TURNER CONSTRUCTION COMPANY | B= | C | 06/19/2019 | Corrections complete verified by plumbing inspector | JEREMYA | JEREMYA | | B= | C | 6236302 |
TURNER CONSTRUCTION COMPANY | B= | P | 05/21/2019 | Temp CO: waiting for electtrical and plumbing finals ( Expires: 6/20/2019 12:00:00 AM) | RITA | RITA | | B= | P | 6205879 |
TURNER CONSTRUCTION COMPANY | B= | P | 05/20/2019 | hand shower control over 48" in height where 48" max is required, remaining items okay. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), APOLLO MECHANICAL CONTRACTORS Plumbing Final Inspection is not Completed yet, TOWER ELECTRIC, INC. Electrical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6205217 |
TURNER CONSTRUCTION COMPANY | BFR | P | 03/07/2019 | exterior side all restroom walls okay, all remaining rooms completed walls and drop framing at windows room 114,122 with completed required inspections okay | NATHAN | NATHAN | | BFR | P | 6127211 |
TURNER CONSTRUCTION COMPANY | BFR | P | 03/01/2019 | frame at walls areas 110,112, 116-134,138,139,141,142,146,147 and hard lids okay with completed required inspections. Reviewed Accessible Elements / still need splice or engineer letter for change of BO5, C05 and bracing change. | NATHAN | NATHAN | | BFR | P | 6121819 |
TURNER CONSTRUCTION COMPANY | BFR | P | 02/15/2019 | wall frame at 102, 103,149-157 okay with completed required inspections | NATHAN | NATHAN | | BFR | P | 6108949 |
TURNER CONSTRUCTION COMPANY | BFR | P | 02/05/2019 | partial frame of B05 and C05 walls to deck need letter for stud spacing of 16" oc at B05 over 24'1" also lateral bracing at 4' oc at C05 wall installed 10' oc. | NATHAN | NATHAN | | BFR | P | 6097750 |
TOWER ELECTRIC, INC. | E= | C | 06/19/2019 | spice received and paid / | MIGUEL | MIGUEL | | E= | C | 6236067 |
TOWER ELECTRIC, INC. | E= | P | 06/03/2019 | corrections made / still need to verify scan of splice / | MIGUEL | MIGUEL | | E= | P | 6218470 |
TOWER ELECTRIC, INC. | ES | P | 05/23/2019 | Commercial Service: pre release ok / | MIGUEL | MIGUEL | | ES | P | 6208079 |
TOWER ELECTRIC, INC. | E= | P | 05/22/2019 | need full size GEC to steel from CT , currently 4/0 AL / need chap 3 wiring methods in RTUs 4,5 / ACCU-3 mini split 30A max on 35A breaker / need to check splice for changes / | MIGUEL | MIGUEL | | E= | P | 6207907 |
TOWER ELECTRIC, INC. | EP | C | 05/22/2019 | AIC ratings installed / | MIGUEL | MIGUEL | | EP | C | 6207913 |
CONVERGINT TECHNOLOGIES, LLC | E= | C | 05/20/2019 | FIRE ALARM INSPECTION: FA complete / | MIGUEL | MIGUEL | | E= | C | 6204712 |
CONVERGINT TECHNOLOGIES, LLC | ER | C | 05/20/2019 | FIRE ALARM INSPECTION: FA complete / | MIGUEL | MIGUEL | | ER | C | 6204713 |
TOWER ELECTRIC, INC. | EP | P | 05/17/2019 | panels need AIC rating labels / 300A L2 ok / 300A L2B ok / L2A- 225A - 250 AL, need to verify demanded load to amp rating of wire, may be over ampacity rating of 250 AL feeders / | MIGUEL | MIGUEL | | EP | P | 6203603 |
TOWER ELECTRIC, INC. | ES | P | 05/17/2019 | Commercial Service: need key to inspect CT / MDP ok, need AIC rating label / need to verify GECs and sizesn need 4/0 per plans / jumper regulator / splice one line to show service conductors increased to 600 CU / | MIGUEL | MIGUEL | | ES | P | 6203602 |
TOWER ELECTRIC, INC. | E= | P | 05/16/2019 | rest of interior rooms ok / lack service, EPs, and RTUs / | MIGUEL | MIGUEL | | E= | P | 6202174 |
TOWER ELECTRIC, INC. | E= | P | 05/10/2019 | offices --see plans in blue / NOTE talked to contractor about rbd fire alarm permit / | BRIAN | BRIAN | | E= | P | 6195710 |
TOWER ELECTRIC, INC. | ER | P | 05/09/2019 | grid ceilings ok / look at rm 136 ceiling on final / | MIGUEL | MIGUEL | | ER | P | 6193519 |
