MWH CONSTRUCTORS, INC. | B= | C | 08/22/2022 | | ADAML | ADAML | | B= | C | 7490189 |
MWH CONSTRUCTORS, INC. | BSP | P | 08/04/2022 | Engineer letters on file for footing/foundation, soils/compaction, open hole, structural steel, concrete | ADAML | ADAML | | BSP | P | 7470653 |
MWH CONSTRUCTORS, INC. | BSP | P | 07/20/2022 | Updated soils on file | ADAML | ADAML | | BSP | P | 7452734 |
MWH CONSTRUCTORS, INC. | BE | C | 10/04/2021 | | AMYP | AMYP | | BE | C | 7128373 |
WEIFIELD GROUP CONTRACTING INC. | E= | C | 08/17/2022 | | JOHNN | JOHNN | | E= | C | 7485289 |
STURGEON ELECTRIC CO INC | E= | C | 06/06/2022 | scope: controls | JOHNN | JOHNN | | E= | C | 7400565 |
WEIFIELD GROUP CONTRACTING INC. | E= | R | 05/25/2022 | need labels on discos and equipment/ need panels, transformers open for inspection/ | JOHNN | JOHNN | | E= | R | 7389020 |
STURGEON ELECTRIC CO INC | EE | L | 03/23/2021 | Renewed for No Fee at 3/23/2021 9:27:00 AM | DEAN | DEAN | | EE | L | 6907103 |
WEIFIELD GROUP CONTRACTING INC. | EE | L | 02/22/2021 | Renewed online for 1/2 Fee at 2/22/2021 7:57:36 AM (RECEIPT #: 1751634) | WEBSITE | WEBSITE | | EE | L | 6875991 |
WEIFIELD GROUP CONTRACTING INC. | ESP | C | 03/19/2020 | -----------------------------------No inspections indoors on this site for minimum 2 weeks. Can only perform outdoor inspections, and those need to be with no contact from on site personnel--------------------- | DEAN | DEAN | | ESP | C | 6516434 |
HORIZON MECHANICAL SOLUTIONS | H= | C | 07/11/2022 | CORRECTION MADE | MARKB | MARKB | | H= | C | 7441595 |
STRAIT MECHANICAL LLC | H= | C | 07/11/2022 | 2 WATER HEATER VENTS COMPLETE | MARKB | MARKB | | H= | C | 7441591 |
HORIZON MECHANICAL SOLUTIONS | H= | P | 04/22/2022 | FINAL PENDING - Need water vents permitted and inspected. OTHER CORRECTIONS MADE. | MARKB | MARKB | | H= | P | 7349459 |
HORIZON MECHANICAL SOLUTIONS | HSP | P | 04/22/2022 | TEST AND BALANCE REPORT FOR 3 BUILDINGS RECEIVED - SEE IMAGES | MARKB | MARKB | | HSP | P | 7348361 |
HORIZON MECHANICAL SOLUTIONS | H= | P | 12/06/2021 | FINAL PENDING - Need mechanical contractor attached to permit for water heater vents and vent inspections. Complete condensate piping MUA and FCU. Provide test and balance report. | MARKB | MARKB | | H= | P | 7199280 |
HORIZON MECHANICAL SOLUTIONS | HI | C | 04/02/2021 | 10 Lb test ok / | MATTM | MATTM | | HI | C | 6920126 |
HORIZON MECHANICAL SOLUTIONS | HE | L | 02/22/2021 | Renewed online for 1/2 Fee at 2/22/2021 9:50:58 AM (RECEIPT #: 1751722) | WEBSITE | WEBSITE | | HE | L | 6876136 |
HORIZON MECHANICAL SOLUTIONS | HD | P | 08/20/2020 | EXTERIOR DUCT CONNECTIONS OK AT MUA UNIT | JERRYF | JERRYF | | HD | P | 6680493 |
HORIZON MECHANICAL SOLUTIONS | HRP | P | 08/20/2020 | PRESSURE TEST OK AND PIPING PER PLAN | JERRYF | JERRYF | | HRP | P | 6680465 |
