HENSEL PHELPS CONSTRUCTION CO | B= | C | 10/31/2019 | All other required Final inspections are complete. (This is a computer generated result) | DAKOTAB | DAKOTAB | | B= | C | 6384302 |
HENSEL PHELPS CONSTRUCTION CO | B= | P | 09/20/2019 | Items from previous inspection corrected -- Building final OK pending other finals. Additional Inspections Required (computer generated): ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, RK MECHANICAL, INC Mechanical Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 6342606 |
HENSEL PHELPS CONSTRUCTION CO | B= | P | 09/11/2019 | restroom A1346UT - side wall grab bar still needs to be max. 12" out of the corner and minimum 54" to end of bar out of the corner / mirror and rear grab bars now OK / need to complete all other finals -- Schedule a new Building Final when above items are complete. | DANE | DANE | | B= | P | 6331327 |
HENSEL PHELPS CONSTRUCTION CO | B= | P | 09/04/2019 | restroom A1346UT - rear grab bar at toilet is in wrong position / side wall grab bar is to be a 42" bar that in max 12" out of the corner and minimum 54" to end out of the corner / mirror is higher than 40" above floor to reflective surface / rest of scope of work OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, RK MECHANICAL, INC Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 6323223 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 08/13/2019 | above ceiling reinspection at control room and soiled linen rooms / control room penetrations now OK / need to fix penetration of duct through U419 wall in soiled utility room above ceiling where damper has been removed and placed in the rated ceiling | DANE | DANE | | BSP | P | 6298973 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 08/01/2019 | rock and attachments of rock OK at UL U419 wall at north end of soiled utility room A1321A OK / all penetrations in fire barrier at east side of A1321A OK / all above ceiling labeling and penetrations OK at all scope of work except for penetrations at conduits over door to control room and flex conduit above access in southeast corner of smoke partition in MDIL room | DANE | DANE | | BFR | P | 6285378 |
HENSEL PHELPS CONSTRUCTION CO | BSP | R | 07/30/2019 | above ceiling at control room and HDIL room / need to label smoke partitions above these ceilings and need to seal around pipes over door to control room and above the ceiling access in the southeast corner need to seal around flex and hard conduits / need to inspect all penetrations behind fur out wall inside of soiled utility room at sink and all labeling and penetrations above ceilings at soiled utility and clean utility east wall when ready | DANE | DANE | | BSP | R | 6281438 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 07/29/2019 | Wall framing at UL U419 smoke partition at soiled utility room A1321A OK pending other roughs | DANE | DANE | | BFR | P | 6279779 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 07/26/2019 | Remainder of 2nd layer and fire tape above hard like at soiled utility rooms OK per UL I503 | DAKOTAB | DAKOTAB | | BFR | P | 6278145 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 07/25/2019 | 1st layer and 1/2 of 2nd layer of rock installed above hard lid in soiled utility rooms OK per UL I503 | DAKOTAB | DAKOTAB | | BSP | P | 6276556 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 07/23/2019 | framing OK at UL I503 (changed from UL I506) ceiling assembly at soiled utility room A1321A OK pending other roughs / 1st and 2nd layers of rock at bottom side of assembly OK pending other roughs / discussed need to have mechanical look at damper framing and drywall inside of damper opening and inspection process for rock at upper side of joists | DANE | DANE | | BFR | P | 6273146 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 07/17/2019 | 2 in wall floor penetrations OK at new copper pipes at north wall of corridor A1324 / no progression at lid of room A1321A but met with contractor and discussed assembly on site | DANE | DANE | | BSP | P | 6266556 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 07/12/2019 | first layer of rock and joint laps to second layer OK at UL I506 