COMMONWEALTH CONSTRUCTION CORPORATION | B= | C | 10/11/2022 | all required paperwork from inspection dated 12/30/20 on file | DANE | DANE | | B= | C | 7546654 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 09/22/2022 | Temp CO: extension ( Expires: 10/22/2022 12:00:00 AM) | JANE | JANE | | B= | P | 7526048 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 06/29/2022 | Temp CO: extension paid 150 1879123 ( Expires: 7/29/2022 12:00:00 AM) | JANE | JANE | | B= | P | 7430154 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 03/23/2022 | Temp CO: extension paid $200 1852667 ( Expires: 4/22/2022 12:00:00 AM) | JANE | JANE | | B= | P | 7311330 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | T | 11/10/2021 | PAID (REC#1837607) Temp CO: Extension pending required finals ( Expires: 12/10/2021 12:00:00 AM) | MATTHEWM | MATTHEWM | | B= | T | 7172958 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | T | 10/08/2021 | PAID (REC#1817962) Temp CO: extension ( Expires: 11/7/2021 12:00:00 AM) | NELIDA | NELIDA | | B= | T | 7134898 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | T | 09/02/2021 | PAID (REC#1804316) Temp CO: extension ( Expires: 10/2/2021 12:00:00 AM) | NELIDA | NELIDA | | B= | T | 7095768 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 08/03/2021 | Temp CO: extension ( Expires: 9/2/2021 12:00:00 AM) | JANE | JANE | | B= | P | 7059099 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 06/18/2021 | Temp CO: extension ( Expires: 7/18/2021 12:00:00 AM) | GITA | GITA | | B= | P | 7007909 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 05/20/2021 | Temp CO: extension ( Expires: 6/19/2021 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 6975146 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | T | 04/07/2021 | PAID (REC#1764565) TCO Extension. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), COMPREHENSIVE MAINTENANCE SOLUTIONS Mechanical Final Inspection is not Completed yet. | GITA | GITA | | B= | T | 6925425 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 04/07/2021 | Temp CO: Extension ( Expires: 5/7/2021 12:00:00 AM) | GITA | GITA | | B= | P | 6925422 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | T | 03/04/2021 | PAID (REC#1754757) tco extension. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), COMPREHENSIVE MAINTENANCE SOLUTIONS Mechanical Final Inspection is not Completed yet. | GITA | GITA | | B= | T | 6889057 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 03/04/2021 | Temp CO: extension ( Expires: 4/3/2021 12:00:00 AM) | GITA | GITA | | B= | P | 6889046 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | T | 01/29/2021 | PAID (REC#1754757) TCO extension. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), COMPREHENSIVE MAINTENANCE SOLUTIONS Mechanical Final Inspection is not Completed yet. | GITA | GITA | | B= | T | 6852871 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 01/29/2021 | Temp CO: extension ( Expires: 2/28/2021 12:00:00 AM) | GITA | GITA | | B= | P | 6852858 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 01/11/2021 | Site visit not needed provide previously requested paperwork for building final. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), COMPREHENSIVE MAINTENANCE SOLUTIONS Mechanical Final Inspection is not Completed yet, IRON HORSE OF COLORADO, LLC Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6831343 |
COMMONWEALTH CONSTRUCTION CORPORATION | BE | T | 12/30/2020 | PAID (REC#1739727) TCO | JANE | JANE | | BE | T | 6821933 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 12/30/2020 | Temp CO: need p, h and b ( Expires: 1/29/2021 12:00:00 AM) | JANE | JANE | | B= | P | 6821930 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | P | 12/30/2020 | Stamped open excavation letter needed, foundation insulation needed, structural evaluation letter for foundation and steel after fire is needed, Complete all required inspections and items from previous Building final inspection. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), COMPREHENSIVE MAINTENANCE SOLUTIONS Mechanical Final Inspection is not Completed yet, IRON HORSE OF COLORADO, LLC Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6821909 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFT | P | 12/29/2020 | Provide open excavation, foundation insulation, and evaluation observation of foundation after fire / letter for original footer, foundation and compaction observation on file. | NATHAN | NATHAN | | BFT | P | 6821063 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/29/2020 | Need structural observation for elements left after the fire, foundation and steel, Training with Adam R2, A occupancy, fire partitions, accessibility. | NATHAN | NATHAN | | BSP | P | 6821016 |
