK | JERRYF | JERRYF | | H= | P | 6641524 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 07/13/2020 | NEED KANSAS CITY DRAIN REMOVED IN RETURN AIR PLENUM AND DRAIN INSTALLED TO MATCH NEW DRAWING DETAIL DATED 7 / 10 SHEET P1.1 CIRCLED ON ON SITE PLANS - NEED NEW DRAIN PIPING PROTECTED TO 25 / 50 FLAME SPREAD IN RETURN AIR PLENUM - NEED THIS SHEET SPLICED INTO PLANS | JERRYF | JERRYF | | H= | P | 6635066 |
FRONTIER MECHANICAL SYSTEMS INC | HSP | P | 07/06/2020 | AFTER REVIEW WITH SENIOR PLUMBING INSPECTOR KANSAS CITY DRAIN CANNOT BE LOCATED IN RETURN AIR PLENUM - NEED TO RELOCATE DRAIN TO AN APPROVED LOCATION | JERRYF | JERRYF | | HSP | P | 6627663 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 07/06/2020 | PARTIAL PENDING CONSULT ON KANSAS CITY DRAIN IN RETURN AIR PLENUM | JERRYF | JERRYF | | H= | P | 6627412 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 06/11/2020 | CHANGED INSPECTION TO HEAT FINAL - NEED THE FOLLOWING - ALL GRILLES AND CONDENSATE DRAIN COMPLETED AT AC 1 - CONTROLS - TAB REPORT NOTES: ALL OTHER GRILLES ARE COMPLETE | JERRYF | JERRYF | | H= | P | 6601301 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 05/13/2020 | ABOVE CEILING SA / RA / TRANSFER DUCTS AND MAN BARS OK IN SECURED AREA - STILL AC 1 | JERRYF | JERRYF | | HD | P | 6570378 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 01/08/2020 | NOT READY FOR FINAL NEED A/C-1 INSTALLED IN SECURE AREA AND CONDENSATE RAN TO COMMON DRAIN | BENH | BENH | | H= | P | 6446971 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 08/06/2019 | CONDENSATE DRAIN PROTECTION OK IN UNSECURED AREA ONLY - STILL DRAINS COMPLETED IN SECURED AREA | JERRYF | JERRYF | | H= | P | 6290319 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 07/31/2019 | ALL PVC PIPE NEEDS TO BE ISOLATED IN PLENUM | BENH | BENH | | H= | P | 6283123 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 07/24/2019 | COULD NOT VERIFY PLASTIC PIPE WAS ISOLATED FROM RETURN PLENUM SINCE ALL TILE WAS DROPPED, CONNECTIONS TO A/C-1 AND CONDENSATE DRAIN OK | BENH | BENH | | H= | P | 6275061 |
FRONTIER MECHANICAL SYSTEMS INC | HWP | P | 03/22/2019 | PRESSURE TESTS OK - PIPING PER PLAN - STILL NEED FINAL CONNECTIONS AT AC1 IN SECURED AREA ROOM 5 - NEED DRAIN COMPLETED AT AC1 IN ROOM 12 - NEED ALL PLASTIC PIPING IN PLENUM PROTECTED TO 25 / 50 FLAME SPREAD IN ALL AREA'S - | JERRYF | JERRYF | | HWP | P | 6141257 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 03/21/2019 | NEED CONDENSATE DRAIN COMPLETED BY FINAL | JERRYF | JERRYF | | HD | P | 6139802 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 02/07/2019 | NEED WATER PIPING AND CONDENSATE DRAINS CLAIMED BY SOMEONE ON PERMIT AND INSPECTED WHEN READY - STILL NEED THE FOLLOWING - HEAT PUMPS AND DUCT AND RUN OUTS - MEDIUM PRESSURE TIE IN AT VAV BOX NOTES: ABOVE CEILING MAINS AND RUN OUTS OK IN BOTH SECURED AND UNSECURED AREAS - ALL SA GRILLES AND CONNECTIONS ARE COMPLETE IN UNSECURED AREA - 4 MAN BARS OK | JERRYF | JERRYF | | HD | P | 6100847 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 03/20/2019 | | JOSEPHD | JOSEPHD | | P= | C | 6138692 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 03/05/2019 | note: check vent connection in ceiling at final, water heater ok | JOSEPHD | JOSEPHD | | PTO | C | 6124777 |
EL PASO ELECTRIC, LLC. | XES | T | 03/21/2019 | PAID (REC#1584154) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Add panel 13PC | SHELBY | SHELBY | | XES | T | 6139456 |