assembly at ceiling of room A1321A soiled utility room pending damper framing inspection and other roughs / discussed with contractor the need for damper framing inspection by mechanical inspector | DANE | DANE | | BSP | P | 6262280 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 07/10/2019 | framing for ceiling of soiled utility room A1321A is OK per listed assembly UL I506 that has been spliced in and is now available to see in plan image on electronic images / discussed inspection process with contractor | DANE | DANE | | BFR | P | 6258601 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 06/26/2019 | hard lid ceiling for smoke partition at door A1312A to bulkhead that continues up to deck OK pending splice images being scanned in so that it is visible of permit / did inspection from contractor copy of plans as spice image is not visible / discussed inspection process for UL I506 rated ceiling at room A1321A soiled utility and need for all penetrations above framing to be fixed at framing inspection | DANE | DANE | | BFR | P | 6244624 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 06/18/2019 | framing of new walls and doorways in corridor A1321 - doors to corridors A1321D and A1342 are in smoke partitions doors to A1312A and A1221C are unrated doors and walls in corridor A1321 / light gauge framing at smoke partition and doors to A1342 OK pending other roughs / light gauge framing at smoke partition and doors to A1321D is not able to extend to the bottom of the deck above as the concealed space is filled with ductwork above the new doorway - need to splice in the design change of how to maintain the continuity to the deck above and also need to splice in the design changes at the fire barriers at room A1221A soiled utility / light gauge framing at doors to A1312A and A1321C OK pending other roughs / stamped RFI for how to support the soffit at the south side of room A1320 MDIL - framing inspected at last inspection | DANE | DANE | | BFR | P | 6234941 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 06/03/2019 | room A1320 MIDL - soffit at south side of room OK pending receipt of stamped copy of architects design for support (viewed electronic copy on site) / screws and rock at UL U419 at wall between clean utility and soiled utility OK at west side of wall - still need to complete east side of wall / still need to splice in design change of how to complete continuity of smoke barrier at new entry foyer to clean and soiled utility rooms / discussed need for 3rd party inspection on mono coat at steel beam over UL U419 wall between clean and soiled utility rooms | DANE | DANE | | BFR | P | 6218180 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 05/22/2019 | interior light gauge wall framing OK at MDIL room A1320 and soffits at north west and east sides of room OK but need stamped design for how to build and support the soffit at the south edge of the room where the duct work is in the plain of the soffit / discussed need to label the smoke partitions above the ceiling and need to seal several penetrations / rock at the storage room A1321B side of the U419 wall installed OK - discussed need to remove fire caulking around damper and need to have above ceiling inspections by building and mechanical before ceiling tiles are installed / discussed need to splice in stamped design for how to build smoke barrier at corridor side of room A1321A soiled utility where ducts are in the way to get to the deck above / discussed need for 3rd party inspection observation for all roof structure heavy gauge steel above rooms A1321A and A1321B | DANE | DANE | | BFR | P | 6207142 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 04/25/2019 | head of wall and all penetrations at U 419 wall above ceiling in storage room 1323 and equipment room 1323 A OK / still need to do screw and drywall and penetrations on other side of wall | DANE | DANE | | BFR | P | 6177757 |