COMMONWEALTH CONSTRUCTION CORPORATION | B= | R | 12/29/2020 | Pending all other required finals / Need all foundation paperwork and 3rd party observations for structural steel and welding / Note- Remove fire caulk around damper in ALL mechanical closets throughout / Unit 102 - Type A Accessible Unit - Missing pipe protection at kitchen sink / Missing transition strip at roll in shower / Unit 103- Type A Accessible Unit - Missing pipe protection at kitchen sink / Missing transition strip at roll in shower / Units 201-304 - Non Accessible Units OK other than fire caulk around damper in mechanical closets / Missing self closing doors for draft stop at roof/ Clubhouse - Missing all door hardware / Remove fire caulk at damper in mechanical closet / Training with PPRBD Inspector Nathan / Reviewed Accessible elements and other final items for A and R Occupancies /. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), External Agency Inspection N= by ENGINEERING is not Completed yet (Contact: City Engineering Inspections 719-385-5977), ADVANCED ELECTRIC, LLC Electrical Final Inspection is not Completed yet, COMPREHENSIVE MAINTENANCE SOLUTIONS Mechanical Final Inspection is not Completed yet, IRON HORSE OF COLORADO, LLC Plumbing Final Inspection is not Completed yet, KIMBEL MECHANICAL SYSTEMS, INC. Plumbing Final Inspection is not Completed yet. | ADAML | ADAML | | B= | R | 6821009 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/18/2020 | 3rd layer rock and rock attachment at L577 clubhouse ceiling ok | TIMOTHYS | TIMOTHYS | | BSP | P | 6813667 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/17/2020 | Clubhouse / 2nd layer drywall installed okay at ceiling ======= except mechanical room . | NATHAN | NATHAN | | BSP | P | 6811522 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/16/2020 | 1st club house, 1st layer and RC at ceiling per L577 | NATHAN | NATHAN | | BSP | P | 6810331 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/15/2020 | 2nd layer drywall at community room perimeter wall per U301 and discussed L577 for ceiling. | NATHAN | NATHAN | | BSP | P | 6808747 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/07/2020 | club house first layer drywall at W10 walls per U301 | NATHAN | NATHAN | | BSP | P | 6798937 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/04/2020 | 1st floor wall and ceiling drywall at apartments completed clubhouse remaining | NATHAN | NATHAN | | BSP | P | 6796781 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/03/2020 | 1st floor unit 103 only okay for drywall screw inspection 101 not ready. | NATHAN | NATHAN | | BSP | P | 6795372 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 12/01/2020 | 1st floor RC at ceiling and walls okay at apartments only. 2nd and 3rd drywall screw inspections at walls and ceiling including all mechanical rooms per U344, U305 and L563 at ceiling | NATHAN | NATHAN | | BSP | P | 6792772 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 11/30/2020 | 2nd floor drywall screw inspection 2 east units not ready, 2 west units except laundry okay . 1st floor RC at east units okay clubhouse not ready. | NATHAN | NATHAN | | BSP | P | 6790973 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 11/25/2020 | 1st floor RC not ready | NATHAN | NATHAN | | BSP | R | 6789575 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 11/24/2020 | 3rd floor all units bathroom walls not ready for drywall waiting on gas ========= 3rd floor drywall screw inspection per P522 at ceiling, U344 breezeway walls, U305 common walls okay | NATHAN | NATHAN | | BSP | P | 6788142 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 11/23/2020 | 2nd floor RC still need dead air space ceilings completed with drywall at ceilings | NATHAN | NATHAN | | BSP | P | 6786372 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 11/20/2020 | 2nd floor unit 201 R/C at ceiling okay, remaining units 202 ,203, 204 not ready also dead air chases need prerocked at ceiling and walls. 3rd floor ceiling at dead air chases need drywall, walls okay at chases. | NATHAN | NATHAN | | BSP | P | 6784846 |
COMMONWEALTH CONSTRUCTION CORPORATION | BIN | P | 11/19/2020 | 1st floor firecaulking at plates and insulation completed at walls | NATHAN | NATHAN | | BIN | P | 6783239 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 11/19/2020 | 2nd floor RC at ceiling not ready | NATHAN | NATHAN | | BSP | R | 6783234 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 11/18/2020 | 1st need all penetrations at plates fire caulked, 3rd floor RC at ceiling okay EXCEPT AT MISSING HEAT VENTS. | NATHAN | NATHAN | | BFR | P | 6780890 |