TOWER ELECTRIC, INC. | ER | P | 05/03/2019 | ceilings ---marked in blue see plans / | BRIAN | BRIAN | | ER | P | 6187310 |
TOWER ELECTRIC, INC. | ER | P | 04/29/2019 | remaining hardlids ok / | MIGUEL | MIGUEL | | ER | P | 6182007 |
TOWER ELECTRIC, INC. | ER | P | 04/26/2019 | Above ceiling rough in okay in all areas except areas 112, 122, 136, 141, 142, 147, 150, and hallways past exit sign near area 142. | CHIPO | CHIPO | | ER | P | 6179586 |
TOWER ELECTRIC, INC. | ESL | C | 04/10/2019 | 3 under slab feeds to furniture in back of suit --ok | BRIAN | BRIAN | | ESL | C | 6162188 |
TOWER ELECTRIC, INC. | ER | P | 03/26/2019 | rest of walls and bath hard lids ---see plans- | BRIAN | BRIAN | | ER | P | 6145180 |
TOWER ELECTRIC, INC. | ES | P | 03/15/2019 | Commercial Service: Pre release ok / changing MDP and CT can out to 800 amp rated service | CHIPO | CHIPO | | ES | P | 6133233 |
TOWER ELECTRIC, INC. | ER | P | 02/28/2019 | walls --see plans yellow highlighter--ok---------NOTE contractor stated all fire alarm will be in the ceiling | BRIAN | BRIAN | | ER | P | 6120664 |
TOWER ELECTRIC, INC. | ER | P | 02/14/2019 | walls in rooms 100, 102, 150, 152-157 ok / Fire Alarm permit is required, will need to attach to permit before next inspection / | MIGUEL | MIGUEL | | ER | P | 6106994 |
TOWER ELECTRIC, INC. | ESL | C | 02/07/2019 | floor boxes ok, 4 total / | MIGUEL | MIGUEL | | ESL | C | 6101211 |
APOLLO MECHANICAL CONTRACTORS | H= | C | 05/20/2019 | TAB REPORT AND ENGINEER LETTER RECEIVED | JERRYF | JERRYF | | H= | C | 6204167 |
APOLLO MECHANICAL CONTRACTORS | H= | P | 05/17/2019 | SA READINGS FOR F1 ARE OUTSIDE +/- 10% - NEED LETTER FROM ENGINEER APPROVING THESE READINGS OR SUBMIT NEW TAB REPORT - NEED OSA READINGS LISTED ON TAB REPORT FOR F1 AND F2 | JERRYF | JERRYF | | H= | P | 6202299 |
APOLLO MECHANICAL CONTRACTORS | H= | P | 05/16/2019 | PARTIAL PENDING LETTER FROM FIRE CONTROLS CONTRACTOR STATING THAT SMOKE SHUTDOWN IS MONITORED THROUGH FIRE PANEL ADD REVIEW OF TAB REPORT ON 5/17 | JERRYF | JERRYF | | H= | P | 6201066 |
APOLLO MECHANICAL CONTRACTORS | HV | C | 05/10/2019 | WATER HEATER VENT ISOLATED FROM RETURN PLENUM. | DUSTINS | DUSTINS | | HV | C | 6194775 |
APOLLO MECHANICAL CONTRACTORS | HD | C | 05/10/2019 | ALL ABOVE CEILING DUCTS, FLEX AND DIFFUSERS OK. DSS-1 AND CONDENSATE LINES OK. STILL NEED ROOF INSPECTION AND ALL PREVIOUS COMMENTS ABOUT FINAL INSPECTIONS. | DUSTINS | DUSTINS | | HD | C | 6194752 |
APOLLO MECHANICAL CONTRACTORS | HV | P | 05/06/2019 | ADD WATER HEATER VENT TO PERMIT WORK SCOPE - NEED TO PROTECT WATER HEATER VENTS IN RETURN PLENUM TO 25/50 FLAME SPREAD | JERRYF | JERRYF | | HV | P | 6188074 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 05/06/2019 | ALL SA / RA AND EXHAUST GRILLES AND CONNECTIONS ARE COMPLETE - STILL NEED ROOF INSPECTION AND TAB REPORT - LETTER FROM FIRE PROTECTION COMPANY STATING SMOKE SHUTDOWN IS TIED TO BUILDING FIRE SYSTEM - TRANSFER GRILLE INSTALLED AT WATER HEATER ROOM FOR GAS REGULATOR VENTING | JERRYF | JERRYF | | HD | P | 6188073 |
APOLLO MECHANICAL CONTRACTORS | HC | C | 05/03/2019 | OK TO RELEASE 2# METER | JERRYF | JERRYF | | HC | C | 6186520 |
APOLLO MECHANICAL CONTRACTORS | HI | C | 05/03/2019 | PRESSURE TEST OK - AT FINAL VERIFY ROOF LABELS REGULATORS AND VENTS AND WATER HEATER LABEL | JERRYF | JERRYF | | HI | C | 6186503 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 05/02/2019 | ALL SA / RA AND EXHAUST GRILLES OK IN THE FOLLOWING ROOMS -135 - 136 - 128 - 129 - 142 - 112 - 12" EXHAUST DUCT IN PRODUCTION AREA - SA / RA DUCT DROPS FROM RTU TO TIE IN AT RTU 5 | JERRYF | JERRYF | | HD | P | 6184906 |