HENSEL PHELPS CONSTRUCTION CO | BFR | R | 04/16/2019 | walls in newly spliced storage room A1323 (use to be locker room) / walls spliced in are to be "A" full height to deck above floor but were built as "B" walls to 6" above ceiling / walls still need to have all electrical work and need to splice in the new wall height / new wall framing at storage room A1323 OK pending splice to change wall height that is on splice dated 4/10/19 and electrical inspection / no electronic copy of splice dated 4/10/19 available - used site copy of splice | DANE | DANE | | BFR | R | 6166916 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 04/08/2019 | rock and attachments OK per UL U419 on staff locker and MRI equipment side of wall - still need to inspect listings for penetrations through wall on both sides and rock and attachments on clean utility/equipment storage room | DANE | DANE | | BFR | P | 6158651 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 04/02/2019 | wall at room A1321B U419 OK and prerock at column OK pending other roughs | DANE | DANE | | BFR | P | 6151970 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 03/27/2019 | fire barrier (UL U419) at clean utility/equipment storage A1321B // entire new wall has been installed and not just an infill as the original wall was not built per the U419 - framing installed OK but need to inspect the prerock between the concrete column and new wall as soon as it is inspected / still need to install dampers and discussed need to have damper framing inspected by mechanical inspector before framing is covered / correct USG rock on site - using 5C system for rock in U419 / discussed need for listings for all penetration in wall including 8" duct and 12x12 duct and 18x18 duct and multiple conduit penetrations with contractor | DANE | DANE | | BFR | P | 6146080 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 03/05/2019 | framing at door and fur out wall at scrub room A1319 and floor penetration at drain line OK pending other roughs / met with Superintendent Zach and discussed scope of work and rated assemblies and dampers through rated assemblies and discussed the UL U419 listed assembly for the fire barriers at the new clean linen and soiled linen rooms / discussed need to have mechanical inspector do all damper faming inspections / discussed differences between fire barriers and smoke partitions / discussed OK to use 3rd party engineer for structural steel welding and bolting inspection with a stamped letter of observation to follow | DANE | DANE | | BSP | P | 6124323 |
HENSEL PHELPS CONSTRUCTION CO | BSP | R | 03/04/2019 | field canceled / not ready per Zach | DANE | DANE | | BSP | R | 6123190 |
ENCORE ELECTRIC, INC. | E= | C | 10/30/2019 | FIRE ALARM INSPECTION: | RANDY | RANDY | | E= | C | 6384301 |
ENCORE ELECTRIC, INC. | ER | C | 10/30/2019 | FIRE ALARM INSPECTION: | RANDY | RANDY | | ER | C | 6384300 |
ENCORE ELECTRIC, INC. | E= | C | 10/25/2019 | | RANDY | RANDY | | E= | C | 6380597 |
ENCORE ELECTRIC, INC. | E= | C | 10/25/2019 | | RANDY | RANDY | | E= | C | 6380583 |
ENCORE ELECTRIC, INC. | ER | C | 10/25/2019 | | RANDY | RANDY | | ER | C | 6380582 |
ENCORE ELECTRIC, INC. | ER | P | 09/11/2019 | FIRE ALARM INSPECTION: red card signed | RANDY | RANDY | | ER | P | 6331724 |
ENCORE ELECTRIC, INC. | E= | P | 09/06/2019 | MDIL final | RANDY | RANDY | | E= | P | 6326888 |
ENCORE ELECTRIC, INC. | E= | P | 08/19/2019 | MDIL outlets and lights marked on plans---no equipment at this time | RANDY | RANDY | | E= | P | 6305413 |
ENCORE ELECTRIC, INC. | ER | P | 08/19/2019 | no rough | RANDY | RANDY | | ER | P | 6305410 |
ENCORE ELECTRIC, INC. | ER | P | 08/14/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6300592 |
ENCORE ELECTRIC, INC. | ER | P | 08/14/2019 | rest of MDIL ceiling marked on plans | RANDY | RANDY | | ER | P | 6300571 |
ENCORE ELECTRIC, INC. | ER | P | 08/09/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6295385 |
ENCORE ELECTRIC, INC. | ER | P | 08/09/2019 | MDIL walls marked on plans | RANDY | RANDY | | ER | P | 6295380 |
ENCORE ELECTRIC, INC. | ER | P | 08/07/2019 | MDIL control and storage room----soiled utility ceilings | RANDY | RANDY | | ER | P | 6291778 |
ENCORE ELECTRIC, INC. | ER | P | 08/07/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6291777 |
ENCORE ELECTRIC, INC. | ER | P | 07/29/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6279910 |