COMMONWEALTH CONSTRUCTION CORPORATION | BIN | P | 11/12/2020 | 1st floor apartment units only walls and rim / still need clubhouse area frame and MEP's . 2nd floor walls and rim okay 3rd floor okay all walls and rim. | NATHAN | NATHAN | | BIN | P | 6775019 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 11/10/2020 | 1st floor exterior walls only with completed required inspections, FC, hold downs and framing. 3rd floor breezeway RC okay | NATHAN | NATHAN | | BFR | P | 6771308 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 10/28/2020 | 2nd floor with completed required inspections frame okay 3rd floor frame items corrected 2nd and 3rd floor breezeway drywall per U344 okay. | NATHAN | NATHAN | | BFR | P | 6756872 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 10/27/2020 | 2nd floor straps at top plates, collars at 4" pipes, remaining frame items okay. | NATHAN | NATHAN | | BFR | P | 6755888 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 10/19/2020 | Units 301, 303 lateral brace R08, R12, R13 , add lumber behind hangers at R02 to R20 girder, need collar at 4" pipes, gypcrete dead air chase floors, missing entry door holddowns, Unit 302,304 Lateral brace on R08, R12,R13, add lumber behind hangers at R02 to R20 girder, need collar at 4" pipes, Gypcrete at dead air spaces, 3th floor prerock at all shower/tub spaces okay. 2nd and 1st RC at tub/shower space okay. | NATHAN | NATHAN | | BFR | P | 6746781 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 10/13/2020 | exterior straps and sheer okay, 3rd floor RC at bathroom walls and okay to RC ceiling. | NATHAN | NATHAN | | BFR | P | 6740288 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | P | 09/22/2020 | Preliminary walk of rated walls and construction for Building 2 discussed back to back boxes Dryer box ratings and prerock. | NATHAN | NATHAN | | BFR | P | 6715239 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 08/13/2020 | 1st floor drywall at corridor west side per U344 and 2nd layer east side of W10 U301 okay | NATHAN | NATHAN | | BSP | P | 6672263 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 08/12/2020 | 1st layer east side of W10 per U301 and hold downs and bolting with frame at W9 U344 corridor wall. | NATHAN | NATHAN | | BSP | P | 6670832 |
COMMONWEALTH CONSTRUCTION CORPORATION | B16 | P | 06/05/2020 | Per contractor letter in images file, all previous inspection history for Nathan except the foundation elements have been updated to rejection previous to this date. | BERTW | BERTW | | B16 | P | 6595195 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 06/04/2020 | discussed fire damage wrecking requirements for rebuild .Updated on 6/5/2020 to a R | NATHAN | NATHAN | | BSP | R | 6594329 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFR | R | 04/28/2020 | frame and firecaulk behind tub/shower walls only okay all units, discussed rated walls and continuity at clubhouse.Updated on 6/5/2020 to a R | NATHAN | NATHAN | | BFR | R | 6554739 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 04/21/2020 | breezeway drywall attachment okay 1-3Updated on 6/5/2020 to a R | NATHAN | NATHAN | | BSP | R | 6547217 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 04/15/2020 | Need drywall of W10 U301 wall to go through floor ceiling assembly to bottom of floor sheathing of 2nd floor, 2nd layer drywall attachment at interior side of corridor okayUpdated on 6/5/2020 to a R | NATHAN | NATHAN | | BSP | R | 6542014 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 04/09/2020 | fire separation wall first layer at club house per U301. east wall west face.Updated on 6/5/2020 to a R | NATHAN | NATHAN | | BSP | R | 6535810 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | R | 10/02/2019 | trusses pending still on plans, all foundation paperwork to follow. discussed with Mike. Updated on 6/5/2020 to a R | NATHAN | NATHAN | | BSP | R | 6354519 |
COMMONWEALTH CONSTRUCTION CORPORATION | BSP | P | 08/19/2019 | over excavation still being completed / plans are still marked trusses pending | NATHAN | NATHAN | | BSP | P | 6306162 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFN | P | 07/29/2019 | Authorized 3rd party engineer inspection with all observation paperwork to follow / | NATHAN | NATHAN | | BFN | P | 6280485 |
COMMONWEALTH CONSTRUCTION CORPORATION | BFT | P | 07/29/2019 | Authorized 3rd party engineer inspection with all observation paperwork to follow / | NATHAN | NATHAN | | BFT | P | 6280484 |
COMMONWEALTH CONSTRUCTION CORPORATION | BE | L | 07/24/2019 | Renewed for No Fee at 7/24/2019 10:17:56 AM | JLANE | JLANE | | BE | L | 6274742 |
ADVANCED ELECTRIC, LLC | ES | C | 12/29/2020 | Commercial Service: 800A 3w 120 / 240V service ok / no action required, all meters have been installed / | MIGUEL | MIGUEL | | ES | C | 6821113 |
ADVANCED ELECTRIC, LLC | E= | C | 12/29/2020 | corrections in club house made / all A/Cs 25A / pole lights ok / | MIGUEL | MIGUEL | | E= | C | 6821112 |
ADVANCED ELECTRIC, LLC | EP | C | 12/28/2020 | all 100A sub panels ok / | MIGUEL | MIGUEL | | EP | C | 6819772 |
ADVANCED ELECTRIC, LLC | E= | P | 12/28/2020 | club house wall heaters require disconnect switch at unit or breaker lock / GFCI for fountain can not be behind unit / all A/Cs require 25A min breaker, 20A currently installed / | MIGUEL | MIGUEL | | E= | P | 6819770 |
BW ELECTRIC, INC. | E= | C | 12/23/2020 | FIRE ALARM INSPECTION: | LOGANP | LOGANP | | E= | C | 6818043 |
ADVANCED ELECTRIC, LLC | E= | P | 12/23/2020 | Clubhouse not ready / | LOGANP | LOGANP | | E= | P | 6818041 |
ADVANCED ELECTRIC, LLC | E= | P | 12/22/2020 | Corrections made in 201 -- 202 -- 203 -- 204 -- / Units 102 & 103 ok / all units have 20-amp A/C breakers / 1st & 2nd floor corridors ok / | LOGANP | LOGANP | | E= | P | 6816199 |
