WELLS & WEST GENERAL CONTRACTORS, INC. | B= | C | 05/10/2019 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 6194552 |
WELLS & WEST GENERAL CONTRACTORS, INC. | B= | P | 03/01/2019 | suite numbers installed OK / final OK pending other finals. Additional Inspections Required (computer generated): NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 6121594 |
WELLS & WEST GENERAL CONTRACTORS, INC. | B= | P | 02/27/2019 | need to install suite numbers outside of both doors -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 6119358 |
WELLS & WEST GENERAL CONTRACTORS, INC. | BFR | P | 02/27/2019 | frame inspections complete and OK pending other roughs | DANE | DANE | | BFR | P | 6119351 |
WELLS & WEST GENERAL CONTRACTORS, INC. | BFR | P | 02/15/2019 | first and second layers of rock and attachments at shaft wall OK / first and second and 3rd layers of rock and attachments and joint laps OK at new entrance wall | DANE | DANE | | BFR | P | 6108454 |
WELLS & WEST GENERAL CONTRACTORS, INC. | BFR | P | 02/14/2019 | shaft liner framing and shaft liner now OK and done per splice / framing at new doorway OK / discussed how to install and have inspections for rock at both 2 layer and 3 layer systems with on site rep Matt | DANE | DANE | | BFR | P | 6107611 |
WELLS & WEST GENERAL CONTRACTORS, INC. | BFR | R | 01/30/2019 | new shaft assembly (V455) needs to be spliced into plans as it is a design change / need listed horizontal assembly for wher shaft walls have been moved / need to stop the new shaft walls at the under side of a rated assembly or the underside of the roof deck and now just stop inside of shaft and horizontal shaft liner is attached to side of shaft wall / discussed need for rock on both side of studs at new rated corridor walls at new door - currently no rock on back side | DANE | DANE | | BFR | R | 6092483 |
WELLS & WEST GENERAL CONTRACTORS, INC. | BFR | P | 01/22/2019 | framing at both new entries need to extend through the existing non-rated soffits and extend to the under side of the rated structure above need to be framed per the UL V489 for the American rock that is on site / still need to inspect the shaft liner wall (UL U498 National Gyp) once it has been installed / all other interior light gauge non load bearing framing is OK pending other roughs / discussed accessible elements including need for break room sink to be no higher than 34" to the rim of the sink of counter top - which ever is higher as this is an interior finish and not an interior remodel / still need to attach mechanical permit | DANE | DANE | | BFR | P | 6084980 |
EL PASO ELECTRIC, LLC. | E= | C | 02/26/2019 | | BRET | BRET | | E= | C | 6117515 |
EL PASO ELECTRIC, LLC. | ER | C | 02/21/2019 | ceiling | BRET | BRET | | ER | C | 6112973 |
EL PASO ELECTRIC, LLC. | ER | P | 01/18/2019 | walls lacking proper working space at panel (existing wall built covering 1/4 of panel and boxes) - deemed pre-existing non-conforming. | BRET | BRET | | ER | P | 6082711 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 05/10/2019 | LETTER FROM ENGINEER APPROVING READINGS FOR TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6194551 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 03/28/2019 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. READING FOR FPB-02, FPB-03, FPB-04, FPB-06, FPB-08 HAVE READINGS OUTSIDE THE +/- 10% ALLOWABLE READINGS, TAB FOR VAV-01 STATES THERE ARE TWO ADDITIONAL SUPPLY ADDED TO THIS VAV BUT THE PLAN SPLICE SHOWS THESE ARE FOR THIS VAV BUT THE READINGS ON PLAN SHOW 240 CFM FOR THE TWO NEW 8" SUPPLY AND TAB SAYS DESIGN IS 170 CFM WHICH WOULD PUT THESE OUTSIDE +/- 10%. VAV-04 DOES NOT HAVE ANY FINAL READINGS. VAV-06 TAB SAYS DESIGN IS 425 EACH, PLAN SAYS DESIGN IS 200 AND 250 WHICH WOULD MAKE THESE TWO SUPPLY OUTSIDE +/- 10%. NEED REVISED TEST AND BALANCE REPORT OR ENGINEER TO APPROVE THESE READINGS. | DUSTINS | DUSTINS | | H= | P | 6147061 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 03/27/2019 | PLAN SPLICE NOT ATTACHED TO PERMIT AT THIS TIME TO REVIEW TEST AND BALANCE REPORT READINGS PER NEW PLAN. I WILL RESCHEDULE THIS INSPECTION FOR TOMORROW 3-28-19 AND SEE IF THE PLAN IS ATTACHED TO REVIEW TEST AND BALANCE REPORT. | DUSTINS | DUSTINS | | H= | P | 6145626 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 02/14/2019 | PLAN SPLICE NOT REQUIRED, MISSING SUPPLY DUCTS WERE INSTALLED PER ORIGINAL PLAN. FLEX AND DIFFUSERS OK. MECHANICAL FINAL OK PENDING TEST AND BALANCE REPORT. | DUSTINS | DUSTINS | | H= | P | 6107175 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 02/05/2019 | CONTRACTOR WORKING ON PLANS NOT STAMPED BY PPRBD, NEED PLANS SUBMITTED AND APPROVED. NEW SUPPLY AIR DUCTS OK, OK TO WRAP EXCEPT: MISSING 2 8" SUPPLY AIR FROM VAV 850, MISSING 2 8" SUPPLY AIR FROM VAV 1080, MISSING 1 12" SUPPLY AIR FROM FPB 1350. | DUSTINS | DUSTINS | | HD | P | 6098195 |
NIELSEN MECHANICAL CONTRACTORS, INC. | XMS | P | 03/26/2019 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: delta 2 | DALEH | DALEH | | XMS | P | 6144193 |
WELLS & WEST GENERAL CONTRACTORS, INC. | XBS | T | 02/12/2019 | PAID (REC#1576166) PLAN SPLICE FEE: $50 by: DANM for Construction: Revisions to shaft and Atrium Rating Continuation detail added | DANM | DANM | | XBS | T | 6104874 |