ENCORE ELECTRIC, INC. | ER | P | 07/29/2019 | 1st fl MDIL walls and ceiling marked on plans------panel IPP | RANDY | RANDY | | ER | P | 6279905 |
ENCORE ELECTRIC, INC. | ER | P | 07/16/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6265386 |
ENCORE ELECTRIC, INC. | ER | P | 07/16/2019 | ceilings in clean utility storage----marked on plans | RANDY | RANDY | | ER | P | 6265372 |
ENCORE ELECTRIC, INC. | ER | P | 06/14/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6231620 |
ENCORE ELECTRIC, INC. | ER | P | 06/14/2019 | walls only---marked on plans | RANDY | RANDY | | ER | P | 6231616 |
ENCORE ELECTRIC, INC. | ER | P | 06/10/2019 | Can light in main hall alcove okay | CHIPO | CHIPO | | ER | P | 6226054 |
ENCORE ELECTRIC, INC. | ER | P | 06/03/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6217896 |
ENCORE ELECTRIC, INC. | ER | P | 06/03/2019 | can lights in soffit marked on plans | RANDY | RANDY | | ER | P | 6217888 |
ENCORE ELECTRIC, INC. | ER | P | 05/30/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6214817 |
ENCORE ELECTRIC, INC. | ER | P | 05/30/2019 | walls in MDIL and clean storage room, marked on plans | RANDY | RANDY | | ER | P | 6214800 |
ENCORE ELECTRIC, INC. | ER | P | 05/23/2019 | FIRE ALARM INSPECTION: walls with electric | RANDY | RANDY | | ER | P | 6209353 |
ENCORE ELECTRIC, INC. | ER | P | 05/23/2019 | MDIL walls marked on plans | RANDY | RANDY | | ER | P | 6209350 |
ENCORE ELECTRIC, INC. | E= | P | 05/08/2019 | storage room 1323 ok | RANDY | RANDY | | E= | P | 6192566 |
ENCORE ELECTRIC, INC. | ER | P | 05/08/2019 | no rough | RANDY | RANDY | | ER | P | 6192563 |
ENCORE ELECTRIC, INC. | ER | P | 04/18/2019 | walls for storage room marked on plans | RANDY | RANDY | | ER | P | 6170277 |
ENCORE ELECTRIC, INC. | ER | P | 04/08/2019 | clean utility walls marked on plans | RANDY | RANDY | | ER | P | 6158973 |
ENCORE ELECTRIC, INC. | E= | P | 03/28/2019 | scrub room final---marked on plans | RANDY | RANDY | | E= | P | 6147847 |
ENCORE ELECTRIC, INC. | ER | P | 03/28/2019 | | RANDY | RANDY | | ER | P | 6147844 |
ENCORE ELECTRIC, INC. | ER | P | 03/18/2019 | FIRE ALARM INSPECTION: FA marked with electric | RANDY | RANDY | | ER | P | 6135390 |
ENCORE ELECTRIC, INC. | ER | P | 03/18/2019 | scrub room ceiling marked on plans | RANDY | RANDY | | ER | P | 6135384 |
ENCORE ELECTRIC, INC. | ER | P | 02/26/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6118201 |
ENCORE ELECTRIC, INC. | ER | P | 02/26/2019 | scrub room walls marked on plans | RANDY | RANDY | | ER | P | 6118200 |
RK MECHANICAL, LLC | H= | C | 10/30/2019 | MECHANICAL FINAL OK. REVISED TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. | NANCY | NANCY | | H= | C | 6383439 |
RK MECHANICAL, LLC | H= | P | 10/29/2019 | TEST AND BALANCE REPORT RECEIVED. REPORT LACKS READINGS FOR CRAC-103. | NANCY | NANCY | | H= | P | 6383230 |
RK MECHANICAL, LLC | H= | P | 10/29/2019 | REVISE SCOPE OF WORK. PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 6383057 |
RK MECHANICAL, LLC | H= | P | 10/24/2019 | FOR FINAL - REVISE SCOPE OF WORK, SEE INSPECTION COMMENTS DATED 4/2/19. ADD NEW UNIT INSTALLED ON LAST SPLICE TO SCOPE OF WORK. COMPLETE ALL ITEMS NOTED ON HD AND HWP INSPECTIONS DATED 10/24/19. PROVIDE TEST AND BALANCE REPORT. | NANCY | NANCY | | H= | P | 6379407 |
RK MECHANICAL, LLC | HWP | P | 10/24/2019 | INSULATE, LABEL AND SUPPORT HOT WATER SUPPLY/RETURN LINES TO NEW UNIT. OK TO SEND PICTURES AT NEXT INSPECTION REQUEST. PIPING INSTALLED AS PER SPLICE ON SITE DATED 10/24/19. HOT WATER SUPPLY/RETURN LINES ALREADY UNDER WORKING PRESSURE, NO VISIBLE LEAKS. | NANCY | NANCY | | HWP | P | 6379400 |
RK MECHANICAL, LLC | HD | P | 10/24/2019 | INSULATE DUCTS AT NEW UNIT. OK TO SEND PICTURES AT NEXT INSPECTION REQUEST. NEW UNIT INSTALLED AS PER SPLICE ON SITE DATED 10/24/19. | NANCY | NANCY | | HD | P | 6379396 |
RK MECHANICAL, LLC | H= | P | 08/16/2019 | ((CHANGED TO H= (LM) 8/20/19 ))SOILED UTILITY ROOM : SUPPLY AND RETURN DAMPER INSTALL, ANGLES AND ACCESS OK . NEED TO LABEL DAMPER ACCESS / GRILLS INSTALLED. ROOM # A1308 SUPPLY AND RETURN GRILLS FROM CRAC 103 OK . NEED TO COMPLETE CONDENSATE TERMINATION IN BATHROOM FOR CRAC-3 .