ADVANCED ELECTRIC, LLC | E= | R | 12/21/2020 | Units 201-- 202 -- 204 Bath fan runs all the time / 203 Bath fan is buried / 204 Bath fan switches with lights / | LOGANP | LOGANP | | E= | R | 6815399 |
ADVANCED ELECTRIC, LLC | E= | P | 12/17/2020 | Units 301 -- 302 -- 303 -- 304 --3rd floor corridor ok / All have 20a A/C circuit breakers / | LOGANP | LOGANP | | E= | P | 6811080 |
ADVANCED ELECTRIC, LLC | EUG | C | 11/18/2020 | S. pole lights ok / | MIGUEL | MIGUEL | | EUG | C | 6780774 |
ADVANCED ELECTRIC, LLC | ER | P | 11/18/2020 | club house ok / | MIGUEL | MIGUEL | | ER | P | 6780772 |
ADVANCED ELECTRIC, LLC | ES | P | 11/04/2020 | Commercial Service: 800A 3w service ok up to main / ok to energize / | MIGUEL | MIGUEL | | ES | P | 6765512 |
ADVANCED ELECTRIC, LLC | ER | P | 11/03/2020 | units 102 and 103 ok / | MIGUEL | MIGUEL | | ER | P | 6763063 |
ADVANCED ELECTRIC, LLC | EUG | P | 10/30/2020 | N. and E PVC for pole lights ok / | MIGUEL | MIGUEL | | EUG | P | 6759831 |
ADVANCED ELECTRIC, LLC | ES | P | 10/21/2020 | Commercial Service: Need work permit from utility to install service feeder conductors to transformer / | LOGANP | LOGANP | | ES | P | 6750124 |
ADVANCED ELECTRIC, LLC | ER | P | 10/21/2020 | Need to install house panel / | LOGANP | LOGANP | | ER | P | 6750121 |
ADVANCED ELECTRIC, LLC | ER | P | 10/19/2020 | all 2nd floor units--ok / | BRIAN | BRIAN | | ER | P | 6746218 |
ADVANCED ELECTRIC, LLC | ER | P | 10/15/2020 | 202 ok, #6AL range, 1/0 AL panel / | MIGUEL | MIGUEL | | ER | P | 6743293 |
BW ELECTRIC, INC. | ER | P | 10/14/2020 | FIRE ALARM INSPECTION: FA in all units and community center ok / lacking riser room / | MIGUEL | MIGUEL | | ER | P | 6741281 |
ADVANCED ELECTRIC, LLC | ER | P | 10/14/2020 | 3rd floor corridor lid ok / 1st floor sconces next to stairs ok / 1st floor closet walls ok / | MIGUEL | MIGUEL | | ER | P | 6741262 |
BW ELECTRIC, INC. | ER | R | 10/12/2020 | FIRE ALARM INSPECTION: 301,302,303,304, add mudrings to boxes / cable ok / | MIGUEL | MIGUEL | | ER | R | 6738632 |
ADVANCED ELECTRIC, LLC | ER | P | 10/12/2020 | 301,302,303,304 ok / typical #6 AL to range, 1/0 AL to panel / Electrical wall rough ok, FA not complete,-------- do not close walls-------------- / | MIGUEL | MIGUEL | | ER | P | 6738631 |
ADVANCED ELECTRIC, LLC | ES | R | 06/23/2020 | temporary service requires own permit / 100A 3w service ok / | MIGUEL | MIGUEL | | ES | R | 6614655 |
ADVANCED ELECTRIC, LLC | EUG | R | 06/19/2020 | underground from transformer to pedestal is a CSU inspection / | MIGUEL | MIGUEL | | EUG | R | 6610751 |
ADVANCED ELECTRIC, LLC | ESP | P | 06/08/2020 | Per contractor letter in images file, all previous inspection history for Brian and Miguel have been updated to rejection previous to this date. | DEAN | DEAN | | ESP | P | 6596192 |
ADVANCED ELECTRIC, LLC | ES | R | 04/17/2020 | Commercial Service: 800A 3w new service ok to energize and set all meters for house panel, 102,103,201,202,203,204,301,302,303,304 / all panels are 100A / RBD Notes: one-line needs to match plans: 1/0 AL MC cable feeding sub panels, 250AL GEC to cold water, 3 sets of 350AL service conductors not 400AL / need to expose rebar and attach ufer #4 ufer / | MIGUEL | MIGUEL | | ES | R | 6544321 |
BW ELECTRIC, INC. | E= | R | 04/13/2020 | FIRE ALARM INSPECTION: not ready / | MIGUEL | MIGUEL | | E= | R | 6538774 |
BW ELECTRIC, INC. | ER | R | 04/13/2020 | FIRE ALARM INSPECTION: install mudrings on ceiling boxes in club house, boxes flush with bottom of rafters / install KO filler in 303 / still need riser room / | MIGUEL | MIGUEL | | ER | R | 6538768 |
BW ELECTRIC, INC. | E= | R | 12/18/2019 | FIRE ALARM INSPECTION: wrong address called in for insp / still need framing complete / | BRIAN | BRIAN | | E= | R | 6431301 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | C | 10/10/2022 | MECHANICAL CONTRACTOR COMPLETE. | PAULO | PAULO | | H= | C | 7545573 |
WESTERN PEAK PLUMBING LLC | H= | C | 10/07/2022 | FINAL FOR MECHANICAL CONTRACTOR | BILLS | BILLS | | H= | C | 7543120 |
WESTERN PEAK PLUMBING LLC | H= | P | 10/03/2022 | received photos of East side furnace & A/C corrections (SEE IMAGES). FINAL PENDING CONTRACTOR ADDRESSING THE FOLLOWING-- STILL NEED WEST FURNACE VENT TO BE PRIMER & GLUED TO FURNACE VENT COLLARS, PLUG ALL OPEN CONDENSATE DRAINS AT COIL CABINET NOT USED, COMPLETELY INSULATE AND SEAL LINE SET SUCTION LINES FROM CEILING TO COIL CABINET, CORRECT SIZED FURNACE FILTER FOR WEST SIDE FURNACE (WILL NEED AN ON SITE INSPECTION FOR CORRECTIONS). | PAULO | PAULO | | H= | P | 7537009 |