HORIZON MECHANICAL SOLUTIONS | HC | C | 05/29/2020 | RELEASE METER | JERRYF | JERRYF | | HC | C | 6587992 |
HORIZON MECHANICAL SOLUTIONS | HI | C | 05/29/2020 | PRESSURE TEST OK AND PIPING PER PLAN | JERRYF | JERRYF | | HI | C | 6587970 |
HORIZON MECHANICAL SOLUTIONS | HD | P | 04/08/2020 | UNIT HEATER VENTING / FCU MAINS AND RUN OUTS OK IN ELECTRIC AND TANK ROOM - STILL NEED HRP INSPECTION | JERRYF | JERRYF | | HD | P | 6535373 |
STRAIT MECHANICAL LLC | P= | C | 05/13/2022 | | JOSEPHD | JOSEPHD | | P= | C | 7374904 |
STRAIT MECHANICAL LLC | PTO | C | 05/13/2022 | | JOSEPHD | JOSEPHD | | PTO | C | 7374898 |
STRAIT MECHANICAL LLC | PTO | P | 05/11/2022 | changed to pto, need removal access to expansion tank, rest ok, can complete P= once that is done | JOSEPHD | JOSEPHD | | PTO | P | 7371455 |
STRAIT MECHANICAL LLC | P= | P | 04/26/2022 | Spoke With GC Kenny / Plumbing Contractor Needs To Go Through Water Pipe ISO & Verify Correct Plan Page SFA-H6 / Need To Complete T&P @ Water Heater / Need To Complete Drain @ Back Flow / Need To Verify Eye Wash Has Mixing Valve / | TRAVISR | TRAVISR | | P= | P | 7352472 |
STRAIT MECHANICAL LLC | PE | L | 02/18/2021 | Renewed online for 1/2 Fee at 2/18/2021 12:09:56 PM (RECEIPT #: 1751130) | WEBSITE | WEBSITE | | PE | L | 6874055 |
STRAIT MECHANICAL LLC | PRD | C | 01/21/2020 | | SAMH | SAMH | | PRD | C | 6457854 |
STRAIT MECHANICAL LLC | PE | L | 01/20/2020 | Renewed online for 1/2 Fee at 1/20/2020 2:20:17 PM (RECEIPT #: 1656839) | WEBSITE | WEBSITE | | PE | L | 6457423 |
STRAIT MECHANICAL LLC | PB | C | 06/21/2019 | 1-1/2" water in. SFA-H4 | SAMH | SAMH | | PB | C | 6240307 |
STRAIT MECHANICAL LLC | PRD | P | 06/21/2019 | Underground roof drain OK. | SAMH | SAMH | | PRD | P | 6240289 |
STRAIT MECHANICAL LLC | PB | P | 05/14/2019 | Checked 3" trap arm under slab at SA building. pg SFA-H4. | SAMH | SAMH | | PB | P | 6198099 |
STRAIT MECHANICAL LLC | PB | R | 03/05/2019 | wrong permit called in | JOSEPHD | JOSEPHD | | PB | R | 6124925 |
MWH CONSTRUCTORS, INC. | XBS | T | 06/28/2022 | PAID (REC#1884319): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Stresscon panels | MICHAELA | MICHAELA | | XBS | T | 7427054 |
HORIZON MECHANICAL SOLUTIONS | XMS | P | 05/17/2022 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: see reviewer comments | DALEH | DALEH | | XMS | P | 7378568 |
MWH CONSTRUCTORS, INC. | XBS | T | 03/25/2022 | PAID (REC#1859444): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Detail revisions | MICHAELA | MICHAELA | | XBS | T | 7314407 |
MYERS AND SONS CONSTRUCTION, LP | XBS | T | 04/24/2019 | PAID (REC#1611164) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Deflagration panel installation | SHELLEY | SHELLEY | | XBS | T | 6176262 |