| LIDO | LIDO | | H= | P | 6303868 |
RK MECHANICAL, LLC | HWP | P | 08/05/2019 | (BDA 133/ 138 ) M201 . 1ST FLOOR - H-201: NEED REVISED / APPROVED PRINT TO SHOW PIPE SIZES FOR LOW PRESSURE STEAM SUPPLY AND RETURN PIPING / 3/4" INSTALLED FROM EXISTING 2". LOW PRESSURE STEAM SUPPLY AND RETURN UNDER WORKING PRESSURE NO VISIBLE LEAKS. VAV 228: NEED REVISED / APPROVED PRINT FOR HEAT WATER SUPPLY AND RETURN / PLAN SHOWS EXISTING 1" BUT EXISTING IS 3/4"/ SPLICE WILL NEED TO REFLECT 1/2 " INSTALLED OFF THE 3/4" EXISTING AND 1/2" TIED INTO VAV . VAV-228 HEAT WATER SUPPLY AND RETURN UNDER WORKING PRESSURE NO VISIBLE LEAKS. | LIDO | LIDO | | HWP | P | 6288322 |
RK MECHANICAL, LLC | HD | P | 07/23/2019 | SOILED UTILITY: DAMPER FRAMING IN UL I503 ASSEMBLY OK, OK TO LINE DAMPER OPENING WITH SHEET ROCK PER NOTE 5 OF ASSEMBLY. OK TO INSTALL DAMPERS, ALSO SEE NOTE 5 REGARDING DAMPER INSTALLATION. | NANCY | NANCY | | HD | P | 6273704 |
RK MECHANICAL, LLC | HWP | P | 07/16/2019 | M201 (BDA 154) - NEED REVISED/APPROVED PRINT SHOWING NEW CONDENSATE DRAIN LOCATION FOR CRAC 103 AND HUMIDIFIER. REVISED PRINT TO ALSO SHOW LOCATION OF NEW CONDENSATE PUMP AND ELECTRICAL FOR PUMP. CRAC 103: CONDENSATE ABOVE CEILING AND IN WALL OK, OK TO INSULATE AND LABEL. CHILLED WATER SUPPLY/RETURN OK FROM TAPS IN BASEMENT TO UNIT, ALREADY UNDER WORKING PRESSURE, NO VISIBLE LEAKS. OK TO INSULATE AND LABEL. HUMIDIFIER: CONDENSATE DRAIN IN WALL OK, OK TO LABEL INSULATION. COMPLETE DRAIN FROM WALL TO HUMIDIFIER. | NANCY | NANCY | | HWP | P | 6265729 |
RK MECHANICAL, LLC | HWP | P | 07/15/2019 | M201 (BDA 154) - 1 INCH CHILLED WATER SUPPLY/RETURN IN WALL UNDER WORKING PRESSURE, NO VISIBLE LEAKS. OK TO INSULATE AND LABEL. | NANCY | NANCY | | HWP | P | 6264076 |
RK MECHANICAL, LLC | HD | P | 07/15/2019 | AC110 (BDA 151) - UL I506 ASSEMBLY HAS NO FRAMING DETAIL FOR DAMPER OPENINGS OR LIST OF APPROVED DAMPERS FOR OPENINGS THROUGH ASSEMBLY. NEED ENGINEER TO ADDRESS OPENINGS THROUGH UL I506 | NANCY | NANCY | | HD | P | 6264075 |
RK MECHANICAL, LLC | HD | P | 07/02/2019 | M101 (BDA 132) - H-201: MEDIUM AND LOW PRESSURE SUPPLY TRUNK LINES OK, OK TO WRAP. | NANCY | NANCY | | HD | P | 6251857 |
RK MECHANICAL, LLC | HD | P | 05/29/2019 | M101: NEED REVISED/APPROVED PRINT SHOWING NEW FIRE DAMPER INTO SOILED UTILITY, CHANGES TO DUCT LAYOUT IN MDIL AND RELOCATION OF CRAC 103. FRAMING FOR DAMPER ABOVE DOOR INTO SOILED UTILITY OK, OK TO INSTALL DAMPER. PROPERLY ATTACH RETAINING ANGLES FOR 22 X 10 DAMPER TO WALL PER MANUFACTURER'S INSTRUCTIONS. MDIL ROUGH DUCTS ABOVE CEILING OK, OK TO WRAP SUPPLIES. CRAC 103 SUPPLY/RETURN TRUNK LINES AND LATERALS OK, OK TO WRAP SUPPLIES. | NANCY | NANCY | | HD | P | 6213443 |
RK MECHANICAL, LLC | HD | P | 04/02/2019 | REVISE SCOPE OF WORK TO 1 CRAC UNIT, 1 VAV, 1 HUMIDIFIER, HYDRONIC PIPING AND DUCTS. 24 X 12 FIRE DAMPER FRAMED OPENING OK, INSTALL KICKERS PER DAMPER MANUFACTURER. OK TO INSTALL ANGLES. | NANCY | NANCY | | HD | P | 6152556 |
RK MECHANICAL, LLC | P= | C | 09/04/2019 | | TAYLOR | TAYLOR | | P= | C | 6323172 |
RK MECHANICAL, LLC | PTO | C | 07/29/2019 | this completes all PTO phases. NOTE: hammer arrestor above clinical sink @ A1321B | JOHNS | JOHNS | | PTO | C | 6280676 |
RK MECHANICAL, LLC | PTO | P | 06/19/2019 | ok for test / design @ in wall dwv / h20 @ bath @ rm# A1346. NOTE: vtr (existing), trap primers in wall @ bath @ front left side, hammer arrestor above w/c @ drop ceiling, **VERIFY access panel @ opposite incoming wall for RP @ final