WESTERN PEAK PLUMBING LLC | H= | P | 09/27/2022 | FINAL PENDING CONTRACTOR ADDRESSING THE FOLLOWING-- BOTH FURNACE VENTS TO BE PRIMER & GLUED TO FURNACE VENT COLLARS, PLUG ALL OPEN CONDENSATE DRAINS AT BOTH COIL CABINETS NOT USED, COMPLETELY INSULATE AND SEAL BOTH LINE SET SUCTION LINES FROM CEILING TO COIL CABINET, CORRECT SIZED FURNACE FILTER FOR WEST SIDE FURNACE (WILL NEED AN ON SITE INSPECTION FOR CORRECTIONS). | PAULO | PAULO | | H= | P | 7531074 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 08/19/2022 | ADDED NOTES 8/23/22: LETTER RECEIVED FOR SHUTDOWNS CAN BE ACCEPTED AS THE LETTER FOR CRD's IS FROM THE ARCHITECT ENGINEER OF RECORD. CONTRACTOR STILL NEEDS RETURNS TIED IN, GAS TIED IN TO FURNACES IN CLUBHOUSE, LOCK BOXES FOR THERMOSTATS IN CLUBHOUSE,NEED CONDENSERS COMPLETED AND LABELED. | PAULO | PAULO | | H= | P | 7488438 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | R | 07/01/2022 | CALL AHEAD AT 11:25, NO ACCESS (LOCKED) TO MECHANICAL ROOM, NO CONTRACTOR ON SITE, LEFT AT 12:00. | PAULO | PAULO | | H= | R | 7433270 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 02/09/2022 | NOT READY/TOO MANY TO LIST, REVIEWING ALL NOTES FOR UPDATES (SPLICES) AND ANY UN-INSPECTED ITEMS AND LOOSE ENDS/WILL UPDATE WHEN DONE. | PAULO | PAULO | | H= | P | 7264583 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 01/13/2021 | INSPECTION TODAY WAS FOR CLUBHOUSE FURNACE SUPPLY TIE INS, STILL NEED RETURNS TIED IN, GAS TED IN TO FURNACES IN CLUBHOUSE, LOCK BOXES FOR THERMOSTATS IN CLUBHOUSE,NEED CONDENSERS COMPLETED AND LABELED, AND ALL PLAN REVISIONS FROM PREVIOUS NOTES ADDRESSED | BENH | BENH | | H= | P | 6834858 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 01/08/2021 | INSPECTION TODAY WAS FOR 2ND FLOOR UNITS AND 1ST FLOOR UNITS, AND VENTS INSULATED IN ATTIC FOR 3 RD FLOOR UNITS, STILL NEED CLUBHOUSE COMPLETED, NEED CONDENSERS LABELED AND LINE SETS COMPLETED, NEED EXHAUST FAN FOR JANITOR ROOM IN CLUBHOUSE DELETED ON PLANS, NEED REVISED PLANS FOR RELOCATED RETURNS AND DELETED BOOSTER FANS, NEED REVISED EQUIPMENT SCHEDULE, NEED OUTSIDE AIR DELETED FROM PLANS OR INSTALLED FOR CLUBHOUSE | BENH | BENH | | H= | P | 6830062 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 01/07/2021 | ALL 3RD FLOOR UNITS ARE OK EXCEPT FURNACE VENTS NEED TO INSULATED IN ATTIC, STILL NEED TO ADDRESS ALL OTHER PREVIOUS ITEMS FROM INSPECTION DATED 12/29/20 | BENH | BENH | | H= | P | 6828631 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 01/06/2021 | ALL 3RD FLOOR UNITS NEED FIRE DAMPER LABELING, NEED TO REMOVE FIRE CAULK AROUND SUPPLY PLENUMS, NEED MAKE UP AIR TO ALL LAUNDRY ROOMS, NEED TO LABEL ALL DRYER VENT LENGTHS ON DRYER BOX, NEED TO INSULATE ALL VENTS IN ATTIC | BENH | BENH | | H= | P | 6827395 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | H= | P | 12/29/2020 | NEEDED FOR FINAL: NEED TO ADDRESS GAPS AROUND PLENUMS IN MECHANICAL ROOM FROM SHEET ROCK TO CRDS, NEED TO COMPLETE SUPPLY AND RETURN DUCT IN CLUBHOUSE MECHANICAL ROOM, MISSING OUTSIDE AIR LOUVER AND DUCT FOR CLUBHOUSE , NEED TO CHANGE BIRDSCREEN TO A FLAPPER ON EXHAUST TERMINATIONS NEED ACCESS DOORS INSTALLED IN ALL SUPPLY PLENUMS IN ALL MECHANICAL ROOMS AND LABELED, NEED TO COMPLETE ALL CONDENSATE DRAINS FOR FURNACE VENTS AND A/C'S WITH SECONDARY PROTECTION, NEED TO INSULATE ALL REFRIGERANT LINES IN MECHANICAL ROOMS, NEED MAKE UP AIR GRILLES INSTALLED TO ALL LAUNDRY ROOMS, NEED STICKERS INSTALLED AT DRYER BOX SHOWING THE LENGTHS OF DRYER VENTS, NEED ALL CONDENSERS TIED INTO LINE SETS AND LABELED,NEED REVISED PLANS FOR DELETED BOOSTER FANS AND RELOCATED RETURNS, NEED ENGINEER TO ADDRESS SHUTDOWNS OF ALL UNITS SINCE CRD ARE STATIC ONLY AND SYSTEM IS DYNAMIC, NEED REVISED EQUIPMENT SCHEDULE SINCE SECOND FLOOR IS USING GOODMAN AND 1ST AND 3RD FLOORS ARE USING RHEEM | BENH | BENH | | H= | P | 6821625 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | P | 12/28/2020 | NEED TO INSULATE ALL RHEEM VENTS ON 3RD FLOOR IN ATTIC, ALL SECOND FLOOR UNITS HAVE BEEN SWITCHED BACK TO GOODMAN AND FALL WITHIN GOODMANS VENTING GUIDELINE THEREFORE VENTS WILL NOT NEED TO BE CHANGED OUT TO 3" FROM 2", NEED TO COMPLETE VENTS TO FURNACES IN CLUB HOUSE | BENH | BENH | | HV | P | 6820391 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/28/2020 | STILL NEED TO ADDRESS GAPS AROUND PLENUMS IN MECHANICAL ROOM FROM SHEET ROCK TO CRDS, NEED TO COMPLETE SUPPLY AND RETURN DUCT IN CLUBHOUSE MECHANICAL ROOM, MISSING OUTSIDE AIR LOUVER AND DUCT FOR CLUBHOUSE , NEED TO CHANGE BIRDSCREEN TO A FLAPPER ON EXHAUST TERMINATIONS NEEDED FOR FINAL: NEED ACCESS DOORS INSTALLED IN ALL SUPPLY PLENUMS IN ALL MECHANICAL ROOMS AND LABELED, NEED TO COMPLETE ALL CONDENSATE DRAINS FOR FURNACE VENTS AND A/C'S WITH SECONDARY PROTECTION, NEED TO INSULATE ALL REFRIGERANT LINES IN MECHANICAL ROOMS, NEED MAKE UP AIR GRILLES INSTALLED TO ALL LAUNDRY ROOMS, NEED STICKERS INSTALLED AT DRYER BOX SHOWING THE LENGTHS OF DRYER VENTS, NEED ALL CONDENSERS TIED INTO LINE SETS AND LABELED,NEED REVISED PLANS FOR DELETED BOOSTER FANS AND RELOCATED RETURNS, NEED ENGINEER TO ADDRESS SHUTDOWNS OF ALL UNITS SINCE CRD ARE STATIC ONLY AND SYSTEM IS DYNAMIC, NEED REVISED EQUIPMENT SCHEDULE SINCE SECOND FLOOR IS USING GOODMAN AND 1ST AND 3RD FLOORS ARE USING RHEEM | BENH | BENH | | HD | P | 6820331 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | P | 12/22/2020 | FURNACE MANUFACTURER HAS BEEN CHANGED FROM GOOD MAN TO RHEEM AND WILL NEED TO REFLECT THAT AND BTU CHANGE ON EQUIPMENT SCHEDULE, ALL VENTS IN ATTIC NEED TO BE INSULATED PER