APOLLO MECHANICAL CONTRACTORS | HI | P | 05/01/2019 | CANNOT TIE INTO GAS METER BETWEEN FIRST 2 FITTINGS NEED TO TIE AFTER - NEED 10# ON 30# GAUGE BEFORE METER RELEASE - NEED TO VERIFY ALL LABELS INCLUDING LINE AT METER / REGULATORS AND VENTS AT FUTURE INSPECTION | JERRYF | JERRYF | | HI | P | 6183545 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 04/30/2019 | RTU 2 RTU DROPS OK AND EF 1 EXHAUST DUCT FROM ROOF TO FLOOR OK | JERRYF | JERRYF | | HD | P | 6182295 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 04/26/2019 | ----STILL NEED "HI" INSPECTION---- ABOVE CEILING DUCT - RETURN MAINS FOR RTU'S # 4 & 5 INSTALLED PER PLAN OK TO WRAP. | MARKB | MARKB | | HD | P | 6179844 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 04/25/2019 | RTU-6 SUPPLY/RETURN AIR DROPS AND TIE INS OK, OK TO WRAP. | DUSTINS | DUSTINS | | HD | P | 6177706 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 04/24/2019 | M2.0 (BDA 43) PUTTING PLANS IN SHARED FILE. SUPPLY/RETURN AIR FLEX AND DIFFUSERS MARKED ON PLANS OK. RTU-1 AND RTU-3 SUPPLY/RETURN DROPS AND TIE INS OK, OK TO WRAP. EF-2 EXHAUST DROP AND TIE INS OK. STILL NEED TO SEE THE OTHER RTU AND EXHAUST FANS AND TIE INS. | DUSTINS | DUSTINS | | HD | P | 6176232 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 03/13/2019 | ABOVE CEILING SUPPLY/RETURN AND EXHAUST MAINS AND RUN OUTS OK FROM GRID LINE D THROUGH A EXCEPT RTU-6 NO RETURN AIR INSTALLED YET, OK TO WRAP. STILL NEED TO SEE ALL RTU AND EXHAUST DROPS TO MAIN DUCT TIE INS. | DUSTINS | DUSTINS | | HD | P | 6132774 |
APOLLO MECHANICAL CONTRACTORS | HD | P | 02/27/2019 | ABOVE CEILING SA / RA AND EXHAUST MAINS AND RUN OUTS OK FROM FRONT OF BUILDING TO BACK OF BUILDING STOPPED INSPECTION BETWEEN GRID LINES C AND D - STILL NEED ALL RTU AND EXHAUST RTU DROPS TO MAIN DUCT TIE INS - BY FINAL NEED TO ADD 10 COMMERCIAL DUCTS TO PERMIT | JERRYF | JERRYF | | HD | P | 6118935 |
APOLLO MECHANICAL CONTRACTORS | P= | C | 05/28/2019 | corrections made | JOSEPHD | JOSEPHD | | P= | C | 6212181 |
APOLLO MECHANICAL CONTRACTORS | PTO | C | 05/28/2019 | | JOSEPHD | JOSEPHD | | PTO | C | 6212171 |
APOLLO MECHANICAL CONTRACTORS | P= | P | 05/24/2019 | not ready | JOSEPHD | JOSEPHD | | P= | P | 6210256 |
APOLLO MECHANICAL CONTRACTORS | P= | P | 05/20/2019 | diverter valves in both showers to high, other corrections made | JOSEPHD | JOSEPHD | | P= | P | 6204965 |
APOLLO MECHANICAL CONTRACTORS | P= | P | 05/17/2019 | pto was never completed needed to see shower valves, shower diverter to high at both showers, 106 sink to high off floor, women bathroom accessible toilet to far off side wall, accessible drinking fountain to low, still need to see roof penetration, rest ok | JOSEPHD | JOSEPHD | | P= | P | 6203178 |
APOLLO MECHANICAL CONTRACTORS | PTO | P | 03/19/2019 | in walls ok except shower valves, over head ok except vent penetration, still need to see floor flanges anchored, discussed accessible requirements | JOSEPHD | JOSEPHD | | PTO | P | 6136453 |
APOLLO MECHANICAL CONTRACTORS | PB | C | 02/05/2019 | | JOSEPHD | JOSEPHD | | PB | C | 6097603 |
TOWER ELECTRIC, INC. | XES | T | 06/18/2019 | PAID (REC#1607260): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Add IT panel | SHELBY | SHELBY | | XES | T | 6234451 |
TOWER ELECTRIC, INC. | XES | T | 05/24/2019 | PAID (REC#1603110) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revised one line | SHELBY | SHELBY | | XES | T | 6209880 |
TURNER CONSTRUCTION COMPANY | XBS | T | 05/14/2019 | PAID (REC#1598544) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise stud spacing | MICHAELA | MICHAELA | | XBS | T | 6197794 |