**STILL NEED re circ tie in @ A1319, over head piping, and remainder of scope | JOHNS | JOHNS | | PTO | P | 6236139 |
RK MECHANICAL, LLC | PTO | P | 05/31/2019 | ok for test / design @ scrub sink only (rm # A1320). NOTE: vtr (existing) **STILL NEED re circ tie in @ rm # A1319, and remainder of scope | JOHNS | JOHNS | | PTO | P | 6215782 |
RK MECHANICAL, LLC | PTO | P | 03/05/2019 | **NEED RFI to engineer about re circ pipe size (plans call for 1", contractor installed 1/2") rest ok for test and design @ scrub sink only (rm # A1319), MINUS re circ tie in and remainder of scope. NOTE: vtr (existing), check other PTO notes for @ final items | JOHNS | JOHNS | | PTO | P | 6124262 |
ENCORE ELECTRIC, INC. | XES | T | 10/24/2019 | PAID (REC#1639872) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Remove scope from E 203 | SHELBY | SHELBY | | XES | T | 6379262 |
RK MECHANICAL, LLC | XMS | P | 10/24/2019 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: okay new splice reroute water lines rerouted ducts adjusted schedules | DALEH | DALEH | | XMS | P | 6379206 |
RK MECHANICAL, LLC | XMS | P | 08/15/2019 | PLAN SPLICE: (No Fee) by: DALEH for Mechanical: clouded revisions only | DALEH | DALEH | | XMS | P | 6301649 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 07/22/2019 | PAID (REC#1615944) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise UL listing | MICHAELA | MICHAELA | | XBS | T | 6271530 |
RK MECHANICAL, LLC | XMS | T | 07/18/2019 | PAID (REC#1615394) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: see comment letter for note | TCRIPPEN | TCRIPPEN | | XMS | T | 6269036 |
RK MECHANICAL, LLC | XMS | T | 07/09/2019 | PAID (REC#1613870): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: new splice re route CHR and CHS one inch lines | TCRIPPEN | TCRIPPEN | | XMS | T | 6257502 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 06/25/2019 | PAID (REC#1609310) PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised ceiling assemblies in soiled linen A1321A & hall A1312 | LBENNETT | LBENNETT | | XBS | T | 6243478 |
RK MECHANICAL, LLC | XMS | T | 06/05/2019 | PAID (REC#1604145) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: mechanical splice see 8.8 x 11.5 pages for changes | TCRIPPEN | TCRIPPEN | | XMS | T | 6221373 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 04/30/2019 | PAID (REC#1594480) PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised wall type for storage room A1323 | LBENNETT | LBENNETT | | XBS | T | 6182512 |
ENCORE ELECTRIC, INC. | XES | T | 04/17/2019 | PAID (REC#1591304): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Change Staff Locker Room to Storage | BERTHA | BERTHA | | XES | T | 6169336 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 04/10/2019 | PAID (REC#1590429): PLAN SPLICE FEE: $50 by: DANM for Construction: Change Staff Locker Room to Storage | DANM | DANM | | XBS | T | 6162166 |
RK MECHANICAL, LLC | XPS | T | 03/21/2019 | PAID (REC#1585305) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 3/21/19: Delta 1 revisions - Revised detail 4 and schedule to change hub drains to auxiliary drain boxes with louvered face plate. Revised key note to indicate RPZ-1 is alone behind access panel. Removed sink, water piping and DWV piping in Clean Supply room. Relocated medical gas zone valve box from behind corridor door. Revised plan and key note to indicate hub drains being revised to auxiliary drain boxes for condensate and humidifier drains. | SHANEN | SHANEN | | XPS | T | 6139372 |
ENCORE ELECTRIC, INC. | XES | P | 03/20/2019 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: REvise one line and luminaire schedule. | SHELBY | SHELBY | | XES | P | 6138470 |