MANUFACTURERS INSTRUCTIONS, 2" VENTS ARE ONLY ALLOWED TO HAVE MAXIMUM OF 20 FEET WITH 2 ELBOWS, CONTINUE AT YOUR OWN RISK | BENH | BENH | | HV | P | 6817614 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/22/2020 | NEED ENGINEER TO ADDRESS SHUTDOWN OF FURNACES SINCE CRDS ARE STATIC ONLY AND SYSTEM IS DYNAMIC, NEED REVISED EQUIPMENT SCHEDULE SINCE EQUIPMENT SUBMITTED WAS GOODMAN AND RHEEM IS INSTALLED AND ALSO SHOW NEW BTU INPUT FOR FURNACES SINCE THEY'VE BEEN CHANGED TO 84K, NEED PLAN REVISION FOR RELOCATED RETURNS AND DELETED BOOSTER FANS,NEED CRD'S INSTALLED IN SUPPLY AND RETURN DUCTS IN MECHANICAL ROOM IN CLUBHOUSE, THERMOSTATS IN CLUBHOUSE TO TERMINATE NO HIGHER THAN 48" ABOVE FLOOR, NEED FIRE CAULKING REMOVED AROUND SUPPLY PLENUMS IN ALL UNITS IN MECHANICAL ROOMS, NEED SUPPLY PLENUMS TIED INTO FURNACES AND ACCESS DOORS INSTALLED AND LABELED, NEED CONDENSATE DRAINS COMPLETED FOR FURNACE AND A/C AND SECONDARY PROTECTION FOR CONDENSATES ON 2ND AND 3RD FLOOR, NEED MAKE UP AIR TO LAUNDRY ROOM COMPLETED, LABEL ALL CONDENSERS | BENH | BENH | | HD | P | 6817612 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | P | 12/21/2020 | NEED TO INSULATE ALL EXHAUST IN ATTIC FOR FURNACE VENTS AND COMPLETE CONCENTRICS ON ROOF, ALL VENTS ARE TIED IN TO FURNACES | BENH | BENH | | HV | P | 6815783 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/21/2020 | NEED FIRE CAULKED REMOVED AROUND SUPPLY PLENUMS IN MECHANICAL ROOMS , MISSING MAKE UP AIR FOR ALL LAUNDRY ROOMS, NEED ALL PLENUMS TIED INTO FURNACES, LINE SET BRAZED IN , SECONDARY PROTECTION FOR A/C COILS, CONDENSATE DRAINS COMPLETED, | BENH | BENH | | HD | P | 6815781 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | T | 12/21/2020 | PAID (REC#1738151) AFTER-HOURS INSPECTION: $200 From: NELIDA per Jack | NELIDA | NELIDA | | HV | T | 6815372 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | T | 12/21/2020 | PAID (REC#1738150) AFTER-HOURS INSPECTION: $200 From: NELIDA per Jack | NELIDA | NELIDA | | HV | T | 6815365 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | T | 12/21/2020 | PAID (REC#1738148) AFTER-HOURS INSPECTION: $200 From: NELIDA per Jack | NELIDA | NELIDA | | HV | T | 6815351 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HSP | P | 12/21/2020 | INSPECTION TODAY WAS FOR CONSULTATION FOR GAPS AROUND SUPPLY PLENUMS IN MECHANICAL ROOMS AND AFTER DISCUSSION WITH BUILDING INSPECTOR FIRE CAULKING IS NOT ALLOWED TO BE BETWEEN DUCT AND SHEET ROCK DUE TO FIRE CAULKING EXPANDING DURING FIRE AND NOT ALLOWING DAMPER TO CLOSE, ENGINEER TO ADDRESS, ALSO STILL NEED SHUTDOWNS FOR ALL UNITS ADDRESSED SINCE DAMPERS ARE STATIC ONLY AND SYSTEM IS DYNAMIC | BENH | BENH | | HSP | P | 6814570 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/16/2020 | ENGINEER TO ADDRESS CRD'S FOR CLUBHOUSE , CONTINUE AT YOUR OWN RISK , NEED PLAN REVISION FOR DELETED EXHAUST FAN IN MECHANICAL ROOM AREA ALSO FOR 14" ROUND TRUNKLINE THAT WAS CHANGED TO SQUARE, ENGINEER TO ADDRESS SHUTDOWNS OF SYSTEM SINCE DAMPERS ARE STATIC AND SYSTEM IS DYNAMIC ,INSPECTION TODAY WAS FOR CLUBHOUSE(ONLY) ANNULAR SPACE AROUND CRD'S ON 1ST LAYER OF ROCK, WILL NEED TO SEE CRD'S AFTER 3RD LAYER OF SHEETROCK IS INSTALLED BEFORE GRILLES ARE ON SO I CAN MAKE SURE DAMPERS ARE IN LISTING, STILL NEED PLENUM CRD'S INSTALLED IN MECHANICAL ROOM IN CLUBHOUSE, NEED FURNACES IN PLACE AND ALL TIE INS COMPLETE FOR CLUBHOUSE | BENH | BENH | | HD | P | 6810425 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | T | 12/16/2020 | PAID (REC#1737083) AFTER-HOURS INSPECTION: $200 From: TERRI 12/16/20 4PM | TERRI | TERRI | | HD | T | 6809278 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/14/2020 | ENGINEER TO ADDRESS UL 577 LISTING FOR CRD'S, NEED PLAN REVISION FOR SQUARE TRUNKLINE IN JOIST FOR CLUBHOUSE SINCE PLANS CALL FOR 14" ROUND, OUTSIDE AIR LOUVER IS NOT INSTALLED YET AND DUCT WORK ISN'T COMPLETED, CONTRACTOR TO PROCEED AT OWN RISK | BENH | BENH | | HD | P | 6806559 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HSP | P | 12/11/2020 | HAD CONSULTATION WITH CONTRACTOR AND G.C. ABOUT CLUBHOUSE HAS NOT BEEN LOOKED AT ALL AND WILL REQUIRE COMPLETE INSPECTION BEFORE SHEET ROCK IS INSTALLED , CRD GAPS BETWEEN DUCT AND SHEET ROCK IS MAXIMUM 1/8" ALLOWABLE GAP AND ENGINEER WILL NEED TO ADDRESS IF GAPS ARE BIGGER THAN 1/8", FURNACES ARE GETTING CHANGED TO RHEEM AND THAT WILL NEED TO REFLECT THAT ON EQUIPMENT SCHEDULE AND DRAIN PANS ARE REQUIRED UNDERNEATH FURNACES THAT ARE ON 2ND AND 3RD LEVELS PER RHEEM AND VENTS IN ATTIC WILL REQUIRE INSULATION ON EXHAUST VENT, | BENH | BENH | | HSP | P | 6805249 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/08/2020 | INSPECTION TODAY WAS FOR PLENUM CRD'S ABOVE FURNACE IN UNITS 301,302,303,AND 304 NEED LETTER FROM CRD MANUFACTURER OR PROPER INSTRUCTIONS ALLOWING SUPPORT FOR CRD TO BE SCREWED INTO BOTTOM OF TRUSSES, CONTINUE AT YOUR OWN RISK, ALSO FURNACE VENTS ARE BEING REROUTED AND WILL REQUIRE ANOTHER VENT INSPECTION FOR ALL VENTS | BENH | BENH | | HD | P | 6799831 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HSP | P | 12/07/2020 | HAD CONSULTATION ABOUT DAMPER INSTALLATION ABOVE FURNACES AND WILL NEED TO INSTALL PER MANUFACTURERS INSTRUCTIONS, CONTRACTOR TO ADDRESS INSTALLATION OF CRD'S AND DUCT DESIGN OF CLUBHOUSE | BENH | BENH | | HSP | P | 6798254 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HC | C | 12/03/2020 | RELEASE METER 11 METERS THANKS | BENH | BENH | | HC | C | 6795230 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HI | C | 12/03/2020 | | BENH | BENH | | HI | C | 6795224 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/02/2020 | INSPECTION WAS FOR 3RD FLOOR UNITS FOR ANNULAR SPACING AROUND SUPPLY BOOTS BEFORE REGISTER IS INSTALLED, INSTALLATION OK, STILL NEED CRD INSTALLED IN ALL SUPPLY PLENUMS ABOVE FURNACE IN ALL UNITS WITH INSTALLATION INSTRUCTIONS AT TIME OF INSPECTION | BENH | BENH | | HD | P | 6794116 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HI | P | 12/02/2020 | NEED CORRECT STRIKER PLATES INSTALLED FOR CSST GAS LINES IN ALL UNITS ON WEST TOWER IN MECHANICAL ROOMS | BENH | BENH | | HI | P | 6794098 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 12/01/2020 | 3RD FLOOR SUPPLY BOOT CEILING RADIATION DAMPER ANNULAR SPACING : CONTRACTOR MUST HAVE CRD DAMPER INSTALL INSTRUCTIONS ON SITE FOR INSPECTION. IF ANNULAR SPACING AROUND CRD DAMPER EXCEEDS THE MAXIMUM ALLOWED BY THE MANUFACTURER THE ENGINEER WILL NEED TO ADDRESS / | LIDO | LIDO | | HD | P | 6792269 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HI | P | 12/01/2020 | 1ST FLOOR - SUPPORT CSST TRAC PIPE AT LEAST 2" ABOVE BOTTOM OF FLOOR JOIST OR INSTALL SHIELDING ( Striker plate ) PER CSST INSTALL INSTRUCTION PAGE #35. CSST INSTALLED ABOVE UNITS 102 AND 103 WAS COVERED PRIOR TO BEING INSPECTED. INSTALL STRIKER PLATE AT TOP OF WALL IN CLUB HOUSE AREA MECHANICAL ROOM / 2ND AND 3RD FLOOR -SHEET ROCK WAS PUT ON WALLS PRIOR TO BEING INSPECTED. REMOVE SHEET ROCK FOR INSPECTION . RE INSPECT ALL GAS INSTALL . A NEW PRESSURE TEST IS ALSO REQUIRED (Fyi- 10 lbs on a 30 lb gauge) | LIDO | LIDO | | HI | P | 6792257 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 11/30/2020 | NOT READY / FIELD CANCELED BY MECHANICAL CONTRACTOR ( David) / | LIDO | LIDO | | HD | P | 6790435 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HI | P | 11/30/2020 | NOT READY / FIELD CANCELED BY MECHANICAL CONTRACTOR ( David) / | LIDO | LIDO | | HI | P | 6790429 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HRP | P | 11/23/2020 | ALL LINE SET PRESSURE TEST OK ON EAST AND WEST TOWERS EXCEPT UNIT 204 ON EAST TOWER IT IS SITTING AT 0 PSI | BENH | BENH | | HRP | P | 6785485 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | P | 11/20/2020 | QUESTIONING VENT HEIGHT PROTRUDING THROUGH WALL IN ALL MECHANICAL ROOMS, LABELING OF CONCENTRIC VENT PIPE IS BACKWARDS IN MECHANICAL ROOM | BENH | BENH | | HV | P | 6783708 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 11/20/2020 | STILL NEED PLAN REVISION FOR DELETED BOOSTER FANS FOR DRYER VENTS AND RELOCATED RETURNS,INSPECTION TODAY WAS FOR 3RD FLOOR UNITS 301,302,303,304, ABOVE CEILING SUPPLY AND EXHAUST AND DRYER VENT OK, NEED TO INSULATE ALL SUPPLY PLENUMS IN ATTIC IN ALL UNITS, STILL NEED CRD'S INSTALLED FOR ALL SUPPLY PLENUMS IN MECHANICAL ROOMS IN ALL UNITS ON WEST TOWER WITH INSTALLATION INSTRUCTIONS FOR CRD'S, STILL NEED HRP INSPECTION COMPLETED FOR ALL UNITS ON WEST TOWER BEFORE SHEET ROCK IS COMPLETED | BENH | BENH | | HD | P | 6783697 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 11/19/2020 | NEED REVISED PLANS FOR DELETED BOOSTER FANS AND RELOCATED RETURNS, INSPECTION TODAY WAS FOR ABOVE CEILING DUCT IN UNITS 102, 103, 201,202,203, AND 204, UNIT 102: NEED NAIL PROTECTION FOR DRYER VENT, DRYER VENT HAS EXCEEDED 35 FOOT LIMIT IN ALL UNITS , PLEASE PROVIDE DRYER VENT LENGTH ALLOWED FROM DRYER MANUFACTURER, UNIT 103: NEED NAIL PROTECTION FOR LINE SET, OK TO INSULATE TRUNK LINES IN UNITS 102,103,201,202,203,204, CRD ARE NOT INSTALLED IN ALL UNITS ON WEST TOWER ABOVE FURNACE, WILL NEED TO SEE THOSE INSTALLED BEFORE SHEET ROCK IS INSTALLED IN MECHANICAL ROOM, | BENH | BENH | | HD | P | 6782187 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HV | P | 11/19/2020 | QUESTIONING VENT HEIGHT TERMINATION IN MECHANICAL ROOM IN RELATION TO PITCH TO FURNACE, ALL HORIZONTAL RUNS NEED TO BE SUPPORTED EVERY 4 FEET, WILL NEED TO REINSPECT VENTS IN UNITS 102,103, 201,202,203, 204, HAVE NOT INSPECTED VENTS ON 3RD FLOOR WEST TOWER, OR EAST TOWER | BENH | BENH | | HV | P | 6782142 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 11/19/2020 | RECEIVED LETTER FROM ARCHITECT APPROVING DAMPERS FOR THIS LISTING, ALSO RECEIVED INSTALLATION INSTRUCTIONS FOR BROAN EXHAUST FANS, SEE IMAGES | BENH | BENH | | HD | P | 6781929 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 11/18/2020 | NEED GAS CONTRACTOR TO ATTACH TO PERMIT AND CALL FOR INSPECTION, NEED STAMPED LETTER FROM ENGINEER APPROVING DAMPERS FOR THIS LISTING, WILL ALSO NEED ENGINEER TO ADDRESS SHUTDOWN OF UNITS SINCE DAMPERS ARE STATIC ONLY AND SYSTEM IS DYNAMIC,INSPECTION TODAY WAS FOR UNIT 204, SUPPORT DRYER VENT EVERY 4 FEET, QUESTIONING INSTALLATION OF EXHAUST FAN CEILING RADIATION DAMPER, PROVIDE INSTALLATION INSTRUCTIONS FOR CEILING RADIATION DAMPERS, NEED REVISED PLANS FOR RELOCATED RETURNS AND DELETED BOOSTER FANS FOR DRYER VENT, PLAN IS FOR UNIT TYPE #16 | BENH | BENH | | HD | P | 6781010 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 11/10/2020 | GAS CONTRACTOR MUST ATTACH TO THE PERMIT / 2ND FLOOR UNIT #204 CONSULT - LLOYD CEILING RADIATION DAMPER IS APPROVED FOR FLOOR / CEILING ASSEMBLY UL L563. DAMPER MUST BE INSTALLED PER THE MANUFACTURER REQUIREMENTS / 26 GAUGE IS THE MINIMUM GAUGE THE DUCT CAN BE INCLUDING THE SUPPLY BOOT THAT THE CEILING RADIATION DAMPER IS BEING INSTALLED IN / BROAN CEILING RADIATION DAMPER IS NOT APPROVED FOR UL L563 LISTED ASSEMBLY. ENGINEER TO ADDRESS / CONTRACTOR TO PROVIDE INFORMATION ON CEILING RADIATION DAMPER ABOVE FURNACE FOR CONSULT / ROOF/CEILING ASSEMBLY P522 - BROAN RDM2 CEILING RADIATION DAMPER IS APPROVED FOR THE UL P-522 LISTING. LLOYD IS NOT. ENGINEER TO ADDRESS / | LIDO | LIDO | | HD | P | 6771020 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HRP | P | 11/10/2020 | FIELD CANCELED BY CONTRACTOR. NOT READY. | LIDO | LIDO | | HRP | P | 6770998 |
COMPREHENSIVE MAINTENANCE SOLUTIONS LLC | HD | P | 10/28/2020 | CONSULT ON INSPECTION PROCESS / NEED INSTALL INSTRUCTIONS FOR FURNACES TO INSPECT VENTS / NEED CEILING RADIATION DAMPER INSTALL INSTRUCTIONS PROVIDED FOR DAMPER CONSULT / | LIDO | LIDO | | HD | P | 6756404 |
IRON HORSE OF COLORADO, LLC | P= | C | 01/11/2021 | Drinking Fountain complete. | SAMH | SAMH | | P= | C | 6831938 |
IRON HORSE OF COLORADO, LLC | P= | P | 12/30/2020 | Inspected Community area. Complete Drinking Fountain. ( Unit is on Backorder from supplier.) | SAMH | SAMH | | P= | P | 6822801 |
IRON HORSE OF COLORADO, LLC | P= | P | 12/29/2020 | Complete excluding Community area, and Mop sink faucet. | SAMH | SAMH | | P= | P | 6821144 |
IRON HORSE OF COLORADO, LLC | P= | P | 12/23/2020 | 2nd and 3rd floors complete excluding Dishwasher high loops. | SAMH | SAMH | | P= | P | 6818584 |
IRON HORSE OF COLORADO, LLC | PTO | C | 10/27/2020 | Check Mechanical room at final. AAV at kitchen sinks. Verify access panels for unit main shut off valves. | SAMH | SAMH | | PTO | C | 6755260 |
IRON HORSE OF COLORADO, LLC | PTO | P | 10/23/2020 | 3rd floor complete excluding tubs, flanges, and nail protection. | SAMH | SAMH | | PTO | P | 6753235 |
IRON HORSE OF COLORADO, LLC | PTO | L | 10/15/2020 | Cancel per contractor request. | SAMH | SAMH | | PTO | L | 6742893 |
KIMBEL MECHANICAL SYSTEMS, INC. | P16 | L | 09/21/2020 | Met with General Contractor on site to access and identify underground stacks stubbed up through floor. If Alternate Plumbing Contractor completes job Permit must be attached prior to work being started. | SAMH | SAMH | | P16 | L | 6713264 |
KIMBEL MECHANICAL SYSTEMS, INC. | P16 | P | 09/06/2019 | any plan revisions / engineers letter needed will be posted here
1. need engineers letter for aav in lieu of loop vents - 9/5/19 pb | JOHNS | JOHNS | | P16 | P | 6326289 |
KIMBEL MECHANICAL SYSTEMS, INC. | PB | C | 09/06/2019 | | JOHNS | JOHNS | | PB | C | 6326288 |
KIMBEL MECHANICAL SYSTEMS, INC. | PB | P | 09/05/2019 | need engineers letter allowing AAV 's in lieu of loop vents, cover @ own risk
2 traps on 1 trap arm @ both common baths (x2), rest ok. NOTE: water stubbed into water entry, waters loped underground, plans marked | JOHNS | JOHNS | | PB | P | 6324735 |
KIMBEL MECHANICAL SYSTEMS, INC. | PB | P | 08/29/2019 | Riser main deep base ok, plans marked. | DANR | DANR | | PB | P | 6319268 |
KIMBEL MECHANICAL SYSTEMS, INC. | PB | P | 08/26/2019 | deep base ok except for hub drain by water entry and to see all units piped, water entry ok | JOSEPHD | JOSEPHD | | PB | P | 6313561 |
KIMBEL MECHANICAL SYSTEMS, INC. | PB | P | 08/23/2019 | plans call for solid core pvc underground, also show 6" running to floor clean out and sink wye, need to bed and support pipe to code, will need plan splice for adding floor drain in trash bin room, this is for deep base only still need to see riser room dwv and units piped | JOSEPHD | JOSEPHD | | PB | P | 6311903 |
BW ELECTRIC, INC. | XES | T | 10/22/2020 | PAID (REC#1739402) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revised service lateral and GEC | SHELBY | SHELBY | | XES | T | 6750606 |
COMMONWEALTH CONSTRUCTION CORPORATION | XMS | T | 06/11/2020 | PAID (REC#1703619) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Gas lines ran in 3/4 Gastite CSST | JUSTINC | JUSTINC | | XMS | T | 6600919 |
COMMONWEALTH CONSTRUCTION CORPORATION | XBS | T | 04/22/2020 | PAID (REC#1675625): PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: Revised R/C assembly listing. | BPHILLIPS | BPHILLIPS | | XBS | T | 6547356 |
COMMONWEALTH CONSTRUCTION CORPORATION | XBS | T | 12/04/2019 | PAID (REC#1673980): PLAN SPLICE FEE: $50 by: BPHILLIPS for Construction: Provided floor and roof trusses with layouts. | BPHILLIPS | BPHILLIPS | | XBS | T | 6415578 |